Cost To Complete - Draft
Cost To Complete - Draft
Contract : Proposed Workshop Building Complex for Sri Lanka Ports Authority
Contract No: SLPA/ADB/OCB/PAEH/CW/04
Contractor : BEL-DGES
Period : 15th February 2022 to 30 th April 2022
Date of Commencement 09 th September 2021 Accepted contract Amount (Without VAT) RS 1,090,080,446.34
8 Add: Variations - - - -
Contract : Proposed Workshop Building Complex for Sri Lanka Ports Authority
Contract No: SLPA/ADB/OCB/PAEH/CW/04
Contractor : BEL-DGES
Period : 01 November 2022 to 30st November 2022
PAYMENT CERTIFICATE
IPA -07
Date of Submission 05th May 2022
A Total Contract Price (Without VAT) 1,090,080,446.36
D Variations/Claims -
Less:
a. Cumulative Retention Money ( 10% of (C + D + E) until max 5% of A ) 24,926,183.99
Prepared By: M.A Thilini Bhagya Checked By: Lasanath Dadallage Certified by :
Intended Date of Completion : 09 th June 2022 Advance Payment Amount Rs. : 215,094,929.27
Maximum Retention Amount Rs. : 54,504,022.32
Cumulative Value Value of Current Cumulative Value up to end of
up to end of Measurement Period Current Measurement Period
BOQ
NO DESCRIPTION previous
Measurement
Amount (Rs.) Period(Rs.)
Amount Amount (Rs.) Amount (Rs.)
………………………………… …………………………………
Quantity Surveyor Deputy Project Director
Date : : Date :
Certified by:
Client Representative
Date :
Interim Payment Application-Summary 4 of 86
No any variation -
VO 01.3 Steel Plate shoring work for filling item 1 827,781.00 827,781.00 1.00 827,781.00 1.00 827,781.00 Completed 100%
70% certified as on
Total (Carried to Summary of Bills) 6,595,684.75 - 11,492,607.30 11,492,607.30
account
Supply and Laying Rubble Boulders packing for under -2 MSL (Payment Base on the Measurement Taken by actual bulk received to the
site-Gate 02
A Materials
Annex-04,
Supply C1 Rubble (450mm - 650mm) rate
Annex-05,
A/1 inclusive of transport/ Loading & Unloading Cube 9.00 7,346.00 66,114.00
Annex-17 &
by Dump Truck
Annex-06
A/4 GI Pipe - 20' & 10' for setting out Item 1,000.00 67,954.00
B Manpower
B/1 Skill Worker ( 5Nr @ 1 Day) Day 2.00 2,800.00 5,600.00 5,600.00 Annex-03
Supply, Fabricate and erect of Steel Platform (Moving excavator to middle of the cannel)
RATE SUB TOTAL TOTAL
ITEM DESCRIPTION UNIT QTY. REMARKS
Rs. Rs. Rs.
Annex-01 &
A/1 Steel ( H iron /Plate ) Kg 4,688.00 125.00 586,000.00
09
B/2 unskill Worker ( 3Nr @ 1 Day) Day 3.00 2,000.00 6,000.00 13,000.00 Annex-03
D Welding plant , Cutter and other tools Item 1.00 30,000.00 55,000.00
E/2 unskill Worker( 2Nr @ 1 Day) Day 2.00 2,000.00 4,000.00 40,000.00 Annex-03
F/2 Skill Worker ( 2Nr @ 3 Hrs) Day 0.75 2,800.00 2,100.00 15,600.00 Annex-03
G/2 Skill Worker ( 2Nr @ 3 Hrs) Day 0.75 2,800.00 2,100.00 15,600.00 Annex-03
Note: Assuming shoring work for Gate No-2 should be 2 times per one side therefore 4times total gate No-2. Material should be used
thrice per gate no 2 & also reused one time. Manpower & machine will be four times.
C/2 Skill Worker ( 4Nr @ 1 Day) Day 16.00 2,800.00 44,800.00 188,800.00 Annex-03
Supply and Laying ABC for -2 MSL (Payment Base on the Measurement Taken by actual Cubes received to the site-Gate 02
A Materials
78,300.00
B Manpower
B/1 Skill Worker ( 2Nr @ 1 Day) Day 2.00 2,800.00 5,600.00 5,600.00 Annex-03
A Material
139,340.00
C Manpower
C1 Skill Workers( 1Nr @ 1 Day) handling
moving and keep alignment of packed gabion
box Day 1.50 2,800.00 4,200.00 Annex-03
44,200.00
B Manpower
B/1 Skill Workers( 2Nr @ 1 Day) Day 2.00 2,800.00 5,600.00 Annex-03
B/2 Diver ( 1Nr @ 2 Day) No 6.00 1,000.00 6,000.00 Annex-20
11,600.00
A Material
Supply of Geotextile - 2mm thickness non-
A1 m2 36.00 160.00 5,760.00 Annex-24
Woven
5,760.00
B Manpower
B/1 Unskilled Worker( 5Nr @ 15 minutes) Day 0.16 2,000.00 312.00 Annex-03
B/2 Diver( 1Nr @ 15 minutes) Day 0.03 9,500.00 285.00 597.00 Annex-20
A Material
50,000.00
B Manpower
B/1 Welder( 2Nr @ 1 Day) Day 1.00 3,500.00 3,500.00 Annex-03
B/2 Unskilled Worker( 2Nr @ 1 Day) Day 1.00 2,000.00 2,000.00 Annex-03
5,500.00
Analysis for ; (10m legth and 9m hight sheet pile wall (Average length of sheet piles: 9m & width: 400mm )
Stage 01
Mobilization & demobilization work of
1.1 Item 1.00 250,000.00 250,000.00
Excavator,Vibro hamer & Crane
Stage 02
Mobilization & demobilization work of
2.1 Item 1.00 250,000.00 250,000.00
Excavator,Vibro hamer & Crane
Stage 03
Construction of Temporary coffer dam using Jumbo bag-ABC Rate Breakdown For Gate Our Ref No. ;
Filling 03
DGES/DC0062
A Material
A2 ABC for filling of jumbo bag Cube 3.32 7,200.00 - ABC qty already payid
53,500.00
9,000.00
C Manpower
12,000.00
Date:………………. Date:……………….
Democratic Socialist Republic of Sri Lanka Ministry of Ports & Shipping
Proposed Workshop Building Complex for Sri Lanka Ports Authority
Bill No 01 PRELIMINARIES IPA-08 01 November 2022 to 30st November 2022
1.10 Provide and maintenance of project name board LS 150,000.00 150,000.00 150,000.00 - 1.00 150,000.00
1.00 -
Total for Bill No.1 (Carried to Summary of Bills) . 63,675,230.00 54,184,675.00 209,000.00 54,393,675.00
0.85 70,958,219.99
2.4.2 Blacksmith Shop LS 39,112,643.77 0.72 28,161,103.51
2.4.3 Steel Fabrication Shop LS 389,442,875.28 469,172,522.10 673,736,174.24
2.4.4 Fitting Shop LS 83,134,177.59 0.37 30,759,645.71
Civil works for Electrical Substation
2.5 LS
Building 4,495,948.60
2.6 Water Sump LS 5,500,000.00
2.7 Cooling Tower LS 1,000,000.00
BOQ - 01
BILL NO 02 : CIVIL WORKS
2.1 Retaining wall -130m
Excavate trenches for the Retaining wall include
2.1.1 351.00 m3 900.00 315,900.00 200 900.00 180,000.00
Disposal
2.1.5 90mm dia Pvc Pipe G200 for weep holes 270.00 m 1,610.00 434,700.00
TOTAL 12,474,195.00 180,000.00
Page 19 of 86
BILL OF QUANTITIES
BOQ - 03
2.3 Civil works up to ground flow level
2.3.1 Machine Shop
Excavation
Removing top soil for preservation average depth
1 200.00 m3 492.00 98,400.00 200.00 492.00 98,400.00
150 mm
2 Excavation to reduced level 2110.00 m 3
400.00 844,000.00 2110.00 400.00 844,000.00
Excavate pits & trenches for Foundation not
3 exceeding 2.5m deep commencing at formed ground 390.00 m3 2,000.00 780,000.00 390.00 2,000.00 780,000.00
level.
Foundation
Filling with ABC fill material, to make up levels
5 under floors Compacted ,well rammed and 300.00 m3 5,592.00 1,677,600.00 300.00 5,592.00 1,677,600.00
consolidated
6 Shoring 800.00 m2 650.00 520,000.00 800.00 650.00 520,000.00
7 In 50mm thick blinding layer under Foundation 90.00 m2 2,000.00 180,000.00 90.00 2,000.00 180,000.00
BOQ - 04
2.3 Civil works up to ground flow level
2.3.2 Blacksmith
Excavation
1 Removing top soil for preservation average depth 102.00 m3 492.00 50,184.00 102.00 492.00 50,184.00
2 Excavation to reduced level 1354.00 m3 492.00 Deleted
Excavate pits & trenches for Foundation not
3 exceeding 2.5m deep commencing at formed ground 230.00 m3 2,000.00 460,000.00 230.00 2,000.00 460,000.00
level.
4 Disposal directed by an Engineer 400.00 m3 840.00 336,000.00 400.00 840.00 336,000.00
Foundation
Filling with ABC fill material, to make up levels
5 under floors Compacted ,well rammed and 200.00 m3 5,592.00 1,118,400.00 200.00 5,592.00 1,118,400.00
consolidated
6 Shoring 500.00 m2 650.00 325,000.00 500.00 650.00 325,000.00
7 In 50mm thick blinding layer under Foundation 60.00 m2 2,000.00 120,000.00 60.00 2,000.00 120,000.00
Foundation
Filling with ABC fill material, to make up levels
5 under floors Compacted ,well rammed and 300.00 m3 5,592.00 1,677,600.00 135 5,592.00 754,920.00
consolidated
6 Shoring 750.00 m2 650.00 487,500.00 337.5 650.00 219,375.00
7 In 50mm thick blinding layer under Foundation 90.00 m2 2,000.00 180,000.00 40.5 2,000.00 81,000.00
1.1 Transport to site & Erection 24.41 ton 84,000.00 2,050,650.00 18.135 84,000.00 1,523,340.00 For column 26
2 Supply Fabricate of Steel Fire Stare case ( 9m H) 2.00 Nos 638,000.00 1,276,000.00
2.1 Erect of Steel Fire Stare case ( 9m H) 2.00 Nos 112,000.00 224,000.00
3 Gr 8.8 Bolt & Nuts 0.13 ton 444,611.70 55,576.46
6 Supply & Fabricate of steel structure with painting 63.47 ton 387,000.00 24,563,857.50 63.47 387,000.00 24,563,857.50
Page 21 of 86
BILL OF QUANTITIES
16 Supply & Fabricate of steel structure with painting 10.28 ton 387,000.00 3,977,005.50 10.28 387,000.00 3,977,005.50
1 Supply & Fabricate of steel structure with painting 8.14 ton 387,000.00 3,149,212.50 8.14 387,000.00 3,149,212.50
2 Supply Fabricate of Steel Fire Stare case ( 9m H) 1.00 Nos 638,000.00 638,000.00
2.1 Erect of Steel Fire Stare case ( 9m H) 1.00 Nos 112,000.00 112,000.00
6 Supply & Fabricate of steel structure with painting 21.16 ton 387,000.00 8,187,952.50 21.16 387,000.00 8,187,952.50
16 Supply & Fabricate of steel structure with painting 3.26 ton 387,000.00 1,259,685.00 3.26 387,000.00 1,259,685.00
1 Supply & Fabricate of steel structure with painting 22.05 ton 387,000.00 8,533,350.00 22.05 387,000.00 8,533,350.00
2 Supply Fabricate of Steel Fire Stare case ( 9m H) 2.00 Nos 638,000.00 1,276,000.00
2.1 Erect of Steel Fire Stare case ( 9m H) 2.00 Nos 112,000.00 224,000.00
6 Supply & Fabricate of steel structure with painting 57.33 ton 387,000.00 22,186,710.00 45.86 387,000.00 17,749,368.00
16 Supply & Fabricate of steel structure with painting 8.82 ton 387,000.00 3,413,340.00 7.06 387,000.00 2,730,672.00
Page 23 of 86
CONSTRUCTION OF PROPOSED FACTORY FOR STRAINTEC (PVT) LTD. AT KOGGALA - KOGGALA EXPORT PROCESSING ZONE,SRI LANKA.
COST TO COMPLETION DATE OF
2 BUILDING WORKS
Up to Ground Floor level - - - - 13,494,717.92 13,494,717.92
Above Ground Floor Level - 1,669,605.18 - 1,669,605.18 44,307,311.37 44,307,311.37
Plumbing work - 465,647.04 - 465,647.04 698,470.56 698,470.56
Sub Total - 2,135,252.22 - 2,135,252.22 58,500,499.85 58,500,499.85
Cash Inflow
Up to date Work Done 118,042,662.25
Variation ( Up to date ) -
Balance Work Done 6,477,319.82
Variation (Balance Work Done) -
Estimated @ completion Income(Civil ) 124,519,982.07
Cash Outflow
Bill - 01
1 PRELIMINARIES
1.2 Provide insurance for contractor’s plant & equipment LS 350,000.00 350,000.00 100.00% #REF!
1.4 Provide insurance for Contractor’s personnel LS 260,000.00 260,000.00 100.00% #REF!
1.5 Provide professional indemnify insurance for Contractors’ Design LS 1,200,000.00 1,200,000.00 100.00% #REF!
1.7 Maintenance of engineer’s Office 9.00 Mon 40,000.00 360,000.00 122.22% 3,960,000.00
1.8 Monthly progress report including progress photographs 9.00 Mon 9,000.00 81,000.00 133.33% 972,000.00
1.10 Provide and maintenance of project name board LS 150,000.00 150,000.00 100.00% #REF!
1.11.1 Perfomene Cecurity/ Advance bond 1.00 Item 2,783,230.00 2,783,230.00 100.00% #REF!
1.11.2 Design
1.11.2.1 Surveying & Soil Investigation 1.00 Item 1,495,000.00 1,495,000.00 100.00% #REF!
1.11.2.2 Design of Civil, WS&D, Electrical, Mechanical, ICT 1.00 Item 14,000,000.00 14,000,000.00 90.00% #REF!
1.11.2.3 shop drawings and as built drawings 1.00 Item 460,000.00 460,000.00 0.00% #REF!
