NAME OF THE WORK : APPROXIMATE BOQ FOR PROPOSED MRC FACILITY AT TAKWE
1 of 16
KBP CIVIL ENGG. SERVICES, PUNE. Abstract
2 of 16
KBP CIVIL ENGG. SERVICES, PUNE. Abstract
CPWD Extra for compaction of earth work in embankment under optimum moisture conditions to
4.0 2021/16.2/325 give at least 95% of the maximum dry density (proctor density).
3 of 16
KBP CIVIL ENGG. SERVICES, PUNE. Abstract
4 of 16
KBP CIVIL ENGG. SERVICES, PUNE. Abstract
CPWD Laying, spreading and compacting stone aggregate of specified sizes to WBM specifications
2021/16.4/325 in uniform thickness, hand picking, rolling with 3 wheeled road/vibratory roller 8-10 tonne
6.0 capacity in stages to proper grade and camber, applying and brooming requisite type of
screening / binding material to fill up interstices of coarse aggregate, watering and
compacting to the required density .
1 3 lane High speed city ring Roads Cum
(200m length) 720.00 865.8 623376
2 3 lane High speed city ring Roads Cum 1080.00 865.8 935064
3 (300m
4 length)
lane High speed city Roads Cum 1111.50 865.8 962336.7
4 Inner city roads Cum 672.00 865.8 581817.6
5 4 lane road Cum 1800.00 865.8 1558440
6 7(Rural road) Cum 225.00 865.8 194805
7 Mini s curve Cum 189.00 865.8 163636.2
8 S curve Cum 900.00 865.8 779220
9 Signal intersection Cum 159.60 865.8 138181.68
10 pedestrian crossing Cum 14.70 865.8 12727.26
11 Underpass Cum 360.00 865.8 311688
12 Round about Cum 48.00 865.8 41558.4
13 Euroncap junction Cum 84.00 865.8 72727.2
Total Quantity Cum 7363.80 865.8 6,375,578.04
CPWD Scarifying metalled (water-bound) road surface including disposal of rubbish, lead upto 50 m
7.0 2021/16.9/326 and consolidation of the aggregate received from scarifying with power road roller of 8 to 10
tonne capacity.
1 3 lane High speed city ring Roads Cum
(200m length) 2400.00 27.55 66120
2 3 lane High speed city ring Roads Cum 3600.00 27.55 99180
3 (300m
4 length)
lane High speed city Roads Cum 3705.00 27.55 102072.75
4 Inner city roads Cum 2240.00 27.55 61712
5 4 lane road Cum 3600.00 27.55 99180
6 7(Rural road) Cum 750.00 27.55 20662.5
7 Mini s curve Cum 588.00 27.55 16199.4
8 S curve Cum 1064.00 27.55 29313.2
9 Signal intersection Cum 400.00 27.55 11020
10 pedestrian crossing Cum 147.00 27.55 4049.85
11 Underpass Cum 1200.00 27.55 33060
12 Round about Cum 480.00 27.55 13224
13 Euroncap junction Cum 280.00 27.55 7714
Total Quantity SqM 20454.00 27.55 563,507.70
5 of 16
KBP CIVIL ENGG. SERVICES, PUNE. Abstract
PWD SSR 2021- Prime coat - Providing and applying primer coat with bitumen emulsion on prepared surface
8.0 22/139/28 of granular Base including cleaning of road surface and spraying, primer at the rate of 0.60
kg/sqm using mechanical means.
1 3 lane High speed city ring Roads Cum
(200m length) 2400.00 26 62400
2 3 lane High speed city ring Roads Cum 3600.00 26 93600
3 (300m
4 length)
lane High speed city Roads Cum 3705.00 26 96330
4 Inner city roads Cum 2240.00 26 58240
5 4 lane road Cum 3600.00 26 93600
6 7(Rural road) Cum 750.00 26 19500
7 Mini s curve Cum 588.00 26 15288
8 S curve Cum 1064.00 26 27664
9 Signal intersection Cum 400.00 26 10400
10 pedestrian crossing Cum 147.00 26 3822
11 Underpass Cum 1200.00 26 31200
12 Round about Cum 480.00 26 12480
13 Euroncap junction Cum 280.00 26 7280
Total Quantity SqM 20454.00 26 531,804.00
SSR 2021- DENSE BITUMINOUS MACADAM:--Providing and laying dense bituminous macadam using
22/3.46/31 crushed aggregate of grading 1, premixed with bituminous binder Bitumen of specified
grade,@ 4.50 % by weight of total mix and filler, transported at site with VTS, laid over a
previously prepared surface , finished to the required grade ,level, alignment,and rolling to
achieve the desired density for 76/100 mm compacted thickness with drum mix type hot
mix plant with SCADA having complying essential features of Hot mix plant as per IRC-27-
9.0
2009 specified conditions and attachments such as electronic load sensor based belt
conveyers, automatic synchronization of bitumen and aggregate fedder,built in dust
controller system and PLC for Drum Mix plant ,Sensor paver, and Vibratory roller excluding
prime/Tack coat etc. complete --Bitumen VG-30 grade with stone dust filler (VG-30 bulk
bitumen rates are considered to arrive at rates)
6 of 16
KBP CIVIL ENGG. SERVICES, PUNE. Abstract
CPWD Providing and applying tack coat using bitumen emulsion conforming to IS:8887, using
10.0 2021/16.31/329 emulsion pressure distributer including preparing the surface & cleaning with mechanical
broom.
