ZX3 Manual
ZX3 Manual
User Manual
Hoist Serial No.: __________
CDE
Street Crane Company Limited
Chapel-en-le-Frith
High Peak
SK23 0PH
United Kingdom
e-mail [email protected]
web http://www.streetcrane.co.uk
Tel +44 (0) 1298 812456
Fax +44 (0) 1298 814945
Street Crane Company Limited reserve the right to alter or amend the details given in this publication without prior notification.
Street Crane Company Limited 2005
Document Reference: D1122.rev.G
(Hoist Unit)
FOREWORD
Street Crane Co. Limited, do not accept responsibility either for the manner in which these instructions are
observed or for any consequences thereof.
REF: mmmi006a.doc
1/1
(ZX3 Hoist Unit)
CONTENTS SHEET
Nameplates And Model Code
Installation & Commissioning
Operating Instructions
Hoist Inspection & Maintenance Schedule
Hoist Lubrication Schedule
‘SK-F’ Drive Unit Lubrication Schedule
‘ABM’ Drive Unit Lubrication Schedule
Hoist Brake
Hoist Motor & Adapter
Removal & Fitting of Wire Rope/Rope Guide
“Slack Rope” Check On The Hoist Unit
Rope terminations: Wedge & Socket
Bottom Block
Spur & Pinion Inspection & Maintenance Schedule
Direct Drive Inspection & Maintenance Schedule
Crab Direct Drive Wheel Assembly
Low Headroom Cross Travel Wheels
‘SK-F’ Drive Unit
Travel Brake Motors Type ‘EFB2’ & ‘EFB3’
Fault Finding
Steel Wire Ropes
Sound Levels
Optional Extras
• 7101 Travel / Traverse Limit Switch
• Ultimate Limit Switch
• Control Pendants
Inspection & Maintenance Log
REF : D1122CONT
CDE Page 1 of 1
This Street Crane product has been designed in accordance with the following standards and
regulations:-
The symbol specific to your product is displayed on hoist nameplate
Lee Osborn
Quality/Safety Manager
30 April 2007
REF: MMMI014C
CDE 1/1
(ZX Series Hoist Units)
REF: MMZX011A.DOC
1/2
(ZX Series Hoist Units)
REF: MMZX011A.DOC
2/2
(ZX Series Hoist Units)
REF: MMMI003B.DOC
1/11
(ZX Series Hoist Units)
REF: MMMI003B.DOC
2/11
(ZX Series Hoist Units)
Fig MI003/1
Slow supply connections 1U, 1V, 1W Dual supply connections 2U, 2V, 2W
REF: MMMI003B.DOC
3/11
(ZX Series Hoist Units)
The ZX Crab Unit is supplied with 60mm diameter rubber buffers on each corner of the frame.
Suitable endstops should be positioned centrally on the crab rails at either end of the two crane
beams.
REF: MMMI003B.DOC
4/11
(ZX Series Hoist Units)
• Ensure that the counterweight is fixed at the correct mounting position (Table MI003/6).
• Adjust the drive trolley to suit the flange width. The clearance between the inside of the wheel
flanges and the runway beam should be 1.5-2.5mm at each side i.e. 3-5mm overall
(Fig MI003/6). See also “Running & Mounting Surfaces”.
• Drill a 6mm diameter dowel hole into each hoist leg through the pilot holes provided in the feet.
• Slide the drive trolley backwards sufficient to allow the hoist to fit onto the beam. In some cases,
two of the securing bolts may have to be removed to do this.
• Lift the hoist up onto the runway beam and slide the drive trolley forwards until all the wheels are
resting on the running surface of the runway flange.
• If previously removed, re-fit, but do not tighten, the securing bolts
• Adjust the drive trolley until the dowel spring pin can be fitted into the pre-drilled hole.
• Torque the securing bolts to 252Nm.
• Check the security of the counterweight securing bolts.
Fig MI003/6
REF: MMMI003B.DOC
5/11
(ZX Series Hoist Units)
• Ensure that the counterweight is fixed at the correct mounting position (Table MI003/2).
• Adjust the drive trolley to suit the flange width. The clearance between the inside of the wheel
flanges and the runway beam should be 1.5-2.5mm at each side i.e. 3-5mm overall
(Fig MI003/7). See also “Running & Mounting Surfaces”.
• Drill a 6mm diameter dowel hole into each hoist leg through the pilot holes provided in the feet.
• Slide the drive trolley backwards sufficient to allow the hoist to fit onto the beam. In some cases,
two of the securing bolts may have to be removed to do this.
• Lift the hoist up onto the runway beam and slide the drive trolley forwards until all the wheels are
resting on the running surface of the runway flange.
• If previously removed, re-fit, but do not tighten, the securing bolts
• Adjust the drive trolley until the dowel spring pin can be fitted into the pre-drilled hole.
• Torque the securing bolts to 252Nm.
• Check the security of the counterweight securing bolts.
Fig MI003/7
REF: MMMI003B.DOC
6/11
(ZX Series Hoist Units)
The ZX stationary hoist is suitable for base mounting only i.e. as shown. It is supplied with four
18mm diameter holes in each end frame and should be secured to its support structure* utilising only
the two outer holes in each side frame (Fig MI003/8). Street Crane Company recommends that four
M16 fixing bolts of grade 8.8 or higher be used together with a locknut and a flat washer. Bolt
tightening torque 252Nm.
Fig MI003/8
CAUTION: The support structure must be suitably designed to support both the hoist and its maximum
Safe Working Load. The vertical misalignment of the mounting surfaces should be in accordance with
the “Running & Mounting Surfaces”.
REF: MMMI003B.DOC
7/11
(ZX Series Hoist Units)
The tests and inspections listed below should be carried out by competent and fully trained personnel
after installation and electrical connecting of the hoist unit prior to putting it into regular service.
REF: MMMI003B.DOC
8/11
(ZX Series Hoist Units)
Each ZX model hoist unit is fitted with the upper and lower limit switches (Fig MI003/4). These are
intended as a safety feature and should not be used deliberately to prevent overhoisting or
overlowering. The limit switches are actuated by the travel movement of the rope guide.
Fig MI003/4.