1.11.3 Contractor’s facility
1.11.3.1 Site Office / Stores - DGES 9.00 Mon 157,000.00 1,413,000.00 90.00% #REF!
1.11.3.2 Transport 1.00 Item 519,000.00 519,000.00 100.00% #REF!
1.11.3.3 Water, Electricity supply 1.00 Item 172,500.00 172,500.00 100.00% #REF!
1.11.3.4 Water, Electricity for Construction 9.00 Mon 193,500.00 1,741,500.00 70.00% #REF!
1.11.3.5 Temporary sheds and Workers Huts 1.00 Item 814,000.00 814,000.00 100.00% #REF!
1.11.3.7 Site running expences 9.00 Mon 64,500.00 580,500.00 70.00% #REF!
1.11.3.10 Vehicle For Site 9.00 Mon 601,166.67 5,410,500.00 70.00% #REF!
Project staff (PM, Des Eng, Architect, MEP Eng, Cons Eng, Mec
1.11.3.11 9.00 Mon 2,197,566.67 19,778,100.00 79.00% #REF!
Eng, Elect Eng, TO-3, Supervisors-3)
1.11.3.13 Construction of Tempory Fence 1.00 Item 1,593,900.00 1,593,900.00 100.00% #REF!
1.11.3.14 Pass & Approvels 9.00 Mon 110,500.00 994,500.00 60.00% 538,843.00
Removal of all rubbish and debris in all three sites and clearing of
1.11.3.15 1.00 Item 537,500.00 537,500.00 0.00% #REF!
site on completion
BILL - 02.1
BILL NO 02 : CIVIL WORKS
2.1 Retaining wall -130m
2.1.1 Excavate trenches for the Retaining wall include Disposal 351.00 m3 1,725.00 605,475.00 100.00% #REF!
2.1.2 Shoring 468.00 m2 920.00 430,560.00 100.00% 177,274.80
2.1.3 50mm thick screed concretes 195.00 m2 1,138.50 222,007.50 95.00% #REF!
2.1.4 Rubble stone masonry work in Retaining wall 994.50 m3 12,880.00 12,809,160.00 85.00% #REF!
2.1.5 90mm dia Pvc Pipe G200 for weep holes 270.00 m 1,380.00 372,600.00 85.00% #REF!
2.1.1 Plump Concrte-80m Item Item 8,663,881.50 10,688,160.00 8,663,881.50 10,688,160.00 12,655,042.83 95.00% 7,219,901.25
2.1.2 Soil Nails-50m Item Item 5,775,921.00 23,567,895.00 5,775,921.00 23,567,895.00 9,992,343.33
TOTAL 14,439,802.50 34,256,055.00 22,647,386.16 7,219,901.25
Excavate pits & trenches for Foundation not exceeding 2.5m deep
3 390.00 m3 960.00 374,400.00 100.00% 374,400.00
commencing at formed ground level.
Foundation
7 In 50mm thick blinding layer under Foundation 90.00 m2 2,000.00 180,000.00 100.00% 180,000.00
Page 26 of 86
BILL OF QUANTITIES
9 Sawn timber and plywood sheet form work for column footings 230.00 m2 1,662.00 382,260.00 100.00% 382,260.00
10 Cold worked high yield steel bar reinforcement in Foundation 7150.00 kg 210.00 1,501,500.00 100.00% 1,501,500.00
Bill-02.3.2-Blacksmith
2.3 Civil works up to ground flow level
2.3.2 Blacksmith
Excavation
1 Removing top soil for preservation average depth 148.94 m3 492.00 73,278.48 100.00% 73,278.48
2 Excavation to reduced level 1354.00 m3 492.00 Deleted -
Excavate pits & trenches for Foundation not exceeding 2.5m deep
3 230.00 m3 960.00 220,800.00 100.00% 220,800.00
commencing at formed ground level.
Foundation
7 In 50mm thick blinding layer under Foundation 60.00 m2 2,000.00 120,000.00 100.00% 120,000.00
10 Cold worked high yield steel bar reinforcement in Foundation 4100.00 kg 210.00 861,000.00 100.00% 861,000.00
17 Supply & placing compacting and curing Grade 30 concrete in GF 135.40 m3 23,520.00 Deleted
18 Sawn timber and plywood sheet form work for GF 102.00 m 200.00 Deleted
19 Cold worked high yield steel bar reinforcement in GF 12321.40 kg 210.00 Deleted
20 Expansion/ construction joints 255.00 m 1,200.00 Deleted
Sub Total -
Dewatering
21 Dewatering 1.00 m2 200,000.00 200,000.00 100.00% 200,000.00
200,000.00 200,000.00
Page 27 of 86
BILL OF QUANTITIES
Excavate pits & trenches for Foundation not exceeding 2.5m deep
3 1100.00 1311.99 m3 920.00 1,683.00 1,012,000.00 2,208,079.17 1,149,632.00 90.00% 910,800.00
commencing at formed ground level.
5 Disposal directed by an Engineer 4064.00 4275.99 m3 805.00 976.70 3,271,520.00 976.70 3,716,446.72 90.00% 2,944,368.00
Foundation -
Approved dry earth filling with available soil in the Ground Floor
780.00 m3 1,200.00 936,000.00
area rammed and consolidated in layers
7 Shoring 1500.00 250.00 m2 900.00 900.00 1,350,000.00 225,000.00 2,444,850.00 90.0% 1,215,000.00
8 Dewatering 460,000.00 950,000.00 833,060.00 90.0% 414,000.00
9 In 50mm thick blinding layer under Foundation 320.00 408.94 m2 1,309.28 3,144.00 418,968.00 1,285,699.50 758,751.05 90.0% 377,071.20
11 Sawn timber and plywood sheet form work for column footings 384.00 400.37 m2 1,592.75 1,825.00 611,616.00 730,675.25 1,107,636.58 90.0% 550,454.40
12 Cold worked high yield steel bar reinforcement in Foundation 22880.00 16339.64 kg 206.00 541.00 4,713,280.00 8,839,742.54 8,535,750.08 90.0% 4,241,952.00
19 Supply & placing compacting and curing Grade 30 concrete in GF 540.00 437.41 m3 22,020.00 47,250.00 11,890,800.00 20,667,575.25 20,571,084.00 -
20 Sawn timber and plywood sheet form work for GF 248.00 273.35 m 230.00 456.00 57,040.00 124,647.60 98,679.20 -
21 Cold worked high yield steel bar reinforcement in GF 49140.00 44435.2 kg 206.00 520.00 10,122,840.00 23,106,304.00 17,512,513.20 -
22 Expansion/ construction joints 826.00 708.00 m 1,380.00 1,800.00 1,139,880.00 1,274,400.00 1,971,992.40 -
Sub Total 23,697,010.00 45,672,822.85 40,995,827.30
Page 28 of 86
BILL OF QUANTITIES
Bill-02.3.4-Fitting Shop
2.3 Civil works up to ground flow level
2.3.4 Fitting Shop
Excavation
1 Removing top soil for preservation average depth 150 mm 214.50 m3 492.00 105,534.00 90.00% 94,980.60
2 Excavation to reduced level 1950.00 m3 492.00 Deleted
Excavate pits & trenches for Foundation not exceeding 2.5m deep
3 380.00 m3 960.00 364,800.00 90.00% 328,320.00
commencing at formed ground level.
Foundation
7 In 50mm thick blinding layer under Foundation 90.00 m2 2,000.00 180,000.00 90.00% 162,000.00
9 Sawn timber and plywood sheet form work for column footings 150.00 m2 1,662.00 249,300.00 90.00% 224,370.00
10 Cold worked high yield steel bar reinforcement in Foundation 6700.00 kg 210.00 1,407,000.00 90.00% 1,266,300.00
Sub Total 6,681,984.00 6,013,785.60
Anti Termite Treatment
Bill-02.4.1-Machine Shop
2.4 Civil works above ground flow level
2.4.1 Machine Shop
Columns
Supply, fabricate & erect in the position of steel structure
1 24.63 24.63 ton 70,730.00 520,456.00 11,271,601.25 100.00% 11,271,601.25
consisting of columns with painting
2 Supply Fabricate, erect of Steel Fire Stare case ( 9m H) 2.00 2.00 Nos 750,000.00 1,080,367.00 1,500,000.00 85.00% 1,275,000.00
3 Gr 8.8 Bolt & Nuts 0.13 0.25 ton 444,611.70 489,072.87 55,576.46 100.00% 55,576.46
Supply & Fix MS anchor bolts , 24mm dia x 600 Gr 8.8 and
4 necessary nuts washers etc. Rate to include for provinding non - 300 140 Nos 2,600.00 2,993.59 780,000.00 100.00% 780,000.00
shrinkage grouts to column top and holes
5 Concrete / Fw/ Rf for stiffener column 100.00 48.00 m 1,600.00 2,200.00 160,000.00
Sub Total 13,767,177.71 13,382,177.71
Beams
Supply, fabricate & erect in the position of steel structure
6 64.03 64.03 ton 70,730.00 520,456.00 29,306,163.25 100.00% 29,306,163.25
consisting of columns with painting
7 Gr 8.8 Bolt & Nuts 0.33 0.40 ton 444,611.70 489,072.87 144,498.80 100.00% 144,498.80
8 Concrete / Fw/ Rf for stiffener column 100.00 105.00 m 1,600.00 2,200.00 160,000.00 100.00% 160,000.00
Sub Total 29,610,662.05 29,610,662.05
Slab
9 Supply & fixing of 0.75mm Structural Decking 35.00 30.00 m2 5,094.74 178,315.90
10 Supply & fixing of Decking end closures 40.00 27.00 m 5,094.74 203,789.60
11 Supply and fixing of Sher struds 1500.00 377.00 Nos 477.48 360.00 716,220.00 135,720.00
12 Supply & placing compacting and curing Grade 30 concrete in GF 7.00 6.00 m3 23,520.00 164,640.00
13 Sawn timber and plywood sheet form work for GF 35.00 - m2 1,800.00 63,000.00
14 Cold worked high yield steel bar reinforcement in GF 630.00 200.00 kg 220.50 138,915.00
15 Expansion/ construction joints 35.00 - m 1,600.00 56,000.00
Sub Total 1,520,880.50 -
Roof
Supply, fabricate & erect in the position of steel structure
16 9.85 9.85 ton 70,730.00 4,508,640.50 100.00% 4,508,640.50
consisting of columns with painting
17 Gr 8.8 Bolt & Nuts 0.05 0.10 ton 444,611.70 22,230.59 100.00% 22,230.59
18 G 450 Purling Coating 200g/m2 3191.48 2020.00 m 1,906.06 6,083,175.00 100.00% 6,083,175.00
19 Zn/Al Roofing 0.47mm thick, 550MPa, AZ 200 1550.00 1480.00 m2 2,672.63 6,411.00 4,142,576.50 9,488,280.00 7,502,206.04 100.00% 4,142,576.50
20 Supply & Installation of Ridge Cap 140.00 70.00 m 2,536.21 355,069.40 100.00% 355,069.40
21 Supply & Installation of Gutter 280.00 136.00 m 2,536.21 710,138.80 100.00% 710,138.80
22 Supply & Installation of Down pipe 420.00 378.00 m 2,660.23 1,117,296.60
23 Supply & Installation of Roof Insulation 1400.00 - m2 1,482.04 2,074,856.00 100.00% 2,074,856.00
24 Supply & Fix Tie rods 542.50 - Nos 300.00 162,750.00 100.00% 162,750.00
25 Supply & Fix Barge / eaves & Coner capping 420.00 378.00 m 1,600.00 672,000.00 100.00% 672,000.00
Sub Total 19,848,733.39 18,731,436.79
26 Cladding 900.00 797.52 m2 2,672.63 6,044.67 2,405,367.00 4,820,744.75 4,245,472.76 50.00% 1,202,683.50
Sub Total 2,405,367.00 1,202,683.50
Doors
27 D3 – 2100 x 900 AL Framed Signal Sashed Glazed Door 1.00 1.00 Nos 38,400.00 38,400.00
28 D4 – 2100 x 900 AL Framed Signal Sashed Louver Door 1.00 1.00 Nos 65,696.40 65,696.40
Page 29 of 86
BILL OF QUANTITIES
Windows
31 W 396.00 381.92 m2 25,178.40 9,970,646.40
32 W3 2.00 . Nos 192,432.00 384,864.00
33 W4 2.00 Nos 102,630.48 205,260.96
34 FL 1800 x 600 2.00 Nos 21,600.00 43,200.00
Sub Total 10,603,971.36 -
Chain link fence
35 CF - Al Framed Chain link fence Meash 171.36 m2 6,250.00 1,071,000.00 1,852,830.00
CF-Box Bar frame with Chain link fence 109.50 m2 15,447.60 1,691,512.20
Sub Total 1,071,000.00 1,691,512.20 1,852,830.00 -
Partition
36 Glazed Aluminium Fabric Partition office area 55.00 m2 17,431.20 958,716.00
