Ceo P 800202
Ceo P 800202
Protection Guidelines
CEOP8002.02
CONTENTS
1.0 PURPOSE............................................................................................................................ 3
1.1 Role of Protection ........................................................................................................... 3
2.0 ACTIONS ............................................................................................................................. 4
2.1 Protection Design ........................................................................................................... 4
2.2 Protection General Requirements ................................................................................. 5
2.2.1 Protection Scheme Selection ..................................................................................... 5
2.2.2 Fault Clearance Times ............................................................................................... 5
2.2.3 Distribution Protection ................................................................................................ 5
2.2.4 Primary Protection ..................................................................................................... 6
2.2.5 Backup Protection...................................................................................................... 6
2.2.6 Alternative Network Arrangements............................................................................. 6
2.2.7 33kV distribution feeders and hybrid subtransmission networks ................................ 6
2.2.8 Bypass of Reclosers for Maintenance ........................................................................ 7
2.2.9 Distribution Transformers ........................................................................................... 7
2.2.10 Distribution Network Capacitor Banks ........................................................................ 7
2.3 Setting Philosophy – Distribution Schemes ................................................................. 8
2.3.1.1 Protection – Zone Substation - Distribution Feeders .................................................. 8
2.3.1.2 Feeder Overcurrent and Earth Fault Protection ......................................................... 8
2.3.1.3 Feeder Sensitive Earth Fault (SEF) Protection ........................................................ 11
2.3.1.4 Negative Phase Sequence (NPS) Protection ........................................................... 11
2.3.1.5 Protection Groups .................................................................................................... 13
2.3.1.6 Live Line Work Settings ........................................................................................... 13
2.3.1.7 Bushfire Protection Settings (Total Fire Ban Settings).............................................. 14
2.3.1.8 Shunt Capacitor Protection ...................................................................................... 15
2.3.2 Distribution Automatic Reclose ................................................................................ 15
2.3.2.1 Automatic Reclose Justification ............................................................................... 15
2.3.2.2 Automatic Reclose Attempts .................................................................................... 16
2.3.2.3 Reclaim Time ........................................................................................................... 16
2.3.3 Automatic Field Reclosers............................................................................................. 17
2.3.3.1 O/C, E/F and SEF Protection online Reclosers ........................................................ 17
2.3.3.2 Inrush Restraint ....................................................................................................... 17
2.3.3.3 Cold Load Pickup..................................................................................................... 17
2.3.3.4 Recloser Delayed Operation .................................................................................... 18
2.3.3.5 Coordination- Grading between ZS Relays, Reclosers and Recloser in Series ........ 18
2.3.3.6 Coordination between Recloser and Sectionaliser in Series .................................... 18
2.3.3.7 Coordination between Reclosers and Fuses in Series: ............................................ 18
2.3.3.8 Coordination between Fuses and Downstream Reclosers ....................................... 20
1.0 PURPOSE
This Operational Procedure sets out the general requirements for protection systems installed on
Essential Energy’s distribution system.
The guidelines in this document cover Essential Energy’s Distribution high voltage systems
(6.35kV, 6.6kV, 11kV, 22kV, 33kV, 12.7kV SWER, 19.1kV SWER).
In special cases both CEOP8002.01 and CEOP8002.02 should be referred to in order to determine
the most appropriate protection requirements. An example would be locations where a primary
distribution feeder may link zone substations or a hybrid feeder.
This document does not preclude the installation or maintenance of protection that exceeds the
requirements of this Procedural Guideline; or protection that does not completely meet the
requirements of this Procedural Guideline where special considerations exist. In cases where the
requirements of this guideline cannot be meet then this must be documented and approved by the
relevant Network Planning Manager.
While it is not possible to eliminate risk to personnel and livestock from power lines and equipment
energised at the voltages covered by this document, an important role of protection equipment is to
reduce the level of such risk to an acceptable minimum. Protection equipment should be designed
to detect and clear all faults on the high voltage system rapidly while maintaining supply to the
largest possible proportion of the electricity supply system in a manner that avoids (wherever
possible) danger to personnel or livestock or damage to equipment.