Setup
• Lower the hook to the desired lowest operating level. (Normally the lower limit is set to stop the hook
approx. 150mm clear of the operating level when lowering at full speed). CAUTION: Ensure that
there is a minimum of 10mm between the rope guide at its lowest position and the rope anchors on
the barrel.
• Slacken the two bolts securing the limit switch mounting bracket and slide the limit switch up to the
rope guide until the limit switches.
• Tighten the bracket bolts. CAUTION: Do not run the hoist until the lower limit switch bracket has
been tightly fixed or correctly positioned.
• Test the limit position.
• The upper limit switch is pre-set for both the stationary hoist and the crab unit to suit the hoist
design. CAUTION: The factory pre-set should not be tampered with.
• The position of the upper limit switch for a low headroom hoist unit should be set by the end user
depending on its respective runway flange width (F). The figures shown in the graphs below indicate
highest positioning of the bottom block for the varying flange widths. CAUTION: Serious damage to
the hoist unit / rope may result if the upper limit is set at less than the recommended ‘C’ dimension.
REF: MMMI003B.DOC
9/11
(ZX Series Hoist Units)
Each rated capacity limiter despatched form Street Crane is pre-loaded to suit the SWL and the
number of falls of the hoist unit.
Pre-Loading Setup
• Withdraw the Bottom Support Pin from the Rod End Joint
• Unscrew both the Rod End Joint and Locknut ‘Y’ by 2-3 threads and re-tighten against each other
• Whilst holding Locknut ‘Y’ with a spanner, tighten Locknut ‘X’ to give the desired Dimension “A”
(Table MI003/3).
• Re-tighten both Rod End Joint and Locknut ‘Y’ up against Locknut ‘X’
Fig MI003/5
REF: MMMI003B.DOC
10/11
(ZX Series Hoist Units)
Setup
• Ensure that the grub screw (1) directly above the limit switch (2) is unscrewed to clear the switch
actuator.
• Load the hoist with the calibrated test weight. To set the rated capacity limiter it is recommended
that a load of SWL + 5% is applied (Table MI003/4). Where a dual switch rated capacity limiter is
fitted, the first limit should be set to warn of approach of the SWL (approx. 95% of SWL)
• Tighten the grub screw directly above the limit switch until the switch just operates.
• Lower the load and repeat the lift at slow hoisting speed to prove the operation of the switch.
REF: MMMI003B.DOC
11/11
OPERATING INSTRUCTIONS
ZX SERIES HOIST UNITS
This document should be kept in a safe place and all the personnel who are directly involved with the
Hoist's operation should be made aware of its presence and location. The manual has been compiled
to ensure the safety of personnel and to assist in maintaining the Street Hoist at its designed
performance level. The manual provides details and explanations, concerning operation of the Hoist,
procedures for planned inspection, overhaul and maintenance. These are imperative to maximise the
Hoists life expectancy and avoid time lost to breakdown. It is important that all functions are carried
out by fully trained and competent personnel.
In Great Britain a code of practice exists for the Safe Use of Cranes. BS 7121 covers the following
subjects: -
• Safe systems of work.
• Management of the lifting operation.
• Planning of the lifting operation.
• Selection and duties of personnel and their minimum attributes.
• Maintenance of Cranes.
• Inspection, Testing and Examination.
It is advisable that a copy of this code of practice be kept alongside this manual.
In addition management and supervision have an important role to play in any safety programme by
ensuring that: -
• The equipment is suitable for the job intended.
• A safety procedure is adopted for emergency situations i.e. power failure.
• A safe system of work is adopted for maintenance personnel.
Scope
This document gives guidance on Street Crane Company's standard designs of ZX Hoist units.
Nomenclature
Throughout the manual words appear in bold capital letters, these words are defined as follows:-
Hoist Description.
The Hoist / Crab Unit is of the wire rope type. The vertical motion is provided by an electrically driven
drum. As the drum rotates the wire rope scrolls around the drum providing vertical movement of the
hook. The hoist is fitted with a brake, which automatically applies when the motion is switched off.
The Cross Travel (where fitted) is the motion along either the Crane bridge girder(s) or along a single
runway beam. The cross travel motor is fitted with a brake, which is applied automatically when the
motion is switched off.
REF: OIZX002D
CDE 1/7
OPERATING INSTRUCTIONS
ZX SERIES HOIST UNITS
The Hoist has a maximum load that it is permitted to lift. This is referred to as the Safe Working Load
(SWL). The SWL is clearly marked on the Hoist and the hook. For Crabs with a main and auxiliary
hoist, a selector switch is provided which allows only one hoist to be used at any one time. A load
must ONLY be attached to the selected hoist. Also located on the Hoist are data plates identifying the
following: -
• The manufacturers name.
• The serial number.
• The year of manufacture.
• Hoist classification.
• Mechanism classifications.
The information on these data plates will be required when ordering replacement component parts.
Classification
A method of classification exists which defines the duty of each hoist dependant upon its application.
Each hoist and its individual components are designed to suit their particular application. This can
vary from light duty to very heavy duty. The classification not only gives an indication of the type of
duties that the hoist will perform but also its design life and the frequency of maintenance routines.
The classification for the hoist and the cross travel as a whole is represented by the letter “M”. This
letter is followed by a number from 1 to 8. Generally the higher the number, the more arduous the
duty. For a more detailed explanation of the classification method refer to BS 466:1984.
The classification of each hoist is marked on the hoist nameplate and is also indicated on the
Technical Data Sheet. It is essential that you understand the system of classification and operate the
hoist within its rating. “KNOW YOUR HOIST”.
REF: OIZX002D
CDE 2/7
OPERATING INSTRUCTIONS
ZX SERIES HOIST UNITS
Service Conditions
Street Cranes Overhead Travelling Cranes are designed to operate in “Normal service conditions” as
defined in BS 466:1984 namely: -
• Indoor use.
• Ambient temperatures from -10 to +40°C with no sources of local heating, such as furnaces or
radiant panel heaters.
• For use in clean still contamination free atmosphere at normal levels of humidity.
General
There is no single factor more important than minimising the possibility of injury to the Operator and/or
those working in the area, or damage to property, equipment and/or materials.
No Operator should be permitted to use the equipment unless they are familiar with its operations.
They should be physically and mentally fit and trained in Safe Hoisting Practices. Hazards can only
be minimised by care, common sense and the operator being alert at all times.
