Based on the given project details, the project plan for the development of e-service portal
project for eLicences can be created as follows:
Q1. Start Date: Week 2 of Semester 1, 2023
Q2. Duration: 6 weeks
Q3. Total Budget: $4m
Q4. Resources:
• 10 units of Develops (C)
• 2 units of Project Managers (P)
• 5 units of Testing (D)
Q5. Cost per Hour:
• Develops ©: $1500/hour
• Project Managers (P): $900/hour
• Testing (D): $400/hour
Q6. Precedence: Finish-to-Start
Q7. Task Duration: Fixed Duration
Q8. Future Information: Contact Convenor
Based on these details, the project plan can be created using MS Project 2019 or any
other project management software. The tasks can be identified, and the dependencies
between them can be established based on the finish-to-start method. The resources can
be allocated to the tasks based on their availability and cost per hour. The duration of
each task can be estimated based on its complexity and the resources allocated to it.
Gantt Chart
Task Name Duration Start Finish Predecessors
Phase 1 42 days 3/21/23 5/17/23
Project Initiation 4 days 3/21/23 3/24/23
Requirement
5 days 3/27/23 3/31/23 2
development
Phase 2 33 days 4/3/23 5/17/23
Design Development 1 day 4/3/23 4/3/23 3
Program Design 2 days 4/3/23 4/4/23
Stuff Themes 2 days 4/5/23 4/6/23
Decide 2 days 4/7/23 4/10/23
Pass To Code
1 day 4/11/23 4/11/23
developer
Code Development 2 days 4/13/23 4/14/23 5
Programing Expert 2 days 4/13/23 4/14/23
Program Checker 2 days 4/17/23 4/18/23
Program Designer 1 day 4/19/23 4/19/23
Move for Testing 1 day 4/21/23 4/21/23
Phase 3 17 days 4/25/23 5/17/23
Tester 2 days 4/25/23 4/26/23 10
Check Bugs 2 days 4/26/23 4/27/23
Debug the code 2 days 4/28/23 5/1/23
User Acceptance
2 days 5/2/23 5/3/23
Testing
Approved Code 1 day 5/4/23 5/4/23 16
Phase 4 9 days 5/5/23 5/17/23
Deployment 4 days 5/5/23 5/10/23 20
Deploy in Place 2 days 5/5/23 5/8/23 22
Rolling 2 days 5/8/23 5/9/23 23
Project Closure 5 days 5/11/23 5/17/23 24
Network Diagram: