System Startup and Testing Rev.1
System Startup and Testing Rev.1
3 ٣ الحزمة رقم
Design and Construction of New Runway 15R/33L, إعادة إنشاء المدرج،15R/33L تصميم و إنشاء المدرج الجديد
Reconstruction of Runway 15L/33R, Associated البنى التحتية و الخدمات، ممرات الطائرات ذات الصلة،15L/33R
Taxiways, Infrastructure and Utilities
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the startup and testing requirements for the equipment/systems
supplied and/or installed. The Contractor shall be responsible for providing complete
startup, testing, and operator training services to demonstrate operability of all electrical
and mechanical equipment/systems supplied and any Employer-furnished components and
materials provided using Contractor’s own power generators.
B. In the absence of main permanent power availability from the Utility Provider or any other
permanent source, the Contractor shall be responsible for providing the full power required,
on temporary basis, using Contractor’s own power generators, for all systems startup,
testing and commissioning activities. Such temporary power from Contractor’s own power
generators shall remain in operation until the issuance of the substantial completion
certificate.
1.2 SUBMITTALS
A. Comply with Section 01305, “Data Requirements” for data and document submittals.
PART 2 - PRODUCTS
(Not Applicable)
PART 3 - EXECUTION
A. All mechanical and electrical equipment including the interfaces with the building
management system, control systems, communication systems, software and all alarm
circuits and operating modes for each piece of equipment shall be tested by the Contractor
and approved by the Engineer before any facility is put into operation. Tests shall be as
specified herein and in the Specification section applicable to and as specified for the
various pieces of equipment. The testing and commissioning is to be done in the presence
of the equipment manufacturer/supplier authorized representative. As a minimum, the
startup tests shall be sufficiently detailed and comprehensive to demonstrate and verify that
the equipment has been properly assembled, aligned, and connected and that the control and
information circuitry and any associated controllers, panels, and software systems are fully
operational and functioning as designed. Any changes, adjustments, or replacements
required to make the equipment operate as specified shall be performed as part of the
Works.
1. At least sixty (60) days before the time allowed in the construction schedule for
commencing testing and startup activities, submit to the Engineer three (3) copies of
the detailed procedures proposed for testing and startup of all mechanical (including
instrumentation and controls) and electrical equipment. Procedures shall be required
SYSTEM STARTUP AND TESTING 01652 - Page 1 of 3
K07098-3-SPC-PMC-01 REV 1
Package No. 3 ٣ الحزمة رقم
Design and Construction of New Runway 15R/33L, إعادة إنشاء المدرج،15R/33L تصميم و إنشاء المدرج الجديد
Reconstruction of Runway 15L/33R, Associated البنى التحتية و الخدمات، ممرات الطائرات ذات الصلة،15L/33R
Taxiways, Infrastructure and Utilities
for each major piece of equipment, each subsystem which can logically be treated as
an integral group and division for purposes of testing and demonstrating system
operability.
2. Testing and startup procedures shall include detailed descriptions of all pre-
operational electrical, mechanical, communication and software and instrumentation
testing work. Each control device, item of mechanical, electrical, and
instrumentation equipment, software and all control circuits shall be considered in
the testing procedures. The testing procedures shall be established / prepared in a
stepwise, logical sequence to verify that all equipment has been properly serviced,
aligned, connected, wired, calibrated, and adjusted prior to operation. Motors shall
be tested in accordance with ANSI/IEEE Publication 112. Testing procedures shall
be designed to duplicate as nearly as possible all conditions of operations, and shall
be carefully selected to ensure that the equipment is not damaged as a result of the
testing program. All filters and filter elements shall be installed prior to beginning
the tests. Construction or temporary filters shall be used during startup activities.
3. Once the testing procedures have been approved by the Engineer, provide checkout,
alignment, adjustment, and calibration signoff forms for each item of equipment and
system that will be used. The signoff forms shall be used at the Site jointly with
Engineer, to demonstrate that each item of electrical, mechanical, and
instrumentation equipment and system has been properly installed and tested.
Cooperate with the contractors of other systems / facilities where startup and testing
is to be conducted concurrently.
4. Any special testing equipment, loads or instrumentation required shall be provided
to the Employer at the Contractor’s cost during startup and pre-operational testing of
systems and equipment.
B. Before starting a system, perform all service on all equipment, which comprises the system
and associated equipment that supports the system, which normally requires service in
accordance with the Operation & Maintenance Manual instructions. Submit a detailed
maintenance schedule and be responsible for lubrication and maintenance of equipment and
filters throughout the entire equipment break-in period indicated by the manufacturer. Note
that when the manufacturer does not specify a break-in period, construction or temporary
filters shall be installed, and the new and clean filters shall be installed only after the
system and equipment are thoroughly cleaned to the satisfaction of the Engineer.
A. After all testing is completed, demonstrate to the Employer the proper manner of operating
the equipment, making adjustments, responding to alarms and emergency signals, and
maintaining the systems. Each system shall include a minimum of 8 hours of operator
training. Note that major systems shall be tested and a minimum of 8 hours of operator
training provided for each major sub-system as defined in the Division 15 and/or 16
specifications, or as with the Engineer. Operator schools shall be conducted as applicable
with duly qualified instructors. Work performed by the manufacturer's representative
required for testing shall not be considered as operator training even if the operators are
present and witnessing the adjustments. Equipment testing shall be completed and
Operations and Maintenance Manuals submitted and approved before the required on-the-
job operator training begins.
B. Prepare and furnish training materials for use in training Employer’s personnel. The
training materials shall be submitted for the Engineer's review 3 weeks in advance of
training and shall include detailed comprehensive written documents/procedures which
clearly describe all startup, maintenance, troubleshooting, and service procedures for all
equipment and systems. DVD in jpeg or equivalent format, professionally produced and
edited may be utilized as suitable media for at least a portion of the training program.
C. The Contractor shall carry out, to the satisfaction of the above Clauses to Employer,
preventive and breakdown maintenance for the equipment and systems as per
manufacturer’s recommendations.
A. Be responsible for a thirty (30) day period of completed systems operation, during which
electrical and mechanical equipment, fixtures, and associated devices shall be energized
and operated under local and automatic (remote) controls, in all intended design operating
modes. Be present with system manufacturer’s/supplier’s representative(s) during the
startup period with adequate labor and support personnel to perform needed adjustments
and troubleshoot system failures and/or any performance deficiencies that might arise and
to perform necessary corrective actions.
C. If adjustments fail to correct the operation and performance of equipment, remove the
equipment from the Site and replace it with new equipment that meets the specified
requirements.
A. The thirty (30) day startup (system warranty run) period shall commence at the time of
completion. If during this period, the system fails to operate and perform in accordance
with Contract Document requirements, the failure shall be corrected and the 30 day
performance warranty run period shall begin again.