Creating Shared Value in The Mining Industry - Rev 3
Creating Shared Value in The Mining Industry - Rev 3
chain in optimising
coal mine
development
CLIENT
• Study Management
• Resource Geology
• Mine Design
• Ore Characterisation / GeoMetTM
• Process (flow sheet) Design
• Infrastructure Design
• Minor/General Process Eng
• Major/Specialist Process Eng
• SD Consulting (SUSOPTM)
Provide: Provide:
• Ore Characterisation/GeoMetTM
• Study Management
• Process (flow sheet) Design
• Infrastructure Design
• Sustainable Development
• Minor/General Process Eng
Consulting via SUSOPTM
Sub-Consultants
3
What is Coal Mining?
Hogsback – International
Longwall News – 9 February
2012
4
How bad can it be?
Merrow 2011 5
Linear Approach to Mine Development
Declining grades
8
Increasing Remoteness and Challenging Geography
The “easy”
mines have all
been done.
9
Infrastructure now a critical cost driver
10
Show me the money!! High impact
Mission critical cost
but less
impacts
Mechanisms Rating Base Case Data Rating
quantifiable
Pit Integrity
Phasing Gaps
Opportunity Assessment
Financial model
Schedule
Impact
Best Practices Applied
Cut-off Dependability
High
5-35% NPV uplift
Stockpiling
plus improved
Blending
Software Tools Rating Sustainability
Processing
Strategic
Products Software
Logistics Scheduling
Capital
Impact
Risk and Sustainability Rating
Low
Uncertainty
Social Impact Asset today
Activity Based
Costing Environmental
Basic Advanced
Theory of Political
Constraints
Infrastructure Legend Best Practice Rating
Geo-metallurgy
Not Applied
Partial
11
Integrated
Linking infrastructure into mine planning
decisions
12
13
Case Study: Nickel Mine, Western Australia
14
Project Outcome - Optimised Case
15
Holistic Solutions – Key Metrics
• Time to market
• Reliability of supply
16
Role of Operational Analysis in Coal Mine
Development
(Simulation Modelling, Numerical Optimisation)
17
Simulation Modelling in Planning and Design
18
Numerical Optimisation of Coal Chain Concept
25 300
300
calculated!
Throughput (Mtpa)
200
Very long
150
Long
100
Medium
50
Short-Medium
19
Short
0
Haulage Distance (km)
19
PT Kaltim Prima Coal (KPC) project
(detailed simulation analysis)
20
Overview of Simulation model layout for the Tanjung
Bara Coal Terminal (TBCT)
Ship loading at
berths with ship
queue based on
Overland conveyors random arrivals
stacking to stockpiles 2 northern stockpile
lines or allows direct rows, with stacker,
loading stacker/reclaimers, and
stamlers
2 southern stockpile
rows, with stacker and
large reclaimers
Barging to offshore
trasnshipment
21
21
Comparison of expansion targets against
throughput capacity for all cases
target 1
Case 2 - Adds OLC-
400 02 and Stockpile line
3 Expansion
350 target 2
300
Required
250
by barge
200 Capacity
150
100
50
0
22
10.0 20.0 30.0 40.0 50.0 60.0 70.0
Loaded Throughput [Mtpa]
22
Example Animation
(Proposed Abbot Point Coal Terminal)
23
Time is Money – Operational Readiness Pays!
24
A Systematic Approach – from early planning
through to operational improvement
25
Good system optimisation (debottlenecking)
Let down by Operational lack of Readiness
26
Conclusions
27