Whenever possible all faults shall be seen by a backup protection device as detailed within this
document, with the exception of network assets protected by fuses.
Protection schemes applied to Essential Energy’s high voltage distribution system are not normally
set to protect against overload conditions unless specifically required. To achieve this, the
protection scheme must be designed to:
• detect all faults (where possible) that can occur within the protected zone;
• clear the fault as quickly as practical;
• discriminate (isolate the minimum proportion of the system consistent with clearing the fault);
• protect EE network and equipment;
• be reliable (operate when it is required to); and
• be secure (not operate when it is not required to).
It is not always possible to achieve all these goals. In particular, the goals of reliability and security
can conflict. If all goals cannot be achieved, then the minimum requirement is that the protection
must detect and clear all faults.
HV Equipment must never be left energised without adequate protection. If in any instance the
normal protection equipment is out of service, the equipment must either:
• be de-energised; or
• be energised from a source that can provide adequate protection; or
• be provided with a backup or alternative temporary protection.
2.0 ACTIONS
Where practical, protection systems should be designed to achieve the following objectives:
• to detect all short circuit faults between phases and/or phase(s) and earth;
• to detect abnormal operating conditions which may lead to failure of the network or an unsafe
condition arising;
• To consider all reasonable network states including (but not limited to)
o System normal, minimum and maximum fault levels
o Alternative network switching configurations that are likely to occur
• to allow the primary system being protected to operate within its rated voltage range and carry
its rated normal and emergency load currents, without the protection system operating, failing
or being damaged;
• to disconnect the faulted part of the network from the rest of the system in the minimum
practical time in order to:
o minimise damage to the equipment and remainder of the network.
o minimise the probability of injury to personnel and livestock exposed to the faulty equipment
or to the faulted part of the network.
o minimise the probability or extent of damage to Essential Energy’s property or to other
person’s property as a result of the fault.
o minimise the extent and duration of interruption to supply as a result of the fault.
• to ensure compliant step and touch potentials on the faulted network in conjunction with the
earthing system
• to operate in a selective manner so that the minimum amount of the network is taken out of
service after a protection operation
• to be as reliable as possible, within cost-justifiable limits. To this end, duplicate or back-up
protection systems will be required in many situations
• to ensure that allowance is made for future growth in the network and changes in customer
load requirements.
Whilst consideration should always be given to meeting the protection device operating times in
Table 2, the justification must be financially viable based on the risk involved in not meeting these
protection device operating times.
Protection schemes applied should minimise voltage fluctuations experienced by other customers.
The use of instantaneous settings can assist with this aim.
2.2.4 Primary Protection
The Primary Protection scheme shall be ‘stand-alone’ protection designed for high reliability,
security, and discrimination. The role of this protection is to clear any fault in the fastest possible
time.
2.2.5 Backup Protection
Backup Protection shall be designed for reliability and security. The role of Backup Protection is to
be available if the Primary Protection is unavailable (due to repair or maintenance etc.) or fails to
operate. It shall then clear any fault in the protected zone in as short a time as is necessary.
2.2.6 Alternative Network Arrangements
When the network is not in its normal arrangement, the minimal protection requirements which
would need to be satisfied would be the backup protection requirements. This would require all
protective devices to protect assets in the primary zone with a minimum 1.5 operating factor. This
requirement is based on the understanding that generally the network would be in an abnormal
state as a result of a network constraint and would only occur for relatively short periods (hours to
days) for either planned or unplanned events while restoration/rectification work occurs.
When the alternative arrangement is used for extended periods (months or more) and regularly, for
example during high load periods, the protection scheme should be designed to consider these
arrangements as part of the normal operation of the network.
2.2.7 33kV distribution feeders and hybrid subtransmission networks
Essential Energy utilises 33kV as both a subtransmission and distribution voltage across its
network. In some circumstances a 33kV feeder can be a hybrid, supplying/ interconnecting Zone
Substations as well as supplying distribution customers via direct connection to the 33kV. Due to
these conditions’ responsibility for determination of protection setting’s/ applied philosophy can be
split between the Network Protection Group (applying CEOP8002.01) and Network Planning
(applying CEOP8002.02).
The definitions and responsibilities relating to these networks are.
33kV Subtransmission
Feeders which supply/ interconnect between electrical/ terminal stations and/ or zone substations
and have no distribution customers connected directly to them.
The Network Protection Group shall have responsibility for these feeders including any field
Reclosers that are installed.
33kV Distribution
Feeders which supply distribution customers only and do not supply and or interconnect electrical/
terminal stations and/ or zone substations.
Network Planning shall have responsibility for these feeders including any field Reclosers that are
installed. For distribution circuit breakers within zone substations on these feeders, these settings
must be agreed upon and applied by the Network Protection Group.
33kV Hybrid Feeders
Feeders which supply/ interconnect between electrical/ terminal stations and/ or zone substations
and have distribution customers connected directly to them.
Determination of appropriate settings needs to be agreed by both Network Protection Group and
Network Planning. Initiation of the studies can be from either group and will depend on the
motivation/project. This is to include all protection devices installed on these feeders, including
those not in the main feeder segment (tee’s and/or spur’s). Creating or modifying and sending of
PSAs and setting files for devices located within Zone Substations shall be the responsibility of the
Network Protection group. Creating or modifying and sending of PSAs and setting files for field
reclosers shall be the responsibility of Network Planning.
The majority of distribution transformers and SWER isolation transformers should be protected with
fuses as specified in the Essential Energy Policy Distribution Transformer Fusing CEOP5099.
Most distribution reactors are installed without specific protection, except for surge suppression
devices.
It is accepted practice to connect SWER reactors to existing rural substations (preferably non-
residential due to noise) using the same substation EDO fuse. This allows for easy detection of
faulty reactors or fuses blown by lightning, which might otherwise remain undetected as no
customer call would be received for a reactor site.
On SWER systems the general arrangement has an isolating transformer installed at the point
where the single wire separates from the two or three phase networks. The isolating transformer
will generally be protected by fuses installed on the primary side, which can be used to provide
backup protection for Reclosers installed on the secondary (SWER) side.
Linked out (Solid) fusing systems can be used where the cost to improve the protection of a linked-
out system does not add sufficient value after appraisal using CECG1140 Appraisal Value
Framework.
Distribution feeder protection settings applied to protection devices contained within Zone
Substations should be set in accordance with the philosophy covered in this policy
(CEOP8002.02). As the distribution circuit breakers are the point of common coupling between the
Distribution and Sub-transmission networks, these settings must be agreed upon and applied by
the Network Protection Group.
Where protection setting changes are required for a protection device within a Zone Substation, a
“Subtransmission Protection Design Request” (CEOF6186) shall be submitted to
[email protected]. Where the requested protection settings cannot be
accommodated due to coordination problems or protection relay limitations, protection settings
shall be jointly agreed upon.
• ensure coordination of the Zone Substation feeder protection with downstream distribution
reclosers, relays & fuses
• ensure that the Zone Substation primary distribution feeder protection settings offers adequate
primary fault coverage
• ensure that the Zone Substation primary distribution feeder protection settings offer adequate
backup fault coverage for the failure of downstream devices, protection bypasses, or alternate
network configurations
• ensuring compliance with CEOP8002.02
• provide fault levels within the distribution network to the Network Protection Group (for the
failure of the Zone Substation primary distribution feeder protection)
OVERCURRENT PICKUP
*Note: this margin may be increased for feeders where the backup requirements are met at higher
settings.
As an alternative to a permanent overcurrent setting above the cold load, the “Cold Load” multiplier
function available within some recloser controllers may be used to ensure the recloser can be
closed onto cold load. This function should only be used when absolutely necessary, refer to
section 2.3.4.3.
*Note: In the event that the above operating factor cannot be achieved without excessive and/or
uneconomic system redesign, then all of the following shall apply:
AND
The effect of minimum feeder load current should be used in the software calculation of the
minimum current seen by the relay for phase-phase faults. The ratio of this calculated minimum
current (including load) to primary relay current pickup should exceed 1.75.
