OPERATION INSTRUCTION P:01
SYSTEM
SYSTEM
THE AIR INCL. DUST & FIBER PASSING THROUGH FILTER DRUM FROM OUTSIDE
OF DRUM. DRUM IS COVERED WITH "SAMTEN" FILTER SCREEN IN ORDER TO
CATCH FIBER & DUST. AT EACH DRUM SECTION THERE IS ONE SUCTION
NOZZLE. FILTER DRUM CONTINUOUSLY ROTARES AND SUCTION NOZZLE
RECIPROCALLY MOVING. EVACUATION FAN GIVES SUCTION AIR PRESSURE AT
NOZZLE TO SUCK FIBER & DUST FROM FILTER SCREEN TO DUST COLLECTOR.
4.3 GEARMOTOR
FEED OIL FOR GEARMOTOR.
FILTER EFFICIENCY. NOZZLE CAN NOT DIRECTLY TOUCH FILTER DRUM MESH
EVACUATION FAN
2.4 SUPPORT
SUPPORT ANGLE FIX IN FAN CASING FOR WALL INSTALLATION.
4.1 MOTOR
CLEAN COOLING END OF MOTOR TO AVOID FIBER TO PILE UP THERE,
THAT CAN CAUSE DAMAGE.
BEARING OF MOTOR
REPLACE MOTOR BEARING AFTER 5 YEARS RUNNING.
BESTAIR ENGINEERING
OPERATION AND MAINTENANCE INSTRUCTION P:07
DUST COLLECTOR
EVACUATED AIR TOGETHER WITH FIBER AND DUST IS BLOWN INTO COLLECT
-OR INLET BOX BY EVACUATION FAN. AIR FLITTED BY CLOTH TUBE CATCH
FIBER AND DUST PILE UP INSIDE CLOTH TUBE. CLEAN AIR MOVES THROUGH
CLOTH TUBE AND RECYCLES BACK TO FILTER ROOM. KEEP EVACUATION FAN
INTERMITTER RUNNING ( 15-20 MIN. ON / 3-5 MIN. OFF ) DURING EVACUATION
OFF, RETURN AIR FAN SUCTION PRESSURE CAUSE PIPE AIR REVERSE WITH
SLOW SPEED. BASE ON REVERSE PRESSURE, FIBER AND DUST IS TAKEN OFF
FROM CLOTH TUBE AND DROP TO BOTTOM OF WASTE BAG.
1. OPERATION INSTRUCTION
AIR WASHER
1. OPERATION INSTRUCTION
AIR WASHER
WATER PUMP
2.1 CASING
MADE BY STEEL SHEET, THAT IS WELDED AND CONNECTED WITH MOTOR BASE
2.2 IMPELLER
MADE BY STEEL.
2.3 MOTOR
USING HORIZONTAL FOOT MOUNTED.
3.1 MOTOR
PAY ATTENTION TO THE ROTATION DIRECTION.
3.2 IMPELLER
SHOULD BE CLEANED REGULARLY TO AVOID WASTE OR FIBER STICK OVER
THERE, THAT CAN MAKE MOTOR OVERLOAD BECAUSE OF OVERWEIGHT
IMPELLER.
BESTAIR ENGINEERING
OPERATION AND MAINTENANCE INSTRUCTION P:17
FIBER COMPACTOR
1. OPERATION INSTRUCTION
MATERIAL TRANSFER FAN TAKE FIBER, DUST AND AIR FROM MACHINES
INTO FIBER COMPACTOR THROUGH WASTE REMOVAL TUBE LINES.
GEARMOTOR DRIVES CONVEYOR WORM THAT PUSH FIBER AND DUST
DOWNWARDS TO THE DIAPHRAGM.
USING THE DIAPHRAGM'S TENSION CAN CROWD OUT FIBER AND DUST.
2.1 GEARMOTOR
FLANGED TYPE MOTOR IS INSTALLED ON THE TOP OF FIBER COMPACTOR
AND CAN DRIVE CONVEYOR WORM.
2.2 CASING
ROLLED STEEL SHEET.
2.6 DIAPHRAGM
THE MATERIAL IS MADE BY STAINLESS STEEL SHEET. AND THEIR TENSION
DEPEND ON THE WASTE MATERIAL.
FIBER COMPACTOR
CENTRIFUGAL BLOWER
2,1 IMPELLER
BEFORE START UP, IMPELER MUST ROTATES MANUALLY. CHECK IT,
WHETHER IT HAVE ABNORMAL NOISE. CLEAN THE FILTH ON
IMPELLER SURFACE DURING MAINTENANCE TO REDUCE LOAD.
2,2 MOTOR
CHECK MOTOR'S ROTATION DIRECTION AND ELECTRIC CONNECTIONS.
2,3 BEARING
MAKE SURE THAT LUBRICATING OIL IS POURED INTO BEARING HOUSE
BEFORE START UP.
BESTAIR ENGINEERING
MAINTENANCE SCHEDULE TABLE P:20
EQUIPMENT D W M Q H Y
AIR CONDITION SYSTEM
RETURN AIR FLOOR GRILL CK,CL
ROTARY AIR FILTER CK CL AJ RP
EVACUATION FAN CK
DUST COLLECTOR CK,CL
AXIAL AIR FAN CK CL
CONTROL AIR DAMPER CK CL
AIR WASHER CK CL
ROTARY WATER FILTER CK,CL
A/C STATION DOOR CK CL
SWITCHBOARD CK CL AJ
ELECTRIC CONTROL SYSTEM CK CL AJ
SUPPLY AIR DUCT CK,CL
UNDERGROUND RETURN AIR DUCT CK,CL
D = DAILY CK = CHECK
W = WEEKLY CL = CLEAN
M = MONTHLY AJ = ADJUST
Q = QUARTERLY RP = REPLACE PARTS
H = HALF YEARLY
Y = YEARLY
BESTAIR ENGINEERING
LUBRICATION FOR BLOWER, PUMP AND GEARBOX P:21
WATER PUMP
GEAR BOX OF
- DISK FILTER
- FIBER COMPACTOR
NOTE
MARKS
: CHECKING
: C G G
CHANGING