Method Statement
Method Statement
CONTRACTOR:
GISCO
APPLICATOR:
RISE & SHINE GROUP
PROJECT:
AL BATEEN EXECUTIVE AIRPORT,ABU DHABI
TABLE OF CONTENTS
ITEM PAGE
CONTENT
NO. NO.
1.0 TITLE
2.3 Materials
1.0 TITLE:
Method statement for 120 minutes Intumescent fire proofing works for steel
structures at project “AL BATEEN EXECUTIVE AIRPORT”.
The following are the scope of work to be carried-out by Rise & Shine,
The responsibility of Rise & Shine is to verify the requirements of this Method
statement, to the extent necessary, are conscientiously observed at all times during
the project period.
2.3 MATERIALS
Jotamastic 80(Primer)
Steel master 1200 WF (Intumescent )
Hard Top XP (Top coat for intumescent)
Once the Intumescent coated surface is dry the DFT shall be checked by
the QC and inspection shall be raised to the contractor/ consultant for
approval. Approved ITP shall be followed.
2.5.4 APPLICATION OF TOP COAT OVER INTUMESCENT
When the Intumescent Paint required thickness as per Loading Chart is
achieved, inspected and approved, Top Coat will be applied.
Upon successful inspection a mist coat of Hard Top XP shall be applied. Mist
coat is Hard Top XP thinned up to 50%.
Apply one full coat of Hard Top XP thinned up to 10% at WFT 100 microns
to achieve a DFT of 50 microns.
Once the topcoat is dry the QC shall inspect and raise inspection to the
contractor/ consultant for approval as per approved ITP.