FMBT-Schemes 93194
FMBT-Schemes 93194
ES Solution Guide
Fast Motor Bus Transfer Schemes
20220324
Author............................................................................................................Mahesh Katuru
This document, and all information contained herein, is proprietary to SEL ES. Any unauthorized use, distribution, or reproduction of this document (in whole or in
part) or of any information contained herein is specifically prohibited. This legend must appear on any authorized reproduction (in whole or in part).
Revision
Date Description Author
Number
All brand or product names appearing in this document are the trademark or registered trademark of their respective holders. No SEL trademarks may be used
without written permission. SEL products appearing in this document may be covered by U.S. and Foreign patents.
SEL products referred to in this report are manufactured by Schweitzer Engineering Laboratories, Inc. (SEL).
Figures
Figure 2.1: Two- Breaker Scheme ................................................................................................................. 3
Figure 2.2: Three-Breaker Scheme ................................................................................................................ 4
Figure 2.3: Studying the Decaying and Healthy Voltages ............................................................................ 5
Figure 3.1: Single-Line Diagram Used to Describe the Problem and the Application in this Solution
Guide.............................................................................................................................................................. 6
Figure 3.2: FMBT Algorithm ........................................................................................................................ 9
Figure 3.3: SEL-451 Functional Overview ................................................................................................. 11
Figure 3.4: SEL-700BT Functional Overview ............................................................................................ 12
Tables
Table 3.1: Analog, DI, and DO Requirements for FMBT Scheme ............................................................... 6
Table 3.2: BOM for FMB Scheme .............................................................................................................. 10
Table 4.1: Relay Word Bits and Logic Settings for Fast Transfer Method ................................................. 21
Table 4.2: Fast Transfer Method Settings.................................................................................................... 21
Table 4.3: Synchronism Check Settings ...................................................................................................... 22
Table 4.4: Relay Word Bits and Logic Settings for In-Phase Transfer Method.......................................... 23
Table 4.5: In-Phase Transfer Method Settings ............................................................................................ 24
Table 4.6: Relay Word Bits and Logic Settings for Residual Transfer Method.......................................... 24
Table 4.7: Residual Transfer Method Settings ............................................................................................ 24
Table 5.1: Negative Test Step-by-Step Procedure ....................................................................................... 32
Table 5.2: New FMBT Panel Functional Test ............................................................................................. 35
Table 5.3: Cubicle Fabrication Functional Test .......................................................................................... 35
Table 5.4: Terminal Block Functional Test ................................................................................................. 35
Table 5.5: Wiring Functional Test ............................................................................................................... 36
Table 5.6: Grounding Functional Test ......................................................................................................... 36
Table 5.7: FMBT Relay Functional Test During FAT ................................................................................ 37
Table 5.8: FMBT Digital Inputs .................................................................................................................. 40
Table 5.9: FMBT Scheme Digital Outputs .................................................................................................. 41
Table 5.10: Simulation Test for Fast Transfer Method ............................................................................... 42
Table 5.11: Simulation Test for Residual Transfer ..................................................................................... 44
1.2 BACKGROUND
FMBT is the process of disconnecting a motor bus from the normal power source and safely reconnecting
it to a designated alternate power source within a short time period, which allows critical processes to
continue without damaging the equipment.
To maintain the plant operation and process continuity, motor buses may require transfer from a present
source to a new source like for power plants and industrial plants with heavy motor/other loads. Such
systems find immense use and importance in several critical situations in continuous process industries
(petrochemical plants, chemical plants, semiconductor manufacturing plants, paper mills, textile mills,
etc.) and fossil-fuel-fired as well as nuclear power generation stations.
A successful bus transfer under contingent conditions provides immense value and benefits to continuous
process operations that cannot afford unplanned interruptions of power supply to plant auxiliaries/loads.
Examples of plants where FMBT is applicable are power generation, refineries, chemical, pulp and paper,
steel, water and wastewater, automotive, and semiconductor.
