Objective
The objective of this document is to identify potential risks for the Plant Pals operations launch
and the plans to mitigate those risks.
Executive Summary
We are expecting to launch the Plant Pals operations plan in few months. This includes training
protocols. See below for risks to this project, and the mitigation plan to address them:
A product vendor loses a Low Monitor the shipments closely for the first few
product shipment weeks after launch
A product vendor charges Medium Accept that this risk could happen and decrease
a higher rate than other areas of the budget
expected
Each delivery truck costs High Avoid risk altogether by switching to a different
$16,000 more than initially vendor with a lower quote
quoted
You cannot hire enough High Ensure that benefits and compensation
employees in time to train packages are fair before starting the hiring
them before launch process
Appendix:
Probability chart:
Probability
Qualitative Quantitative (if measurable)
Low Very low chance of risk occurring. Less than <10% chance of risk occurring.
Types of
Impact Low Medium High
Low financial impact, Medium financial impact, High financial impact,
costing the company $0- costing the company costing the company
Financial $14,000 $15,000-$29,000 $30,000 or more
Medium impact to project
Low impact to project operations, High impact to project
operations, causing with potential to delay operations,
delays of a few days to a project by a month or with potential to cause
Operational few weeks more project failure
Low impact to employee Medium impact to High impact to employee
attrition, with 5%+ of employee attrition, with attrition, with 50%+
employees quitting 25%+ of employees employees quitting
People quitting
Inherent Risk
Impact
Low Medium High
High Medium High High
Probability Medium Low Medium High
Low Low Low Medium