Calculating The As Built Critical Path
Calculating The As Built Critical Path
Long International, Inc. • 10098 Whistling Elk Drive • Littleton, CO 80127-6109 U.S.A. • (303) 972-2443 • long-intl.com
Calculating the As-Built Critical Path
Andrew Avalon, P.E., PSP
Table of Contents
ABSTRACT.................................................................................................................................................. 1
1. INTRODUCTION................................................................................................................................ 1
2. VERIFYING THE ACCURACY OF THE AS-BUILT SCHEDULE ............................................ 1
3. CONVERTING AS-PLANNED LOGIC TO AS-BUILT LOGIC .................................................. 2
4. CREATING AN AS-BUILT CALCULATION SCHEDULE FOR EACH
SCHEDULE ANALYSIS WINDOW ................................................................................................. 8
5. THE DESTATUSING PROCEDURE ............................................................................................. 12
6. DRIVING PREDECESSOR LAG DETERMINATIONS ............................................................. 16
7. CALCULATING AS-BUILT CRITICAL PATHS AND NEAR-CRITICAL
PATHS AND REVIEWING FOR REASONABLENESS ............................................................. 19
8. CONCLUSION .................................................................................................................................. 20
REFERENCES .......................................................................................................................................... 21
List of Tables
Table 1 Actual Date Conditions and Corresponding Actions for Destatusing
Schedule Activities .................................................................................................................... 14
Table 2 Sample Driving Lag Calculations .............................................................................................. 18
List of Figures
Figure 1 Out-of-Sequence Logic Correction: Guideline No. 1 .................................................................. 3
Figure 2 Out-of-Sequence Logic Correction: Guideline No. 2 .................................................................. 4
Figure 3 Out-of-Sequence Logic Correction: Guideline No. 3 .................................................................. 5
Figure 4 Out-of-Sequence Logic Correction: Guideline No. 4 .................................................................. 6
Figure 5 Out-of-Sequence Logic Correction: Guideline No. 5 .................................................................. 7
Figure 6 As-Built Calculation Schedule Creation: Step 1 ....................................................................... 10
Figure 7 As-Built Calculation Schedule Creation: Step 2 ....................................................................... 11
Figure 8 As-Built Calculation Schedule Creation: Step 3 ....................................................................... 12
Figure 9 Activity Status Conditions for Destatusing Procedure .............................................................. 13
Table of Contents
(continued)
List of Equations
EQUATION 1: Finish-to-Start Lag Duration = Successor Start Date – Predecessor
Finish Date – 1 day......................................................................................................... 15
EQUATION 2: Start-to-Start Lag Duration = Successor Start Date – Predecessor
Start Date ........................................................................................................................ 15
EQUATION 3: Finish-to-Finish Lag Duration = Successor Finish Date – Predecessor
Finish Date ..................................................................................................................... 15
EQUATION 4: Start-to-Finish Lag Duration = Successor Finish Date – Predecessor
Start Date + 1 day........................................................................................................... 15
ABSTRACT
The as-built critical path of a project schedule can be determined by developing As-Built
Calculation Schedules for each relevant schedule analysis period. An As-Built Calculation
Schedule removes verified actual dates from the schedule and revises the activity and lag
durations to be equal to the actual durations. The creation of the As-Built Calculation Schedule
enables the CPM scheduling software to then calculate the as-built critical path. To properly
create an As-Built Calculation Schedule, it is necessary to determine the driving predecessor
relationships in the as-built schedule when there are multiple predecessors to an activity. If a
predecessor is not driving, the actual lag duration should be reduced to the originally planned lag
value to create float in the As-Built Calculation Schedule. If the determination of driving
predecessor relationships is not performed, all activities in the As-Built Calculation Schedule
would have zero total float and would be equally critical. This paper presents procedures to
ensure that the as-built driving lag values are determined objectively to avoid inconsistent or
subjective assessments in calculating the as-built critical path.