Apart from Hoist operation, Safe Hoisting Practices involve a programme of periodic inspection and
preventative maintenance. Part of the operator's training should be to make him/her aware of
potential malfunctions requiring adjustments or repairs and the need to bring these to the attention of
the supervisor for corrective action (see ‘Fault Finding’).
REF: OIZX002D
CDE 3/7
OPERATING INSTRUCTIONS
ZX SERIES HOIST UNITS
8. Work with an authorised slinger and operate only to his signals.
9. Ensure that the operator knows the full meaning of the hand signals.
10.Do not park over fumes, steam or dangerous processes when in operation.
11.Do not use the Hoist for anything other than its intended purpose.
12.Ensure that all the necessary test certificates and maintenance records are up to date.
Pre-Start Checks
1. Ensure that a “MEN WORKING OVERHEAD” or a “PERMIT TO WORK” is NOT in force.
2. Ensure that no one is working on or around the Hoist where they could be struck.
3. Make a visual inspection to ascertain that the Hoist is in good working order, paying particular
attention to the rope and hook.
REF: OIZX002D
CDE 4/7
OPERATING INSTRUCTIONS
ZX SERIES HOIST UNITS
10.DO NOT lower the hook so far as to allow the ropes to go slack. If this happens the operator
should determine that the rope is properly reeved on the drum before moving a load.
11.DO NOT leave a load suspended from the hoist unsupervised.
12.DO NOT stand below the load or allow any other personnel to do so.
13.DO NOT lift loads over people. Make personnel aware of approaching loads using audible
warnings when necessary.
14.DO NOT travel with a load dragging along the floor.
15.DO NOT use the Hoist for handling personnel.
16.ENSURE that adequate clearance is maintained between the load or lifting attachment and the
hoist or crane structure (see Fig. OI002/4).
Fig OI002/4
REF: OIZX002D
CDE 5/7
OPERATING INSTRUCTIONS
ZX SERIES HOIST UNITS
Power Failure
The Crane supervisor should establish a safe operating procedure if there is a power failure. The
following procedure is recommended: -
1. Switch off the power supply to the Crane at the main isolator until the electrical supply is
restored.
2. A load left suspended in mid-air and considered to be a hazard should be lowered to the floor
using the hand brake release lever.
• Fence off and clear all personnel from the area under the load.
• Obtain a permit for access to the hoist brake.
• Carefully lower load to the floor using the hoists hand release fail-safe brake. The load
must be lowered under strict control only a few inches at a time before re-applying the
brake.
CAUTION: Serious damage and subsequent failure, of the gearbox may result if the load is
allowed to run away.
• When load is firmly supported at ground level, re-apply the brake mechanism.
3. When the electrical supply is restored, re-establish the Crane power supply.
4. Carry out the Pre-Start/Daily checks.
Legend Nomenclature
The legend plates on control units are provided in either English or International symbols.
Operating Functions
All control pendants are fitted with dual pressure pushbuttons to control hoist and crane motions. To
maintain the selected motion the pushbutton must be held depressed. All the motion pushbuttons are
spring loaded so that when a button is released the particular motion ceases and the brake is
automatically applied.
Single Speed. To operate a single speed motion, press the button fully in.
Slow Speed. To operate slow speed of a dual speed motion, press the button in to the first stage.
Fast Speed. To operate fast speed of a dual speed motion, press the button fully in (i.e. to the second
stage).
Change Speed. (Slow - Fast All motions). To change from slow speed to fast speed depress the
pushbutton fully in to the second stage.
Change Speed. (Fast - Slow for the long travel motion). To change from fast speed to slow speed,
reduce pressure on push button and allow it to come out to the first stage.
• Switchgear controlled - The crane will first stop and then continue at slow speed.
• Inverter controlled – The crane will decelerate to slow speed.
Change Speed. (Fast - Slow hoist and traverse motions). To change from fast speed to slow
speed, release the push button to the first pressure. The hoist will decelerate to slow speed.
REF: OIZX002D
CDE 6/7
OPERATING INSTRUCTIONS
ZX SERIES HOIST UNITS
Emergency Stop. (EMG. STOP)
WARNING: Before starting work it is imperative to check the correct operation of the
emergency stop button.
1. Depressing the EMG. STOP push button will cause all motions to stop and all brakes to
engage.
2. The emergency stop will lock all controls in the off position.
3. If the button is used in an emergency stop situation, ensure that any faults are rectified before
re-establishing the power supply.
4. Twist to release the EMG. STOP button.
NOTE: No functions will be operative until the emergency stop is unlatched and the ON
pushbutton operated.
Switch ON
1. Establish power supply to the conductors via the main isolator (this may be located on a wall
or supporting column).
2. Set the isolator on the end of the crane panel to ON.
3. Momentarily depress the ON pushbutton. This will energise the main contactor and allow
subsequent motions to take place.
Pushbutton Operation
1. Depress the required pushbutton. The crane/hoist will move in the corresponding direction.
2. Releasing the pushbutton will stop the motion and apply the corresponding brake(s).
3. Press the EMG. STOP pushbutton if no further actions are to be taken.
Safety Switches
An overhoist/overlower limit switch is fitted to all hoists. This prevents the hook from going too high
and damaging the hoist and from going too low so as to allow the ropes to go slack. This is a safety
device and should not be used as a normal method of stopping the hoist.
CAUTION: Certain crane configurations allow the upper hook position to be set at a higher
level than the underside of the bridge girders. In such instances the operator must
take extreme care when lifting to ensure that adequate clearance is maintained
between the load or lifting attachment and the hoist or crane structure
(see Fig. OI001/4).
The ultimate limit switch (optional) is used as an emergency limit should the hoist limit fail. It is
operated by the bottom block and will trip out the mains contactor. The bottom block must be lowered
manually and the limit must be reset manually. Should the ultimate limit switch operate, then the
reason for the bottom block passing the normal working limit must be investigated before continuing to
use the crane.
