Method Statement Cable Termination

The document provides instructions for installing low voltage cable. It outlines the responsibilities of those involved, including chargemen, kone testers, kone subcontractors, and contractors. It also lists the necessary tools and safety equipment. Finally, it describes the work flow process which includes approving a method statement, safely parking lifts, disconnecting power, terminating cables, testing, and reconnecting power.

Uploaded by

faizbukhari
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
557 views

Method Statement Cable Termination

The document provides instructions for installing low voltage cable. It outlines the responsibilities of those involved, including chargemen, kone testers, kone subcontractors, and contractors. It also lists the necessary tools and safety equipment. Finally, it describes the work flow process which includes approving a method statement, safely parking lifts, disconnecting power, terminating cables, testing, and reconnecting power.

Uploaded by

faizbukhari
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Rev: 2022-04

LV CABLE INSTALLATION
Date: 11 Oct 2022
INSTALLATION OF LOW VOLTAGE CABLE Page: 1

WMS WORK FLOW


PROJECT HTAR UITM

1.0 WORK FLOW Start

Documentation

Submit the proposed method


statement for cable termination

Remedial
Approval by Superintendent Officer
NO works

YES
Ready all necessary
material and equipment

Termination

FINISH
Rev: 2022-04
LV CABLE INSTALLATION
Date: 11 Oct 2022
INSTALLATION OF LOW VOLTAGE CABLE Page: 2

WMS WORK METHODOLOGY


PROJECT HTAR UITM

2.0 RESPONSIBILITY
1. Chargemen: To safely switch off at any incoming power for termination purposes. To
terminate all cables. To make sure everything post termination according to Borang G and
Borang H and signed.
2. Kone Tester: To safely park all lift prior to power disconnection. To start up the lift once cable
termination is finished and ensure all lifts to run normal.
3. Kone Subcontractor: To rewire all lifts cables from temporary switchboard to permanent
switchboard.
4. UITM: Ensure it is filled and signed by the appointed chargeman
5. Contractor: To prepare and update the attendance list of responsible participants. Also, to
ensure smooth communication between all participants.

3.0 TOOLS
1. Hydraulic crimping tools
2. Gas Torch
3. Insulation tester
4. Rotation meter
5. Spanner (ring-type)
6. Cordless Battery Drills
7. Cutter and Grinder
8. Safety matts
9. Safety glove
Rev: 2021-04
LV CABLE INSTALLATION
Date: 11 Oct 2022

INSTALLATION OF LOW VOLTAGE CABLE Page: 3

WMS WORK PROCEDURE


PROJECT HTAR UITM

4.0 WORK FLOW

1. Method statement shall be approved by the S.O. prior to start the work on site.
2. To ensure nobody in the lift by parking it at ground floor or top floor (whichever convenient)
before power disconnection to avoid mantrap.
3. Kone subcontractor is to be ready at the assigned motor room to dismantle all neccessary
part.
4. To fix heat shrinkage type termination kit for each incoming power cables. Then, crimp the
cable lugs suited for 50mm2 (melati & mawar) & 16mm for DB Lighting cable for termina-

tion purposes. While for FSPU & Old Engineering 25mm2


5. To turn off the power supply at the MCCB for lift and other relevant switch only by chargemen.

Once power supply disconnected, Kone subcontractor will start to switch all the lift cables
into the permanent switchboard.
6. At the same time, chargeman will terminate the cables by screwing the cable lugs in place for
the designated motor room.
7. Once termination is done, chargeman will do insulation test and phase rotation test for the
cables to ensure no electric leakage and other potential hazard.
8. Finally, power supply is turned back on to reenergized the lifts. Repeat step 2 for the other
motor room.