Sub Total 958,716.00 -
Page 30 of 86
BILL OF QUANTITIES
Masonry works
37 225mm thick Brick works 144.00 156.76 m2 4,900.00 7,095.83 705,600.00 1,112,342.72 2,035,587.19 100.00% 705,600.00
38 112.5 mm thick Brick works 167.00 78.00 m2 2,500.00 6,852.00 417,500.00 534,456.00 924,608.88
Sub Total 1,123,100.00 1,646,798.72 2,960,196.07 705,600.00
Tiling
Floor
39 600x300mm homogenous floor tile with bed 5.00 3.75 m2 6,500.00 32,500.00
Wall
40 300x300mm glazed ceramic wall tiles for Washroom 57.00 17.00 m2 5,700.00 5,688.27 324,900.00
Sub Total 357,400.00 -
Plastering
41 internal & external Plastering 622.00 469.52 m2 1,200.00 746,400.00 50.00% 373,200.00
Sub Total 746,400.00 373,200.00
Power trowel finish
42 Power trowel Floor finish GF 2048.00 m2 900.00 Deleted
Sub Total -
Cement Render finish
43 Cement Render finish 18.00 26.00 m2 900.00 16,200.00
Sub Total 16,200.00
Painting
44 External Painting ( 5 coat paint) 207.33 156.76 m2 1,400.00 290,266.67
45 Internal Painting ( 3 coat paint) 414.67 312.76 m2 1,250.00 518,333.33
Sub Total 808,600.00
Waterproofing work
46 Waterproofing Toilets & Slabs 80.00 22.00 m2 2,600.00 208,000.00
Sub Total 208,000.00
ADDITI-NEW
MF-01 D3 – 2100 x 900 AL Framed Signal Sashed Glazed Door -M Floor 32.00
GF Wash Room
Masonry works
37 225mm thick Brick works 22.63 m2 7,095.83 160,578.69 293,859.01 100.00% -
38 112.5 mm thick Brick works 2.85 m2 6,852.00 19,528.20 33,783.79
Plaster 43.00 m2
Painting 43.00 m2
Ceiling 9.20 m2
Tile
Floor
39 600x300mm homogenous floor tile with bed 8.01 m2 6,500.00
Wall
40 300x300mm glazed ceramic wall tiles for Washroom 26.00 m2 6,500.00
FL 3.00 No
Sanitary Fittings
Urinal 2.00
Supervisor room
Doors
D1 1.00
SD 2.00
Partition
Glazed Aluminium Fabric Partition office area 74.00 m2 17,431.20 1,289,908.80
Celling 17.28 m2
CNC Room
D4 1.00 no
W4 2.00 no
FG2' 4.00 no
W3 1.00 no
Slab
RF 905.60 kg
FW 52.64 m2
Concrete 6.70 m3
Page 31 of 86
BILL OF QUANTITIES
Page 32 of 86
BILL OF QUANTITIES
2 Supply Fabricate, erect of Steel Fire Stare case ( 9m H) 1.00 Nos 750,000.00 750,000.00 80% 600,000.00
3 Gr 8.8 Bolt & Nuts 0.13 ton 444,611.70 55,576.46 100% 55,576.46
Supply & Fix MS anchor bolts , 24mm dia x 600 Gr 8.8 and
4 necessary nuts washers etc. Rate to include for provinding non - 200 Nos 2,600.00 520,000.00 100% 520,000.00
shrinkage grouts to column top and holes
5 Concrete / Fw/ Rf for stiffener column 75.00 m 1,600.00 120,000.00
Sub Total 5,908,443.96 5,638,443.96
Beams
Supply, fabricate & erect in the position of steel structure
6 25.35 ton 457,730.00 11,603,455.50 100% 11,603,455.50
consisting of columns with painting
7 Gr 8.8 Bolt & Nuts 0.33 ton 444,611.70 144,498.80 100% 144,498.80
8 Concrete / Fw/ Rf for stiffener column 75.00 m 1,600.00 120,000.00 -
Sub Total 11,867,954.30 11,747,954.30
Slab
9 Supply & fixing of 0.75mm Structural Decking 40.00 m2 5,094.74 203,789.60
12 Supply & placing compacting and curing Grade 30 concrete in GF 8.00 m3 23,520.00 188,160.00
13 Sawn timber and plywood sheet form work for GF 40.00 m2 1,800.00 72,000.00
14 Cold worked high yield steel bar reinforcement in GF 720.00 kg 220.50 158,760.00
15 Expansion/ construction joints 40.00 m 1,600.00 64,000.00
Sub Total 1,504,824.40
Roof
Supply, fabricate & erect in the position of steel structure
16 3.90 ton 457,730.00 1,785,147.00 100% 1,785,147.00
consisting of columns with painting
17 Gr 8.8 Bolt & Nuts 0.05 ton 444,611.70 22,230.59 100% 22,230.59
18 G 450 Purling Coating 200g/m2 7.50 ton 405,545.00 3,041,587.50 100.00% 3,041,587.50
19 Zn/Al Roofing 0.47mm thick, 550MPa, AZ 200 950.00 m2 2,672.63 2,538,998.50 100.00% 2,538,998.50
20 Supply & Installation of Ridge Cap 60.00 m 2,536.21 152,172.60 100.00% 152,172.60
21 Supply & Installation of Gutter 120.00 m 2,536.21 304,345.20 100.00% 304,345.20
22 Supply & Installation of Down pipe 150.00 m 2,660.23 399,034.50
23 Supply & Installation of Roof Insulation 850.00 m2 1,482.04 1,259,734.00 100.00% 1,259,734.00
24 Supply & Fix Tie rods 332.50 Nos 300.00 99,750.00 100.00% 99,750.00
25 Supply & Fix Barge / eaves & Coner capping 180.00 m 1,600.00 288,000.00 100.00% 288,000.00
Sub Total 9,890,999.89 9,491,965.39
Page 33 of 86
BILL OF QUANTITIES
Tiling
36 Floor
37 600x300mm homogenous floor tile with bed 35.00 m2 6,500.00 227,500.00
38 Wall
39 300x300mm glazed ceramic wall tiles for Washroom 75.00 m2 5,700.00 5,688.27 427,500.00
Sub Total 655,000.00
Plastering
40 internal & external Plastering 350.00 m2 1,200.00 420,000.00 50.00% 210,000.00
Sub Total 420,000.00 210,000.00
Power trowel finish
41 Power trowel Floor finish GF 642.00 m2 900.00 Deleted
Sub Total -
Cement Render finish
42 Cement Render finish 35.00 m2 900.00 31,500.00
Sub Total 31,500.00
Painting
43 External Painting ( 5 coat paint) 116.67 m2 1,400.00 163,333.33
44 Internal Painting ( 3 coat paint) 233.33 m2 1,250.00 291,666.67
Sub Total 455,000.00
Waterproofing work
45 Waterproofing Toilets & Slabs 145.00 m2 2,600.00 377,000.00
Sub Total 377,000.00
TOTAL 39,112,643.77 27,766,458.15
Page 34 of 86
BILL OF QUANTITIES
Supply & Fix MS anchor bolts , 24mm dia x 600 Gr 8.8 and
5 necessary nuts washers etc. Rate to include for provinding non - 650 324 Nos 2,990.00 2,993.59 1,943,500.00 969,924.38
shrinkage grouts to column top and holes
6 Concrete / Fw/ Rf for stiffener column 650.00 650.00 m 1,564.00 2,200.00 1,016,600.00 1,430,000.00
Sub Total
Beams
Supply, fabricate & erect in the position of steel structure
7 328.25 328.25 ton 84,000.00 462,000.00 27,573,000.00 151,651,500.00
consisting of columns
10 Concrete / Fw/ Rf for stiffener column 650.00 650.00 m 1,564.00 2,200.00 1,016,600.00 1,430,000.00
Sub Total
Slab
11 Supply & fixing of 0.75mm Structural Decking 4000.00 4130.00 m2 5,120.85 7,155.51 20,483,400.00 29,552,243.79
12 Supply & fixing of Decking end closures 1200.00 884.52 m 5,120.85 1,823.63 6,145,020.00 1,613,040.30
13 Supply and fixing of Sher struds 15000.00 10562.00 Nos 479.92 661.00 7,198,852.50 6,981,482.00
14 Supply & placing compacting and curing Grade 30 concrete in GF 480.00 497.01 m3 22,020.00 47,733.75 10,569,600.00 23,724,151.09
15 Jack supporting for slab 4000.00 4130.00 m2 920.00 1,200.00 3,680,000.00 4,956,000.00
16 Sawn timber and plywood sheet form work for GF 278.00 278.00 m 230.00 420.00 63,940.00 116,760.00
17 Cold worked high yield steel bar reinforcement in GF 16800.00 14296.8143 kg 216.30 525.22 3,633,840.00 7,509,020.46
18 Expansion/ construction joints 1652.00 1652.00 m 1,564.00 2,200.00 2,583,728.00 3,634,400.00
Sub Total
Roof
Supply, fabricate & erect in the position of steel structure
19 50.50 50.50 ton 84,000.00 462,000.00 4,242,000.00 23,331,000.00
consisting of columns
22 G 450 Purling Coating 200g/m2 10.00 9.80 ton 407,625.12 1,310,842.00 4,076,251.20 12,846,251.60
23 Zn/Al Roofing 0.47mm thick, 550MPa, AZ 200 2500.00 2056.66 m2 2,686.95 5,810.00 6,717,375.00 11,949,171.36
24 Supply & Installation of Ridge Cap 310.00 244.84 m 2,549.40 3,824.10 790,314.00 936,292.64
25 Supply & Installation of Gutter 550.00 550.00 m 2,549.40 3,824.10 1,402,170.00 2,103,255.00
26 Supply & Installation of Down pipe 700.00 700.00 m 2,674.35 4,011.53 1,872,045.00 2,808,067.50
27 Supply & Installation of Roof Insulation 1850.00 1850.00 m2 1,489.95 - 2,756,407.50 -
28 Supply & Fix Tie rods 875.00 719.83 Nos 345.00 420.00 301,875.00 302,328.43
29 Supply & Fix Barge / eaves & Coner capping 400.00 400.00 m 1,840.00 2,820.00 736,000.00 1,128,000.00
Sub Total
Doors
ADD D 1.00 145,256.00 145,256.00
ADD DW 3.00 325,684.00 977,052.00
30 D1 – 2550 x 1500 AL Framed Double Sashed Glazed Door 2.00 4.00 Nos 86,580.00 259,740.00 173,160.00 1,038,960.00
31 D2 – 2100 x 1200 AL Framed Signal Sashed Glazed Door 1.00 3.00 Nos 46,800.00 70,200.00 46,800.00 210,600.00
32 D3 – 2100 x 900 AL Framed Signal Sashed Glazed Door 17.00 31.00 Nos 38,610.00 30,701.18 656,370.00 951,736.50
33 D4 – 2100 x 900 AL Framed Signal Sashed Louver Door 11.00 14.00 Nos 51,597.00 58,783.73 567,567.00 822,972.15
D5 – 2100 x 750 AL Framed Composite panel Door (Signal
34 39.00 52.00 Nos 38,610.00 41,988.38 1,505,790.00 2,183,395.50
Sashed)
35 RD 3 – 2700 x 3600 Roller Shatter Door 2.00 7.00 Nos 245,700.00 725,265.00 491,400.00 5,076,855.00
Sub Total
Windows
37 W5 – 1650 x 1200 AL Framed Glass Window with Lover on top 155.00 63 Nos 36,270.00 129,391.79 5,621,850.00 8,151,682.50
38 W8 – 1080 x 900 AL Framed Glass Window with Lover on top 80.00 65 Nos 17,784.00 31,737.60 1,422,720.00 2,062,944.00
39 W9 – 1650 x 2100 AL Framed Glass Window with Lover on top 23.00 23 Nos 63,063.00 91,441.35 1,450,449.00 2,103,151.05
W10 – 1650 x 2100 AL Framed Glass Window with Lover on top 14 91,441.35 1,280,178.90
40 FL – 1080 x 600 Top hung Fanlight 112.00 134 Nos 11,583.00 22,560.00 1,297,296.00 3,023,040.00
Sub Total
Page 35 of 86
BILL OF QUANTITIES
Partition
42 Glazed Aluminium Fabric Partition office area 400.95 244.97 m2 16,995.42 27,270.00 6,814,313.65 6,680,331.90
Sub Total
Masonry works
43 200mm thick solid Block works 2600.00 m2 4,118.40 4,168.97 10,707,840.00 -
225mm thick brick works 2824.00 m2 7,095.83 20,038,631.38
44 150mm thick solid Block works 900.00 1423.00 m2 3,088.80 3,620.00 2,779,920.00 5,151,260.00
45 100mm thick solid Block works 320.00 319.00 m2 2,246.40 3,620.00 718,848.00 1,154,780.00
Sub Total -
Tiling
Floor
46 600x600mm semi glazed homogenous floor tile 1741.04 1351.14 m2 6,435.00 5,688.27 11,203,592.40 7,685,654.53
47 600x300mm homogenous floor tile 80.00 m2 6,435.00 5,688.27 514,800.00 -
48 300x300mm nonskid homogenous floor tile 870.16 m2 6,435.00 5,688.27 5,599,479.60 -
Wall -