REF: OIZX002D
CDE 7/7
ZX SERIES OVERHEAD TRAVELLING CRANES & HOISTS
INSPECTION & MAINTENANCE SCHEDULE
General
To ensure that your overhead travelling crane continues to be safe in operation and operates as
efficiently as possible, regular planned inspection and maintenance of all the associated equipment is
essential. A preventative maintenance programme is included in the following pages. Preventative
maintenance is essential maintenance work, including lubrication, which is undertaken at pre-set
intervals with the objective of keeping the crane or hoist in a serviceable condition.
Follow the recommended maintenance and lubrication procedures to provide maximum protection for
the equipment. Where replacement components are required use only genuine Street Crane parts.
Modifications to the crane or any of its mechanisms should not be carried out without the approval of
Street Crane Company Limited. Failure to adopt these recommendations may invalidate your
warranty.
Attention is drawn to the daily checks, which should be performed before operating the crane or hoist.
In addition, the Lifting Operations and Lifting Equipment Regulations 1998 (LOLER) require that
cranes and hoists are examined at regular intervals throughout its life in accordance with an
appropriate examination scheme. The user has the responsibility for ensuring compliance with these
regulations. BS 7121-2:2003 gives recommendations for the pre-use checks, in-service inspection,
thorough examination and testing of cranes, including associated equipment, and the means by which
tests are to be carried out. The user should maintain records of all inspections.
Maintenance Access
The crane may be fitted with full or partial maintenance access platforms or, for certain types of crane,
no provisions all. The extent of any crane platforms and access to these platforms has been agreed
with the purchaser and Street Crane. Where no platforms or only partial access has been provided on
the crane, separate or additional access equipment will be required to service some of the
components. These components should be accessed via a secure, mobile or temporary structure
e.g. tower scaffold, self-standing stair platforms, scissor-lift or cherry picker. All access equipment
should be assembled and operated by trained personnel in accordance with the manufacturers
instructions following the appropriate health and safety regulations and procedures.
The following should be considered when choosing the most appropriate type of maintenance access
equipment.
• Floor space available for the access equipment
• Working height above floor level
• Number of personnel required to gain access at high level
• Total weight of any parts to be removed/replaced
REF: MMZX007C
CDE 1/4
ZX SERIES OVERHEAD TRAVELLING CRANES & HOISTS
INSPECTION & MAINTENANCE SCHEDULE
REF: MMZX007C
CDE 2/4
ZX SERIES OVERHEAD TRAVELLING CRANES & HOISTS
INSPECTION & MAINTENANCE SCHEDULE
MECHANICAL Duty A B C D E
BRAKES: M3 •
M4 •
Carry out a functional check of each of the motion brakes to
M5 •
ascertain that they operate efficiently. Clean, adjust and renew
worn parts where necessary. In particular check wear on the rotor, M6 •
and the condition of the spline on both rotor and hub. Also check
the condition of the hub key and keyway.
MOTORS & COUPLINGS: M3 •
M4 •
Clean motor fins and fan cowling. Check security of motor and
M5 •
coupling fixings.
M6 •
GEARBOXES: M3 •
M4 •
Inspect around gearbox casing, filler and drain plugs and around oil
M5 •
seals for signs of lubrication seepage. Clean ventilation plug.
M6 •
Tighten fixings and renew seals if necessary.
GEARBOXES: M3 •
M4 •
When gearbox oil is drained during oil replacement, remove the
M5 •
gearbox inspection cover and visually check the gear teeth for
M6 •
wear. Check keys and keyways for security.
WIRE ROPE AND FIXINGS: M3 •
M4 •
Visually inspect the hoist rope for damage, wear and broken wires.
M5 •
Maintain or renew as necessary. Check security of the rope
M6 •
anchors fixings.
ROPE GUIDE: M3 •
M4 •
Examine for signs of wear or damage.
M5 •
M6 •
HOIST BARREL & ROPE SHEAVES: M3 •
M4 •
Examine the rope groove for wear or damage due to rope
M5 •
indentations.
M6 •
DRIVEN COMPONENTS: M3 •
M4 •
Check the condition of the wheels for signs of wear on the tread
M5 •
and inside of the flanges. Inspect the condition of the geared
M6 •
pinions and wheels for damage and wear. Ensure correct meshing.
BOTTOM BLOCK: M3 •
M4 •
Check for cracks, cold deformation, wear and freedom of rotation of
M5 •
the sheaves and hook. Ensure hook safety catch operates
M6 •
correctly. Check security of hook nut.
ENDSTOP & TORQUE ARM RUBBER BUFFERS (where fitted): M3 •
M4 •
Check the condition of the end stops and rubber buffers. Replace if
M5 •
damaged.
M6 •
Maintenance Intervals: - A = Weekly, B = Monthly, C = 3 Monthly, D = Annually, E = Every 2 Years
REF: MMZX007C
CDE 3/4
ZX SERIES OVERHEAD TRAVELLING CRANES & HOISTS
INSPECTION & MAINTENANCE SCHEDULE
MECHANICAL Duty A B C D E
HOIST / CRANE STRUCTURE M3 •
M4 •
Visually inspect overall structure for damage and unusual rubbing
M5 •
marks. Check rail for wear or localised damage. Check security of
M6 •
a reasonable quantity of the bolts. Visually examine welds for signs
of cracks. Clean off any corrosion and apply an approved
protective treatment to the surface.
ELECTRICAL Duty A B C D E
ELECTRCIAL CABLES: M3 •
M4 •
Check for damage or loose connections. Check cable insulation
M5 •
shows for signs of brittleness (does not crack when flexed) or
M6 •
overheating (discolouration). Replace where necessary.
DOWNSHOP LEADS (Overhead Crane Only): M3 •
M4 •
Inspect collector arms and carbon shoes for signs of damage or
M5 •
wear. Replace where necessary. Check joints and insulation for
M6 •
signs of arcing. Rectify as necessary.
TRAVEL/TRAVERSE LIMIT SWITCHES (When fitted): M3 •
M4 •
Inspect for wear or damage. Check for correct operating position.
M5 •
M6 •
OVERHOIST/ LOWER LIMIT SWITCHES. M3 •
M4 •
Inspect for wear or damage. Check for correct operating position.
M5 •
M6 •
OVERLOAD SWITCH (RCL): M3 •
M4 •
Physically check components for wear or damage. Check cables,
M5 •
connections and mounting.
