Qap Tata
Qap Tata
Bare Dia.
Measure By micrometer
Covered Dia.
5 % of bobin (min.) Conducter Inspection Register 0 defects
No. of Covering
Visually Check
Covering Style
Conductor as per IS 7404
2 Conductor(Wire) Weight by Weighing Test Report P V V
Quantity/Weight 100% Stock Register As per PO (Copper) & IS: 6162 (Aluminium)
Scale
Test Certificate Visually Check Every Certificate Certificate Each certificate
check with microohm
Resistity 1 Piece Conducter Inspection Register 0 defects
meter
Bare Dia.
Measure By micrometer
Covered Dia.
5 % of bobin (min.) Conducter Inspection Register 0 defects
No. of Covering
Visually Check
Covering Style
Conductor as per IS 7404
3 Conductor (Strip) Weight by Weighing Test Report P V V
Quantity/Weight 100% Stock Register As per PO (Copper) & IS: 6162 (Aluminium)
Scale
Test Certificate Visually Check Every Certificate Certificate Each certificate
check with microohm
Resistity 1 Piece Conducter Inspection Register 0 defects
meter
LEGEND :
P - PERFOM
M - MANUFACTURER- V - VERIFICATION
C - CONTRACTOR W - WITNESSING
TPI-Third Party Implementing Agency
M C TPI/ Client
BDV Value BDV Test 1 Sample from each supply Oil Inspection File Avg. BDV Should greater than 60 KV
Transformer Oil Test Certificate Each Certificate Test Certificate 0 defects Test Report P V V
Quantity/Weight Quantity/Weight 100% Stock Register 1% of total weight
4 Oil As per IS:335 & Porclain item
Brocken Edges Visually Check do as per IS: 3347
Each Lot
Porcelain Items Quantity Manually Check Stock Register
Test Certificate Visually Check Each Certificate Test Certificate 0 defects Test Report P V V
Fitness
Breather Visually Check Each Lot do 0 defects Register P V V
Silicagel Colour
Dial Type
Fitness Visually Check Each Piece
Thermometer, Inpection Register 0 defects TC P V V
OTI,WTI & CT
TC Certificate Each Certificate
LEGEND :
P - PERFOM
M - MANUFACTURER- V - VERIFICATION
C - CONTRACTOR W - WITNESSING
TPI-Third Party Implementing Agency
M C TPI/ Client
Corner Length
Fin Width
Pressed Steel NO. of fins
7 Visually Check Each Piece Incoming material inspection register 0 defects Test Report P V V Against PO & Drawings
Radiatorr Fitting & Location
Inspection Report/TC
Outside Painting
Inside varnish
Stack Width
Measure by Tap Scale Register P V V
9 Core Assembly Core Dia. 5 Piece of each lot Incoming material inspecion register 0 defects Against PO & Core Drawigns
& Outer Dia.caliper
Window Height
Limp Center
LEGEND :
P - PERFOM
M - MANUFACTURER- V - VERIFICATION
C - CONTRACTOR W - WITNESSING
TPI-Third Party Implementing Agency
M C TPI/ Client
B Inprocess Inspection
In-Process
4 Oil Filtration BDV BDV Test Each Usage Oil Inspection File Avg. BDV Should greater than 60 KV P V V 60 KV min.
Register
M C TPI/ Client
C Final Inspection / Testing
LEGEND :
P - PERFOM
M - MANUFACTURER- V - VERIFICATION
C - CONTRACTOR W - WITNESSING
TPI-Third Party Implementing Agency