Calculation Note (R.C Work) Forklift

This document provides a summary of concrete works for a forklift project. It includes summaries for pedestals, foundations, slabs, walls, and miscellaneous items. Quantities and dimensions are provided for concrete, formwork, and reinforcement. Calculations are also shown for concrete quantities and formwork areas. Reinforcement is referenced to bar bending schedules. The document contains lists, summaries, and calculations for constructing the forklift concrete elements.

Uploaded by

Ukuy Taryana
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
42 views

Calculation Note (R.C Work) Forklift

This document provides a summary of concrete works for a forklift project. It includes summaries for pedestals, foundations, slabs, walls, and miscellaneous items. Quantities and dimensions are provided for concrete, formwork, and reinforcement. Calculations are also shown for concrete quantities and formwork areas. Reinforcement is referenced to bar bending schedules. The document contains lists, summaries, and calculations for constructing the forklift concrete elements.

Uploaded by

Ukuy Taryana
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

3.1 SUMMARY OF R.

C WORKS
[LINE PROJECT >> FORKLIFT]

3.1.1 SUMMARY SHEET[FORKLIFT]


[CONCRETE] [FORM]
DESCRIPTION DESIGN(M3) Q'ty A/A(%) CALCULATE(M3) Q'ty DESCRIPTION DESIGN(M2) Q'ty A/A(%) CALCULATE(M2) Q'ty

F'C=15MPA 10 10 FAIR FACED M2 123.00 123.00


F'C=24MPA 107.00 107.00 NORMAL FACED M2 53.262 53.262

TOTAL 117.00 TOTAL 176.262

[RE-INFORCEMENT]
S/D DESIGN(M) Q'ty WEIGHT OF UNIT(kg/m) INSTALL&FIT(Ton) A/A(%) CONSTRUCTION Q'ty(Ton) S/D DESIGN(M) Q'ty WEIGHT OF UNIT(kg/m) INSTALL&FIT(Ton) A/A(%) CONSTRUCTION Q'ty(Ton)

D10 0.56 3 H10 0.56 3


D12 0.887 3 H13 0.995 3
D16 1.56 3 H16 1.56 3
D19 2.25 3 H19 2.25 3
D20 2.47 3 H22 3.04 3
D25 3.98 3 H25 3.98 3
D29 5.04 3 H29 5.04 3
D32 6.23 3 H32 6.23 3
D35 7.51 3 H35 7.51 3
SUB-TOTAL SUB-TOTAL
TOTAL

ANALYSIS OF WORK
CONCRETE/GROSS AREA: 0.1 M3/M2 FORM/GROSS AREA: 0.61 M2/M2 REBAR/GROSS AREA: 20.69 KG/M2
FORM/CONCRETE: 5.94 M2/M3 REBAR/CONCRETE: 203.26 KG/M3

Page : 1
3.1.1.1 LIST SHEET[FORKLIFT]
FORKLIFT PEDESTAL
FLOOR MARK SHORT LENGTH LONG LENGTH HEIGHT SLAB THK.FDN THK. PLACE CONCRETE FORM LEAN REMARK Cal.Page

GF PEDESTAL P1 0.55 0.55 1.00 0.00 0.60 9 B A UP TO EL+1.400 1

GF PEDESTAL P2 0.10 0.55 1.00 0.00 0.50 7 B A UP TO EL+1.400 1

FORKLIFT FOUNDATION
FLOOR MARK SHORT LENGTH LONG LENGTH HEIGHT PLACE CONCRETE FORM LEAN REMARK Cal.Page

GF ZONE 1 13.55 14.55 0.60 1 B A LINE-500-DC-1-0321 1

GF PIT 1.00 3.80 0.30 1 B A LINE-500-DC-1-0323 1

FORKLIFT SLAB
FLOOR MARK SHORT LENGTH LONG LENGTH SHORT BEAM1 SHORT BEAM2 PLACE CONCRETE FORM LEAN REMARK Cal.Page

FORKLIFT WALL

FLOOR MARK LENGTH THICKNESS HEIGHT PLACE CONCRETE[INT.] CONCRETE[EXT.] FORM[INT.] REMARK Cal.Page

GF W1 36.13 0.15 1.00 1 B A A LINE-500-DC-0324 2

FORKLIFT MISC.
FLOOR MARK LENGTH THICKNESS HEIGHT PLACE CONCRETE FORM REMARK Cal.Page

GF SLOPE 1 5.75 0.40 0.00 1 B A EL+0.400 2

GF STOOP 2.00 0.50 0.00 4 B A EL+0.400 2

Legend
Form ; A : Fair Face, B : Normal Face

Concrete ; A : F'c=15MPA(Lean Con'C), B : F'c=24MPA(Structure Con'C), C : F'c=30MPA(Structure Con'C)

Page : 2
3.1.1.2 CALCULATION SHEET[FORKLIFT]
FORKLIFT PEDESTAL

MARK/FLOOR PLACE No.ROOM ITEM DESCRIPTION CALCULATION SUB-TOTAL


PEDESTAL P1 GROUND FLOOR 9 [REMARK] UP TO EL+1.400
Con'C F'C=24MPA (0.55*0.55)*1*9 = 2.72
FORM FAIR FACED FORM (0.55+0.55)*2*1*9 = 19.80
MAIN BAR REFFER TO BBS (BAR BENDING SCHEDULE)
HOOP
SUPPORT HOOP

PEDESTAL P2 GROUND FLOOR 7 [REMARK] UP TO EL+1.400


Con'C F'C=24MPA (0.4*0.55)*1*7 = 1.54
FORM FAIR FACED FORM (0.4+0.55)*2*1*7 = 13.30
MAIN BAR REFFER TO BBS (BAR BENDING SCHEDULE)
HOOP
SUPPORT HOOP