M6 •
Verify calibration of RCL by applying the necessary calibrated load. ALL •
PENDANT AND/OR RADIO CONTROLLER (where fitted): M3 •
M4 •
Check that controller casing, pushbuttons and their rubber seals are
M5 •
undamaged. Pendant strainer wire fixings secure. Cable entry seal
M6 •
undamaged.
ELECTRICAL PANELS: M3 •
M4 •
Inspect relays and contactors for security and physical damage.
M5 •
Renew if signs of damage or overheating are apparent. Ensure
M6 •
enclosure door closes securely. Lightly lubricate panel hinges and
seals. Clean enclosure filters where fitted.
Maintenance Intervals: - A = Weekly, B = Monthly, C = 3 Monthly, D = Annually, E = Every 2 Years
REF: MMZX007C
CDE 4/4
(ZX3 Series Hoist Units)
LUBRICATION SCHEDULE
ITEM Duty A B C D E Qty Lubricant Characteristics
HOIST GEARBOX: ! M3 • Industrial gear oil :-
Check level via level plug and M4 • As ISO classification 460
top up as required. M5 • Req’d Specific gravity 0.904
M6 • Pour point -18°C
Closed flash point 215°C
Drain and refill to level plug M3 •
Viscosity @ 40°C 460cSt
with new oil M4 • 4.0 L
@100°C 32cSt
M5 • Viscosity Index 96
M6 •
WIRE ROPE: " M3 • “Street-Drako Compound” or
Ensure that rope is clean and M4 • similar oil based rope lubricant
free from dirt/grit. Apply M5 • As with additives for good
lubricant to the full length of M6 • Req’d penetration, adherence and
rope using a brush, swab or corrosion protection.
spray. Effective temperature range
-20 to +60°C.
OPEN GEARS: # M3 • Gear compound :-
Apply evenly to all teeth. M4 • Appearance : Heavy black fluid
Ensure that no grease M5 • As Specific gravity 1.15
reaches the runner tread. M6 • Req’d Timken OK load 60lbs
Viscosity @ 40°C 1000-1300 cSt
@100°C 450-550 cSt
HOOK BLOCK THRUST M3 • EP Grease :-
BEARING: $ M4 • Drop point 175°C
Apply via grease nipple M5 • 3 Pour point -10°C
located on hook crosshead. M6 • shots Flash point 280°C
Timken OK load 45lbs
Viscosity @ 40°C 175cSt
Viscosity Index 80
Unless otherwise specified, the above lubrication schedule is suitable for an ambient temperature range of -10 to +55°C
Lubrication Points
Stationary Hoist & Crab Unit Low Headroom Hoist Unit
LUBRICATION SCHEDULE
ITEM Duty A B C D E Qty Lubricant Characteristics
GEARBOX : M3 • Industrial gear oil :-
Check level via inspection M4 • ISO classification 220
plug and top up as required. M5 • As Specific gravity 0.897
M6 • Req’d Pour point -18°C
M7 • Closed flash point 205°C
M8 • Viscosity @ 40°C 220.2cSt
Drain and refill with new oil. M3 • @100°C 19.5cSt
M4 • Viscosity Index 100
M5 • As
M6 • Req’d
M7 •
M8 •
GEARBOX AND MOTOR M3 • EP Grease :-
BEARINGS : M4 • Drop point 175°C
Only applicable to frame M5 • 2 Pour point -10°C
sizes 225 or higher M6 • shots Flash point 280°C
Apply via grease nipple. M7 • Timken OK load 45lbs
M8 • Viscosity @ 40°C 175cSt
Viscosity Index 80
The above lubrication schedule is suitable for an ambient temperature range of -10 to +55°C
REF : MMLU017A
1/1
“ABM” Drive
LUBRICATION SCHEDULE
ITEM Duty A B C D E Qty Lubricant Characteristics
GEARBOX: M3 Gearbox is greased filled and
M4 Non does not require any lubrication.
M5
M6
M7
M8
The above lubrication schedule is suitable for an ambient temperature range of -10 to +55°C
REF: MMLU012A.DOC
1/1
HOIST BRAKE
Brake Identification
Content Nameplate example: Size 06 – 16
Brake type – brake size Type no.
Rated voltage Rated power Rated brake torque
Date of manufacture
REF: MMN4002G
CDE 1/6
HOIST BRAKE
Brake Data
BFK458- BFK458- BFK458- BFK458- BFK458- BFK458- BFK458- BFK458- BFK458-
06 08 10 12 14 16 18 20 25
Nominal Air
Gap ‘a’ (mm)
0.2 0.2 0.2 0.3 0.3 0.3 0.4 0.4 0.5
+ 0.1mm
- 0.05mm
Max Air
0.5 0.5 0.5 0.75 0.75 0.75 1.0 1.0 1.25
Gap ‘a’ (mm)
Max. Rotor
6.0 7.0 9.0 10.0 10.0 11.5 13.0 16.0 20.0
thickness (mm)
Min Rotor
4.5 5.5 7.5 8.0 7.5 8.0 10.0 12.0 15.5
thickness (mm)
Max. adjustment
admissible wear 1.5 1.5 1.5 2.0 2.5 3.5 3.0 4.0 4.5
(mm)
Tightening torque
of assembly 2.8 5.5 9.5 9.5 23 23 23 46 46
fixings (Nm)
Tightening torque
of hand release 2.8 2.8 4.8 4.8 12 12 23 23 40
lever (Nm)
Mass of brake
assembly 0.75 1.2 2.1 3.5 5.2 7.9 12.0 19.3 29.1
complete (kg)
REF: MMN4002G
CDE 2/6
HOIST BRAKE
• Re-tighten the assembly fixings to the recommended torque value (see Brake Data)
• Re-check the air gap and repeat adjustment if necessary.
REF: MMN4002G
CDE 3/6
HOIST BRAKE
CAUTION: Before changing the rotor, lower the bottom block to a suitable level (floor or
platform) and allow it to rest on a solid support.
• Disconnect the supply to the brake.
• Remove the brake seal (where fitted).
• Loosen the assembly fixings evenly and remove them (take care to support the brake body).
• Remove the brake body, taking note of its orientation.
• The old rotor (brake disc) will now be exposed. Withdraw the rotor from its hub by hand.
• Before replacing the brake rotor, check the condition of the splining on the brake hub.
Replace if damaged.