1. INTRODUCTION
The determination of the as-built critical path of a project is of great importance for the analysis
of schedule delay claims. It is commonly accepted by scheduling practitioners that the critical
path of a project is dynamic and may change over time such that the as-built critical path may be
different from the as-planned critical path. Many contracts require that the Contractor
demonstrate that the claimed delay events impacted the project completion date, which is driven
by the as-built critical path or longest path to completion. The calculation of the as-built critical
path is also essential for performing collapsed as-built or but-for schedule analyses as described
in AACE International Recommended Practice No. 29R-03 on Forensic Schedule Analysis,
Method Implementation Protocols 3.8 and 3.9, for modeled, subtractive delay analyses.
However, as acknowledged in RP No. 29R-03, Subsection 4.3.C, there presently is no consensus
among practitioners regarding a common set of logic rules for accurately determining the as-built
critical path because actual dates override float values. This paper presents proposed guidelines
for calculating the as-built critical path.
The calculation of the as-built critical path requires that an accurate as-built schedule first be
developed. To verify the reliability of the as-built schedule, contemporaneous project records
should be reviewed to confirm the accuracy of the actual dates. Any necessary corrections to
actual dates and progress percent complete values should be documented based on
contemporaneous project data such as daily reports, monthly progress reports, meeting minutes,
payment applications, drawing logs, submittal logs, superintendent logs, and progress
photographs. Source Validation Protocols 2.2 and 2.3 of AACE International Recommended
Practice No. 29R-03 on Forensic Schedule Analysis provide procedures for utilizing as-built
schedule source documentation to reconstruct, validate, and rectify as-built schedules and
schedule updates.
After the as-built schedule dates are validated and rectified, it is necessary to review the
reasonableness of the as-built schedule logic. Work activities may have been performed out-of-
sequence from the as-planned logic. Method Implementation Protocol 3.8.K.2 of AACE
International Recommended Practice No. 29R-03 on Forensic Schedule Analysis provides
procedures for converting as-planned logic to as-built logic. In some cases, the actual sequence
of work and the relationships between activities may be different from the planned sequence of
work and activity relationships. Therefore, the logic relationships between the activities in the
as-built schedule at the end of each window may be different from the planned logic
relationships at the start of the window. Accordingly, if the actual sequence of work indicates
that different logic relationships between activities are warranted, the schedule logic should be
adjusted to represent the as-built conditions and the logic revisions should be documented.
Activities that have out-of-sequence logic with long negative lag values that were completed or
were in-progress within each schedule analysis window should be identified. Guidelines for
correcting out-of-sequence logic with long negative lags are detailed in the following paragraphs.
Often large negative lag relationships may exist in the as-built schedule that stem from the
as-planned schedule logic. To more accurately model the actual work sequences in each
schedule analysis window, adjustments should be made to the as-built schedule logic to replace
out-of-sequence logic and large negative lag values (e.g., greater than 15 work days) with more
reasonable logic ties. While the Contractor’s original logic should be utilized wherever possible,
the following guidelines are recommended when analyzing and rectifying out-of-sequence logic
resulting from the as-built date conditions.
Guideline No. 1: If the as-built date conditions produced a long negative Finish-to-Start (FS)
relationship, where practical, change the long negative FS relationship to a short positive Start-
to-Start (SS) relationship, as shown below in Figure 1.
Guideline No. 2: If the as-built date conditions produced a long negative FS relationship and
Guideline No. 1 would produce a negative SS relationship, where practical, change the long
negative FS relationship to a short positive Finish-to-Finish (FF) relationship, as shown below
in Figure 2.
Guideline No. 3: If the as-built date conditions produced a long SS relationship and the as-built
conditions allow for a reasonable and shorter FS relationship, then, where practical, change the
long SS relationship to a short FS relationship. For example, a SS +35 day relationship between
two activities in the as-built condition could be changed to a FS +10 day relationship between the
same predecessor and successor activities, as shown below in Figure 3, Example A. In other
cases, a short negative FS lag may be more realistic for modeling actual work sequences than a
long SS lag, as shown below in Figure 3, Example B.
Guideline No. 4: If the as-built date conditions produced a long FF relationship and allow for a
reasonable FS tie, then, where practical, change the FF relationship to a FS relationship. For
example, a FF +55 day relationship between two activities in the as-built condition could be
changed to a FS +10 day relationship between the same predecessor and successor activities, as
shown below in Figure 4, Example A. If the as-built conditions would produce a long negative
FS relationship, for which the absolute value of the lag duration is greater than the positive FF
lag value, then the existing FF relationship should be retained, as shown below in Figure 4,
Example B.