The problem encountered by these disconnected motors maintaining a residual voltage is that when
reclosing occurs, the system voltage and machine residual voltage are typically out of phase; the phase
angle difference may even be higher than 100 degrees. Reclosing with the utility (or new incoming
source) can apply voltages above the motor design limits and result in high transient currents (inrush
current) and excessive torque on the motors shaft. Sometimes the inrush current may exceed the normal
starting current, which may generate mechanical stress on winding. During such instances, thermal
protection or short-circuit protection of relay may operate to cause the undesirable opening of CB. The
mechanical shock to the system may create cumulative damage to motor shaft and winding resulting in
reduced life of machine. The induction motor may not immediately fail, but the resulting high-shaft
torque and torque on the coils can eventually result in “unexplained” failures of the machines. The phase
difference between the system voltage per Hertz and the motor residual voltage per Hertz should not
exceed 1.33 per unit volts/Hertz at closing. A historical “rule-of-thumb” for unsupervised reclosing on
motor loads has been to delay the reclosing until the motors residual voltage magnitude has dropped less
than 25 percent of rated. Many designers set 125 percent as a desirable limit of maximum momentary
voltage applied to a motor. To overcome this problem without interruption of power for continuous
process industries, high-speed reclosing is considered to occur within 30 cycles of initial circuit
interruption, supervised by voltage, a sync-check condition, slip, rate-of-change of slip, rate-of-change of
voltage, advanced closing angle and breaker closing times. Sophisticated techniques and algorithms can
be implemented using SEL relays, where the high-speed transfer can be done even in one cycle without
damaging the motors and interruption to the industrial process.
Figure 3.1: Single-Line Diagram Used to Describe the Problem and the Application in this Solution Guide
Table 3.1 represents a typical relay digital inputs (DIs), digital outputs (DOs), and analog inputs (AIs)
requirements for the FMBT scheme shown in Figure 3.1.
No. Description
Binary Inputs
Initiation input from Upstream for Source 1, i.e., Upstream relay output or Upstream lockout
4 relay status or Upstream breaker open status etc.
Initiation input from Upstream for Source 2, i.e., Upstream relay output or Upstream lockout
5 relay status or Upstream breaker open status etc.
6 Auto transfers enable from selector switch (if required)
7 Auto/Manual Switch in Auto position (if required)
8 Auto/Manual Switch in Manual position (if required)
9 Source-1 Lockout (86) relay status
10 Source-2 Lockout (86) relay status
11 Source-1 PT MCB healthy status
12 Source-2 PT MCB healthy status
Binary Outputs
1 Bus coupler close command
2 FMBT device healthy to remote
3 FMBT operated to remote
4 Group Change to Source 1 (if required)
5 Group change to Source 2 (if required)
6 FMBT operated to Annunciation
7 Transfer Fail
8 Transfer Blocked
9 Transfer Successful
10 Loss of Potential
11 Fast transfer operated
12 In-phase transfer operated
13 Residual transfer operated
Analog Inputs
1 Voltage input (PT) form Bus section A
2 Voltage input (PT) form Bus section B
3 Current input (CT) from Line section A
4 Current input (CT) from Line section B
Where:
Δδcomp = Advance compensating closing angle
Slip = Slip between healthy source and decaying motor bus voltage frequencies
TBreaker = Closing time of the breaker
It is essentially a specialized automatic synchronizing under high-slip frequency and a rapidly
decelerating motor bus frequency. This necessitates the use of very fast measurement and output
command techniques. The CB requires some time to close, the in-phase transfer device must predict in
advance when the phase coincide and initiate transfer. The FMBT device has successfully met these pre-
requisites and executed the in-phase transfer.
No Description Quantity
- VE DC
+ VE DC SEL 451
From Field
4.3 CONFIGURATION
4.3.1 Motor Bus Transfer Classification and Transfer Methods
Motor bus transfers can be categorized as closed or open transition. The closed transition transfer involves
brief paralleling of the sources. The closed transition transfer is also commonly referred to as a hot
parallel transfer. Because the new source is connected to the motor bus before the old source is tripped,
transfers are completed without source interruption. On the other hand, open transition transfers do not
parallel the sources because the old source is tripped before the new source is connected to the motor bus.
