Lecture 4 Setting Out
Lecture 4 Setting Out
SETTING OUT
By:
Center of Studies for Surveying Science & Geomatics
FSPU
UiTM Perlis.
OBJECTIVES
Understand the roles of the various personnel involved in
setting out process
Understand the aims of setting out
Appreciate the good working practices that should be
undertaken in order that the aims of setting out can be
achieved
Understand the procedures required to ensure that the
horizontal and vertical control requirements of the setting
out operations can be met.
LECTURE CONTENTS
INTRODUCTION
PERSONNEL INVOLVED INSETTING OUT
AIMS OF SETTING OUT
TECHNIQUE TO ACHIEVE AIMS
PLANS/DRAWINGS IN SETTING OUT
GOOD WORKING PRACTICES
PRINCIPLES OF SETTING OUT
SETTING OUT BUILDINGS
QUESTION… FOR U TO PONDER
SETTING OUT IS …??
WHAT IS IT (THAT WE SET OUT)??
WHEN DO WE PERFORM SETTING OUT ???
WHAT DO WE NEED FOR SETTING OUT ??
DATA…?
INSTRUMENTS…?
LABOUR…?
INTRODUCTION
Setting out definition :
Setting out is the establishment of the marks and lines to define
the position and level of the elements for the construction work so
that works may proceed with reference to them.
This process may be contrasted with the purpose of Surveying which
determine by measurement the positions of existing features
Reverse surveying:
Begin with the plan and ends with the various elements of
particular engineering project correctly positioned in the
area.
Process of transferring data (dist., position, size n shape)
from plan→ ground
INTRODUCTION
As-built Plan
The drawing which shows all the alterations that have taken place
during the course of the works when the scheme completed
GOOD WORKING PRACTICES in SETTING
OUT
1. Keep careful records.
2. Adopt sensible filing procedures
3. Look after instruments and use them safely
4. Check the drawing
5. Walk the site
6. Fix the control points
7. Inspect the site regularly
8. Work to the programme
9. Work to the specifications
10. Maintain accuracy
11. Check the work
12. Communicate
SETTING OUT TECHNIQUE & DEVICES
These are horizontal control points and once they have been located,
they can be used with a positioning techniques to set out E,N
coordinates of the design points
1. Located throughout the site;so design points can be fixed from at least 2
& preferably 3 of them → work can be independently checked.
2. Must be set out to the specified accuracy.
Accuracy must be maintained throughout the control network
→ Achieved by establishing different levels of control based
on 1 of the fundamental tenets of surveying (working from the
whole to the part)
Example???
On some schemes, the same control points used in the
production of the site plan are used for setting out (they must
be resurveyed!)
Baselines
Reference Grids
Offset pegs
1) BASELINES
101 102
(2) Secondary site Baseline
control points on Subsidiary line
baseline established 1002
by bearing and
Design/
distance from 4 & 5
1001 Corner Point
1003
1004
Subsidiary offset lines can be set off at right angles from each end of the
baseline to fix two corners 201 & 202.
Once they have been pegged out, the horizontal length of 201-202 is
measured & checked against its designed value.
In some cases, the designer may specify a baseline that
runs between points on 2 existing buildings.
Design points are then set out from this line either by :
Offsetting at right angles
Measuring bearings/distances from points on the line.
4. Secondary
Control points (in grid system) - 2. Site Grid
Grid enable points to be
set up over a large area
3. Structural Grid
1. Survey Grid
Site Grid
points
3. Structural Grid
Offset Peg
Proposed
building
Corner Peg
7/6/2023
VERTICAL CONTROL TECHNIQUE
1) MASTER BENCH MARKS (MBM)
2) TEMPORARY BENCH MARKS (TBMs)
Vertical Control Techniques
Vertical control are points of known elevation
relative to some specified vertical datum must
be established on the site.
Examples:
7/6/2023
Whatever datum adopted, Master Bench
Mark (MBM) should be established :
To establish point of known Reduced Level near
to proposed scheme.
Known as transferred or Temporary Bench
Marks (TBM)
Any existing horizontal control stations can be
used as TBM.
Must be checked at regular interval and
clearly marked on a copy of site plan (with its
RL)
COORDINATE POSITIONING
TECHNIQUE
Coordinate Positioning Techniques
For setting out by coordinates to be possible, a control
network consisting a coordinated points (with heights) must
be establish on site.
Control Points
Baseline
7/6/2023
7/6/2023
Using total station, each corner would be established by
bearing & distance methods from points in the control
network.
If possible, each corner should be fixed from 2 control
points & checked from a 3rd.
The diagonals are checked & the nails repositioned on the
tops of the pegs as necessary.
SETTING OUT BUILDINGS
1ST STAGE
→ MARK ALL DESIGN POINTS
METHOD: BASELINE/GRID/OFFSET PEGS
COORDINATES
INSTRUMENTS: T.S/THEODOLITE+TAPE
GPS
2ND STAGE
→ CONTROL VERTICALITY OF STRUCTUTE(S)
METHOD: PLUMBOP/THEODOLITE/OPTICAL PLUMBING/LASER
INSTRUMENTS: PLUMBOP/THEODOLITE/OPTICAL PLUMET/LASER
THE VERTICALITY CONTROL
2nd stage :
a. Plumb-bob methods
b. Theodolite methods
c. Optical plumbing methods
d. Laser methods
Principle of Verticality
7/6/2023
1) PLUMBOP METHOD
7/6/2023
Structure’s beam verticality
can be checked and altered
using plumbop or spirit level.
7/6/2023
2) THEODOLITE METHODS
7/6/2023
3) OPTICAL PLUMBING METHOD
7/6/2023
Perspex target
Optical Plumbing
instrument
Ground stations
7/6/2023
Laser method for verticality
checks.
7/6/2023
Alignment laser and rotating
laser’s applications in
constructions.
7/6/2023
IN THE END, I KNOW
THAT SETTING OUT
IS….