Guideline No. 5. If the work activities were performed significantly out-of-sequence and the
as-built date conditions do not allow for a reasonable FS, SS, and/or FF tie, then remove the
inappropriate predecessor logic and replace the relationship with a different, more reasonable
predecessor activity relationship. To select a more reasonable predecessor activity to replace the
inappropriate predecessor, where practical, trace the network logic preceding the inappropriate
predecessor to identify a more appropriate predecessor earlier in the logic chain and then reapply
Guidelines 1 through 4 to determine the appropriate logic tie.
When converting the as-planned logic to the as-built logic, it is generally preferred to select logic
relationships with shorter lag durations rather than longer lag durations, based on a comparison
of the absolute values of the lag durations. Furthermore, physical work flow restraints driving
the actual design, procurement, construction, and commissioning activity sequences should
govern the rectification of the as-built logic. The purpose of the as-built logic rectification is to
realistically model the work sequence relationships for how the project was actually built.
When making the above as-built logic adjustments, it is necessary to identify and correct any
open-ends created while correcting the out-of-sequence logic. The logic should be checked in
the As-Built Calculation Schedule to ensure that no activities have open-ends. If new open-ends
are identified, appropriate logic ties should be added to close the open-ends.
Finally, if Primavera or similar software is used to develop the as-built schedule and the Progress
Override calculation mode is utilized, it may be necessary to identify and correct the logic for
any activities with effective open-ends due to Progress Override. The Progress Override
calculation mode ignores logic relationships and allows an activity with progress to continue
even if its predecessors have not finished. Based on the as-built dates and calculated progress
spanning a schedule window data date, some task activities may have effective open-ends due to
the Progress Override schedule calculation setting. When schedule activities are worked out-of-
sequence, the Progress Override feature nullifies the predecessor-to-successor logic for activities
that started out-of-sequence, and then allows the late finish dates for these activities to slip to the
completion date of the latest finishing activity for the project. This condition is not realistic or
reasonable and the resulting late dates and corresponding float values are incorrect. Therefore,
activities with effective open-ends due to the Progress Override calculation mode for each
analysis window should be identified and appropriate logic adjustments should be made to
eliminate the open-ends.
The specific logic modifications performed to correct any out-of-sequence logic or to close
effective open-ends in each schedule analysis window should be documented in conjunction with
rectifying the as-built logic. Any assumptions made and procedures followed while correcting
the as-built logic should be documented to ensure consistency and avoid subjectivity during the
rectification process.
After verifying the accuracy of the as-built schedule dates and correcting any out-of-sequence
as-built logic ties, an As-Built Calculation Schedule can be developed for each schedule analysis
window. A windows-based analysis is often preferred over a single analysis of the entire project
duration to better account for how the critical path changed over time. The purpose of the
As-Built Calculation Schedule is to calculate the as-built critical and near-critical paths and
as-built float values. The selection of the schedule analysis windows is typically based on the
availability of the schedule updates, key contractual events and issues, changes in the critical
path, and cost and time considerations.
In commonly used scheduling software, such as Primavera, actual dates override the schedule
logic and the actual start and finish dates of activities become fixed regardless of the logic when
actual dates are input to record as-built progress. Therefore, the as-built critical path and float
values, which can only be determined from the schedule logic, are not provided by the software
calculations for the work that was performed prior to the data date. The critical path and float
values are only displayed for work yet to be performed after the data date.
Figures 6, 7, and 8 below summarize three basic steps for creating an As-Built Calculation
Schedule. In Figure 6, Step 1 involves the identification of the as-built dates for the activities
within the schedule analysis window.
In Figure 7, Step 2 involves the calculation of the as-built activity and lag durations for the
activities within the schedule analysis window.
In Figure 8, Step 3, the actual dates are removed and the actual activity and lag durations and
percent complete values are input into the schedule such that the scheduling software calculates
the start and finish dates of the activities to be the same as the as-built start and finish dates. The
removal of the actual dates is referred to as destatusing the schedule.
The schedule is destatused by moving the data date in the As-Built Calculation Schedule from
the end of the schedule analysis window to the beginning of the schedule analysis window.
Figure 9 below presents the potential activity date conditions, where the schedule being analyzed
contains unfinished activities and the analysis period begins later than the Project Start date.
The actual date conditions and corresponding actions for destatusing schedule activities
occurring within each schedule analysis window are summarized in Table 1 below.
Table 1
Actual Date Conditions and Corresponding Actions for Destatusing Schedule Activities
All actual dates prior to the destatused data date are not changed and this portion of the schedule
remains statused with actual dates. All forecast dates after the end-of-window data date also
remained unchanged.
As noted in Table 1, the percent complete and remaining duration values need to be computed
for activities having the date conditions of Activities D and F. Source Validation Protocol
2.3.D.1.a of AACE International Recommended Practice No. 29R-03 on Forensic Schedule
Analysis discusses the “hindsight” method for calculating remaining durations based on actual
dates and durations. The computed percent complete and remaining duration values should be
input into the As-Built Calculation Schedule to maintain the as-built schedule activity start and
finish dates.
At this point in the development of the As-Built Calculation Schedule, the original and remaining
durations of all activities are correctly adjusted but the lag durations for each relationship have not
yet been adjusted to maintain the as-built schedule activity start and finish dates. The early dates
of the activities that have been converted from actual dates should match the as-built schedule
dates. The goal is to quantify the lag durations required to drive the original as-built schedule dates
and model this in the As-Built Calculation Schedule. Each predecessor relationship must be
reviewed for each activity that used to have an actual date but no longer does.
It is then necessary to compute the actual lag duration by converting the beginning date for the
lag into a workday number and the ending date for that lag into a second workday number
and subtracting the two workday values. The following formulas summarize the actual lag
duration calculations:
EQUATION 1:
Finish-to-Start Lag Duration = Successor Start Date – Predecessor Finish Date – 1 day
EQUATION 2:
EQUATION 3:
EQUATION 4:
Start-to-Finish Lag Duration = Successor Finish Date – Predecessor Start Date + 1 day
If using Primavera scheduling software calendar rules, the Activity Calendar for the predecessor
activity should be used in performing the conversion of an activity date to a workday number. If
the activity date is an Actual Start and falls on a non-workday, then the next higher workday is
used. If the activity date is an Actual Finish and the date falls on a non-workday, then the next
lower workday is used. The calculated actual lag durations are then input into the As-Built
Calculation Schedule.
After performing the actions in Table 1, the resulting As-Built Calculation Schedule will have a
new data date at the beginning of the schedule analysis window and the calculated start and
finish dates of each activity within the analysis period will be adjusted to match the actual
conditions shown in the as-built schedule.
The actual lag duration for each relationship within the schedule analysis window should be
calculated but it is not necessary to apply all of the actual lags to all relationships in the As-Built
Calculation Schedule. If all lags in the As-Built Calculation Schedule are converted into the
actual lags, the activity dates in the As-Built Calculation Schedule would be correct but all
activities would have zero Total Float and the entire schedule network would be on the as-built
critical path.
To determine the “driving” relationship, the shortest duration variance between the planned lag
and the actual lag for each predecessor to a successor should be calculated. In other words, it is
necessary to identify the predecessor tie that most probably caused the successor activity to start
or finish based on the “closest” predecessor to the successor activity with consideration for
planned lag durations. If the variance between the planned lag and the actual lag is negative,
then the relationship must become a driving relationship to maintain the correct as-built dates in
the As-Built Calculation Schedule. If multiple relationships have the equally shortest variance
between the planned (Contractor defined) lag and the actual lag, then all relationships with the
equally shortest variance are designated as driving relationships.
The actual lag should only be input for driving relationships and the non-driving lag durations
should be left as originally input in the Contractor’s plan. To ensure that the As-Built
Calculation Schedule driving lag values are determined objectively, and to avoid inconsistent or
subjective assessments in developing the as-built critical path, the following procedure is used:
2. If a successor activity has only one predecessor, then the actual lag value must
be used as the driving lag value to correctly calculate the successor activity
dates to correspond with the verified as-built schedule dates.
4. All actual negative lags must remain negative to retain the original dates in the
verified as-built schedule.
5. If a predecessor is not driving, then the actual lag duration should be reduced
to the planned lag value in the verified as-built schedule to create float in the
As-Built Calculation Schedule.
