Procedure - Testing and Calibration of Metering Equipment
Procedure - Testing and Calibration of Metering Equipment
EQUIPMENT INVOLVED
Testing and I. Testing and Calibration of - Meter Site Analyzer - Metering - Working
Kilowatt-hour Meter - PWS with Phantom Specialist/ Gloves
Calibration of
Loader (alternative) Metering Officer - Safety
Metering - Pliers Shoes
Equipment - Screw drivers
- Connecting wires
- Alligator clips
- ORMECO Seal
● Purpose - Ballpen
– To ensure that - Test Report Form
metering i. Secure Transformer If Consumer owned:
equipments are Recommendation Sheet and
Meter Testing Fee Secure Transformer
compliant with the
Recommendation Sheet
standard set by the and Meter Testing Fee
cooperative and If Coop owned:
ERC, before
acceptance, Secure ERC Test Report
installation, and from the Supplier and
energization Certificate of Acceptance
ii. Inspection of meter Receive the kwh meter
from Warehouse / walk-in
consumer.
● Scope Verify and inspect if there’s
- All type of nothing suspicious, it
meters and should have ERC seal
instrument and/or sticker
transformers Endorsed meter should
comply with recommended
as indicated in the
Transformer
Recommendation Sheet
a. If Compliant:
Proceed to testing
b. If non-compliant:
return to the
supplier/ consumer
subject for
replacement (not
accepted)
iii. Testing of kwh meter Check the connections and
the set-up of test
equipment from the power
source. Engage the meter
to the test equipment but
make sure that no
load/ampere is applied by
the phantom loader to
prevent possible
burns/accident.
Make sure to make proper
connections to the Load
Side and Line side of the
kWh meter.
Switch on the Phantom
Loader and the test
equipment.
Install and align the
impulse sensor to the
LED/impulse indicator of
the meter, then set the
proper configuration
(impulse per kWh) in the
test equipment to be able
to get accurate test results.
Shut down the Phantom
loader and the test
equipment. Gently remove
the connections of the
terminal of the meter from
the Phantom Loader. Put
back the terminal cover
with the screw
iv. Recording of data and secure Record the percent error
test report that appears from the test
equipment.
Observe the meter for
other remarks and
findings.
Jot down information and
test result to the Metering
Equipment Log Book.
a. If Passed: Meter shall
be sealed and approved
for installation; to be
programmed if needed
b. If Failed: Meter shall be
rendered to the
supplier/ consumer
subject for replacement,
together with signed
test report
v. Programming of the meter Meter shall be
programmed by the
Metering Officer/ SE
Section Head depending
on the data/parameters
needed.
A copy of program shall be
printed and filed for future
reference.
vi. End of procedure