Fence Boq - Bubuyan
Fence Boq - Bubuyan
B. SITEWORKS
1.0 Site Clearing and Layout 140.00 sq.m. - 30.00 4,200.00 4,200.00
2.0 Excavation 66.00 cu.m. - 100.00 6,600.00 6,600.00
3.0 Backfill & Compaction 33.00 cu.m. - 35.00 1,155.00 1,155.00
4.0 Gravel Bedding 9.00 cu.m. 750.00 6,750.00 35.00 315.00 7,065.00
5.0 Hauling 1.00 lot - - 3,500.00 3,500.00 3,500.00
C. STRUCTURAL CONCRETE
1.0 Column Footing 3000Psi @ 28days strength 8.20 cu.m. 2,500.00 20,500.00 145.00 1,189.00 21,689.00
2.0 Wall Footing 3000Psi @ 28days strength 10.40 cu.m. 2,500.00 26,000.00 145.00 1,508.00 27,508.00
3.0 Columns 3000Psi @ 28days strength 4.38 cu.m. 2,500.00 10,937.50 145.00 634.38 11,571.88
F. MASONRY
1.0 100mm Ordinary CHB (Including Mortar) 272.00 sq.m. 160.00 43,520.00 160.00 43,520.00 87,040.00
G. WALL FINISHES
1.0 Wall Plastering (1-Side only) 355.00 sq.m. 110.00 39,050.00 80.00 28,400.00 67,450.00
H. GATE
1.0 G1 (4.0M ) Steel Gate 1.00 Set 25,380.00 25,380.00 8,883.00 8,883.00 34,263.00
PREPARED BY:
JEFFREY C. DELA CRUZ
Civil Engineer