Weekly Schedule Inspection & Test 27th February - 5th March 2023 Rev.02

Uploaded by

Borizbo Boris
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

WEEKLY INSPECTION & TESTING SCHEDULE

Period: 27th February - 5th March 2023


No. Date CP Time Type of Activities Accepted Criteria Usage Location Remarks

1 27-Feb-23 203 8:00 AM Rebar Assembly inspection DKP 61 (*) Method Statement & OCS.5 clause 4.5 For Diaphragm Wall Mekarsari workshop Joel

2 27-Feb-23 203 10:00 AM Compressive strength test 30 day Fc' 40 Compressive Strength Test For Diaphragm Wall Trisakti Laboratory Theresia
slump 22 ± 2cm. DKP 10 (Adhimix)

3 28-Feb-23 203 8:00 AM Rebar Assembly inspection DKP 64 (*) Method Statement & OCS.5 clause 4.5 For Diaphragm Wall Mekarsari workshop Joel

4 28-Feb-23 203 8:00 AM BL 11 roof slab casting (*) Method Statement & OCS.5 clause 5 For Slab structure Glodok Station Arsyad

Tensile & Bending Test Rebar CBS for Slab


PT. Master Steel Laboratory ,
5 28-Feb-23 203 9:00 AM structure OCS 5. clause 13 Reinforcement Bar For Slab structure Pulogadung Adnan
(D13, D16, & D32)

Compressive strength test 7 days Trial Mix Fc'


6 28-Feb-23 203 11:00 AM 30 slump 12 ± 2cm & 15 ± 2cm - PT Compressive Strength Test For Slab Structure Trisakti Laboratory Theresia
Pionirbeton Industri Plant Kuningan

Compressive strength test 30 day Fc' 40


7 1-Mar-23 203 10:00 AM slump 22 ± 2cm. DKP 45 & DKP 18 (Adhimix) Compressive Strength Test For Diaphragm Wall Trisakti Laboratory Theresia

8 1-Mar-23 203 2:00 PM Rebar Assembly inspection DKP 49 (*) Method Statement & OCS.5 clause 4.5 For Diaphragm Wall Mekarsari workshop Joel

9 1-Mar-23 203 8:00 AM DKP 58 D-Wall Rebar installation , excavation Method Statement & OCS.5 clause 4.5 For Diaphragm Wall Kota Station Rendhy
and casting (*)

10 2-Mar-23 203 8:00 AM DKP 61 D-Wall Rebar installation , excavation Method Statement & OCS.5 clause 4.5 For Diaphragm Wall Kota Station Adi
and casting (*)

Compressive strength test 28 days Fc' 40


11 2-Mar-23 203 10:00 AM slump 22 ± 2cm. DKP 32 D-Wall (Adhimix) Compressive Strength Test For Diaphragm Wall Trisakti Laboratory Theresia

Compressive strength test 7 days Trial Mix Fc'


12 2-Mar-23 203 10:00 AM 30 slump 12 ± 2,5 cm & 15 ± 2,5 cm - Adhimix Compressive Strength Test For Slab Structure Trisakti Laboratory Theresia
RMC Plant Tanah Abang 1

DKP. 49 D-Wall Rebar installation ,


13 3-Mar-23 203 8:00 AM excavation and casting (*) Method Statement & OCS.5 clause 4.5 For Diaphragm Wall Kota Station Adnan
WEEKLY INSPECTION & TESTING SCHEDULE
Period: 27th February - 5th March 2023
No. Date CP Time Type of Activities Accepted Criteria Usage Location Remarks

14 4-Mar-23 203 2:00 PM Rebar Assembly inspection DKP 62 (*) Method Statement & OCS.5 clause 4.5 For Diaphragm Wall Mekarsari workshop Joel

15 4-Mar-23 203 8:00 AM DKP. 7 D-Wall Rebar installation , excavation Method Statement & OCS.5 clause 4.5 For Diaphragm Wall Kota Station Arsyad
and casting (*)

16 5-Mar-23 203 8:00 AM DKP. 62 D-Wall Rebar installation , Method Statement & OCS.5 clause 4.5 For Diaphragm Wall Kota Station Niko
excavation and casting (*)

( * ) Tentative