16.30.2 On W.B.M / W.M.M. @ 0.4kg/sqm
1 3 lane High speed city ring Roads Cum
(200m length) 2400.00 11.6 27840
2 3 lane High speed city ring Roads Cum 3600.00 11.6 41760
3 (300m
4 length)
lane High speed city Roads Cum 3705.00 11.6 42978
4 Inner city roads Cum 2240.00 11.6 25984
5 4 lane road Cum 3600.00 11.6 41760
6 7(Rural road) Cum 0.00 11.6 0
7 Mini s curve Cum 588.00 11.6 6820.8
8 S curve Cum 1064.00 11.6 12342.4
9 Signal intersection Cum 400.00 11.6 4640
10 pedestrian crossing Cum 49.00 11.6 568.4
11 Underpass Cum 1200.00 11.6 13920
12 Round about Cum 960.00 11.6 11136
13 Euroncap junction Cum 280.00 11.6 3248
Total Quantity SqM 20086.00 11.6 232,997.60
7 of 16
KBP CIVIL ENGG. SERVICES, PUNE. Abstract
CPWD Extra for compaction of earth work in embankment under optimum moisture conditions to
12.0
2021/16.2/325 give at least 95% of the maximum dry density (proctor density).
Cum 70 20.55 1,438.50
SSR 2021- Construction of dry lean cement concrete Sub- base over a prepared sub-grade with coarse
22/5.13,181/37 and fine aggregate ( natural sand/ VSI grade finely washed crushed sand) conforming to IS:
383, the size of coarse aggregate not exceeding 25 mm, , cement content not to be less than
150 kg/ cum, optimum moisture content to be determined during trial length construction,
concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant/ Weigh
13.0 batch mixer, transported to site with all leads and lifts, laid with a paver with electronic
sensor /by suitable means as approved by Engineer-in-charge , compacting with vibratory
roller, finishing, curing and including preparation of sub-grade surface if required etc.
complete.
8 of 16
KBP CIVIL ENGG. SERVICES, PUNE. Abstract
9 of 16
KBP CIVIL ENGG. SERVICES, PUNE. Abstract
10 of 16
KBP CIVIL ENGG. SERVICES, PUNE. Abstract
Providing RCC railing of cast in situ / ready mix RCC posts with M20 CC of trap/ granite/
quartzite/ gneiss metal for horizontal and vertical members as per detailed drawings
PWD SSR 2021- including reinforcement, scaffolding, centering, formwork, compaction, finishing and curing
27.0 22/483,14.49 with watering chemical compound etc. complete. (fully automatic micro processor based
BR51C/74 PLC with SCADA enabled with reversible drum type mixer/ concrete batch mix plant (pan
mixer) fine agreegates of required specifications ( VSI sand finely washed etc
11 of 16
KBP CIVIL ENGG. SERVICES, PUNE. Abstract
13 of 16
KBP CIVIL ENGG. SERVICES, PUNE. Abstract
14 of 16
KBP CIVIL ENGG. SERVICES, PUNE. Abstract
15 of 16
KBP CIVIL ENGG. SERVICES, PUNE. Abstract
Amount ₹ 286,831,314.95
Contengencies charges (2.5%) ₹ 7,170,782.87
Total amount ₹ 294,002,097.82
GST 18% ₹ 52,920,377.61
NET TOTAL AMOUNT ₹ 346,922,475.43
AMOUNT IN WORDS: Thirty four crore sixty nine lakh twenty two thousand four hundred seventy five rupees only.
16 of 16