Project Management - Class Lecture
Project Management - Class Lecture
Some difficulties to meet for the necessary condition for successful project
Badweather
Unforeseeable (হ্ঠাৎ) difficulties at vendors (বিক্রেতারা)who supply
equipment.
Longer than expected time in meeting government requirement.
An unrealistic schedule.
4
Invitation to bid:
Generally the invitation to bid states the requirements and procedures for a
responsive bid and gives additional information pertaining to the contract itself.
Bid form:
The bid form is completed and signed by the bidder and states the terms of their
offer.
Bid breakdown:
The bid breakdown are filled in by the bidder, and it gives the individual price
component that sum to the total contract price component that sum to the total
contract price.
Construction contract:
A construction contract is a mutual or legally binding agreement between owner
and bidder based on policies and conditions recorded in document form. The two
parties involved are one or more owners, and one or more contractors.
7
SignedSignal
Contractor owner
Turkey contracts:
A project whose cost will not be paid until the contractor completes the project and
“Turns the key” over to the owner. In a turkey project the cost of money which the
contractors will be required to borrow over the life of the project in their costs.
9
Bar Chart
Bar chart are most frequently used schedules (সময়সূ চী) abstruction because are
simple and easy to understand. Their simplicity makes them very usefulfor
10
milestone and summary schedules, which are used for global control at the project
management and executive level.
Preparing bar chart:
The anticipated start and completion dates of each major activity is depicted as
horizontal bar.
Bar chart is to develop a list of activities that will be shown on the table. This list
can be extensive (ব্যাপক) and defined as required, but usually is less than 20 activity
11
CPM is used to determine the critical path which is the shortest duration for the
project. Other useful information can be derived from a CPM network, such as
activity time, event time and float.
12
For CPM
Flow time = 0
(অর্থাৎএকটিকাজশেষেএবংআরএকটিকাজশুরুরমাঝেকোনগ্যাপেথাকবেনা)
13
Problem: 2
Activity Description Duration
1-2 A 2
2-3 B 3
2-7 K 1
3-4 C 1
3-9 G 4
4-5 D 2
5-6 E 3
6-12 F 3
7-8 L 2
8-5 M 2
9-10 H 2
10-11 I 3
11-12 J 1
12-13 N 3
Solution:
Problem: 3
Problem: 4
Activity Description Duration
1-2 A 4
2-3 B 2
3-4 C 1
3-5 E 3
4-6 D 1
5-6 F 2
6-7 G 1
16
Solution: