Sample of Hazardous Area Classification
Sample of Hazardous Area Classification
DWC-27-001
Kent W2V Revision: A
Date: 30/11/20
Page: 1 of 35
CONTENTS
REVISION HISTORY
Revision Description
- Draft issue for review prior to construction
A Issued with calculations, updated zones and Hazardous Area Drawings list
GLOSSARY OF TERMS
Acronym Description
AD Anaerobic Digestion
AIT Auto Ignition Temperature
EU ATEX Directives 100a and 137 relating to protection of personnel against fires &
ATEX
explosions
CHP Combined Heat and Power plant
DSEAR Dangerous Substances and Explosive Atmospheres Regulations 2002
LEL Lower Explosive Limit
NE Negligible Extent
UEL Upper Explosive Limit
1 INTRODUCTION
This document is the Hazardous Area Classification for the Kent Waste to Value Plant.
The plant is located next to an existing chicken farm and will process chicken manure to produce
biogas by anaerobic digestion. A portion biogas is used in a Combined Heat and Power plant (CHP) to
produce heat and electricity for the Plant with the bulk of the biogas upgraded to Bio-methane and
injected to the local gas distribution network. The digestate is spread to land for beneficial use.
The plant consists of feedstock mixing and conditioning equipment that mixes the manure with
recovered liquids and pumps the slurry to the digesters. There are two primary plug flow digesters
with concrete roofs. The digester gas spaces are at low pressure, approx. 15mbar and fitted with
overpressure relief valves venting to atmosphere.
Biogas is collected from the roof space of the digesters and is distributed by overground steel
pipework with welded and flanged joints laid to falls with small bore condensate drains taken from
the low points to condensate sumps. The pipework distributes biogas to the gas mixing
compressors, CHP, Biomethane Upgrader, gas storage and flare.
The gas mixing system uses compressors in a plant room to raise the biogas pressure to about 1 bar
and return the gas through below ground welded PE pipe into the digester to provide mixing energy.
The biogas supplying the CHP is treated in a dedicated plant to remove condensate and hydrogen
sulphide. The clean biogas is fed by a gas booster to the CHP container to generate electricity for the
site.
Biogas for upgrading is treated in a dedicated plant to remove condensate and hydrogen sulphide.
The clean biogas is compressed and passed through a containerised membrane system to remove
carbon dioxide. The carbon dioxide is vented to atmosphere and the biomethane is cooled and
transferred to the Grid Entry Unit where the gas is conditioned with odourant, CV adjusted to
Network specification and pressure regulated to enter the Network. Gas not meeting the
specification is rejected and returned to the digester headspace.
The gas storage is a proprietary Combibag (fabric lined lagoon with dual membrane fabric roof) for
storing digestate and biogas. The Combibag operates at around 5mb and a gas blower is used to
raise the outgoing gas pressure to return biogas from storage to the system.
Surplus biogas is burnt in a proprietary flare which has a dedicated gas booster to supply the burner.
The biomethane CV is adjusted by addition of propane from a tank farm of 2t bulk storage tanks.
Liquid propane is pumped to the Grid Entry Unit and vapourised for addition to the biomethane.
Natural gas is imported at the site through a commercial meter skid and piped to the main building
which contains a gas boiler for supplying the process hot water.
“for detailed recommendations regarding the extent of the hazardous areas in specific industries or
applications, reference may be made to the codes relating to those industries or applications”
Therefore Reference 2 has also been applied as this refers specifically to natural gas (which is similar
to biogas) and Reference 4, which has been prepared by the German Safety Agency for biogas
digesters operated at less than 100mbar, is used for direct examples of release types.
There are three basic grades of release defined in References 1 and 2, these being:
Continuous; A release that is continuous or which is expected to occur for long periods
Primary; A release that may be expected to occur periodically or occasionally during normal
operation
Secondary; A release not expected to occur in normal operation, and, if it does occur, is likely to
do so only infrequently and for short periods
Zone Definition
0 Explosive atmosphere is present continuously or for long periods or frequently
(typically defined as >1,000 hours per year, Ref. 2) e.g. inside a vessel.