49 300x300mm glazed ceramic wall tiles for Washroom 410.00 982.485 m2 5,557.50 5,688.27 2,278,575.00 5,588,641.04
Sub Total -
Plastering -
50 internal & external Plastering 7640.00 8105.00 m2 1,404.00 1,832.64 10,726,560.00 14,853,573.14
Sub Total -
Power trowel finish -
51 Power trowel Floor finish GF 2652.00 2537.00 m2 1,053.00 1,018.17 2,792,556.00 2,583,084.61
Sub Total -
-
Painting -
52 External Painting ( 5 coat paint) 2600.00 2767.00 m2 1,638.00 2,077.70 4,258,800.00 5,749,001.99
53 Internal Painting ( 3 coat paint) with potty 2030.00 3454.00 m2 1,462.50 1,985.00 2,968,875.00 6,856,190.00
Sub Total
TOTAL 195,689,879.85 469,172,522.10 -
Page 36 of 86
BILL OF QUANTITIES
Supply & Fix MS anchor bolts , 24mm dia x 600 Gr 8.8 and
4 necessary nuts washers etc. Rate to include for provinding non - 300 Nos 2,600.00 780,000.00 80.00% 624,000.00
shrinkage grouts to column top and holes
5 Concrete / Fw/ Rf for stiffener column 100.00 m 1,600.00 160,000.00
Sub Total 1,861,775.00
Beams
Supply, fabricate & erect in the position of steel structure
6 56.88 ton 70,730.00 4,022,768.75 80.00% 3,218,215.00
consisting of columns with painting
8 Concrete / Fw/ Rf for stiffener column 100.00 m 1,600.00 160,000.00
Sub Total 3,218,215.00
Slab
9 Supply & fixing of 0.75mm Structural Decking 85.00 m2 5,094.74 433,052.90
10 Supply & fixing of Decking end closures 65.00 m 5,094.74 331,158.10
11 Supply and fixing of Sher struds 1500.00 Nos 477.48 716,220.00
12 Supply & placing compacting and curing Grade 30 concrete in GF 17.00 m3 23,520.00 399,840.00
13 Sawn timber and plywood sheet form work for GF 85.00 m2 1,800.00 153,000.00
14 Cold worked high yield steel bar reinforcement in GF 1530.00 kg 220.50 337,365.00
15 Expansion/ construction joints 85.00 m 1,600.00 136,000.00
Sub Total
Roof
Supply, fabricate & erect in the position of steel structure
16 8.75 ton 70,730.00 618,887.50 80.00% 495,110.00
consisting of columns with painting
18 G 450 Purling Coating 200g/m2 13.00 ton 405,545.00 5,272,085.00
19 Zn/Al Roofing 0.47mm thick, 550MPa, AZ 200 1550.00 m2 2,672.63 4,142,576.50
20 Supply & Installation of Ridge Cap 70.00 m 2,536.21 177,534.70
21 Supply & Installation of Gutter 140.00 m 2,536.21 355,069.40
22 Supply & Installation of Down pipe 300.00 m 2,660.23 798,069.00
23 Supply & Installation of Roof Insulation 1400.00 m2 1,482.04 2,074,856.00
24 Supply & Fix Tie rods 542.50 Nos 300.00 162,750.00
25 Supply & Fix Barge / eaves & Coner capping 210.00 m 1,600.00 336,000.00
Sub Total 495,110.00
Page 37 of 86
BILL OF QUANTITIES
Masonry works
38 150mm thick solid Block works 110.00 39.78 m2 3,168.00 3,620.00 348,480.00
39 225mm thick Brick works 259.60 431.768 m2 4,900.00 7,095.83 1,272,040.00
Sub Total
Tiling
40 Floor
41 600x300mm homogenous floor tile with bed 30.00 m2 6,500.00 195,000.00
42 Wall
43 300x300mm glazed ceramic wall tiles for Washroom 110.00 m2 5,700.00 5,688.27 627,000.00
Sub Total
Plastering
44 internal & external Plastering 739.20 m2 1,200.00 887,040.00
Sub Total
Power trowel finish
45 Power trowel Floor finish GF 945.00 m2 900.00 850,500.00
Sub Total
Cement Render finish
46 Cement Render finish 18.00 m2 900.00 16,200.00
Sub Total
Painting
47 External Painting ( 5 coat paint) 246.40 m2 1,400.00 344,960.00
48 Internal Painting ( 3 coat paint) 492.80 m2 1,250.00 616,000.00
Sub Total
Waterproofing work
49 Waterproofing Toilets & Slabs 158.00 m2 2,600.00 410,800.00
Sub Total
Concrete Canopy around the building
50 Supply & placing compacting and curing Grade 30 concrete in GF 37.80 m3 23,520.00 889,056.00
51 Form work 160.00 m 1,662.00 265,920.00
52 Cold worked high yield steel bar reinforcement in GF 3439.80 kg 210.00 722,358.00
Sub Total
TOTAL 47,549,371.74 5,575,100.00
BOQ - 11
2.5 Civil works for Electrical Substation Building
1 Excavation 1.00 Item 146,343.14 146,343.14
2 Foundation 1.00 Item 301,824.98 301,824.98
3 Surface treatment 1.00 Item 25,200.00 25,200.00
4 Ground Beams 1.00 Item 49,805.81 49,805.81
5 Ground floor slab 1.00 Item 371,214.36 371,214.36
6 Dewatering 1.00 Item 40,000.00 40,000.00
7 Columns 1.00 Item 595,972.37 595,972.37
8 Beams 1.00 Item 1,295,825.59 1,295,825.59
9 Roof 1.00 Item 744,766.00 744,766.00
10 Cladding 1.00 Item 98,681.72 98,681.72
11 Doors 1.00 Item 28,282.09 28,282.09
12 Windows 1.00 Item 466,841.56 466,841.56
13 Chain link fence 1.00 Item 43,446.15 43,446.15
14 Partition 1.00 Item 59,756.31 59,756.31
15 Masonry works 1.00 Item 66,482.87 66,482.87
16 Tiling 1.00 Item 33,723.08 33,723.08
17 Plastering 1.00 Item 36,391.38 36,391.38
18 Cement rendering 1.00 Item 664.62 664.62
19 Power trowel finish 1.00 Item 34,892.31 34,892.31
20 Painting 1.00 Item 39,424.00 39,424.00
21 Waterproofing 1.00 Item 16,410.26 16,410.26
TOTAL 4,495,948.60
BOQ - 12
3 BILL NO 03 : WATER SUPPLY AND DRAINAGE WORKS
1 Supply and installation of 40mm Ø PVC T1000 pipes and fitting m 2 1,469.34 2,938.68
2 Supply and installation of 32mm Ø PVC T1000 pipes and fitting m 2 918.34 1,836.68
3 Supply and installation of 25mm Ø PVC T1000 pipes and fitting m 2 783.00 1,566.00
4 Supply and installation of 20mm Ø PVC T1000 pipes and fitting m 10 604.17 6,041.70
Supply and installation of 32mm "Pegler/Kitz" or equvivalent Gate
5 nrs 2 5,945.00 11,890.00
valves
6 Testing and commissioning Item 1 3,386.94 3,386.94
Sub Total 27,660.00
Sanitary Fittings and Fixtures
15 Supply and installation of 40mm Ø T600 uPvc pipes and fittings m 2 1,469.34 2,938.68
16 Supply and installation of 50mm Ø T600 uPvc pipes and fittings m 1 1,885.00 1,885.00
17 Supply and installation of 63mm Ø T600 uPvc pipes and fittings m 3 2,755.00 8,265.00
18 Supply and installation of 110mm Ø T600 uPvc pipes and fittings m 4 6,365.50 25,462.00
Page 38 of 86
BILL OF QUANTITIES
BOQ - 13
3.1 Water supply and drainage works
3.1.2 Blacksmith Shop
Portable Water Supply System
1 Supply and installation of 40mm Ø PVC T1000 pipes and fitting m 2 1,469.34 2,938.68
2 Supply and installation of 32mm Ø PVC T1000 pipes and fitting m 2 918.34 1,836.68
3 Supply and installation of 25mm Ø PVC T1000 pipes and fitting m 4 783.00 3,132.00
4 Supply and installation of 20mm Ø PVC T1000 pipes and fitting m 6 604.17 3,625.02
Supply and installation of 32mm "Pegler/Kitz" or equvivalent Gate
5 nrs 2 5,945.00 11,890.00
valves
6 Testing and commissioning Item 1 2,417.62 2,417.62
Sub Total 25,840.00
Sanitary Fittings and Fixtures
8 SLS 568 - Ceramic Squatting Pans and Traps nrs 2 51,656.40 103,312.80
9 Urinals nrs 1 43,053.60 43,053.60
10 Bidet handspray nrs 2 3,274.80 6,549.60
11 Angle valves nrs 6 2,106.00 12,636.00
12 1/2"X 18" Flexible hose nrs 4 1,801.20 7,204.80
13 S/s Bottle traps for wash basins 1 1/4" nrs 2 6,890.40 13,780.80
14 Robe hook nrs 2 3,247.20 6,494.40
15 S/s Bottle traps for Urinals 1 1/4" nrs 1 6,890.40 6,890.40
Sub Total 286,375.20
Internal Sewege and Wastewater Disposal System
16 Supply and installation of 40mm Ø T600 uPvc pipes and fittings m 4.5 1,469.34 6,612.03
17 Supply and installation of 50mm Ø T600 uPvc pipes and fittings m 6 1,885.00 11,310.00
18 Supply and installation of 63mm Ø T600 uPvc pipes and fittings m 6 2,755.00 16,530.00
19 Supply and installation of 110mm Ø T600 uPvc pipes and fittings m 10 6,365.50 63,655.00
BOQ - 14
3.1 Water supply and drainage works
3.1.3 Steel Fabrication Shop
Portable Water Supply System
Supply and installation of 90mm Ø PP-R Pn10 pipes and fittings
1 m 166 8,893.34 1,476,294.44
for ring main
Supply and install one duty and standby booster pump system with
2 preassure tank fixed with Pegler or approved quality gate valves, set 1 1,125,200.00 1,125,200.00
non - return valves, control panel, etc.,. 4 Lps @ 2bar
Supply and installation of 90mm Butterfly valve with necessary
3 nr 5 106,381.67 531,908.35
fixtures
4 Supply and installation of 63mm Ø PVC T1000 pipes and fitting m 32 2,175.00 69,600.00
5 Supply and installation of 50mm Ø PVC T1000 pipes and fitting m 20 1,846.34 36,926.80
6 Supply and installation of 40mm Ø PVC T1000 pipes and fitting m 134 1,469.34 196,891.56
7 Supply and installation of 32mm Ø PVC T1000 pipes and fitting m 40 918.34 36,733.60
8 Supply and installation of 25mm Ø PVC T1000 pipes and fitting m 50 783.00 39,150.00
9 Supply and installation of 20mm Ø PVC T1000 pipes and fitting m 190 604.17 114,792.30
Supply and installation of 63mm "Pegler/Kitz" or equvivalent Gate
10 nrs 8 12,325.00 98,600.00
valves
Supply and installation of 40mm Ø "Pegler/Kitz" or equvivalent
11 nrs 3 7,200.98 21,602.94
Gate valves
Sub Total 3,747,699.99
Sanitary Fittings and Fixtures
12 Water closet nrs 38 43,226.40 1,642,603.20
13 Wash basin nrs 29 51,656.40 1,498,035.60
14 Squatting pan nrs 1 29,860.80 29,860.80
15 Urinals nrs 28 43,053.60 1,205,500.80
16 Shower nrs 24 15,649.20 375,580.80
17 Gaden taps for work shop nrs 10 6,206.40 62,064.00
18 Bidet handspray nrs 38 3,274.80 124,442.40
19 Angle valves nrs 106 2,106.00 223,236.00
20 1/2"X 18" Flexible hose nrs 68 1,801.20 122,481.60
21 Bib tap for shower area and Sq.pan nrs 25 3,783.60 94,590.00
22 S/s Bottle traps for wash basins 1 1/4" nrs 29 6,890.40 199,821.60
23 S/s Bottle traps for Urinals 1 1/4" nrs 28 6,890.40 192,931.20
24 Robe hook nrs 63 3,247.20 204,573.60
25 24" Towel rails nrs 24 6,660.00 159,840.00
Sub Total 6,135,561.60
Internal Sewege and Wastewater Disposal System
26 Supply and installation of 40mm Ø T600 uPvc pipes and fittings m 33 1,575.67 51,997.11
27 Supply and installation of 50mm Ø T600 uPvc pipes and fittings m 140 1,885.00 263,900.00
28 Supply and installation of 63mm Ø T600 uPvc pipes and fittings m 364 2,755.00 1,002,820.00