Once the motor bus is disconnected, the motors coast down, and reconnection to the new source may
require supervision.
In all methods of transfer, if the new source does not meet the criteria for an acceptable source, and if it is
possible to stay on the old source, the initiation of the transfer should be blocked. If not possible to stay
on the old source, and the old source breaker must be tripped, the completion of the transfer to the new
source should be blocked or possibly delayed permitting the new source to recover. In this latter case,
transfer system logic could also be set up to provide transfer to an alternate new source.
4.3.4 Interlocks
The transfer output will occur when satisfying the following conditions/interlocks:
• FMBT device ready.
• External transfer initiation enable.
• Fast 52b contacts.
• Synchronism check for fast transfer.
• Protection not blocked; the conditions to recognize are breaker failure and close failure. Other
external conditions may apply such as the trip of busbar differential relay.
• PT MCBs healthy.
• CB closing conditions (CB in service, TCS healthy, spring charged, etc.).
• Interlock permissive for CB close (isolator, earth switch etc.).
Table 4.1: Relay Word Bits and Logic Settings for Fast Transfer Method
1 := ENABLED
EFASTTR (enable fast transfer method). 1 := ENABLED
0 := DISABLED
Table 4.4: Relay Word Bits and Logic Settings for In-Phase Transfer Method
1 := ENABLED 1 := ENABLED
EPHSTR (in-phase transfer method).
0 := DISABLED
MXSLP_P (maximum slip allowed before
0–40 Hz < 30 Hz
issuing the close command).
MXDSDTP (maximum rate-of-change of slip
0–40 Hz/second < 30 Hz/Sec
before issuing the close command).
MXDVDTP (maximum rate of voltage decay
Secondary 0–100
(secondary V/second) before issuing the close < 100 dV/dt
V/second
command).
MINV_P (minimum motor bus voltage 0–75 V in steps of
> 15 V
magnitude before issuing the close command). 0.1 V
T_INPHS (total time window for the in-phase
0–100 cycles 30–50 cycles
transfer).
MXROT_P (maximum number of rotations 0–15 number of
3–12
allowed in the in-phase transfer method). rotations
RESIDUAL TRANSFER
Figure 4.7 illustrates the conditions to occur during residual transfer method.
Table 4.6: Relay Word Bits and Logic Settings for Residual Transfer Method
1 := ENABLED 1 := ENABLED
ERESTR (residual transfer method).
0 := DISABLED
VMIN_R (maximum motor bus secondary voltage
0 to 75 V in steps of 0.1 V
to enable the transfer).
Note: T_RES=100 Cycles. It is an intentional time delay that is equal to motor trip time to start residual
transfer. This delay required to avoid unusual closing of bus coupler in residual method before
tripping of motor feeder during tripping of upstream breaker
Note: We must perform the fast bus transfer system validation study for the process plant which
requires FMBT scheme, and based on that, the settings in Table 4.2, Table 4.3, Table 4.5, and
Table 4.7 may change accordingly.
Supervised closure of the new source breaker is permitted without waiting for the breaker status contact
confirmation that the old source breaker has opened.
Simultaneous commands are issued for:
• Old source breaker trip
• New source breaker close initiate
Closure of the new source breaker may be delayed until permitted by the fast, in-phase, or residual
voltage transfer criteria, whichever occurs first.
Note that no matter what criteria are used and whether the electrical torque is calculated, or a more
sophisticated method is used to estimate the electrical or shaft torque based on simulation, the basic goals
of any FMBT schemes are the following:
• Avoid closing into the alternate source when the motor bus voltage and the alternate source
voltage are out of phase.
• Limit the transient torque on the motor as much as possible, while still maintaining the
availability of the process by riding through momentary transfer interruptions and reducing the
occurrence of a sustained and unwanted interruption.