1 Explosive atmosphere is likely to occur in normal operation occasionally
(typically defined as 10 – 1000 hours per year, Ref. 2).
2 Explosive atmosphere is not likely to occur in normal operation, but if it does
occur, is likely to do so for short periods only.
Table 1: Zone Definitions for Gases and Vapours
Zone Definition
20 Explosive atmosphere is present continuously, or for long periods or frequently
for short periods, e.g. inside a vessel.
21 Explosive atmosphere is likely to occur occasionally in normal operation.
22 Explosive mixture is not likely to occur in normal operation, but, if it does occur,
will persist for a short period only.
Table 2: Zone Definitions for Dusts
Zone 0 / 20 Zone 0 / 20
Zone 1 /121
Zone / 21 Zone 1 / 21 Zone 1 / 21 Zone 1 / 21
The point source release approach consists of a specific methodology to identify all possible release
points and their associated release rates. This can be applied to all situations including those for
which there is no direct worked example already available.
The direct example approach was used for this area classification as all situations were covered by
examples found within the guidance.
The Hazardous Classification of package equipment has been provided by the suppliers.
Any of the above could result in a breach of the Basis of Safety for operation of the plant.
For this area classification, the properties of the biogas have been assumed to be the same as for
pure methane. However, as the vapour density of carbon dioxide is much greater than that of
methane, and of air, at certain compositions the vapour density of the biogas may be greater than
air. Following the upgrading process the product gas is methane.
The feeds to the process and the other products (liquid and solid) are non-flammable.
The properties of the hazardous fluids handled / found on the site are outlined in Table 3; taken
from Reference 3.
1
The relative density of biogas is 1.2 due to the carbon dioxide content (typically 40%).
5 AREA CLASSIFICATION
5.1 Feedstock preparation and pumping
5.1.1 Operation
Feedstock preparation and pumping consists of 2 bunkers which hold the manure. Manure is
conveyed to grinder to reduce particle size and discharged into a blending tank where it is mixed
with treated digestate to prepare a slurry.
The slurry passes through a grit settling system, the grit is washed and collected for removal from
site and the de-gritted slurry is pumped to the digesters.
The plant is located in a large shed. The area is naturally well ventilated.
5.2 Digesters
5.2.1 Operation
The digesters are externally insulated rectangular concrete tanks with heating coils on skids within
the digesters. The tanks are covered with a concrete roof with penetrations for the gas pipes and
service openings for mechanical mixers. The gas space is fitted with an over pressure relief valve.
The digester contents are mixed by recirculated biogas through low level nozzles and submersible
propeller mixers in tank. There are 4 steel fabricated service ports on the roof of each digester to
allow access to the mixers, the port has an internal baffle which enters the digestate and isolates the
service area from the main gas storage area. There are also penetrations for condensate return.
The digestate overflows into an effluent chamber which is open to atmosphere and is aerated with
compressed air as it flows into the chamber. The effluent chamber is mixed with submersible mixers.
The biogas is collected in a header pipe on the digester roof and flows either to the gas mixing plant
room or to the biogas utilisation – CHP, BUU, Flare or storage – as demanded by the individual plant.
The service ports can be opened under maintenance conditions which will allow entry of air. The
area below the service port is classified as Zone 2 and the area above the service port is classified as
Zone 2 for an extent of 3m horizontally and upwards. (Reference 4 Para 3.5)
The area around the pipe penetrations is well ventilated and is classified as Zone 2 NE as is the
general digester roof area. The inside of the biogas pipework is above the UEL for methane and is
not classified. The area around the biogas pipe is well ventilated and is classified as Zone 2 NE
(Reference 2 Table 1).