AND
The impact of the installed embedded generation has been considered in the minimum load
current. Embedded generation may in some cases reduce the current flowing through the relay
during a fault and hence reduce the operating factor. If significant embedded generation exists on
the feeder downstream of the protective device, reduced operating factors should not be applied,
unless it can be confirmed by studies, that the protective device cannot be desensitised by the
embedded generation not tripping due to its anti-islanding features.
*Note: In the event that the above operating factor cannot be achieved without excessive and/or
uneconomic system redesign, then all of the following shall apply:
9 March 2020 – Original Issue
Approved By: Manager Asset Management
Next review date: March 2023
Page 9 of 27
UNCLASSIFIED UNCONTROLLED COPY IF PRINTED
Branch Procedure: Distribution Protection Guidelines
CEOP8002.02
UNCLASSIFIED
The feeder overcurrent relay pickup should be set higher than the downstream device(s)
overcurrent pickup. This requirement need not apply in instances where it can be justified that time
grading is still likely to exist between these devices for all practical fault situations.
AND
The impact of the installed embedded generation has been considered in the minimum load
current. Embedded generation may in some cases reduce the current flowing through the relay
during a fault and hence reduce the operating factor. If significant embedded generation exists on
the feeder downstream of the protective device, reduced operating factors should not be applied,
unless it can be confirmed by studies, that the protective device cannot be desensitised by the
embedded generation not tripping due to its anti-islanding features.
Overcurrent timing
The overcurrent element timing shall be set as such:
• Above all downstream devices for three phase, phase to phase and earth faults up to the
maximum fault levels present at the downstream device location.
• Below upstream devices, up to the maximum fault level that the feeder and upstream device
shall simultaneously see for a feeder fault.
• To protect any conductor within its Primary and Backup zone against thermal damage for fault
levels that may be experienced by it.
The Earth Fault pickup should be set to ensure the following Operating Factors are observed:
• for feeders with SEF protection – 2.0 (based on 0 Ohm fault resistance).
• below upstream devices, up to the maximum fault level that the feeder and upstream device
shall simultaneously see for a feeder earth fault; and
• to protect any conductor within its Primary and Backup zone (where required) against thermal
damage for fault levels that may be experienced by the conductor.
• SEF time delay: The SEF time delay shall have a maximum of 10seconds delay and a
minimum of 5 seconds. The recommended time grading margin is 1 second with a minimum of
0.5 seconds grading over downstream SEF relays.
*Note: In general, Sensitive Earth Fault Protection should not be applied to a feeder to which an
un-isolated single wire earth return (SWER) line is connected. SEF may be able to be applied to a
feeder with un-isolated SWER following an assessment of the peak standing EF current caused by
load and providing the SEF can be set with sufficient margin above this to prevent incorrect
operation of the SEF element. If SEF is applied to a feeder with un-isolated SWER, the definite
time delay must be no greater than 10 seconds.
Where negative phase sequence protection is available with a protective device, NPS protection
may be utilised to assist with phase to phase fault detection for both primary and backup
protection. However, it is necessary that 3 phase overcurrent protection is still utilised as per
clause 3.1.1 to ensure fault detection is provided for 3 phase fault conditions.
9 March 2020 – Original Issue
Approved By: Manager Asset Management
Next review date: March 2023
Page 11 of 27
UNCLASSIFIED UNCONTROLLED COPY IF PRINTED
Branch Procedure: Distribution Protection Guidelines
CEOP8002.02
UNCLASSIFIED
NPS pickup
The NPS should be set as follows:
• to be greater than 120% of the normal NPS standing current on the feeder due to phase load
imbalance. Consideration should be given to increased normal NPS standing current due to
load transfer from adjacent feeders, or temporary isolation of large single phase spurs; and
• to grade with downstream protection.
The NPS pickup should be set to ensure the following Operating Factors are observed:
Note: Consideration should be given to the effect of normal NPS standing current on the Operating
Factor. In particular, if phase load imbalance is such that a phase to phase fault results in a
reduced prospective NPS fault current due to the load imbalance, then the NPS pickup must be
reduced to achieve the required Operating Factor, e.g. if minimum prospective NPS fault current =
200 amps, and maximum normal NPS standing current = 20 amps, a reduced minimum NPS fault
current of 180 amps should be used. In this example a maximum NPS pickup of 90 amps should
be used for Primary Operating Factor.