• Check the braking surface on the mounting flange or friction plate. Replace where strong
scoring is observed.
• Measure both the new rotor thickness and length of protrusion of the adjustment tubes from
the back of the brake.
• Calculate the distance between the stator and the armature plate as follows: -
Distance = Rotor thickness + Nominal Air Gap ‘a’ – adjustment tube height
• The adjustment tubes should be unscrewed until the calculated distance between the stator
and the armature plate is reached.
• Slide the new rotor onto the hub.
• Replace the brake assembly in the same orientation as originally.
• Replace the assembly fixings and torque to the value stated in Brake Data.
• Check and adjust, if necessary, the Brake Air Gap ‘a’.
• Replace the brake seal (where fitted).
• Re-connect the brake supply.
REF: MMN4002G
CDE 4/6
HOIST BRAKE
REF: MMN4002G
CDE 5/6
HOIST BRAKE
• Insert the compression springs (14.2) into the bore holes of the armature plate
• Fit the washers (14.3) onto the hexagon screws (14.4) and assemble through the
compression springs (14.2) and the stator (7)
• Fit the barrel nuts (14.5) into the holes provided in the hand release (14.1)
• Position the hand release (14.1) over the stator (7) and tighten the hexagon screws (14.4) into
the barrel nuts (14.5) until the armature plate (1) moves towards the stator (7)
• Adjust the gap between the armature plate (1) and the stator (7) using the hexagon screws
(14.4) to achieve dimension (‘s’+’a’)
• Fit the complete brake assembly onto the hoist. Torque the assembly fixings to the value
stated in Brake Data
• Check, and adjust if necessary the Hand Release Clearance (‘s’) and Nominal Air gap (‘a’)
using hexagon screws (14.4)
• Fit the hand release lever to the hand release (14.1). Torque to the value stated in Brake
Data
REF: MMN4002G
CDE 6/6
(ZX Series Hoist Unit)
Fig ZX006/1.
REF : mmzx006a.doc
1/2
(ZX Series Hoist Unit)
REF : mmzx006a.doc
2/2
(ZX3 Series Hoist Unit)
Before fitting a new rope a visual inspection of the sheaves, barrel grooves and rope guide should be
made (see Steel Wire Ropes: Sheave Groove Inspection). Check the specification of the replacement
steel wire rope ensuring that it is exactly the same as that of the old rope.
REF: MMZX003c.DOC
1/3
(ZX3 Series Hoist Unit)
Fig ZX003/1.
Fig ZX003/2.
Fitting The Rope Guide
• Smear the inside of both halves of the rope guide with rope lubricant (see lubrication schedule).
• Fit the bottom half of the rope guide (see Fig ZX003/4) to the open side of the barrel and rotate it
round to the bottom ensuring that the slot collects the rope which leaves the barrel. Care must be
taken when doing this that tension is maintained in the rope and that no “slack rope” is introduced
behind the rope guide.
• Feed the tension spring through the groove in the bottom half of the guide and hook the ends
together.
• Fit the two M5 socket cap head screws to the top half of the rope guide and secure using the two
plastic anti-loss washers.
• Fit the top half of the rope guide over the barrel ensuring that the tension spring seats in the correct
groove.
• Screw the two halves of the guide together. Rotating the rope guide slightly will allow easier
access to the screws.
• Check that the rope guide is not too tight and can be rotated backwards and forwards freely when
moderate pressure is applied. If this is not the case then; a) the rope guide has been fitted
incorrectly, b) the barrel is damaged, c) the rope guide is damaged.
REF: MMZX003c.DOC
2/3
(ZX3 Series Hoist Unit)
Fig ZX003/3.
Fig ZX003/4
REF: MMZX003c.DOC
3/3
(ZX Series Hoist Units)
CAUTION: If the hoist is operated prior to rectifying the condition then both the rope guide and rope will
be damaged.
Fig ZX015/1
To rectify “Slack Rope” try any of the four methods listed below
Method 1 If the amount of slack rope is small it is some times possible to remove it by applying a
large load to the hook (approx. 75% of the safe working load) and carefully lowering
and lifting the load by 100mm. This should be repeated 10 or 20 times.
CAUTION: If the rope behind the rope guide “backs up” ie. starts to lift out of the barrel
groove, stop immediatley as this will eventually damage the rope guide.
Method 2 Remove the rope guide channel. For a ZX3 hoist this means one of the side frames
and for a ZX4 hoist it means the bolt on limit bar. Holding the rope which falls off the
barrel firmly, rock the rope guide backwards and forwards. This has the effect of
working the rope through the rope guide.
Method 3 Slacken off the rope guide clamping screws and repeat method 2.
Method 4 Completley remove the rope guide and tighten the rope onto the barrel.
REF: MMZX015B.DOC
1/1
ROPE TERMINATIONS : WEDGE & SOCKET
The wedge and socket anchorage system consists of a flat, pear shaped wedge with a radiused
groove to accommodate the wire rope This fits inside a suitably tapered socket or body usually of the
clevis type with an eye and a pin fitting (see Fig.RP002/1).
Fig.RP002/1
Fig.RP002/2
Installation
Each wedge and socket manufactured by Street Crane Co. is clearly identified with the rope diameter
with which it is intended to be used. They are designed to be used as a pair and under no
circumstances should different sized wedges and sockets be used together. Similarly wedges and
sockets supplied from different manufacturers should not be mixed even though they may be labeled
for the same rope size.
The rope should be fitted so that the live or loaded section of the rope is not kinked where it leaves the
socket, but pulls directly in line with the point of attachment of the socket. Incorrect fitting will lead to
premature failure of the rope. The tail end of the rope should be fitted with a simple clamp or wire rope
grip and laid parallel to the loaded rope. If a wire rope grip is used then a length of rope or bar with
same diameter to that of the rope will be necessary to ensure the rope is adequately gripped The
length of the tail should be at least 100mm long. (see Fig RP002/2).
The wire rope grip is required to ensure that the rope does not slip through the anchorage before the
wedge has had chance to seat adequately. The rope grip should be placed well away from the fused
end of the wire rope. Once a new rope has been fitted, the load should be applied gradually before
re-checking that the wedge has seated correctly in the socket.