An explosive vapour atmosphere may be formed by a release from the Pressure Relief Valves on
each of the digesters. The PRV is a low pressure relief with a Zone 2 sphere of 3m diameter around
the PRV with a Zone 1 sphere of 1m radius at PRV. (Reference 4 Para 3.5)
The effluent chamber contains active digestate, the aeration of the digestate will cause the release
of entrained biogas and the oxygen will cause the methanogens to cease activity. However there
will be residual biogas released in the headspace of the effluent chamber which will classified as
Zone 1 (Reference 2 Para 5.4).
There will also be a Zone 1 around the opening of the effluent chamber extending for a radius of
0.5m (Reference 2 Para 7.4).
An explosive atmosphere will not normally occur around digestate sample or drain points because of
a) the small volume of digestate released and b) on contact with air the biologically active species
die and stop producing biogas.
The concentration of H2S in the raw biogas is up to 2000ppm, this is significantly below the LEL of
40,000ppm and therefore H2S is not considered as a potential source of hazardous areas.
submersible propeller mixers. The slurry is pumped in and out through pipes entering the base of
the storage. Gas is collected from take-off connections in the roof. There is a biogas over pressure
relief valve mounted at ground level.
There will be a Zone 2 NE around any flanged or screwed joint (including gas purge points and
instrument connections).
5.9 CHP
5.9.1 Operation
The CHP is a package unit consisting of a containerised CHP and gas pre-treatment. The pre-
treatment consists of a chiller unit to remove condensate and a carbon scrubber to remove H2S. The
container holds the gas booster, gas control valves, spark ignition gas engine, generator, lubrication
oil tanks, ventilation fan, distribution panel and control panel.
The chiller and scrubber pipework is flanged pipework located externally and freely ventilated and
therefore is classified as Zone 2 NE. Sections of the pipework are insulated and the area under the
insulation is classified as Zone 2.
The lubrication oil is stored in a day tank within the CHP container where the temperature is below
the flashpoint. Oil mists could be released from a leak in the circulating oil pipework. Lubrication oil
falls into Release Category III which has been shown (HSL Report rr1107 Area Classification of Oil
Mists) to have little or no ignition risk therefore no hazardous area is associated with the lubrication
oil.
5.10 Flare
5.10.1 Operation
The flare is a package unit by Flare Products designed to burn up to 1000m 3/h of biogas when there
is surplus gas. It is designed to burn all of the biogas.
The boiler is installed in the main building. The natural gas is supplied by steel pipe at a nominal
100mbar to the boiler area. A gas booster located close to the burner raises the pressure by 45mbar.
The boiler area within the building is provided with ventilation from wall louvres.
The boiler is fitted with twin safety shut off valves and valve proving system which verifies the valves
before starting the ignition process.
The gas supply pipework within the building is not confined (not within 1m of 3 surfaces)
Treated biogas is compressed to 8bar and passed through membrane filters to remove carbon
dioxide which is vented at high level. The resultant biomethane is cooled to around 30°C and
transferred to the Grid Entry Unit through a short length of above ground pipe.
There are also high level vents for sample gas and biomethane pressure relief valves.
above 5.8 metres extending 7 metres in diameter and above 7.38 metres extending 10 metres in
diameter.
The container plant room is classified Zone 2.
The propane is stored in 6no 2tonne vessels. Liquid propane is pumped through an underground
pipe to a vapouriser in the GEU
The lines are operated at a maximum pressure of 15mbar (the release pressure of the digester over-
pressure valve). The drain lines run under gravity and discharge below low water level which
provides a water seal against the operating pressure of the gas lines.
When the collected condensate reaches the overflow level it flows by gravity to the process sump.
The overflow drain incorporates a water seal to separate the interior of the condensate sump from
the process sump.
Under normal operating conditions the biogas will be contained within the condensate pipes by the
water seal. However there could be biogas in the headspace of the condensate sump which will
therefore be classified as Zone 1 (Reference 2 Para 5.4).