How is this accomplished? Standards and experience have outlined several methods. This guide focuses
on sequential transfers where the primary source breaker opens before closing the alternate source
breaker, because this is the type of transfer that was selected for the refinery project. Among sequential
transfers, there are three methods: fast transfer, in-phase transfer, and residual transfer.
EVENT COLLECTION
The SEL-451 relay features comprehensive power system data analysis. Raw and filtered events as well
as the SER and signal profile.
Event reports simplify post-fault analysis and help you improve your understanding of protection scheme
operations. Event reports can also aid in testing and troubleshooting relay settings and protection schemes
FILTERED DATA
• Eight- and four samples/cycles filtered event reports
• Available in ASCII format and compressed ASCII format
• Available as command responses or as files
PRE-CONDITIONS:
• Incomer-1 CB is ON.
• Incomer-2 CB is ON.
• All the applicable motor/other feeders are ON.
• Check both VT voltages are available at the FMBT controller as normal voltage from the display.
• Disable under voltage tripping of motor feeder temporarily, if applicable.
• Switch the FMBT to Manual.. This is to avoid automatic closing of the bus coupler.
PRE-COMMISSIONING TEST
The pre-commissioning test will be done immediately after the bus shutdown. The CB on both incomers
shall be OFF and drawn out to TEST position. The CBs may need to be put in service for transfer
simulations, by making sure the line side is de-energized.
Step 1. Initiate all the binary input signals from source point and verify it is reporting up to FMBT
controller.
Step 2. Initiate all the binary outputs signals from FMBT and verify the action up to the destination
points.
Step 3. By voltage simulation, the transfer test sequence shall be tested.
Step 4. All the alarm points to HMI shall be verified.
Step 5. Once the functional test is completed by simulation, the system is ready for commissioning
test.
FMBT device is
Both PT MCBs were tripped and check the FMBT device readiness. not ready for
transfer
FMBT device is
Both incomer 86 trip relays are not operated and check the FMBT device
not ready for
readiness.
transfer
FMBT device is
Both incomer CBs are open and check the FMBT device readiness. not ready for
transfer
FMBT device is
Auto enable input signal is low and check the FMBT device readiness. not ready for
transfer
FMBT device is
BC CB status (Closed status) is high and check the FMBT device
not ready for
readiness.
transfer
Fast transfer method has been disabled on the relay with all the other Fast transfer
necessary conditions are satisfied for fast transfer. failure
Injected the motor bus voltage is less than the threshold setting in the
Fast transfer
FMBT device with all the other necessary conditions are satisfied for fast
failure
transfer.
Transfer initiation provided from IC-1 86 Trip/TF-1 86 Trip but without
Fast transfer
Incomer-1 and -2 CB status with all the other necessary conditions is
failure
satisfied for fast transfer.
Transfer initiation provided from IC-2 86 Trip/TF-2 86 Trip but without
Fast transfer
Incomer-1 and -2 CB status with all the other necessary conditions is
failure
satisfied for fast transfer.
Transfer initiation provided from IC-1 86 Trip/TF-1 86 Trip but without
satisfying the synch check condition (voltage threshold/phase Fast transfer
angle/frequency difference) with all the other necessary conditions are failure
satisfied for fast transfer.
Transfer initiation provided from IC-2 86 Trip/TF-2 86 Trip but without
satisfying the synch check condition (voltage threshold/phase Fast transfer
angle/frequency difference) with all the other necessary conditions are failure
satisfied for fast transfer.
Transfer initiation provided from IC-1 86 Trip/TF-1 86 Trip but with Bus
Fast transfer
coupler breaker closed status and all the other necessary conditions are
failure
satisfied for fast transfer.
Transfer initiation provided from IC-2 86 Trip/TF-2 86 Trip but with Bus
Fast transfer
coupler breaker closed status and all the other necessary conditions are
failure
satisfied for fast transfer.
Fast transfer method and in-phase transfer method were disabled on the
In-phase transfer
relay with all the other necessary conditions are satisfied for in-phase
failure
transfer.
Injected the motor bus voltage is less than the threshold setting in the
In-phase transfer
FMBT device with all the other necessary conditions are satisfied for in-
failure
phase transfer.
