Method Statement Cable Termination
Method Statement Cable Termination
LV CABLE INSTALLATION
Date: 11 Oct 2022
INSTALLATION OF LOW VOLTAGE CABLE Page: 1
Documentation
Remedial
Approval by Superintendent Officer
NO works
YES
Ready all necessary
material and equipment
Termination
FINISH
Rev: 2022-04
LV CABLE INSTALLATION
Date: 11 Oct 2022
INSTALLATION OF LOW VOLTAGE CABLE Page: 2
2.0 RESPONSIBILITY
1. Chargemen: To safely switch off at any incoming power for termination purposes. To
terminate all cables. To make sure everything post termination according to Borang G and
Borang H and signed.
2. Kone Tester: To safely park all lift prior to power disconnection. To start up the lift once cable
termination is finished and ensure all lifts to run normal.
3. Kone Subcontractor: To rewire all lifts cables from temporary switchboard to permanent
switchboard.
4. UITM: Ensure it is filled and signed by the appointed chargeman
5. Contractor: To prepare and update the attendance list of responsible participants. Also, to
ensure smooth communication between all participants.
3.0 TOOLS
1. Hydraulic crimping tools
2. Gas Torch
3. Insulation tester
4. Rotation meter
5. Spanner (ring-type)
6. Cordless Battery Drills
7. Cutter and Grinder
8. Safety matts
9. Safety glove
Rev: 2021-04
LV CABLE INSTALLATION
Date: 11 Oct 2022
1. Method statement shall be approved by the S.O. prior to start the work on site.
2. To ensure nobody in the lift by parking it at ground floor or top floor (whichever convenient)
before power disconnection to avoid mantrap.
3. Kone subcontractor is to be ready at the assigned motor room to dismantle all neccessary
part.
4. To fix heat shrinkage type termination kit for each incoming power cables. Then, crimp the
cable lugs suited for 50mm2 (melati & mawar) & 16mm for DB Lighting cable for termina-
Once power supply disconnected, Kone subcontractor will start to switch all the lift cables
into the permanent switchboard.
6. At the same time, chargeman will terminate the cables by screwing the cable lugs in place for
the designated motor room.
7. Once termination is done, chargeman will do insulation test and phase rotation test for the
cables to ensure no electric leakage and other potential hazard.
8. Finally, power supply is turned back on to reenergized the lifts. Repeat step 2 for the other
motor room.