There will also be a Zone 1 around the top of the condensate sump extending for a radius of 0.5m
(Reference 2 Para 7.4).
Flammable
No. Source of Release Area Materials fluid Ventilation Zone Type Zone Extent Comments
Working Type,
Temp °C degree,
& Pressure availability
4. Digester Gas Mixing Main Building Biogas 40°C Natural Zone 2 NE within plant room High and low level
500mbar Medium ventilation provided
Good to meet “More than
adequate” criteria
Zone 2 NE around drain valves Must be capped or
plugged
5. Ammonia Stripper Process Area Ammonia 65°C Natural Non-hazardous Ammonia & Biogas
Biogas Medium concentration below
Good LEL
6. Ammonia Stripper Process Area Ammonia 65°C Natural Non-hazardous Ammonia & Biogas
Biogas Medium concentration below
Good LEL
7. Gas Storage Lagoon Biogas Ambient Temp Mechanical Unclassified Storage headspace Space is above UEL
(Combibag) 1mbar Medium Zone 2 Between inner & outer
Good roof membranes.
Flammable
No. Source of Release Area Materials fluid Ventilation Zone Type Zone Extent Comments
Working Type,
Temp °C degree,
& Pressure availability
Transfer
9. CHP and gas pre- Plant Area Biogas Ambient Temp Natural Zone 2 NE around gas
treatment 5mb Medium treatment area
Good Zone 2 Below pipe insulation
12. Biomethane Plant Area Biogas Ambient Natural Zone 2 1m around gas pre-
Upgrade Unit 5mb Medium treatment equipment Refer to supplier’s
to Good and container HAC
8bar Zone 1 11m radius at 7.3m
Methane high around vent
Zone 2 7m radius at 5.8m high
and 10m radius at 7.3m
13. Grid Entry Unit Plant Area Methane 35°C Natural Zone 1 In equipment rooms Refer to supplier’s
Flammable
No. Source of Release Area Materials fluid Ventilation Zone Type Zone Extent Comments
Working Type,
Temp °C degree,
& Pressure availability
2bar Medium Zone 1 0.5 around container HAC
Good vents
Zone 2 3m around container
vents
Zone 1 5m radius at 2.25m
around high level vents.
Zone 2 NE around external
pipework.
14. Propane System Propane compound Propane Ambient Temp Natural Zone 1 1m radius around tank Within compound
12bar Medium vents and pumps
Good Zone 2 1m radius around pipe Refer to supplier’s
joints HAC
15. Condensate Sump Digester Biogas Ambient Temp Natural Zone 1 Within sump and 0.5m
5mbar Medium around top of sump
Good
7 CONCLUSIONS
1. All new equipment for use in the hazardous areas should comply with the following ratings:
Temperature Class T1 and Gas Group IIA based on the methane as the potential
explosive source.
All equipment located in hazardous areas should be suitable for use in the given
classification; all new equipment to be ATEX rated.
2. ATEX requires an inventory of all equipment located within the hazardous areas.
3. DSEAR/ATEX requires that formal inspections are carried out on all equipment installed
within hazardous areas in line with BS EN 60079-17. Following the creation of a suitable
database, inspection schedules should be created and formal inspections be carried out by
suitably trained personnel. Any faults discovered during the inspections, will require logging
and the corrective actions will require prioritising and planning, prior to re-inspection. All
equipment within the hazardous areas will require re-inspection at a maximum interval of 3
years.
4. The hazardous area classification is based on the design at time of preparation, if the design
is updated this report and accompanying drawings should be updated.
5. If new projects are implemented the hazardous area classification should be revisited. This
report and accompanying drawings should be updated as required.
6. Restrictions on ignition capable personal equipment, i.e. Mobile phones, car key fobs,
pocket calculators, torches, cigarette lighters/matches etc., should be put in place for people
who access any of the hazardous areas.