T Con'C F'C=15MPA F'C=24MPA D10 D13 D16 D19 D22 D25 D29 D32 D35
O 4.26 RE DWG NO.
T DWG NO. : -
A FAIR FACED NORMAL FACE BAR H10 H13 H16 H19 H22 H25 H29 H32 H35
L Form 33.10

FORKLIFT FOUNDATION

MARK/FLOOR PLACE No.ROOM ITEM DESCRIPTION CALCULATION SUB-TOTAL


ZONE 1 GROUND FLOOR 1 [REMARK] UP TO EL+0.400
Con'C F'C=24MPA (((4.675*11.950)*2*0.3))+((((13.550*14.550)-(4.675*11.95)*2)*0.6)))*1 = 84.77
FORM FAIR FACED FORM (13.55+14.55)*2*0.6*1 = 33.72
BITUMEN ((13.550*0.4)*2)+((14.550*0.4)*2)*1 = 22.48
TOP BAR REFFER TO BBS (BAR BENDING SCHEDULE)
BOTTOM BAR
TENSILE JOINT
COM.JOINT
Top BAR
Center BAR
STIRRUP[END]
STIRRUP[CENTER]
PIT GROUND FLOOR 1 [REMARK] UP TO EL+0.400
Con'C F'C=24MPA (1*3.8)*0.3*1 = 1.14
Con'C F'C=24MPA (((1*3.8)-(0.5*3.3)*1.5)+(0.34*0.3)*0.5*0.4)*1 = 1.35
FORM FAIR FACED FORM ((1+3.8)*2*1.5)+(1.442+0.5)+(0.3+0.5)*4)*1 = 19.54
BITUMEN ((1*1.2)*2)+((3.8*1.2)*2)*1 = 11.52
TOP BAR REFFER TO BBS (BAR BENDING SCHEDULE)
TENSILE JOINT
COM.JOINT
Top BAR
Center BAR
STIRRUP[END]
STIRRUP[CENTER]

T F'C=15MPA F'C=24MPA BITUMEN D10 D13 D16 D19 D22 D25 D29 D32 D35
Con'C
O 87.26 34.00 RE DWG NO.
T DWG NO. : -
A FAIR FACED NORMAL FACE BAR H10 H13 H16 H19 H22 H25 H29 H32 H35
L Form 53.26

FORKLIFT SLAB

MARK/FLOOR PLACE No.ROOM ITEM DESCRIPTION CALCULATION SUB-TOTAL


MPF3 GROUND FLOOR 1 [REMARK] UP TO EL+0.300
Con'C F'C=24MPA
FORM FAIR FACED FORM
TOP BAR[SHOR
BOTTOM BAR[S
TOP BAR[LONG
BOTTOM BAR[L
BUTT END
BUTT END

T Con'C F'C=15MPA F'C=24MPA D10 D12 D16 D19 D22 D25 D29 D32 D35
O RE DWG NO.
T DWG NO. : -
A FAIR FACED NORMAL FACE BAR H10 H13 H16 H19 H22 H25 H29 H32 H35
L Form

Page : 3
FORKLIFT WALL

MARK/FLOOR PLACE No.ROOM ITEM DESCRIPTION CALCULATION SUB-TOTAL


W1 GROUND FLOOR 1 [REMARK] UP TO EL+1.400
Con'C F'C=24MPA (0.15*36.13)*1*1 = 5.42
FORM FAIR FACED FORM (0.15+36.13)*2*1*1 = 72.56
FORM
VERTICAL BAR REFFER TO BBS (BAR BENDING SCHEDULE)

HOR.[INT.] B

HOR.[EXT.] B

CHAIR BAR
VERTICAL BAR

OPENING VERT
OPENING HORI
OPENING SLOP

T F'C=15MPA F'C=24MPA D10 D12 D16 D19 D22 D25 D29 D32 D35
Con'C
O 5.42 RE DWG NO. 2,476.72 110.00 197.60
T DWG NO. : -
A FAIR FACED NORMAL FACE BAR H10 H13 H16 H19 H22 H25 H29 H32 H35
L Form 72.56

FORKLIFT MISC.WORK

MARK/FLOOR PLACE No.ROOM ITEM DESCRIPTION CALCULATION SUB-TOTAL


SLOPE GROUND FLOOR 1 [REMARK] EL+0.300
Con'C F'C=24MPA ((2.014*5.75)*0.15))+(((2.4*5.75)-(0.4*5.75)*04))*1 = 6.34
FORM FAIR FACED FORM (2.4*5.75)2*0.4*1 = 11.04
TOP BAR[LONG
BOTTOM BAR[L REFFER TO BBS (BAR BENDING SCHEDULE)
TOP BAR[SHOR
BOTTOM BAR[SHORT SPAN]

STOOP GROUND FLOOR 2 [REMARK] EL+0.300


Con'C F'C=24MPA (((0.925*2)*0.15))+(((1.2*2)-(0.925*2)*0.5))*2 = 3.23
FORM FAIR FACED FORM (1.2+2)2*0.5*2 = 6.40
TOP BAR[LONG
BOTTOM BAR[L
TOP BAR[SHOR
BOTTOM BAR[S

PARAPET [REMARK] EL+0.300


Con'C F'C=24MPA
FORM FAIR FACED FORM
TOP BAR[LONG
BOTTOM BAR[L
TOP BAR[SHOR
BOTTOM BAR[S

T F'C=15MPA F'C=24MPA D10 D13 D16 D19 D22 D25 D29 D32 D35
Con'C
O 9.56 RE DWG NO.
T DWG NO. : -
A FAIR FACED NORMAL FACE BAR H10 H13 H16 H19 H22 H25 H29 H32 H35
L Form 17.44

Page : 4