Risk Assessment of Shuttering
Risk Assessment of Shuttering
:0
RISK IDENTIFICATION AND CONTROL
Date of Rev:
SIL-HSE-F-06
03.10.07
b) Fall of shuttering b) May cause L a)proper handling of material by skilled worker and ACE
materials injury to no short cut
personnel b) During de-shuttering of material the area is to be ACE
barricaded at bottom side.
02. Working at 1. Defective 1. Fall injury / H 1.Construction of scaffolding only by experienced ACE
height scaffolding fatality persons under the supervision of a competent person
3. vertigo while 3. Dizziness and H 3.a) Confirm non – attack of vertigo in the past before ACE
working at height fall injury / allowing to work at heights
fatality
b) Accompany the workers for the 1st time to check ACE
up and ensure that he does not suffer from vertigo.
HSE MANAGEMENT SYSTEM Rev no.:0
RISK IDENTIFICATION AND CONTROL
Date of Rev:
SIL-HSE-F-06
03.10.07
5. Inadequate area 5. Injury by trip / L 5. Platform to be of sufficient area for optimum ACE
on the platform slip and fall movements of the workers
8. Faulty mounting 8. Injury by trip / L 8. Provide ladder on firm footing at appropriate ACE
of the ladder slip and fall inclination and fasten on top
10. Heavy wind 10. Fall of person, H 10.a) Do not work in the wind speed more than 25 ACE /PME
speed at height as fall of material, knot/hrs. at any time of day.
working near sea deviation of b) Take adequate precaution to hold the material from
shore material and flying.
working plat form c) Hard barrication around, and use of safety net,
safety harness.
d) Use of adequate equipment catering for average
wind speed.
HSE MANAGEMENT SYSTEM Rev no.:0
RISK IDENTIFICATION AND CONTROL
Date of Rev:
SIL-HSE-F-06
03.10.07