7. Information relating to the site’s hazardous areas and the required precautions should be
conveyed to visitors, contractors and staff through site information points, and via site
inductions.
8. Signage should be installed adjacent to hazardous areas to inform personnel of the extent of
these areas.
9. If any of the feeds to the process or other products are shown to be flammable then the
area classification will need to be reviewed and updated.
10. The operator should implement rigorous operating and maintenance systems. This should
ensure that adequate and regular inspection and maintenance activities are defined and
executed by trained and competent personnel. Moreover the operator should also ensure
that their management systems monitors the operating, inspection and maintenance
activities and ensures active management intervention if these are missed or curtailed.
8 REFERENCES
1. BS EN 60079-10-1:2009 Explosive atmospheres – Part 10-1: Classification of areas –
Explosive gas atmospheres
2. Institution of Gas Engineers; Hazardous Area Classification of Natural Gas Installations;
IGEM/SR/25 Edition 2; Communication 1748
3. BS EN 60079-20-1:2010 Material characteristics for gas and vapour classification — Test
methods and data
4. Safety Standards for Agricultural Biogas Installations. Bundesverband der
landwirtschaftlichen Berufsgenossenschaften e.V. Germany
5. Institute of Petroleum; Area classification code for installations handling flammable fluids,
Model Code of Safe Practice, Part 15, 3rd Edition; July 2005; Energy Institute (Inst
Petroleum).
6. 191012-PID-001 to 020 Revision 7 - Plant Piping & Instrumentation Diagrams
Green Create W2V Kent Biomethane Plant – Hazardous Areas LUT-211-001 Sheet 1 revB
Green Create W2V Kent Biomethane Plant – Hazardous Areas LUT-211-001 Sheet 2 revB
Green Create W2V Kent Biomethane Plant – Hazardous Areas LUT-211-001 Sheet 3 revB
Green Create W2V Kent Biomethane Plant – Hazardous Areas LUT-211-001 Sheet 4 revB
Green Create W2V Kent Biomethane Plant – Hazardous Areas LUT-211-001 Sheet 5 revB
Green Create W2V Kent Biomethane Plant – Hazardous Areas LUT-211-001 Sheet 6 revB
Release Rate: The rate at which a material is released affects the size of flammable zone generated.
Release Temperature: The temperature at which a material is released may affect the behaviour of
the release in terms of its buoyancy and the potential for condensation as well as vaporisation rate
of a liquid pool.
Ventilation: The amount and availability of ventilation affect the size and frequency of occurrence of
a flammable mixture. This is of importance where the release occurs inside a room or building. The
presence of ventilation has a major effect on the size of the flammable zone. For outside locations or
in open plant structures the ventilation is classified as “natural” and therefore has 100% availability.
Flammability Limits: Gases and dusts are only flammable over a limited range of compositions. The
limits are known as the upper and lower flammability or explosive limits and are specified under the
conditions that they have been measured. For common materials they are generally stated as being
in air at 25°C but may also be specified under other conditions.
The flammability limits affect the potential size of zone formed. These limits may vary widely
depending on the material. Limits also vary with temperature and pressure, generally increasing as
pressure and temperature increase. The effect is limited at conditions close to atmospheric pressure
and ambient temperatures and therefore tends only to be significant inside pressure vessels.
Minimum Ignition Energy: The minimum ignition energy is a measure of how easy a particular
flammable mixture is to ignite by a spark or flame. The lower the MIE, the easier it is to ignite the
material. This is taken into account by the “Gas Group” of the area classification.
This applies equally to dusts, where MIE is generally used to specify the level of precautions needed
for control of electrostatic ignition sources.
Auto Ignition Temperature: The Auto Ignition Temperature is a measure of how easy it is to ignite a
mixture without the presence of a flame e.g. from a hot surface such as a motor casing. This is taken
into account in the “Temperature Classification” of the equipment. AIT for gases is normally
measured in glass equipment and may be less with other materials e.g. steel. Hence a safety factor
of 2/3 is normally applied.
