1 27-Feb-23 203 8:00 AM Rebar Assembly inspection DKP 61 (*) Method Statement & OCS.5 clause 4.5 For Diaphragm Wall Mekarsari workshop Joel
2 27-Feb-23 203 10:00 AM Compressive strength test 30 day Fc' 40 Compressive Strength Test For Diaphragm Wall Trisakti Laboratory Theresia
slump 22 ± 2cm. DKP 10 (Adhimix)
3 28-Feb-23 203 8:00 AM Rebar Assembly inspection DKP 64 (*) Method Statement & OCS.5 clause 4.5 For Diaphragm Wall Mekarsari workshop Joel
4 28-Feb-23 203 8:00 AM BL 11 roof slab casting (*) Method Statement & OCS.5 clause 5 For Slab structure Glodok Station Arsyad
8 1-Mar-23 203 2:00 PM Rebar Assembly inspection DKP 49 (*) Method Statement & OCS.5 clause 4.5 For Diaphragm Wall Mekarsari workshop Joel
9 1-Mar-23 203 8:00 AM DKP 58 D-Wall Rebar installation , excavation Method Statement & OCS.5 clause 4.5 For Diaphragm Wall Kota Station Rendhy
and casting (*)
10 2-Mar-23 203 8:00 AM DKP 61 D-Wall Rebar installation , excavation Method Statement & OCS.5 clause 4.5 For Diaphragm Wall Kota Station Adi
and casting (*)
14 4-Mar-23 203 2:00 PM Rebar Assembly inspection DKP 62 (*) Method Statement & OCS.5 clause 4.5 For Diaphragm Wall Mekarsari workshop Joel
15 4-Mar-23 203 8:00 AM DKP. 7 D-Wall Rebar installation , excavation Method Statement & OCS.5 clause 4.5 For Diaphragm Wall Kota Station Arsyad
and casting (*)
16 5-Mar-23 203 8:00 AM DKP. 62 D-Wall Rebar installation , Method Statement & OCS.5 clause 4.5 For Diaphragm Wall Kota Station Niko
excavation and casting (*)
( * ) Tentative