Inspection
A wedge and socket termination should be visually inspected in accordance with the maintenance
schedule. In particular, inspect for damage to the rope where it emerges from the socket. The socket
itself should also be noted and should be inspected for deformation and cracks particularly if the
wedge is seen to protrude excessively.
If any damage whatsoever is seen on either the wedge or socket then the pair should be replaced
before the hoist is put back into service.
REF: MMRP002A.DOC
1/1
(ZX Series Hoist Unit)
BOTTOM BLOCK
Each bottom block is clearly labelled with the hoists maximum capacity (safe working load). Two
examples of different types of ZX hoist bottom block are illustrated in Fig ZX010/1.
Fig ZX010/1
Inspection
All bottom blocks should be inspected and maintained at prescribed intervals specified in the
“Inspection & Maintenance Schedule” (MMZX007A) in accordance with the following instructions.
• Ensure that the hook is in good condition and is free from cracks and deformation. Check that the
hook rotates freely.
• Examine the condition of the sheave(s) and ensure that they are free from cracks or damage due to
rope indentations. Check that they can be rotated freely.
• Ensure that the capacity of the hoist is clearly displayed on the bottom block
• Check that the safety catch operates and springs fully closed against the hook
• Check the condition of the sheave covers ensuring that they are free from cracks and chips
• Check the security of the sheave cover fixings
Lubrication
All bearings fitted in the sheaves of a ZX hoist bottom blocks are sealed for life and require no
lubrication. The thrust bearing, located on the hook crosshead requires lubricating via a greasenipple
in accordance with the the “Lubrication Schedule”.
For most models, the greasenipple is clearly located on the crosshead (Fig. ZX010/1). However some
models have a greasenipple inside the sheave cover. A groove in the crosshead indicates which cover
must be removed (Fig. ZX010/2). Once the cover has been removed the greasenipple can be charged
by rotating the sheave until a hole in the sheave lines up to allow access.
REF: MMZX010A.DOC
1/2
(ZX Series Hoist Unit)
BOTTOM BLOCK
Fig ZX010/2
REF: MMZX010A.DOC
2/2
(Spur & Pinion Travel Drive Assembly)
REF : mmlt004a.doc
1/1
(Direct Drive Assembly)
REF : MMLT009A.DOC
1/1
(ZX Crab Unit)
Item Description
1. ...................... End Carriage
2. ...................... Bearing Stub
3. ...................... Wheel Bearing
4. ...................... Wheel
5. ...................... Locking Ring
This assembly is generally maintenance free as the wheel bearings are sealed for life. Only the travel
drive unit gearbox requires lubricating, see lubrication schedule for details.
REF: MMLT010A.DOC
1/2
(ZX Crab Unit)
Fig. LT010/3
Fig. LT010/2
Fig. LT010/1
Locking Rings
Screw Size Allen Key size Tightening
(mm) Torque (Nm)
M6 5 17
M8 6 41
M10 8 83
M12 10 145
M14 12 230
REF: MMLT010A.DOC
2/2
(ZX Series Hoist Unit)
CT002/1.
REF : MMCT002A.DOC
1/2
(ZX Series Hoist Unit)
REF : MMCT002A.DOC
2/2
SK-F DRIVE
REF: MMLT015B
CDE 1/3
SK-F DRIVE
Table LT015/1
REF: MMLT015B
CDE 2/3
SK-F DRIVE
• Re-tighten the assembly fixings to the recommended torque value (see Table LT015/1)
Re-check the air gap and repeat adjustment if necessary.
REF: MMLT015B
CDE 3/3
TRAVEL BRAKE MOTORS TYPE “EFB2” & “EFB3”
Operation Of The Brake
The travel brake is designed to provide a braking action with the removal of the electrical power, either
accidentally of intentionally.
The brake is released by applying a direct current to the brake coil. This causes the pressure plate to
become magnetically attracted towards the brake end shield which in turn releases the brake disc (fan).
When direct current is removed from the brake coil the central brake spring pushes the pressure plate
onto the brake lining thus producing a braking force.
The direct current for the brake is derived from an AC/DC rectifier which is mounted in the drive
treminal box.
Fig LT005/1.
REF: MMLT005A.DOC
1/3
TRAVEL BRAKE MOTORS TYPE “EFB2” & “EFB3”
Adjusting the Air Gap
• Remove the Fan guard.
• Loosen the binding screws.
• Remove O-ring.
• Insert a shim or non-magnetic feeler gauges between Brake end shield and the Pressure plate.
Thickness should be 0.25 - 0.30mm
• Tighten the centre screw until the shim or gauges are a sliding fit (do not clamp tight).
• Check that the Air gap is constant at a minimum of three places around the brake.
• Evenly tighten the binding screws starting with the screw opposite the key. For tightening torque
see Table LT005/1.
• Re-tighten the centre screw.
• Replace O-ring and fan guard.
• Test run brake.
The brake lining should be replaced when it is not possible to re-set the Air gap to the recommended
setting.
Brake Type Nominal Brake Maximum Air Gap Tightening torque for
(See motor Nameplate) Torque (Nm) (mm) binding screws (Nm)
(See motor Nameplate)
6.0 - 7.5 0.6
3.8 - 5.4 0.7
2.9 - 3.7 0.9
EFB2 2.1 - 2.8 0.55 5.5
1.5 - 2.0 0.65
1.0 - 1.4 0.9
0.7 - 1.1 1.1
20.2 - 25.0 0.6
15.2 - 21.6 0.8
EFB3 8.9 - 13.3 1.0 9.0
4.1 - 7.9 0.85
2.9 - 4.7 1.2
1.3 - 2.3 1.4
Table LT005/1
REF: MMLT005A.DOC
2/3
TRAVEL BRAKE MOTORS TYPE “EFB2” & “EFB3”
Brake Rectifier Circuit Diagrams
REF: MMLT005A.DOC
3/3
FAULT FINDING
WARNING : Ensure that the mains power is isolated before starting any maintenance work.
Should you require any assistance from Street Crane Service Department please specify:
• The hoist serial number
• Details from both hoist nameplates
• Motor nameplate details
• Describe the nature and extent of the fault
• Explain under what circumstances the fault occurred
• State your suspected cause
General
REF: MMZX013A.DOC
1/8
FAULT FINDING
Hoist Motion
REF: MMZX013A.DOC
2/8
FAULT FINDING
Hoist Motion cont’d
Hoist will not raise or slowly runs Brake failure Check operation of hoist brake
back when hoist motion is
operated.