29 Supply and installation of 110mm Ø T600 uPvc pipes and fittings m 162 6,365.50 1,031,211.00
Supply and installation of uPVC trapped floor gully with good
30 m 82 8,071.67 661,876.94
quality S/S grating cover
31 Supply and installation of 63mm Ø Vent cowl nrs 10 507.50 5,075.00
TOTAL 20,335,463.96
BOQ - 15
3.1 Water supply and drainage works
TOTAL 1,427,599.60
BOQ - 16
3.1 Water supply and drainage works
3.1.5 External water supply and drainage
Supply and Installation of 40Ø Water meter with 2 nrs valve and
1 valve chamber (Gate valve - Kitz from Japan /Water meter -Baylon nr 1 54,616.67 54,616.67
from Turkey
Supply and Install 7400 gph @ 150ft Head one duty and standby
centrifugal electric water pump fixed with Pegler or approved
quality gate valves, non - return valves, including float switch,
6 control panel, etc. Set 1 1,937,200.00 1,937,200.00
Pump shall be of Europena make, Overall efficiency >60%, IP54,
Insulation Class F, non-overloading, centrifugal, back pull-out
type, end suction type
11 Supply and installation of 63mm Ø PVC T1000 pipes and fitting m 70 2,175.00 152,250.00
12 Supply and installation of 50mm Ø PVC T1000 pipes and fitting m 45 1,846.34 83,085.30
13 Supply and installation of 40mm Ø PVC T1000 pipes and fitting m 57 1,469.34 83,752.38
Supply and installation of 63mm "Pegler/Kitz" or equvivalent Gate
14 nrs 2 12,325.00 24,650.00
valves
Supply and installation of 50mm "Pegler/Kitz" or equvivalent Gate
15 nrs 2 10,560.84 21,121.68
valves with necessary fixtures
Supply and installation of 40mm Ø "Pegler/Kitz" or equvivalent
16 nrs 4 7,201.67 28,806.68
Gate valves with necessary fixtures
Supply and Installation of 40Ø Water meter with 2 nrs. of valve
17 nr 4 54,616.67 218,466.68
and valve chamber with necessary fixtures
Page 40 of 86
BILL OF QUANTITIES
31 Construction of 450 widt Rain water drain with grating cover m 250 8,400.00 2,100,000.00
32 Supply and installation of 225mm Ø RCC hume pipe m 150 6,000.00 900,000.00
Sub Total 14,090,400.00
Page 41 of 86
Bill-02.4.1-Machine Shop unit Ac-Qty
Cladding
Doors
27 D3 – 2100 x 900 AL Framed Signal Sashed Glazed Door Nos 1.00
28 D4 – 2100 x 900 AL Framed Signal Sashed Louver Door Nos 1.00
D5 – 2100 x 750 AL Framed Composite panel Door (Signal
29 Nos 1.00
Sashed)
30 RD 3 – Roller Shatter Door m2 29.45
Windows
W1 Nos 2.00
W2 Nos 3.00
32 W3 Nos 1.00
33 W4 Nos 2.00
34 FL 1200 x 600 Nos 1.00
Partition
36 Glazed Aluminium Fabric Partition office area m2 12.00
Tiling
Floor
39 600x300mm homogenous floor tile with bed m2 3.75
Wall
40 600x300mm glazed ceramic wall tiles for Washroom m2 17.00
Waterproofing work
46 Waterproofing Toilets & Slabs m2 22.00
item
TOTAL ORIGINAL SCOPE
Machine Shop
Portable Water Supply System
Supply and installation of 40mm Ø PVC T1000 pipes and fitting m 2
Supply and installation of 32mm Ø PVC T1000 pipes and fitting m 2
Supply and installation of 25mm Ø PVC T1000 pipes and fitting m 10
Supply and installation of 20mm Ø PVC T1000 pipes and fitting m 20
Supply and installation of 32mm "Pegler/Kitz" or equvivalent Gate
nrs 2
valves
Testing and commissioning Item 1
PLUMBING WORKS
TOTAL
M-01 D3 – 2100 x 900 AL Framed Signal Sashed Glazed Door -M Floor Nos 1.00
M-03.6 Tile
M-03.6.1 Floor
M-03.6.1.1 600x300mm homogenous floor tile with bed m2 8.01
M-03.6.2 Wall
M-03.6.2.1 600x300mm glazed ceramic wall tiles for Washroom m2 26.00
TOTAL
Actual Rate
Amount
(cost)
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Variation Amount
-
-
-
-
-
-
-
- ###
-
-
-
-
-
-
-
-
-
-
-
-
-
Staff salary 1,438,379.00
Vehicle rent 560,000.00
water bill 85,000.00
Electricity 75,358.00
Securyty bills 130,000.00
Pass aproval 210,000.00
Container 85,000.00
Site Running expencess 50,000.00
2,633,737.00 3,160,484.40
Design 2,158,614.00
Other Sub contractor 11,254,865.00
Aluminium
Other Civil Contractors 3,250,000.00 14,504,865.00
E System Cost
DC -88 20,634,175.05
DC -98 35,522,646.40
56,156,821.45
Material @ site
Bill - 01
1 PRELIMINARIES
1.2 Provide insurance for contractor’s plant & equipment LS 350,000.00 350,000.00 100.00% 350,000.00
1.4 Provide insurance for Contractor’s personnel LS 260,000.00 260,000.00 100.00% 260,000.00
1.5 Provide professional indemnify insurance for Contractors’ Design LS 1,200,000.00 1,200,000.00 100.00% 1,200,000.00
1.7 Maintenance of engineer’s Office 9.00 Mon 40,000.00 360,000.00 88.89% 280,000.00
1.8 Monthly progress report including progress photographs 9.00 Mon 9,000.00 81,000.00 88.89% 72,000.00
1.10 Provide and maintenance of project name board LS 150,000.00 150,000.00 100.00% 150,000.00
1.11.1 Perfomene Cecurity/ Advance bond 1.00 Item 2,783,230.00 2,783,230.00 100.00% 2,783,230.00
1.11.2 Design
1.11.2.1 Surveying & Soil Investigation 1.00 Item 1,495,000.00 1,495,000.00 100.00% 1,495,000.00
1.11.2.2 Design of Civil, WS&D, Electrical, Mechanical, ICT 1.00 Item 14,000,000.00 14,000,000.00 90.00% 12,600,000.00
1.11.2.3 shop drawings and as built drawings 1.00 Item 460,000.00 460,000.00 0.00% -
1.11.3 Contractor’s facility
1.11.3.1 Site Office / Stores - DGES 9.00 Mon 157,000.00 1,413,000.00 100.00% 1,413,000.00
1.11.3.2 Transport 1.00 Item 519,000.00 519,000.00 100.00% 519,000.00
1.11.3.3 Water, Electricity supply 1.00 Item 172,500.00 172,500.00 100.00% 172,500.00
1.11.3.4 Water, Electricity for Construction 9.00 Mon 193,500.00 1,741,500.00 100.00% 1,741,500.00
1.11.3.5 Temporary sheds and Workers Huts 1.00 Item 814,000.00 814,000.00 100.00% 814,000.00
1.11.3.7 Site running expences 9.00 Mon 64,500.00 580,500.00 100.00% 580,500.00
1.11.3.10 Vehicle For Site 9.00 Mon 601,166.67 5,410,500.00 100.00% 5,410,500.00
Project staff (PM, Des Eng, Architect, MEP Eng, Cons Eng, Mec
1.11.3.11 9.00 Mon 2,197,566.67 19,778,100.00 100.00% 19,778,100.00
Eng, Elect Eng, TO-3, Supervisors-3)
1.11.3.13 Construction of Tempory Fence 1.00 Item 1,593,900.00 1,593,900.00 100.00% 1,593,900.00
1.11.3.14 Pass & Approvels 9.00 Mon 110,500.00 994,500.00 100.00% 530,677.78
Removal of all rubbish and debris in all three sites and clearing of
1.11.3.15 1.00 Item 537,500.00 537,500.00 0.00% -
site on completion
Page 52 of 86
BILL OF QUANTITIES
BILL - 02.1
BILL NO 02 : CIVIL WORKS
2.1 Retaining wall -130m
2.1.1 Excavate trenches for the Retaining wall include Disposal 351.00 m3 1,725.00 605,475.00 60.00% 363,285.00
2.1.2 Shoring 468.00 m2 920.00 430,560.00 -
2.1.3 50mm thick screed concretes 195.00 m2 1,138.50 222,007.50 -
2.1.4 Rubble stone masonry work in Retaining wall 994.50 m3 12,880.00 12,809,160.00 20.00% 2,561,832.00
2.1.5 90mm dia Pvc Pipe G200 for weep holes 270.00 m 1,380.00 372,600.00 -
TOTAL 14,439,802.50 2,925,117.00
Page 53 of 86
BILL OF QUANTITIES
Bill-02.3.1-Machine Shop
2.3 Civil works up to ground flow level
2.3.1 Machine Shop
Excavation
1 Removing top soil for preservation average depth 150 mm 232.10 m3 492.00 114,193.20 100.00% 114,193.20
2 Excavation to reduced level 2110.00 m3 492.00 1,038,120.00 100.00% 1,038,120.00
Excavate pits & trenches for Foundation not exceeding 2.5m deep
3 390.00 m3 960.00 374,400.00 100.00% 374,400.00
commencing at formed ground level.
Foundation
9 Sawn timber and plywood sheet form work for column footings 230.00 m2 1,662.00 382,260.00 100.00% 382,260.00
10 Cold worked high yield steel bar reinforcement in Foundation 7150.00 kg 210.00 1,501,500.00 100.00% 1,501,500.00
Page 54 of 86
BILL OF QUANTITIES
Bill-02.3.2-Blacksmith
2.3 Civil works up to ground flow level
2.3.2 Blacksmith
Excavation
1 Removing top soil for preservation average depth 148.94 m3 492.00 73,278.48 100.00% 73,278.48
2 Excavation to reduced level 1354.00 m3 492.00 Deleted -
Excavate pits & trenches for Foundation not exceeding 2.5m deep
3 230.00 m3 960.00 220,800.00 100.00% 220,800.00
commencing at formed ground level.
4 Disposal directed by an Engineer 1732.94 m3 840.00 1,455,669.60 100.00% 1,455,669.60
Foundation
10 Cold worked high yield steel bar reinforcement in Foundation 4100.00 kg 210.00 861,000.00 100.00% 861,000.00
17 Supply & placing compacting and curing Grade 30 concrete in GF 135.40 m3 23,520.00 Deleted
18 Sawn timber and plywood sheet form work for GF 102.00 m 200.00 Deleted
19 Cold worked high yield steel bar reinforcement in GF 12321.40 kg 210.00 Deleted
20 Expansion/ construction joints 255.00 m 1,200.00 Deleted
Sub Total -
Dewatering
21 Dewatering 1.00 m2 200,000.00 200,000.00 66.69% 133,387.13
200,000.00 133,387.13
TOTAL 7,760,211.56 7,216,996.75
Page 55 of 86
BILL OF QUANTITIES
Excavate pits & trenches for Foundation not exceeding 2.5m deep
3 1100.00 m3 920.00 1,012,000.00 28.00% 283,360.00
commencing at formed ground level.
Foundation -
11 Sawn timber and plywood sheet form work for column footings 384.00 m2 1,592.75 611,616.00 28.0% 171,252.48
12 Cold worked high yield steel bar reinforcement in Foundation 22880.00 kg 206.00 4,713,280.00 28.0% 1,319,718.40
19 Supply & placing compacting and curing Grade 30 concrete in GF 540.00 m3 22,020.00 11,890,800.00 -
20 Sawn timber and plywood sheet form work for GF 248.00 m 230.00 57,040.00 -
21 Cold worked high yield steel bar reinforcement in GF 49140.00 kg 206.00 10,122,840.00 -
22 Expansion/ construction joints 826.00 m 1,380.00 1,139,880.00 -
Sub Total 23,697,010.00 -
Page 56 of 86
BILL OF QUANTITIES
Bill-02.3.4-Fitting Shop
2.3 Civil works up to ground flow level
2.3.4 Fitting Shop
Excavation
1 Removing top soil for preservation average depth 150 mm 214.50 m3 492.00 105,534.00 100.00% 105,534.00
2 Excavation to reduced level 1950.00 m 3
492.00 Deleted
Excavate pits & trenches for Foundation not exceeding 2.5m deep
3 380.00 m 3
960.00 364,800.00 88.00% 321,024.00
commencing at formed ground level.