Injected the max slip value less than the threshold setting in the FMBT
In-phase transfer
device with all the other necessary conditions are satisfied for in-phase
failure
transfer.
Transfer initiation provided from IC-1 86 Trip/TF-1 86 Trip but with Bus
In-phase transfer
coupler breaker closed status and all the other necessary conditions are
failure
satisfied for in-phase transfer.
Transfer initiation provided from IC-2 86 Trip/TF-2 86 Trip but with Bus
In-phase transfer
coupler breaker closed status and all the other necessary conditions are
failure
satisfied for in-phase transfer.
Fast transfer method, in-phase transfer method and residual transfer
Residual transfer
methods were disabled on the relay with all the other necessary
failure
conditions are satisfied for residual transfer.
Injected the motor bus voltage is greater than the threshold setting in the
Residual transfer
FMBT device with all the other necessary conditions are satisfied for
failure
residual transfer.
5.4.1 Hardware
• Secondary injection test kit
• SEL-451 FMBT IED
• Laptop
• Multimeter, screw drivers, cutter, and other standard hardware tools
5.4.2 Software
• ACSELERATOR QuickSet Software
• SYNCHROWAVE Event software
AC panel illumination
Door alignment
Door alignment
Blocking conditions
1) FMBT ready: FMBT be CB close command is not
enable in Relay (e.g., switch possible
BLK should be in ON position)
2) Protection Lockout: CB close command is not
Simulate protection lockout possible
(e.g., 86 or 96 lockout relay)
Command handling
1) Indications: Change the Positions are according
position from each switching to the primary equipment
object and check the status
CMD indications OPEN and
CLOSED
2) Operating Mode: Check for Operation is possible
each switching object the close from FMBT device
and open command
Current measurement
1) Nominal Values: Inject Primary and secondary
Current nominal current in all phases values are according to
and check values and angles on injection
the display or in HMI
Voltage measurement
1) Nominal Values: Inject Primary and secondary
Voltage nominal voltage in all phases values are according to
and check values and angles on injection
the display or in HMI
Power measurement
1) Nominal Values: Inject Active and Reactive
Power nominal current and voltage in Power are according to
all phases and check values (P, injection
Q) on the display or in HMI
INTRODUCTION
This document describes the tests procedure of the FMBT relay panel. The tests will be carried out for
functions as per this document.
The various tests specified will be conducted at Site. For each part of the test one of the following
alternatives will apply.
LOGIC CHECKS
Cross verify the logics build in the relay with the approved logic in the drawings/scheme. If required,
refer to Section 5.3 for more details of negative testing to make sure whether logic is correct or not.
• Voltage injection will be done through numerical secondary injection kit (Omicron/Double) using
state simulation.
• During State 1, Transfer Ready LED will glow, which confirms that relay logic is ok and ready
for transfer.
• In State 2 we need to give Trip initiation input using output logic of numerical kit and after
receiving trip initiation and verifying logic relay will go for fast transfer for defined transferred
duration.
• Fast Transfer LED will glow, which confirms the successful operation of fast method.
• Actual breaker operation will be checked during simulation.
State 4
State 2 State 3
State 1 Normal State
State Drop in Motor Drop in Motor
Healthy Voltage After
Bus Voltage Bus Voltage
Changeover
• Voltage injection will be done through numerical secondary injection kit (Omicron/Doble) using
state simulation.
• During State 1, Transfer Ready LED will glow, which confirms that relay logic is ok and ready
for transfer.
• In State 2 we need to give Trip initiation input using output logic of numerical kit and after
receiving trip initiation and verifying logic relay will go for residual transfer for defined
transferred duration.
• Residual transfer LED will glow, which confirms the successful operation of residual transfer.
• Actual breaker operation will be checked during simulation.
ES GUIDE FMBT
28022022.rdb
3770_IntroducingSEL 3760_ImproveProces
s_MM-MD_20201020.pptx
-700BT_SW_20201110.pptx