Table 2 below presents examples of driving lag duration calculations. Note that the smallest
value in the variance column for a group of predecessors determines which relationship is
driving. Negative variances are treated as being smaller or shorter than positive variances.
Rows in Table 2 are shaded in yellow for successor activities with multiple predecessors.
Table 2
Sample Driving Lag Calculations
In summary, when there are multiple predecessor activities to a successor activity, the
predecessor with the smallest variance between the actual lag and the planned lag should be used
as the driving predecessor and all other positive lags for predecessors to the same successor are
reset to the planned lag duration. All actual negative lags must remain negative to retain the
original dates in the original schedule.
If two or more predecessors to an activity are equally driving, meaning that they have equal
variances between the actual lag and planned lag, then assign the required lag durations to each
predecessor such that they equally drive the successor activity dates. If a predecessor is not
driving, reduce the actual lag duration to the planned lag value to create float in the As-Built
Calculation Schedule.
After the driving predecessor relationships are determined and input into the As-Built
Calculation Schedule, the schedule is recalculated to determine the float values and as-built
critical and near-critical paths for activities that were completed or were in-progress during
the window.
To ensure that the As-Built Calculation Schedule was developed properly, a variance analysis
should be performed for all activities by comparing the start and finish dates in the As-Built
Calculation Schedule to the verified as-built schedule to ensure that there are no date variances.
If date variances are found when performing this comparison, it is necessary to identify the date
inconsistencies and document the reasons for any acceptable variances. Date variances may
arise from activities having different calendars or when the as-built date falls on a non-work day
as defined by the schedule calendar.
Finally, the calculated critical and near critical paths from the data date at the start of the
window through Project Completion should be checked for reasonableness. Subsection 4.3.C
of AACE International Recommended Practice No. 29R-03 on Forensic Schedule Analysis
discusses questions to consider regarding whether activities on the as-built critical path are
reasonable, including:
• Was the work qualitatively significant to the overall project outcome based on
cost as well as the analyst’s judgment and experience?
Finally, if a delay to any as-built activity would have delayed the overall project completion date
by that same duration, it is reasonable to conclude that the activity was on the as-built critical path.
8. CONCLUSION
Calculating the as-built critical path involves: 1) verifying the accuracy of the as-built schedule
dates, 2) converting as-planned logic to as-built logic, 3) creating an As-Built Calculation
Schedule for each schedule analysis window, 4) destatusing the actual dates and replacing them
with actual activity and lag durations and percent complete values, 5) determining the driving
predecessor relationships, 6) calculating the as-built critical and near-critical paths, and
7) reviewing the calculated as-built critical path for reasonableness. The above steps are
performed prior to any delay analysis and should be performed in a consistent manner. Any
assumptions should be documented to minimize subjectivity. The schedule analyst’s judgment
and experience, however, will always be necessary to ensure the reasonableness of the as-built
critical path calculations.
REFERENCES
1 Hoshino, Kenji P., 2002 Slide presentation (No paper published), Catching the Elusive
As-Built Critical Path, 2002 AACE International Transactions, AACE International,
Morgantown, WV.
2 Winter, Ronald M., 2004, PS.02—Determining the Actual Critical Path, 2004 AACE
International Transactions, AACE International, Morgantown, WV.
3 Nagata PSP, Mark F., 2010, CDR.02—Which Critical Path: As-Planned, Contemporaneous,
or As-Built?, 2010 AACE International Transactions, AACE International, Morgantown, WV.
4 Livengood, CFCC, John C. and Jeffery L. Ottesen, PE CFCC PSP, 2010, CDR.06—The
As-Built Critical Path—Quest or Discovery?, 2010 AACE International Transactions, AACE
International, Morgantown, WV.
5 AACE International Recommended Practice No. 29R-03, Forensic Schedule Analysis, April
25, 2011 Revision, AACE International, Morgantown, WV.
Originally published by AACE International as Technical Paper PS.1691 in the 2014 AACE International Transactions.
Reprinted with the permission of AACE International, 1265 Suncrest Towne Centre Dr., Morgantown, WV 26505 USA
Telephone: +1 (304) 296-8444 Facsimile: +1 (304) 291-5728 Internet: https://web.aacei.org Email: [email protected]
© 2014 by AACE International; all rights reserved.