Foundation
10 Cold worked high yield steel bar reinforcement in Foundation 6700.00 kg 210.00 1,407,000.00 88.00% 1,238,160.00
Sub Total 6,681,984.00 5,145,417.79
Anti Termite Treatment
Page 57 of 86
BILL OF QUANTITIES
Bill-02.4.1-Machine Shop
2.4 Civil works above ground flow level
2.4.1 Machine Shop
Columns
Supply, fabricate & erect in the position of steel structure
1 24.63 ton 457,730.00 11,271,601.25 95.00% 10,708,021.19
consisting of columns with painting
2 Supply Fabricate, erect of Steel Fire Stare case ( 9m H) 2.00 Nos 750,000.00 1,500,000.00 83.00% 1,244,949.16
3 Gr 8.8 Bolt & Nuts 0.13 ton 444,611.70 55,576.46 100.00% 55,576.46
Supply & Fix MS anchor bolts , 24mm dia x 600 Gr 8.8 and
4 necessary nuts washers etc. Rate to include for provinding non - 300 Nos 2,600.00 780,000.00 100.00% 780,000.00
shrinkage grouts to column top and holes
5 Concrete / Fw/ Rf for stiffener column 100.00 m 1,600.00 160,000.00
Sub Total 13,767,177.71 12,788,546.81
Beams
Supply, fabricate & erect in the position of steel structure
6 64.03 ton 457,730.00 29,306,163.25 95.00% 27,840,855.09
consisting of columns with painting
7 Gr 8.8 Bolt & Nuts 0.33 ton 444,611.70 144,498.80 100.00% 144,498.80
8 Concrete / Fw/ Rf for stiffener column 100.00 m 1,600.00 160,000.00
Sub Total 29,610,662.05 27,985,353.89
Slab
9 Supply & fixing of 0.75mm Structural Decking 35.00 m2 5,094.74 178,315.90
10 Supply & fixing of Decking end closures 40.00 m 5,094.74 203,789.60
11 Supply and fixing of Sher struds 1500.00 Nos 477.48 716,220.00
12 Supply & placing compacting and curing Grade 30 concrete in GF 7.00 m3 23,520.00 164,640.00
13 Sawn timber and plywood sheet form work for GF 35.00 m2 1,800.00 63,000.00
14 Cold worked high yield steel bar reinforcement in GF 630.00 kg 220.50 138,915.00
15 Expansion/ construction joints 35.00 m 1,600.00 56,000.00
Sub Total 1,520,880.50 -
Roof
Supply, fabricate & erect in the position of steel structure
16 9.85 ton 457,730.00 4,508,640.50 95.00% 4,283,208.48
consisting of columns with painting
17 Gr 8.8 Bolt & Nuts 0.05 ton 444,611.70 22,230.59 100.00% 22,230.59
18 G 450 Purling Coating 200g/m2 15.00 ton 405,545.00 6,083,175.00
19 Zn/Al Roofing 0.47mm thick, 550MPa, AZ 200 1550.00 m2 2,672.63 4,142,576.50
20 Supply & Installation of Ridge Cap 140.00 m 2,536.21 355,069.40
21 Supply & Installation of Gutter 280.00 m 2,536.21 710,138.80
22 Supply & Installation of Down pipe 420.00 m 2,660.23 1,117,296.60
23 Supply & Installation of Roof Insulation 1400.00 m2 1,482.04 2,074,856.00
24 Supply & Fix Tie rods 542.50 Nos 300.00 162,750.00
25 Supply & Fix Barge / eaves & Coner capping 420.00 m 1,600.00 672,000.00
Sub Total 19,848,733.39 4,305,439.06
Page 58 of 86
BILL OF QUANTITIES
Masonry works
37 225mm thick Brick works 144.00 m2 4,900.00 705,600.00 70.00% 493,920.00
38 112.5 mm thick Brick works 167.00 m2 2,500.00 417,500.00
Sub Total 1,123,100.00 493,920.00
Tiling
Floor
39 600x300mm homogenous floor tile with bed 5.00 m2 6,500.00 32,500.00
Wall
40 300x300mm glazed ceramic wall tiles for Washroom 57.00 m2 5,700.00 324,900.00
Sub Total 357,400.00 -
Plastering
41 internal & external Plastering 622.00 m2 1,200.00 746,400.00
Sub Total 746,400.00 -
Power trowel finish
42 Power trowel Floor finish GF 2048.00 m2 900.00 Deleted
Sub Total -
Cement Render finish
43 Cement Render finish 18.00 m2 900.00 16,200.00
Sub Total 16,200.00
Painting
44 External Painting ( 5 coat paint) 207.33 m2 1,400.00 290,266.67
45 Internal Painting ( 3 coat paint) 414.67 m2 1,250.00 518,333.33
Sub Total 808,600.00
Waterproofing work
46 Waterproofing Toilets & Slabs 80.00 m2 2,600.00 208,000.00
Sub Total 208,000.00
TOTAL 83,480,258.81 45,573,259.76
Page 59 of 86
BILL OF QUANTITIES
3 Gr 8.8 Bolt & Nuts 0.13 ton 444,611.70 55,576.46 90% 50,018.82
Supply & Fix MS anchor bolts , 24mm dia x 600 Gr 8.8 and
4 necessary nuts washers etc. Rate to include for provinding non - 200 Nos 2,600.00 520,000.00 100% 520,000.00
shrinkage grouts to column top and holes
5 Concrete / Fw/ Rf for stiffener column 75.00 m 1,600.00 120,000.00
Sub Total 5,908,443.96 5,181,386.80
Beams
Supply, fabricate & erect in the position of steel structure
6 25.35 ton 457,730.00 11,603,455.50 95% 11,023,282.73
consisting of columns with painting
7 Gr 8.8 Bolt & Nuts 0.33 ton 444,611.70 144,498.80 90% 130,048.92
8 Concrete / Fw/ Rf for stiffener column 75.00 m 1,600.00 120,000.00
Sub Total 11,867,954.30 11,153,331.65
Slab
9 Supply & fixing of 0.75mm Structural Decking 40.00 m2 5,094.74 203,789.60
10 Supply & fixing of Decking end closures 20.00 m 5,094.74 101,894.80
11 Supply and fixing of Sher struds 1500.00 Nos 477.48 716,220.00
12 Supply & placing compacting and curing Grade 30 concrete in GF 8.00 m3 23,520.00 188,160.00
13 Sawn timber and plywood sheet form work for GF 40.00 m2 1,800.00 72,000.00
14 Cold worked high yield steel bar reinforcement in GF 720.00 kg 220.50 158,760.00
15 Expansion/ construction joints 40.00 m 1,600.00 64,000.00
Sub Total 1,504,824.40
Roof
Supply, fabricate & erect in the position of steel structure
16 3.90 ton 457,730.00 1,785,147.00 95% 1,695,889.65
consisting of columns with painting
17 Gr 8.8 Bolt & Nuts 0.05 ton 444,611.70 22,230.59 90% 20,007.53
18 G 450 Purling Coating 200g/m2 7.50 ton 405,545.00 3,041,587.50
19 Zn/Al Roofing 0.47mm thick, 550MPa, AZ 200 950.00 m2 2,672.63 2,538,998.50
20 Supply & Installation of Ridge Cap 60.00 m 2,536.21 152,172.60
21 Supply & Installation of Gutter 120.00 m 2,536.21 304,345.20
22 Supply & Installation of Down pipe 150.00 m 2,660.23 399,034.50
23 Supply & Installation of Roof Insulation 850.00 m2 1,482.04 1,259,734.00
24 Supply & Fix Tie rods 332.50 Nos 300.00 99,750.00
25 Supply & Fix Barge / eaves & Coner capping 180.00 m 1,600.00 288,000.00
Sub Total 9,890,999.89 1,715,897.18
Page 60 of 86
BILL OF QUANTITIES
Tiling
36 Floor
37 600x300mm homogenous floor tile with bed 35.00 m2 6,500.00 227,500.00
38 Wall
39 300x300mm glazed ceramic wall tiles for Washroom 75.00 m2 5,700.00 427,500.00
Sub Total 655,000.00
Plastering
40 internal & external Plastering 350.00 m2 1,200.00 420,000.00
Sub Total 420,000.00
Power trowel finish
41 Power trowel Floor finish GF 642.00 m2 900.00 Deleted
Sub Total -
Cement Render finish
42 Cement Render finish 35.00 m2 900.00 31,500.00
Sub Total 31,500.00
Painting
43 External Painting ( 5 coat paint) 116.67 m2 1,400.00 163,333.33
44 Internal Painting ( 3 coat paint) 233.33 m2 1,250.00 291,666.67
Sub Total 455,000.00
Waterproofing work
45 Waterproofing Toilets & Slabs 145.00 m2 2,600.00 377,000.00
Sub Total 377,000.00
TOTAL 39,112,643.77 18,161,495.62
Page 61 of 86
BILL OF QUANTITIES
3 Supply Fabricate, erect of Steel Fire Stare case ( 9m H) 4.00 Nos 735,000.00 2,940,000.00
Supply & Fix MS anchor bolts , 24mm dia x 600 Gr 8.8 and
5 necessary nuts washers etc. Rate to include for provinding non - 650 Nos 2,990.00 1,943,500.00
shrinkage grouts to column top and holes
6 Concrete / Fw/ Rf for stiffener column 650.00 m 1,564.00 1,016,600.00
Sub Total 64,208,348.86
Beams
Supply, fabricate & erect in the position of steel structure
7 328.25 ton 332,189.73 109,041,277.80
consisting of columns
8 Sand blasting & prime coat , Painting , Fir Proof Painting 328.25 ton 122,135.85 40,091,093.42
20 Sand blasting & prime coat , Painting , Fir Proof Painting 50.50 ton 122,135.85 6,167,860.53
Page 62 of 86
BILL OF QUANTITIES
Page 63 of 86
BILL OF QUANTITIES
2 Supply Fabricate, erect of Steel Fire Stare case ( 9m H) 2.00 Nos 750,000.00 1,500,000.00
3 Gr 8.8 Bolt & Nuts 0.13 ton 444,611.70 55,576.46 80.00% 0.00
Supply & Fix MS anchor bolts , 24mm dia x 600 Gr 8.8 and
4 necessary nuts washers etc. Rate to include for provinding non - 300 Nos 2,600.00 780,000.00 88.00% 0.01
shrinkage grouts to column top and holes
5 Concrete / Fw/ Rf for stiffener column 100.00 m 1,600.00 160,000.00
Sub Total 12,508,420.21 8,510,917.20
Beams
Supply, fabricate & erect in the position of steel structure
6 56.88 ton 457,730.00 26,033,393.75 80.00% 20,826,715.00
consisting of columns with painting
7 Gr 8.8 Bolt & Nuts 0.33 ton 444,611.70 144,498.80 80.00% 115,599.04
8 Concrete / Fw/ Rf for stiffener column 100.00 m 1,600.00 160,000.00
Sub Total 26,337,892.55 20,942,314.04
Slab
9 Supply & fixing of 0.75mm Structural Decking 85.00 m2 5,094.74 433,052.90
10 Supply & fixing of Decking end closures 65.00 m 5,094.74 331,158.10
11 Supply and fixing of Sher struds 1500.00 Nos 477.48 716,220.00
12 Supply & placing compacting and curing Grade 30 concrete in GF 17.00 m3 23,520.00 399,840.00
13 Sawn timber and plywood sheet form work for GF 85.00 m2 1,800.00 153,000.00
14 Cold worked high yield steel bar reinforcement in GF 1530.00 kg 220.50 337,365.00
15 Expansion/ construction joints 85.00 m 1,600.00 136,000.00
Sub Total 2,506,636.00
Roof
Supply, fabricate & erect in the position of steel structure
16 8.75 ton 457,730.00 4,005,137.50 80.00% 3,204,110.00
consisting of columns with painting
17 Gr 8.8 Bolt & Nuts 0.05 ton 444,611.70 22,230.59
18 G 450 Purling Coating 200g/m2 13.00 ton 405,545.00 5,272,085.00
19 Zn/Al Roofing 0.47mm thick, 550MPa, AZ 200 1550.00 m2 2,672.63 4,142,576.50
20 Supply & Installation of Ridge Cap 70.00 m 2,536.21 177,534.70
21 Supply & Installation of Gutter 140.00 m 2,536.21 355,069.40
22 Supply & Installation of Down pipe 300.00 m 2,660.23 798,069.00
23 Supply & Installation of Roof Insulation 1400.00 m2 1,482.04 2,074,856.00
24 Supply & Fix Tie rods 542.50 Nos 300.00 162,750.00
25 Supply & Fix Barge / eaves & Coner capping 210.00 m 1,600.00 336,000.00
Sub Total 17,346,308.69 3,204,110.00
Page 64 of 86
BILL OF QUANTITIES
Page 65 of 86
BILL OF QUANTITIES
Masonry works
38 150mm thick solid Block works 110.00 m2 3,168.00 348,480.00
39 225mm thick Brick works 259.60 m2 4,900.00 1,272,040.00
Sub Total 1,620,520.00
Tiling
40 Floor
41 600x300mm homogenous floor tile with bed 30.00 m2 6,500.00 195,000.00
42 Wall
43 300x300mm glazed ceramic wall tiles for Washroom 110.00 m2 5,700.00 627,000.00
Sub Total 822,000.00
Plastering
44 internal & external Plastering 739.20 m2 1,200.00 887,040.00
Sub Total 887,040.00
Power trowel finish
45 Power trowel Floor finish GF 945.00 m2 900.00 850,500.00
Sub Total 850,500.00
Cement Render finish
46 Cement Render finish 18.00 m2 900.00 16,200.00
Sub Total 16,200.00
Painting
47 External Painting ( 5 coat paint) 246.40 m2 1,400.00 344,960.00
48 Internal Painting ( 3 coat paint) 492.80 m2 1,250.00 616,000.00
Sub Total 960,960.00
Waterproofing work
49 Waterproofing Toilets & Slabs 158.00 m2 2,600.00 410,800.00
Sub Total 410,800.00
Concrete Canopy around the building
50 Supply & placing compacting and curing Grade 30 concrete in GF 37.80 m3 23,520.00 889,056.00
51 Form work 160.00 m 1,662.00 265,920.00
52 Cold worked high yield steel bar reinforcement in GF 3439.80 kg 210.00 722,358.00
Sub Total 1,877,334.00
TOTAL 83,134,177.59 32,657,341.24
Page 66 of 86
BILL OF QUANTITIES
2.1.5 90mm dia Pvc Pipe G200 for weep holes 270.00 m 1,800.00 486,000.00 2.62%
TOTAL 18,547,290.00 104.91% 4.64%
BOQ - 03
2.3 Civil works up to ground flow level
2.3.1 Machine Shop
Excavation
Removing top soil for preservation average depth
1 200.00 m3 500.00 100,000.00 0.80% 100.00% 0.80%
150 mm
2 Excavation to reduced level 2110.00 m3 698.00 1,472,780.00 11.74% 100.00% 11.74%
Excavate pits & trenches for Foundation not
3 exceeding 2.5m deep commencing at formed ground 390.00 m3 1,250.00 487,500.00 3.89% 100.00% 3.89%
level.
