Fence Boq - Bubuyan

The document is a bill of materials for a proposed perimeter fence project located in Bubuyan, Philippines. It lists the materials, quantities, unit costs, and total costs for siteworks, structural concrete, structural steel, forms and scaffolds, masonry, wall finishes, and a gate. The grand total cost for all items is 328,068.44 Philippine pesos. The owner of the project is listed as Allan Villela.

Uploaded by

Eugene Villalva
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
191 views

Fence Boq - Bubuyan

The document is a bill of materials for a proposed perimeter fence project located in Bubuyan, Philippines. It lists the materials, quantities, unit costs, and total costs for siteworks, structural concrete, structural steel, forms and scaffolds, masonry, wall finishes, and a gate. The grand total cost for all items is 328,068.44 Philippine pesos. The owner of the project is listed as Allan Villela.

Uploaded by

Eugene Villalva
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 1

BILL OF MATERIALS

Project : PROPOSED PERIMETER FENCE


Location : BUBUYAN, BRGY. A. DALUSAG, GENERAL EMILIO AGUINALDO, CAVITE
Owner : ALLAN VILLELA

MAT'L UNIT LABOR UNIT


DESCRIPTION QTY UNIT MATERIAL COST LABOR COST LINE TOTAL
AMT AMT
A. GENERAL REQUIREMENTS 1.00 Lot 10,000.00

B. SITEWORKS
1.0 Site Clearing and Layout 140.00 sq.m. - 30.00 4,200.00 4,200.00
2.0 Excavation 66.00 cu.m. - 100.00 6,600.00 6,600.00
3.0 Backfill & Compaction 33.00 cu.m. - 35.00 1,155.00 1,155.00
4.0 Gravel Bedding 9.00 cu.m. 750.00 6,750.00 35.00 315.00 7,065.00
5.0 Hauling 1.00 lot - - 3,500.00 3,500.00 3,500.00

C. STRUCTURAL CONCRETE
1.0 Column Footing 3000Psi @ 28days strength 8.20 cu.m. 2,500.00 20,500.00 145.00 1,189.00 21,689.00
2.0 Wall Footing 3000Psi @ 28days strength 10.40 cu.m. 2,500.00 26,000.00 145.00 1,508.00 27,508.00
3.0 Columns 3000Psi @ 28days strength 4.38 cu.m. 2,500.00 10,937.50 145.00 634.38 11,571.88

D. STRUCTURAL STEEL G.40


1.0 Column Footing 320.00 kgs. 25.00 8,000.00 3.00 960.00 8,960.00
2.0 Wall Footing 283.00 kgs. 25.00 7,075.00 3.00 849.00 7,924.00
3.0 Columns 400.00 kgs. 25.00 10,000.00 3.00 1,200.00 11,200.00
4.0 Tie wires 24.07 kgs. 80.00 1,925.76 25.00 601.80 2,527.56

E. FORMS & SCAFFOLDS


1.0 Form Plywood 25.00 sq.m. 140.00 3,500.00 110.00 2,750.00 6,250.00
2.0 Form Lumber 92.00 bd.ft. 45.00 4,140.00 15.00 1,380.00 5,520.00
3.0 Scaffoldings 1.00 lot 1,800.00 1,800.00 1,500.00 1,500.00 3,300.00
4.0 Assorted Nails 4.60 kgs. 75.00 345.00 Included 345.00

F. MASONRY
1.0 100mm Ordinary CHB (Including Mortar) 272.00 sq.m. 160.00 43,520.00 160.00 43,520.00 87,040.00

G. WALL FINISHES
1.0 Wall Plastering (1-Side only) 355.00 sq.m. 110.00 39,050.00 80.00 28,400.00 67,450.00

H. GATE
1.0 G1 (4.0M ) Steel Gate 1.00 Set 25,380.00 25,380.00 8,883.00 8,883.00 34,263.00

GRAND TOTAL 328,068.44

PREPARED BY:
JEFFREY C. DELA CRUZ
Civil Engineer

07/25/2023 06:10:46 1 of 1 680876133.xls Detailed Breakdown I