FMFormulas
FMFormulas
𝐹𝑉 In Excel
𝑃𝑉 =
(1+𝑟) =PV(rate,nper,pmt,[fv],[type])
In Excel
𝐶𝐹 1 =PV(rate,nper,pmt,[fv],[type])
𝑃𝑉 = 1−
𝑟 (1 + 𝑟 ) =PV(rate,nper,pmt,0,0)
In Excel
𝐶𝐹 1 =PV(rate,nper,pmt,[fv],[type])
𝑃𝑉 = 1− (1 + 𝑟)
𝑟 (1 + 𝑟 ) =PV(rate,nper,pmt,0,1)
𝐶𝐹
𝑃𝑉 =
𝑟
𝐶𝐹
𝑃𝑉 =
𝑟−𝑔
m = no. of times per year interest is compounded. Quarterly =PV ( rate/4, nper*4, 0,fv,0)
n = no. of year
Annually, m = 1
Bi-monthly =PV ( rate/6, nper*6, 0,fv,0)
Semi-annually, m = 2
Quarterly, m = 4
Monthly =PV ( rate/12, nper*12, 0,fv,0)
Bi-monthly, m = 6
Monthly, m =12
Continious Compounding
∗ In excel
𝐹𝑉 = 𝑃𝑉 ∗ 𝑒
= PV*EXP(Rate* no. of years)
Yield Curve
IR/YTM
YTM is usually upward sloping (economy id
good condition)
Time to Maturity
IR/YTM
Indication of Recession
Time to Maturity
Bond Valuation
1 1 In Excel:
= 𝐶𝐹 + 𝐹𝑉
(1 + 𝑟) (1+𝑟)
=PV(rate,nper,pmt,[fv],[type]) +
PV(rate,nper,pmt,[fv],[type])
𝐶𝐹 1 1 Example:
= 1− + 𝐹𝑉
𝑟 (1 + 𝑟 ) (1+𝑟) =PV(8%/2,10*2,-50,0,0) + =PV(8%/2,10*2,0,-1000)
Or,
Semi-annually (m)
𝐶𝐹 1 1 =PV(8%/2,10*2,-50,-1000,0)
= 𝑟 1− 𝑟 + 𝐹𝑉 ∗
(1 + ) ∗ (1+𝑟)
𝑚 𝑚
YTM
In Excel
𝐹𝑉
𝑅𝑎𝑡𝑒 = =Rate(nper,pmt,pv,[fv],[type],[guess])
𝑃𝑉
YTM Annual Interest
In Excel
=IRR(values,guess)
Current Yield
𝐶𝑜𝑢𝑝𝑜𝑛 𝑌𝑖𝑒𝑙𝑑
𝐶𝑢𝑟𝑟𝑒𝑛𝑡 𝑌𝑖𝑒𝑙𝑑 =
𝐶𝑢𝑟𝑟𝑒𝑛𝑡 𝑀𝑎𝑟𝑘𝑒𝑡 𝑝𝑟𝑖𝑐𝑒
𝐵𝑜𝑜𝑘 𝑉𝑎𝑙𝑢𝑒 =
𝑃𝐸 = , 𝐸𝑃𝑆 =
.
,
Payback Period: The amount of time required for the firm to recover its initial investment in a project (as calculated
from the cash flow).
In Case of Annuity
the payback period can be found by dividing the initial investment by annual cash flow.
the yearly cash inflows must be accumulated until the initial investment is recovered.
Decision Criteria:
If payback period < maximum acceptable payback period => ACCEPT Project
If payback period > maximum acceptable payback period => REJECT Project
Ex- Calculate payback period and discounting payback period for the below project
0 1 2 3 4 5
0 1 2 3 4 5 Total
-10000 3000 5000 6000 4000 3000
6000/12
500*4
8000 2000 10000
2yrs 4 months
Discounting @10 %
0 1 2 3 4 5 Total
-10000 3000 5000 6000 4000 3000
3000/1.1 5000/1.1^2 6000/1.1^3
2727.2727 4132.2314 4507.88881 11367.39
4507/12
375*10
2727.2727 4132.2314 3750 10609.5
2 yrs 10 months