NPS timing
The relay NPS timing shall be set as such:
The equivalent overcurrent and earthfault curve for the NPS curve grade with the downstream and
upstream protective devices, as follows:
• above all downstream devices for equivalent phase to phase and equivalent earth faults up to
the maximum fault levels present at the downstream device location; and
• below upstream devices, up to the maximum fault level that the feeder and upstream device
shall simultaneously see for a phase to phase fault.
The NPS equivalent overcurrent curve should coordinate with overcurrent curve to extend the
protection reach for phase to phase faults. The NPS curve and overcurrent curve may have a
crossover point for the protective device such that the NPS curve will detect the lower level faults,
and the overcurrent curve will detect the higher-level faults.
NPS IDMT curves
Where possible, IEC 60255 “SI” or “VI” curves are preferred. Other curves may be used where the
downstream protection does not suit the use of the preferred curves.
work. This is accepted to reduce the risk to staff and the network from the live line work and on the
understanding live line work would not occur during high fault risk times such as during storms.
Note 2- For SWER networks use the Overcurrent Live Line work settings above.
Note 3- Circuit Breakers/ Reclosers contained within Zone Substations supplying Distribution
Feeders may not have the capability to enable use of a Live Line setting.
During Total Fire Ban Day’s, the reclosers in the designated area will be automatically switched to
group 4 (D) settings and have auto reclose disabled. The proposed Group 4 (D) Overcurrent and
Earth Fault protection settings should be set as fast as practical to enable the fault to be cleared in
the minimum time while maintaining discrimination between reclosers. Grading margins can be
reduced to 100ms between electronic devices to assist in speeding up protection operation.
Discrimination between reclosers and fuses in the network may be compromised to allow faster
clearance times, particularly in fire prone areas. The Sensitive Earth Fault settings would keep the
same current values as the normal settings but have reduced time grading between devices. The
last recloser on each line section will be set at 1 second with every upstream recloser set at 0.5
seconds higher progressing back along the feeder towards the zone substation.
Note: it is acknowledged that the move to a defined bushfire setting group will occur over time in
conjunction with the recloser inspection cycle and that implementation of the bushfire settings may
not occur until Group 4 (D) settings have been installed in all communications equipped electronic
reclosers within a designated area. Initially, during Total Fire Ban Days, reclosers will have auto
reclose disabled only.
Fused capacitors - These banks usually consist of series and/or parallel combinations of individual
capacitor cans per phase. Each unit is protected by its own fuse. Operation of a single fuse does
not necessarily render the entire bank inoperative; however multiple failures can cause excess
voltages to be impressed on the remaining cans.
The type of fault covered by this type of protection is rarely, if ever transient in nature and often
may be a danger to the general public.
Sensitive earth fault protection shall not be used to initiate an automatic reclose operation.
Distribution feeders
For the purpose of automatic reclose, distribution feeders can be categorised into overhead or
underground types of feeders.
Overhead distribution feeders can be further categorised into the following groups:
• Urban overhead distribution feeders
Any overhead feeder that supplies predominantly urban areas, i.e. towns, villages etc
• Rural overhead distribution feeders
Any overhead feeder that supplies predominantly rural areas, i.e. farms, hamlets etc
• Industrial overhead distribution feeders
Any overhead feeder that supplies predominantly industrial areas, i.e. industrial parks etc.
Generally, these feeders are short, with limited exposure, but are subject to high vehicle/ plant
activity. For these reasons transient faults are not common and automatic reclose should, as a
preference, not be implemented. Use of auto reclose may be considered on a case by case
basis, where the network warrants it’s use. Where a feeder traverses a large section of rural
area which may be subject to transient faults, automatic reclose may be considered.
Underground distribution feeders
An underground distribution feeder is a feeder that is predominantly underground in construction; it
may have some small sections of overhead construction
Faults on underground feeders are usually not transient in nature; therefore, automatic reclose
shall not be implemented on underground distribution feeders.