Layer Ignition Temperature: For dusts, the Layer Ignition Temperature is a measure of the ease of
ignition for a layer of the material on a flat, hot surface and is the temperature at which smouldering
or combustion occurs. Generally the LIT decreases as the layer thickness increases. Standard tests
are carried out in the EU with a 5mm thick layer.
Conductivity: For dusts and non-conductive liquids conductivity is a measure of the potential for the
material to become charged and thus cause a static electricity ignition hazard. This may also be
expressed as Relaxation Time i.e. the time taken for a charge to dissipate.
Location: The location of a release is important in terms of the grade of the release. A release in a
confined area e.g. a pit or other poorly ventilated area may result in a higher grade of release than
one occurring outdoors.
The ignition energy or “Gas Group” relates to the potential ignition energy of the equipment in
terms of spark energy. This is important to ensure that electrical equipment is safe for use with
various gases. Gases are grouped into three categories based MIC (Minimum Ignition Current) or
MESG (Maximum Experimental Safe Gap), which are defined below.
MESG – Maximum gap between the two parts of the interior chamber which under test conditions
prevents ignition of the external gas mixture through a 25mm long flame path when the internal
mixture is ignited for all concentrations of the tested gas or vapour in air.
MIC – Minimum current in resistive or inductive circuits that causes the ignition of the explosive test
Zone 20 IP6X
Zone 21 IP6X
Zone 22 Non-conductive dusts IP5X
Conductive dusts IP6X
12 APPENDIX D: CALCULATIONS
ITEM Nsn Nsa f(i) Tmax Tactual Tsn Tsa Nsn.f(i).Tsn Nsa.f(i).Tsa TABLE 7
flex pipes and bellow in Adverse 0 4 0.01 2 2 0.167 0.167 0.0000 0.0067
Regulator diagphragm 0 0.005 4 2 0.167 0.167 0.0000 0.0000 Sum Nx.f(i).Tx X
Rising stem valve 8 0.005 4 2 0.167 0.167 0.0067 0.0000 <0.001 1
Rotating stem valve 40 0.001 6 2 0.167 0.167 0.0067 0.0000 <0.01 2
Screwed union 0 0.001 6 2 0.167 0.167 0.0000 0.0000 <0.05 3
Screwed fitting, sealed 16 8 0.0008 6 2 0.167 0.167 0.0021 0.0011 <0.1 4
Flange, flexible pipes in Normal 108 8 0.0005 6 2 0.167 0.167 0.0090 0.0007 >0.1 Z1
. >1 Z0
Sum Nx.f(i).Tx 0.0245 0.0084
From Table 7 Xn = 3
Xa = 2
Calculate release rate under adverse conditions at 5mb and 500mb. – IGEM/SR/25 Cl 5.2.2.2
Calculate release rate under normal conditions at 5mb and 500mb. – IGEM/SR/25 Cl 5.2.2.2
Buoyancy Driven
Area of ventilation A 11.4 m2
-0.5 2
More than Adequate A> 7762xGxL 3.63 m Gas Release in kg/s G 0.000826 kg/s
Distance between louvre centres L 3.113 m
Adequate A> 1964xGxL-0.5 0.92 m
2
Height of enclosure H1 3.866 m
Hourly mean windspeed U10-50 4.25 m/s p59 SR25
-0.5 2
Inadequate A< 1964xGxL 0.92 m
For Nat Gas lower area of Bouyancy or Wind Driven is sufficent
-0.5 2
Poor A> 694xGxL 0.32 m For Biogas Wind Driven is preferable if SG is close to 1
Wind Driven
Required free area of ventilation on 2 walls is 10.05m2 which is greater than 11.4m2 of proposed louvres.
Therefore area is classified as Zone 2 NE.