02 Variable Load Problems
02 Variable Load Problems
• The ratio of minimum daily output to maximum daily output is between 0.5
to 0.8
– This ratio is even smaller for annual minimum to annual maximum
• Due to these variations, a certain percentage of power plant capacity
remains unused – frequently called the annual system capacity factor,
which is generally 60%
Electricity Demand and Power Plant Choice
and Operation
• Base level of demand is met with “baseload” generating units
which have low variable operating costs
– Baseload units can also meet some of the demand above the
base, and can reduce output when demand is unusually low
• The units do this by “ramping” generation up and down to meet
fluctuations in demand
25 25
20 20
Load in MW
Load in MW
15 15
10 10
5 5
0 0
12 4 8 12 16 20 24 0 4 8 12 16 20 24
Time of day Hours duration
Load curve Load duration curve
Load Duration Curve (LDC)
• The following points may be noted about the
LDC
– The LDC gives the data in a more
presentable form; in other words, it readily
shows the number of hours during which
the given load has prevailed
– The area under the LDC is equal to that of
the corresponding load curve
– The LDC can be extended to include any
period of time; the variation and distribution
of demand for an entire year can be
summarised in one curve – the annual load
duration curve
Load Duration Curve (LDC)
• When planning a power plant, the two basic parameters to
be decided are
– Total power output to be installed (kWinst)
– Size of the generating units
Straight-Line Depreciation
Power Plant Economics
• A certain price per units (kWh) is charged for all or any part of
block of each unit and for succeeding blocks of energy the
corresponding unit charges decrease
• It is expressed by the expression
– Y = E1Z1 + E2Z2 + E3Z3 + E4Z4 + ...
– where E1, E2, E3... are unit energy charges for energy blocks of
magnitude Z1, Z2, Z3,... respectively
Theory of Rates – Two Part Tariff (Hopkinson
Demand Rate)