Kurva S (01 Agustus 23)

This document outlines the renovation time schedule for Graha Construction in 2023. It details 15 interior finishing work items and their planned progress in each month from July to November. The total planned work is 100% and will be completed in stages throughout the months. The schedule shows the percentage of work planned and actual progress achieved each week to monitor deviations from the plan.

Uploaded by

Hegar Grafika
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
40 views1 page

Kurva S (01 Agustus 23)

This document outlines the renovation time schedule for Graha Construction in 2023. It details 15 interior finishing work items and their planned progress in each month from July to November. The total planned work is 100% and will be completed in stages throughout the months. The schedule shows the percentage of work planned and actual progress achieved each week to monitor deviations from the plan.

Uploaded by

Hegar Grafika
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

CONSTRUCTION GRAHA RENOVATION TIME SCHEDULE

2023

TAHUN 2023
No Working Plan Bobot July Agustus September Oktober November
17-23 24-31 '01-06 07-13 14-20 21-27 28-03 04-10 11-17 18-24 25-30 01-08 09-15 16-22 23-31 01-05 06-12 13-18

I General Work 2,44% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14%

Kick Of Meeting 0,05% 0,05%

II Interior Finishing Work

1 Drof off 1,56% 0,26% 0,26% 0,26% 0,26% 0,26% 0,26%

2 Lobby 1st Floor 9,93% 1,42% 1,42% 1,42% 1,42% 1,42% 1,42% 1,42%

3 Lobby 2nd Floor 10,89% 2,18% 2,18% 2,18% 2,18% 2,18%

4 Guest Area 2,37% 1,19% 1,19%

5 Corridor 8,41% 2,10% 2,10% 2,10% 2,10%

6 Guest Room 3,64% 0,61% 0,61% 0,61% 0,61% 0,61% 0,61%

7 Meeting Room 1 4,25% 0,71% 0,71% 0,71% 0,71% 0,71% 0,71%

8 Meeting Room 2 3,92% 0,65% 0,65% 0,65% 0,65% 0,65% 0,65%

9 Meeting Room 3 7,01% 1,00% 1,00% 1,00% 1,00% 1,00% 1,00% 1,00%

10 Trainning Room 3,43% 0,57% 0,57% 0,57% 0,57% 0,57% 0,57%

11 Gathering Room 15,85% 1,22% 1,22% 1,22% 1,22% 1,22% 1,22% 1,22% 1,22% 1,22% 1,22% 1,22% 1,22% 1,22%

12 Staircase 10,21% 1,46% 1,46% 1,46% 1,46% 1,46% 1,46% 1,46%

13 Lobby Multipurpose 1,95% 0,28% 0,28% 0,28% 0,28% 0,28% 0,28% 0,28%

14 Multipurpose Hall 6,12% 0,87% 0,87% 0,87% 0,87% 0,87% 0,87% 0,87%

15 Multipurpose Hall 1st Floor 7,98% 1,33% 1,33% 1,33% 1,33% 1,33% 1,33%

TOTAL 2,27% 2,36% 2,36% 4,33% 4,90% 4,90% 9,62% 10,79% 10,79% 10,01% 7,34% 7,57% 6,98% 3,15% 3,15% 3,15% 3,15% 3,15%
JUMLAH BOBOT % 100,00% 2,27% 2,36% 2,36% 4,33% 4,90% 4,90% 9,62% 10,79% 10,79% 10,01% 7,34% 7,57% 6,98% 3,15% 3,15% 3,15% 3,15% 3,15%
BOBOT RENCANA / MINGGU INI % 2,27% 4,64% 7,00% 11,33% 16,23% 21,14% 30,75% 41,55% 52,34% 62,35% 69,69% 77,26% 84,24% 87,39% 90,54% 93,70% 96,85% 100,00%
BOBOT AKTUAL MINGGU INI % 1,08% 1,08%
DEVIASI -1,19% -3,55%

PT.KUAT ANDAL NAN GEMILANG

AMIN
PROJECT MANAGER