Foundation
Filling with ABC fill material, to make up levels
5 under floors Compacted ,well rammed and 300.00 m3 6,825.00 2,047,500.00 16.32% 100.00% 16.32%
consolidated
6 Shoring 800.00 m2 - - 0.00% 100.00% 0.00%
7 In 50mm thick blinding layer under Foundation 90.00 m2 2,334.00 210,060.00 1.67% 100.00% 1.67%
BOQ - 04
2.3 Civil works up to ground flow level
2.3.2 Blacksmith
Excavation
1 Removing top soil for preservation average depth 102.00 m3 500.00 51,000.00 0.77% 100.00% 0.76547960742063100%
2 Excavation to reduced level 1354.00 m 3
886.00 Deleted
Excavate pits & trenches for Foundation not
3 exceeding 2.5m deep commencing at formed ground 230.00 m3 2,200.00 506,000.00 7.59% 100.00% 7.59%
level.
4 Disposal directed by an Engineer 400.00 m3 1,370.00 548,000.00 8.23% 100.00% 8.23%
Foundation
Filling with ABC fill material, to make up levels
5 under floors Compacted ,well rammed and 200.00 m3 6,800.00 1,360,000.00 20.41% 100.00% 20.41%
consolidated
6 Shoring 500.00 m2 - - 0.00% 100.00% 0.00%
7 In 50mm thick blinding layer under Foundation 60.00 m2 2,440.00 146,400.00 2.20% 100.00% 2.20%
Page 67 of 86
BILL OF QUANTITIES
BOQ - 05
2.3 Civil works up to ground flow level
2.3.3 Steel Fabrication Shop
Excavation
Removing top soil for preservation average depth
1 410.00 m3 848.00 347,680.00 347,680.00 0.69% 100.00% 0.69%
150 mm
2 Excavation to reduced level 800.00 m 3
900.00 720,000.00 648,000.00 1.42% 90.00% 1.28%
Excavate pits & trenches for Foundation not
3 exceeding 2.5m deep commencing at formed ground 1100.00 m3 1,475.00 1,622,500.00 352,717.39 3.20% 21.74% 0.70%
level.
4 De watering 200,000.00 43,478.26 0.39% 21.74% 0.09%
5 Disposal directed by an Engineer 2310.00 m3 1,195.00 2,760,450.00 600,097.83 5.45% 21.74% 1.18%
Foundation
9 In 50mm thick blinding layer under Foundation 320.00 m2 2,438.00 780,160.00 169,600.00 1.54% 21.74% 0.33%
Page 68 of 86
BILL OF QUANTITIES
TOTAL 50,658,593.50
BOQ - 06 14.27%
4 Disposal directed by an Engineer 600.00 m3 1,370.00 822,000.00 369,900.00 4.26% 45.00% 1.92%
Foundation
Filling with ABC fill material, to make up levels
5 under floors Compacted ,well rammed and 300.00 m3 7,850.00 2,355,000.00 1,059,750.00 12.20% 45.00% 5.49%
consolidated
6 Shoring 750.00 m2 1,525.00 1,143,750.00 514,687.50 5.92% 45.00% 2.67%
7 In 50mm thick blinding layer under Foundation 90.00 m2 2,440.00 219,600.00 98,820.00 1.14% 45.00% 0.51%
BOQ - 07
2.4 Civil works above ground flow level
2.4.1 Machine Shop
Columns
1 Supply & Fabricate of steel structure with painting 24.41 ton 750,270.00 18,315,966.38 18,315,966.38 21.37% 100.00% 21.37%
1.1 Transport to site & Erection 24.41 ton 100,800.00 2,460,780.00 2,249,856.00 2.87% 91.43% 2.62%
2 Supply Fabricate of Steel Fire Stare case ( 9m H) 2.00 Nos 638,000.00 1,276,000.00 1.49%
2.1 Erect of Steel Fire Stare case ( 9m H) 2.00 Nos 112,000.00 224,000.00 0.26%
3 Gr 8.8 Bolt & Nuts 0.13 ton 533,534.04 55,576.46 0.06%
6 Supply & Fabricate of steel structure with painting 63.47 ton 750,270.00 47,621,512.58 47,621,512.58 55.55% 100.00% 55.55%
6.1 Transport to site & Erection 63.47 ton 100,800.00 6,398,028.00 6,398,028.00 7.46% 100.00% 7.46%
7 Gr 8.8 Bolt & Nuts 0.33 ton 638,000.00 207,350.00 207,350.00 0.24% 100.00% 0.24%
8 Concrete / Fw/ Rf for stiffener column 100.00 m 2,500.00 250,000.00 0.29%
Page 69 of 86
BILL OF QUANTITIES
16 Supply & Fabricate of steel structure with painting 10.28 ton 750,270.00 7,710,149.66 7,710,149.66 8.99% 100.00% 8.99%
16.1 Transport to site & Erection 10.28 ton 100,800.00 1,035,871.20 880,490.52 1.21% 85.00% 1.03%
Sub Total -
Cement Render finish
43 Cement Render finish 18.00 m2 900.00 16,200.00 0.02%
Sub Total 16,200.00
Painting
44 External Painting ( 5 coat paint) 207.33 m2 1,400.00 290,266.67 0.34%
45 Internal Painting ( 3 coat paint) 414.67 m2 1,375.00 570,166.67 0.67%
Sub Total 860,433.33
Waterproofing work
46 Waterproofing Toilets & Slabs 80.00 m2 2,600.00 208,000.00 0.24%
Sub Total 208,000.00
Page 70 of 86
BILL OF QUANTITIES
BOQ - 08
2.4 Civil works above ground flow level
2.4.2 Blacksmith Shop
Columns
1 Supply & Fabricate of steel structure with painting 8.14 ton 750,270.00 6,105,322.13 6,105,322.13 16.39% 100.00% 16.39%
1.1 Transport to site & Erection 8.14 ton 100,800.00 820,260.00 779,247.00 2.20% 95.00% 2.09%
2 Supply Fabricate of Steel Fire Stare case ( 9m H) 1.00 Nos 638,000.00 638,000.00 1.71%
2.1 Erect of Steel Fire Stare case ( 9m H) 1.00 Nos 112,000.00 112,000.00 0.30%
6 Supply & Fabricate of steel structure with painting 21.16 ton 750,270.00 15,873,837.53 15,873,837.53 42.61% 100.00% 42.61%
6.1 Transport to site & Erection 21.16 ton 100,800.00 2,132,676.00 2,026,042.20 5.73% 95.00% 5.44%
7 Gr 8.8 Bolt & Nuts 0.33 ton 638,000.00 207,350.00 196,982.50 0.56% 95.00% 0.53%
8 Concrete / Fw/ Rf for stiffener column 75.00 m 2,500.00 187,500.00 0.50%
Sub Total 10,297,181.30
Slab
9 Supply & fixing of 0.75mm Structural Decking 40.00 m2 5,451.37 218,054.87 0.59%
10 Supply & fixing of Decking end closures 20.00 m 5,094.74 101,894.80 0.27%
11 Supply and fixing of Sher struds 1500.00 Nos 477.48 716,220.00 1.92%
Supply & placing compacting and curing Grade 30
12 8.00 m3 25,872.00 206,976.00 0.56%
concrete in GF
13 Sawn timber and plywood sheet form work for GF 40.00 m2 2,200.00 88,000.00 0.24%
Cold worked high yield steel bar reinforcement in
14 720.00 kg 230.00 165,600.00 0.44%
GF
15 Expansion/ construction joints 40.00 m 1,600.00 64,000.00 0.17%
Sub Total 1,560,745.67
Roof
16 Supply & Fabricate of steel structure with painting 3.26 ton 750,270.00 2,442,128.85 2,442,128.85 6.56% 100.00% 6.56%
16.1 Transport to site & Erection 3.26 ton 100,800.00 328,104.00 311,698.80 0.88% 95.00% 0.84%
17 Gr 8.8 Bolt & Nuts 0.05 ton 638,000.00 31,900.00 30,305.00 0.09% 95.00% 0.08%
18 G 450 Purling Coating 200g/m2 7.50 ton 446,099.50 3,345,746.25 8.98%
19 Zn/Al Roofing 0.47mm thick, 550MPa, AZ 200 950.00 m2 2,672.63 2,538,998.50 6.82%
20 Supply & Installation of Ridge Cap 60.00 m 2,536.21 152,172.60 0.41%
21 Supply & Installation of Gutter 120.00 m 2,536.21 304,345.20 0.82%
22 Supply & Installation of Down pipe 150.00 m 2,660.23 399,034.50 1.07%
23 Supply & Installation of Roof Insulation 850.00 m2 1,482.04 1,259,734.00 3.38%
24 Supply & Fix Tie rods 332.50 Nos 300.00 99,750.00 0.27%
25 Supply & Fix Barge / eaves & Coner capping 180.00 m 1,600.00 288,000.00 0.77%
Sub Total 9,943,116.64
Page 71 of 86
BILL OF QUANTITIES
37 600x300mm homogenous floor tile with bed 35.00 m2 6,800.00 238,000.00 0.64%
38 Wall
300x300mm glazed ceramic wall tiles for
39 75.00 m2 6,270.00 470,250.00 1.26%
Washroom
Sub Total 708,250.00
Plastering
40 internal & external Plastering 350.00 m2 1,200.00 420,000.00 1.13%
Sub Total 420,000.00
Power trowel finish
41 Power trowel Floor finish GF 642.00 m2 900.00 Deleted
Sub Total -
Cement Render finish
42 Cement Render finish 35.00 m2 900.00 31,500.00 0.08%
Sub Total 31,500.00
Painting
43 External Painting ( 5 coat paint) 116.67 m2 1,400.00 163,333.33 0.44%
44 Internal Painting ( 3 coat paint) 233.33 m2 1,375.00 320,833.33 0.86%
Sub Total 484,166.67
Waterproofing work
45 Waterproofing Toilets & Slabs 145.00 m2 2,600.00 377,000.00 1.01%
Sub Total 377,000.00
TOTAL 37,251,307.26 28,358,364.00
BOQ - 09 76.13%
1 Supply & Fabricate of steel structure with painting 116.81 ton 387,000.00 45,206,437.50 11.59%
3.1 Erect of Steel Fire Stare case ( 9m H) 4.00 Nos 112,000.00 448,000.00 0.11%
7 Supply & Fabricate of steel structure with painting 303.71 ton 387,000.00 117,536,737.50 30.14%
19 Supply & Fabricate of steel structure with painting 46.73 ton 387,000.00 18,082,575.00 4.64%
Page 72 of 86
BILL OF QUANTITIES
Windows
W – 2400 x Varies AL Framed Glass Window with
36 5.00 Nos 84,240.00 421,200.00 0.11%
Lover on both side
W5 – 1650 x 1200 AL Framed Glass Window with
37 155.00 Nos 36,270.00 5,621,850.00 1.44%
Lover on top
W8 – 1080 x 900 AL Framed Glass Window with
38 80.00 Nos 17,784.00 1,422,720.00 0.36%
Lover on top
W9 – 1650 x 2100 AL Framed Glass Window with
39 23.00 Nos 63,063.00 1,450,449.00 0.37%
Lover on top
40 FL – 1080 x 600 Top hung Fanlight 112.00 Nos 11,583.00 1,297,296.00 0.33%
Sub Total 10,213,515.00
Chain link fence
CF - Al Framed Chain link fence Meash ( 5000 x
41 36.00 Nos 35,100.00 1,263,600.00 0.32%
1200)
Sub Total 1,263,600.00
Partition
42 Glazed Aluminium Fabric Partition office area 400.95 m2 18,302.76 7,338,491.62 1.88%
Sub Total 7,338,491.62
Masonry works
43 200mm thick solid Block works 2600.00 m2 4,530.24 11,778,624.00 3.02%
44 150mm thick solid Block works 900.00 m2 3,397.68 3,057,912.00 0.78%
45 100mm thick solid Block works 320.00 m2 2,471.04 790,732.80 0.20%
Sub Total 15,627,268.80
Tiling
Floor
46 600x600mm semi glazed homogenous floor tile 1741.04 m2 6,800.00 11,839,072.00 3.04%
47 600x300mm homogenous floor tile 80.00 m2 6,800.00 544,000.00 0.14%
48 300x300mm nonskid homogenous floor tile 870.16 m2 6,756.75 5,879,453.58 1.51%
Wall
300x300mm glazed ceramic wall tiles for
49 410.00 m2 6,113.25 2,506,432.50 0.64%
Washroom
Sub Total 20,768,958.08
Plastering
50 internal & external Plastering 7640.00 m2 1,404.00 10,726,560.00 2.75%
Sub Total 10,726,560.00
Power trowel finish
51 Power trowel Floor finish GF 2652.00 m2 1,200.00 3,182,400.00 0.82%
Sub Total 3,182,400.00
Painting
52 External Painting ( 5 coat paint) 2600.00 m2 1,638.00 4,258,800.00 1.09%
53 Internal Painting ( 3 coat paint) with potty 2030.00 m2 1,608.75 3,265,762.50 0.84%
Sub Total 7,524,562.50
TOTAL 389,908,972.38
BOQ - 10
2.4 Civil works above ground flow level
2.4.4 Fitting Shop
Columns
1 Supply & Fabricate of steel structure with painting 22.05 ton 750,270.00 16,543,453.50 16,543,453.50 18.79% 100.00% 18.79%
1.1 Transport to site & Erection 22.05 ton 100,800.00 1,852,200.00 2.10%
2 Supply Fabricate of Steel Fire Stare case ( 9m H) 2.00 Nos 638,000.00 1,276,000.00 1.45%
2.1 Erect of Steel Fire Stare case ( 9m H) 2.00 Nos 112,000.00 224,000.00 0.25%
6 Supply & Fabricate of steel structure with painting 57.33 ton 750,270.00 43,012,979.10 38,711,681.19 48.86% 90.00% 43.98%
1.1 Transport to site & Erection 57.33 ton 100,800.00 4,815,720.00 5.47%
16 Supply & Fabricate of steel structure with painting 8.82 ton 750,270.00 6,617,381.40 5,955,643.26 7.52% 90.00% 6.77%
16.1 Transport to site & Erection 8.82 ton 100,800.00 740,880.00 0.84%
Page 73 of 86
BILL OF QUANTITIES
BOQ - 11 69.54%
BOQ - 12
BILL NO 03 : WATER SUPPLY AND
3
DRAINAGE WORKS
3.1 Water supply and drainage works
3.1.1 Machine Shop
Portable Water Supply System
Supply and installation of 40mm Ø PVC T1000
1 m 2 1,469.34 2,938.68 0.25%
pipes and fitting
Supply and installation of 32mm Ø PVC T1000
2 m 2 918.34 1,836.68 0.16%
pipes and fitting
Supply and installation of 25mm Ø PVC T1000
3 m 2 783.00 1,566.00 0.13%
pipes and fitting
Supply and installation of 20mm Ø PVC T1000
4 m 10 604.17 6,041.70 0.52%
pipes and fitting
Supply and installation of 32mm "Pegler/Kitz" or
5 nrs 2 5,945.00 11,890.00 1.02%
equvivalent Gate valves
6 Testing and commissioning Item 1 3,386.94 3,386.94 0.29%
Sub Total 27,660.00
Sanitary Fittings and Fixtures
20 Supply and installation of 63mm Ø Vent cowl nrs 1 507.50 507.50 0.04%
21 Supply and installation of 110mm Ø Vent cowl nrs 1 783.00 783.00 0.07%
22 Testing and commissioning Item 1 2,425.48 2,425.48 0.21%
Sub Total 58,410.00
Rainwater Disposal System
23 Construction of 300 width drain around the building m ### 5,400.00 928,800.00 79.79%
Sub Total 928,800.00
TOTAL 1,164,117.60
BOQ - 13
3.1 Water supply and drainage works
3.1.2 Blacksmith Shop
Portable Water Supply System
Supply and installation of 40mm Ø PVC T1000
1 m 2 1,469.34 2,938.68 0.27%
pipes and fitting
Supply and installation of 32mm Ø PVC T1000
2 m 2 918.34 1,836.68 0.17%
pipes and fitting
Supply and installation of 25mm Ø PVC T1000
3 m 4 783.00 3,132.00 0.29%
pipes and fitting
Supply and installation of 20mm Ø PVC T1000
4 m 6 604.17 3,625.02 0.34%
pipes and fitting
Supply and installation of 32mm "Pegler/Kitz" or
5 nrs 2 5,945.00 11,890.00 1.11%
equvivalent Gate valves
6 Testing and commissioning Item 1 2,417.62 2,417.62 0.23%
Sub Total 25,840.00
Sanitary Fittings and Fixtures
Page 75 of 86
BILL OF QUANTITIES
8 SLS 568 - Ceramic Squatting Pans and Traps nrs 2 51,656.40 103,312.80 9.66%
9 Urinals nrs 1 43,053.60 43,053.60 4.03%
10 Bidet handspray nrs 2 3,274.80 6,549.60 0.61%
11 Angle valves nrs 6 2,106.00 12,636.00 1.18%
12 1/2"X 18" Flexible hose nrs 4 1,801.20 7,204.80 0.67%
13 S/s Bottle traps for wash basins 1 1/4" nrs 2 6,890.40 13,780.80 1.29%
14 Robe hook nrs 2 3,247.20 6,494.40 0.61%
15 S/s Bottle traps for Urinals 1 1/4" nrs 1 6,890.40 6,890.40 0.64%
Sub Total 286,375.20
Internal Sewege and Wastewater Disposal
System
Supply and installation of 40mm Ø T600 uPvc pipes
16 m 4.5 1,469.34 6,612.03 0.62%
and fittings
Supply and installation of 50mm Ø T600 uPvc pipes
17 m 6 1,885.00 11,310.00 1.06%
and fittings
Supply and installation of 63mm Ø T600 uPvc pipes
18 m 6 2,755.00 16,530.00 1.55%
and fittings
Supply and installation of 110mm Ø T600 uPvc
19 m 10 6,365.50 63,655.00 5.95%
pipes and fittings
Supply and installation of uPVC trapped floor gully
20 m 4 8,071.67 32,286.68 3.02%
with good quality S/S grating cover
21 Supply and installation of 63mm Ø Vent cowl nrs 1 507.50 507.50 0.05%
22 Supply and installation of 110mm Ø Vent cowl nrs 1 783.00 783.00 0.07%
23 Testing and commissioning Item 1 4,355.79 4,355.79 0.41%
Sub Total 136,040.00
Rainwater Disposal System
24 Construction of 300 width drain around the building m 120 5,175.00 621,000.00 58.08%
621,000.00
TOTAL 1,069,255.20
BOQ - 14
3.1 Water supply and drainage works
3.1.3 Steel Fabrication Shop
Portable Water Supply System
Supply and installation of 90mm Ø PP-R Pn10 pipes
1 m 166 8,893.34 1,476,294.44 7.26%
and fittings for ring main
Supply and install one duty and standby booster
pump system with preassure tank fixed with Pegler
2 set 1 1,125,200.00 1,125,200.00 5.53%
or approved quality gate valves, non - return valves,
control panel, etc.,. 4 Lps @ 2bar
Supply and installation of 90mm Butterfly valve
3 nr 5 106,381.67 531,908.35 2.62%
with necessary fixtures
Supply and installation of 63mm Ø PVC T1000
4 m 32 2,175.00 69,600.00 0.34%
pipes and fitting
Supply and installation of 50mm Ø PVC T1000
5 m 20 1,846.34 36,926.80 0.18%
pipes and fitting
Supply and installation of 40mm Ø PVC T1000
6 m 134 1,469.34 196,891.56 0.97%
pipes and fitting
Supply and installation of 32mm Ø PVC T1000
7 m 40 918.34 36,733.60 0.18%
pipes and fitting
Supply and installation of 25mm Ø PVC T1000
8 m 50 783.00 39,150.00 0.19%
pipes and fitting
Supply and installation of 20mm Ø PVC T1000
9 m 190 604.17 114,792.30 0.56%
pipes and fitting
Supply and installation of 63mm "Pegler/Kitz" or
10 nrs 8 12,325.00 98,600.00 0.48%
equvivalent Gate valves
Supply and installation of 40mm Ø "Pegler/Kitz" or
11 nrs 3 7,200.98 21,602.94 0.11%
equvivalent Gate valves
Sub Total 3,747,699.99
Sanitary Fittings and Fixtures
12 Water closet nrs 38 43,226.40 1,642,603.20 8.08%
13 Wash basin nrs 29 51,656.40 1,498,035.60 7.37%
14 Squatting pan nrs 1 29,860.80 29,860.80 0.15%
15 Urinals nrs 28 43,053.60 1,205,500.80 5.93%
16 Shower nrs 24 15,649.20 375,580.80 1.85%
17 Gaden taps for work shop nrs 10 6,206.40 62,064.00 0.31%
18 Bidet handspray nrs 38 3,274.80 124,442.40 0.61%
19 Angle valves nrs 106 2,106.00 223,236.00 1.10%
20 1/2"X 18" Flexible hose nrs 68 1,801.20 122,481.60 0.60%
21 Bib tap for shower area and Sq.pan nrs 25 3,783.60 94,590.00 0.47%
22 S/s Bottle traps for wash basins 1 1/4" nrs 29 6,890.40 199,821.60 0.98%
23 S/s Bottle traps for Urinals 1 1/4" nrs 28 6,890.40 192,931.20 0.95%
24 Robe hook nrs 63 3,247.20 204,573.60 1.01%
25 24" Towel rails nrs 24 6,660.00 159,840.00 0.79%
Sub Total 6,135,561.60
Internal Sewege and Wastewater Disposal
System
Supply and installation of 40mm Ø T600 uPvc pipes
26 m 33 1,575.67 51,997.11 0.26%
and fittings
Supply and installation of 50mm Ø T600 uPvc pipes
27 m 140 1,885.00 263,900.00 1.30%
and fittings
Supply and installation of 63mm Ø T600 uPvc pipes
28 m 364 2,755.00 1,002,820.00 4.93%
and fittings
Supply and installation of 110mm Ø T600 uPvc
29 m 162 6,365.50 1,031,211.00 5.07%
pipes and fittings
Supply and installation of uPVC trapped floor gully
30 m 82 8,071.67 661,876.94 3.25%
with good quality S/S grating cover
31 Supply and installation of 63mm Ø Vent cowl nrs 10 507.50 5,075.00 0.02%
32 Supply and installation of 110mm Ø Vent cowl nrs 8 783.00 6,264.00 0.03%
Page 76 of 86
BILL OF QUANTITIES
TOTAL 20,335,463.96
BOQ - 15
3.1 Water supply and drainage works
Sanitary
Supply and Fittings and Fixtures
fix pedestal type water closet including
cistern, approval with all accessories such as WC
connector, flush pipe, seat cover approved angle
valves and flexible connector installed etc.
7 nrs 3 43,226.40 129,679.20 9.08%
complete to working order ( Water Closet will be
Rocell - Aqua+ Product Number is
RB.AQP.03G119.01.09 or equalent and white
color)
8 Construction of 300 width drain around the building nrs 2 51,656.40 103,312.80 7.24%
9 Urinals nrs 1 43,053.60 43,053.60 3.02%
10 Gaden taps nrs 2 6,206.40 12,412.80 0.87%
11 Bidet handspray nrs 3 3,274.80 9,824.40 0.69%
12 Angle valves nrs 8 2,106.00 16,848.00 1.18%
13 1/2"X 18" Flexible hose nrs 5 1,801.20 9,006.00 0.63%
14 S/s Bottle traps for wash basins 1 1/4" nrs 2 6,890.40 13,780.80 0.97%
15 S/s Bottle traps for Urinals 1 1/4" nrs 1 6,890.40 6,890.40 0.48%
16 Robe hook nrs 3 3,247.20 9,741.60 0.68%
17 Sub Total 354,549.60
Internal Sewege and Wastewater Disposal
18
System
Supply and installation of 40mm Ø T600 uPvc pipes
19 m 4.5 1,575.67 7,090.52 0.50%
and fittings
Supply and installation of 50mm Ø T600 uPvc pipes
20 m 3 1,885.00 5,655.00 0.40%
and fittings
Supply and installation of 63mm Ø T600 uPvc pipes
21 m 10 2,755.00 27,550.00 1.93%
and fittings
Supply and installation of 110mm Ø T600 uPvc
22 m 10 6,365.50 63,655.00 4.46%
pipes and fittings
Supply and installation of uPVC trapped floor gully
23 m 5 8,071.67 40,358.35 2.83%
with good quality S/S grating cover
24 Supply and installation of 63mm Ø Vent cowl nrs 1 507.50 507.50 0.04%
25 Supply and installation of 110mm Ø Vent cowl nrs 1 783.00 783.00 0.05%
26 Testing and commissioning Item 1 6,290.63 6,290.63 0.44%
TOTAL 1,427,599.60
BOQ - 16
3.1 Water supply and drainage works
3.1.5 External water supply and drainage
Page 77 of 86
BILL OF QUANTITIES
Page 78 of 86
Democratic Socialist Republic of Sri Lanka Ministry of Ports & Shipping
0
Bill No 03 WATER SUPPLY AND DRAINAGE WORKS 0 -
Material
7.9 Cement OPC in 50kg bag No 10 1,200.00 12,000.00
7.10 Reinforcing steel t 1 156,000.00 156,000.00
7.11 River Sand cu.m 5 8,040.00 40,200.00
7.12 20mm Aggregate cu.m 5 3,480.00 17,400.00
7.13 150 – 225mm Rubble cu.m 5 2,880.00 14,400.00
7.14 Concrete G 15 cu.m 5 15,600.00 78,000.00
7.15 Concrete G 25 cu.m 5 16,800.00 84,000.00
7.16 ABC cu.m 5 3,000.00 15,000.00
7.17 Asphalt concrete hot mix t 10 15,000.00 150,000.00
Equipment
7.18 Lorry 3-5 ton hr 60 2,400.00 144,000.00
7.19 Dump Truck 4-6 Ton hr 60 2,400.00 144,000.00
7.20 Dump Truck 10 Ton hr 60 2,640.00 158,400.00
7.21 Water Bowser hr 60 2,640.00 158,400.00
7.22 Bitumen Distributer hr 60 3,500.00 210,000.00
7.23 Bull Dozer wheeled or tracked, 100 to 200 hp hr 60 4,320.00 259,200.00
7.24 Backhoe tracked 50 – 100 hp hr 60 3,840.00 230,400.00
7.25 Excavator 200 or equivalent hr 60 4,600.00 276,000.00
Total for Bill No.1 (Carried to Summary of Bills) 2,605,800.00 - - -
8.4 Spatial tests ordered by the engineer PS Item 2,000,000.00 0.2724875 544,975.00 - 21,900.00 0.2834375 566,875.00
Payment of employer’s protection to the Dispute
8.5 PS Item 1,000,000.00
Board
8.6 Reinstatement of utilities and road works PS Item 5,000,000.00
Total for Bill No.1 (Carried to Summary of Bills) . 12,000,000.00 544,975.00 21,900.00 566,875.00
-
TOTAL AMOUNT WITHOUT VAT 47,526,575.46