9 March 2020 – Original Issue
Approved By: Manager Asset Management
Next review date: March 2023
Page 15 of 27
UNCLASSIFIED UNCONTROLLED COPY IF PRINTED
Branch Procedure: Distribution Protection Guidelines
CEOP8002.02
UNCLASSIFIED
The same principle detailed above should be applied to all field reclosers, however it is
acknowledged that some recloser types installed on the network cannot alter either their number of
reclose attempts or their dead times. These units are exempt from the requirements of 2.3.3.2,
however if the units are replaced, they shall be upgraded to a device type that can comply.
Reclaim time must in all cases be longer than the operating time of any protection that may initiate
an auto-reclose operation. (See 1 below).
Reclaim time settings must consider the mechanical limitations of the Recloser, CB and protection
relays, which include but are not limited to:
• switch operating mechanism reset and stabilise time, such as spring charge time required
to set up CB for a normal trip-close-trip sequence;
• thermal limits requiring cooling time between successive fault current incidents in
equipment; and
• time for electromechanical relays to reset.
Generally, a reclaim time of 30s is sufficient, however refer to Attachment A for Total Fault Clearing
Time calculations, methods and Terms.
1 This can be quite long for an Extremely Inverse IDMT overcurrent relay operating at about 150% of its nominal
setting.
An automatic recloser is a self-contained device with the necessary circuit intelligence to sense
overcurrents, to time and interrupt the overcurrents, and to reclose automatically to re-energize the
line. If the fault should be “permanent” the recloser will “lock open” after the pre-set number of
operations (usually one to three) and thus isolate the faulted section from the main part of the
system.
Modern automatic reclosers enjoy the feature that they can employ different curves for each
reclose attempt. If there are line section fuses downstream of the recloser it is beneficial to have at
least one fast shot to provide some protection for the fuses for a transient fault.
Reclosers Classifications
Automatic circuit reclosers are classified on the basis of single or three phases, Hydraulic;
Electronic or Microprocessor controls, Oil or vacuum interrupters.
Typical settings for this function are 4 x full load current with a time setting of 0.15 second.
How Cold Load pickup is applied can vary between recloser types, including when it becomes
enabled. It is important to understand the particular implementation in the recloser being set by
referring to the manufacturer’s literature.
If cold load pickup is implemented, then backup and primary operating factors need to be
maintained as per section 2.3.1.1 while cold load pickup is active.
Typical settings for this function are 1.5 - 2 x full load current and a time setting of 120 minutes
Dead times should take into account slow reset times of hydraulic reclosers and margins between
hydraulic devices should be increased with the number of reclose attempts.
Where fuse saving schemes are employed that use fast/slow curves upstream reclosing devices
shall have sequence control enabled.
*Note: 300ms is recommended, however this margin can reduce to 200ms if required. The
reduction should be applied to the devices affecting the least number of customers.
2.3.3.6 Coordination between Recloser and Sectionaliser in Series
Installation of a sectionaliser does not affect the operating factor required at the recloser.
2.3.3.7 Coordination between Reclosers and Fuses in Series:
Coordination will depend on the number of shots set on the recloser for the downstream fuses.
In rural areas where transient faults may be a problem, reclosers may be set to give at least one
fast trip, so if the fault is of a transient nature, it can be cleared without blowing the fuse and
interrupting supply.
For optimum coordination between a recloser and fuse, their characteristics should be such that
whilst all transient faults would be cleared by one or more fast recloser operations without the fuse
blowing, permanent faults would blow the fuse before the recloser reached the lockout condition.
This ideal is not always attainable for all faults values, yet a reasonable compromise can often be
achieved by examination of recloser and fuse characteristics where ideally the fuse characteristic
should fit between the instantaneous and the delay tripping for the recloser.
Where fast curves are employed on reclosers to protect fuses during transient faults, a minimum of
1.5 times operating factor should be used for fault detection.
For electronic reclosers the preferred fast trip is to use an Instantaneous setting. When using
instantaneous trips a minimum time (usually 0.1 sec) should be used to prevent unnecessary
spurious trips and provide protection stability e.g. from indirect lightning surges etc.
Where fuses are used to provide backup protection for a recloser a minimum operating factor of
3.0 times the fuse rating should be used for the backup fault coverage.
Consideration should be given to fuse element heating when coordinating with fuses, the grading
margin will decrease for source side fuses with subsequent recloses, an increased grading margin
and/or reclose times should be considered to ensure grading, the grading margin for load side
fuses will be increased by successive recloses.
It is common on isolated SWER systems, rural zone substations and other rural networks for fuses
to be the primary SWER isolation or zone substation transformer protection, with reclosers used to
clear faults on the downstream distribution network respectively.
The source side fuses will normally be rated to provide protection to the transformer and will
basically determine what the combination of recloser curves will be used, so that the fuse does not
interrupt the circuit for any fault current on the recloser. The recloser’s modified delayed curve
must be faster than the fuse’s minimum melt curve.
For the maximum available recloser fault current, the fuse minimum melting time must be greater
than the average clearing time of the recloser delayed curve, multiplied by a specific factor which
includes the impact of fuse heating (during the fault) and fuse cooling (during recloser deadtimes).
The impact of this factor is usually expressed as an adjusted recloser delay curve which is
coordinated with the fuse minimum-melting time curve. A tool to assist the calculation of this factor
is included in the Essential Energy Grading Spreadsheet. This tool should be used to ensure
correct coordination between the upstream fuse and downstream recloser.
In this scenario a fuse is being used to provide backup fault coverage for a Recloser.
A minimum operating factor of 3.0 times the fuse rating should be used when selecting fuses for
the primary protection zone. Where a fuse is required to provide backup fault coverage for a
downstream device (such as a Recloser) a minimum operating factor of 3.0 times the fuse rating
should also be used.
2.3.3.9 Basic Coordination Principles to be Observed
• The load-side device must clear permanent or temporary faults before the source side
device interrupts the circuit (fuse link) or operates to lockout (recloser)
• Outages caused by permanent faults must be restricted to the smallest section of the
distribution system.
These principles primarily influence the selection of curves and the sequences of operation of both
source side and load side devices, and the general location of these devices on the distribution
system.
Fuses are the most basic protection devices available for overcurrent protection on a distribution
system. Their primary function is to serve as inexpensive weak links in the circuit that open to clear
(interrupt) overcurrent and protect equipment against overload and short circuit. They can also be
used as line sectionalising.
Backup protection is not required for high voltage fuses. Where a fuse is required to provide
backup fault coverage for a downstream device (such as a Recloser) refer to sect 2.3.3.8
All fuses operate in the same way. A conductor of limited cross-section is heated by current
passing through it until it melts. This takes time, represented in time/current characteristics for the
fuse. On melting, a break is caused in the element, at which an electrical arc is established. The
arc burns in the fuse until the current returns to zero. Thus, there are two stages in fuse operation:
• The pre-arcing time (time/current characteristics)
• The arcing time.
The arcing behaviour is different for small, large and intermediate overcurrents.
The most common fuse type in use on the Essential Energy network are K type expulsive drop out
(EDO) type. A minimum operating factor of 3.0 times the fuse rating should be used when
selecting fuses. Note that fuse continuous rating is typically above nominal rating. Always check
the actual clearing time. For fuses other than K type refer to the manufacturer’s literature for
clearing characteristics
2.4 Generators
All Generation proposed for installation on Essential Energy’s Network shall be assessed on an
individual case basis considering the type of Generator proposed and the proposed location on the
network.
Reference should be made to the Generation Connection Protection guidelines CEOP8012 when
checking/applying protection for these systems.
The customer is to provide a protective system approved by Essential Energy to disconnect their
equipment from the supply in the event of a fault on their equipment:
• all protection settings shall provide suitable discrimination with Essential Energy’s system
protection.
• protection pickup values should be set to 120% of agreed transfer capacity.
• all protective equipment must be maintained to an industry recognised standard.