Motor failure Check operation of hoist motor
and that all phases are present
at the motor terminals.
Fuse blown or circuit breaker Replace fuse or reset circuit
tripped breaker. Investigate reasons for
the fault.
Hoist will not switch from slow Pendant fault Check condition of
speed to fast speed corresponding pushbutton and
(two speed motors only) pendant wiring.
Fast speed contactor fault Check the operation of the Fast
hoist contactor. Replace if
necessary
REF: MMZX013A.DOC
3/8
FAULT FINDING
Traverse Motion
REF: MMZX013A.DOC
4/8
FAULT FINDING
Hoist and Traverse Brakes
REF: MMZX013A.DOC
5/8
FAULT FINDING
Motor Units
REF: MMZX013A.DOC
6/8
FAULT FINDING
Motor overheats Running period and/or starting Adjust the operating conditions
class are exceeded to the design cycle otherwise
consult Street Crane
Motor too noisy Bearings distorted, damaged or Consult Street Crane
dirty
Rotating parts vibrate Consult Street Crane
Foreign matter in the cooling air Clean cooling air passages
passages
REF: MMZX013A.DOC
7/8
FAULT FINDING
Gearboxes
REF: MMZX013A.DOC
8/8
STEEL WIRE ROPES
All Street wire rope hoists use a multi-strand, low rotational type rope. These ropes are constructed
from two or more layers of strands which are laid in opposite directions so that their rotational
characteristics when under load act in opposition. The rope will therefore not twist when it is loaded or
stretched. This low rotational characteristic between the strands is only maintained so long as the rope
remains in good condition.
Storage
Always follow the manufacturers storage recommendations for steel wire ropes. Generally they
should always be stored in a cool dry environment preferably indoors. The ropes should never be
stored where they are likely to be affected by chemical fumes, steam or other corrosive agents. They
should be stored off the ground on raised pallets and away from walls. If outdoor storage is
unavoidable then the rope must be covered with a tarpaulin and air allowed to circulate to prevent the
build up condensation and moisture. If the coils are to be stored for any length of time then they
should be periodically rotated through 180° to prevent the lubricant draining to the bottom of the reel in
hot weather.
Handling
To avoid physical damage ropes should be offloaded with care. The reels or coils should be handled
by inserting a steel bar through the centre hole of the reel and lifted by means of a suitable sling.
Installation
To prevent the possibility of kinking or imparting any rotation into the rope, it should be uncoiled
without slack and in a straight line. If the strands are disturbed, malformation of the rope may develop
during subsequent use. Coils should be paid out from a turntable or on a pair of stands supported by
a shaft, alternatively short lengths of rope can be uncoiled along the ground (see Fig. RP001/1.). The
rope should never be uncoiled by throwing off turns from a stationary reel. During this operation the
rope should be kept as clean as possible.
When transferring a rope from reel to barrel, make certain that the rope bends in the same direction.
The reel and barrel should be spaced well apart and always reeved from top to top or from bottom to
bottom (see Fig. RP001/2.). Whilst transferring the rope ensure that sufficient tension is applied to
the reel to prevent loops forming. This tension can be provided by means of a simple plank rigged to
bear against the reel flanges. For smaller ropes tension can be applied with suitably gloved hands.
Fig. RP001/1
REF: MMRP001A.DOC
1/2
STEEL WIRE ROPES
Fig. RP001/2
Running In
After installation of a new rope it is important to run through the hoists operating cycle for a number of
operations at reduced speeds and loads to allow the rope to adjust to the working conditions.
REF: MMRP001A.DOC
2/2
SOUND LEVELS
The mean sound pressure level was measured in accordance with BS EN ISO 3744:1994.
For measurement purposes the hoist unit was operated under normal loading conditions for a full
operating cycle.
The sound pressure level is reduced by approx. 3dB(A) each time the distance form the sound source
is doubled.
REF: MMMI011A.DOC
1/1
THIS PAGE IS INTENTIONALLY BLANK
CDE
Optional Extras
7101 LIMIT SWITCH
The 7101 limit switch is normally used to indicate the position of the crane/hoist. The switch is
operated by a striker peg, which rotates an operating arm as it comes into contact with it.
Operation
Standard Setup - Once tripped then the relative motion becomes operable in slow speed only.
Optional Setup - Once tripped then the relative motion will stop.
On each of the above, when the limit is tripped, normal operation is available in the opposite direction
to that which caused the switch to operate. Once the crane/hoist has passed back through the limit
switch, re-setting it, that motion will return to perform its original function.
Setup
To ensure reliable operation of the switch, the dimension from the edge of the striker peg to the centre
line of the horizontal arm should be as shown above. The striker pegs should be located so that the
switch is not rotated more than 90° in any one direction. Failure to comply with this will result in
permanent damage to the switch.
When setting the point of operation for the limit switch, account should be taken of the crane/hoist
speed and the stopping distance. The point of operation should be set to allow a fully loaded
crane/hoist to stop from fast speed before reaching the required position. After setting, the correct
operating position of the switch should be proven.
Contacts
REF: MMEL019A.DOC
1/1
ULTIMATE LIMIT SWITCH
The Ultimate Limit Switch, when operated, will interrupt power to the hoist unit. This will only occur if
the hoists normal overhoist limit switch has failed to operate. NOTE: The reason for the normal
overhoisting limit switch to become inoperative should be investigated and rectified, prior to putting the
hoist back into service.
REF: MMEL015A.DOC
1/1
CONTROL PENDANTS
Maintenance
• Ensure that all legends are clean and legible.
• Check to ensure that each button performs its stated function.
• Check the condition of each of the function buttons and their respective rubber seals. Replace
damaged function buttons if necessary.
• Check the condition of the casing to ensuring that it is free from cracks. Replace if necessary.
• Check the condition of the cable entry rubber seal. Replace if damaged.
• Check security of all strainer wire fixings.
REF : mmel005a.doc
1/1
Street
Inspection & Maintenance Log
Crane / Hoist Ref :
Description of any Inspections, Maintenance work and Parts replaced :-