• Essential Energy’s is not required to provide backup protection to customer’s equipment
• fuses can be used as the connection point for customers <1MVA. For customers => 1MVA, a
recloser is to be used as the minimum connection point device to ensure that other Essential
Energy customers are not affected by faults in the HV customer’s network.
• if auto reclose is nominated for use refer to conditions in 2.3.3.2.
• minimum requirement would be OC, EF and SEF; and
• for UG networks use of an approved protection relay with a minimum of OC and EF. A self-
powered type relay is acceptable.
Summarise responsibilities allocated to employees (by job/position title) within the process
specified under Actions.
Head of Asset Management • Shall have overall responsibility for the content,
approval and maintenance of this Guideline.
Network Planning Manager and • shall be responsible for the implementation of this
Regional Planning Managers Guideline.
4.0 DEFINITIONS
Backup protection
Protection system that provides protection coverage on the network to back-up a protective device
that fails to operate or is out of service to the next downstream protective device.
EI
Extremely Inverse characteristic as defined in IEC 60255
Discrimination/ Grading
The coordination of non-unit protection by time
IDMT
Inverse Definite Minimum Time – A relay/ device operating characteristic that is inversely
proportional to the measured quantity, eg, as the current increases, the operating time decreases.
The definite minimum time varies between relay types, and typically occurs at 20 or 30 times the
relay pickup.
Operating Factor- Safety Margin
Fault level divided by the protection pickup value.
Maximum Fault level
Fault level with maximum (lowest impedance) network configuration.
Minimum Fault level
Fault level with weakest (highest impedance) network configuration.
Normal Fault level
Fault level with normal network configuration.
NPS
Negative Phase Sequence – an overcurrent protection where the operating quantity is the I2 or
Negative Phase Sequence current that is derived from the three phase quantities.
Operating Factor
The fault level divided by the pickup (setting value) with reference to an overcurrent, earth fault or
NPS relay.
Overcurrent
An overcurrent protection where the operating quantity is derived from any of the three phase
quantities.
Primary distribution feeder
a distribution line connecting a sub-transmission asset to either other distribution lines that are not
sub-transmission lines, or to distribution assets that are not sub-transmission assets. (from NER)
PSA
Protection Setting Advice
Primary protection
Protection system that provides protection coverage on the network to the next downstream
protective device.
SCADA
Supervisory Control and Data Acquisition.
SI
Standard Inverse characteristic as defined in IEC 60255
Sub-transmission
any part of the power system which operates to deliver electricity from the transmission system to
the distribution network and which may form part of the distribution network, including zone
substations.
Sub-transmission line
a power line connecting a sub-transmission asset to either the transmission system or another sub-
transmission asset. (from NER)
SWER
Single wire earth return.
NPS
Negative phase sequence.
SEF
Sensitive earth fault.
VI
Very Inverse characteristic as defined in IEC 60255
Zone Substation
A substation for the purpose of connecting a distribution network to a sub-transmission network
(from NER).
5.0 REFERENCES
Internal
External
ENA C(b)1-2006 : Guidelines for design and maintenance of overhead distribution and
transmission lines.
“Guide to the Application of Autoreclosing to Radial Overhead Lines Supplying Urban and Rural
Areas”, D (b) 12 1991, Electricity Supply Association of Australia.
6.0 RECORDKEEPING
The Essential Energy employees associated with protection shall be responsible for the recording,
storage and maintenance of all protection records. Details of all the current and historic settings,
tripping schemes, instrument transformer ratios, reclose times, configurations, software files,
firmware and software versions, calculations and analysis details etc of all transmission, sub-
transmission and distribution protection equipment and devices, should be stored. All Essential
Energy employees associated with planning, protection, control and maintenance should have
read access to PSAs
7.0 REVISIONS
Figure 1 and Figure 2 show the method of calculation of Total Clearing Time and clarify
some of the terms used.
Fault Detected
Trip Reclose Trip to Lockout
On
Off
Figure 2 Permanent Fault Sequence with Three Recloses when used in conjunction
with a sectionaliser
Fault Detected
Reclose Trip to Lockout
Trip Trip Reclose Trip Reclose
On
Off