Chapter 6. Hydrology Analysis (Final)
Chapter 6. Hydrology Analysis (Final)
2. The objective of the project is to improve of priority rural road in 3 provinces, to provide reliable
all year road access from provincial towns and agricultural rural area to markets.The project consists
of one civil work contract package such as in Pursat, Battambang, and BantheyMeanchey province.
3. The objectives and scope of the hydrological and drainage reporting are therefore to present:
Description of hydrological analysis carried out, but this study compares with data rainfall of
Historical Cambodian Weather Data in target regions of provinces, Conclusions on drainage
requirement.
6.4 Hydrology
b. Land Use
6. Cambodia is considered to be an agriculture country so almost entire catchment area crossed
the project road are villages’ farming, a typical rice paddy field or village garden crop as found
throughout lowland Cambodia. Traditionally land is ploughed and crops planted at the beginning of
the wet season in May or June and harvesting at beginning of dry season usually in late October or
early November.
c. Rainfall Analyses
7. Rainfall is a random event that cannot be predicted based on historical data. However, any
given precipitation event has several distinct and independent characteristics which can be quantified
as follows:
. Duration : The length of time over which precipitation occurs (hours).
. Depth : The amount of precipitation occurring throughout the storm duration (mm).
. Frequency : The recurrence interval of events having the same duration and volume.
. Intensity : The depth divided by the duration (mm per hour).
d. Frequency Analysis
8. Gumbel distribution is a statistical law often used for predicting extreme hydrological events
such as rainfall. The equation for fitting the Gumbel distribution to observed series of rainfall at
different return periods T is:
Rt Rav + Kσ
=
(eq.01)
Where R t denotes the magnitude of the T-year Rainfall event, K is the frequency factor, R av
and are the mean and the standard deviation of the maximum instantaneous rainfall respectively.
The frequency factor K is expressed as:
Where π = 3.14, λ is the Euler constant (=0.5772) and 𝑙𝑙𝑙𝑙 is the natural logarithm.
9. The relation between rainfall intensity and duration is commonly expressed in form:
a
I= (eq.03)
(b + T ) n
10. The first stage in developing this equation for a particular area involves fitting the data to the
equation. This is done by estimating rainfall intensities using extreme value analysis.
log e I =log e a − n log e (b + T ) (eq.04)
11. Thus the optimum values of the constants a, b and n can be found by entering values of loge I
and loge ( b + T ) into a linear regression equation program for a range of values of b, then selecting
equation that gives the closest fit to a straight line. This was done for the rainfall data for return
periods of 2.33, 10 and 50 years and the constants determined and shown in Table 6-1.
Table 6-1. Derived constants for Intensity Duration Equation (Watkin & Fiddes,1984)
Period b n a
10 0.37 0.88 98
12. The Rainfall Ratio Method allows rainfall, and therefore rainfall intensities of durations required
for drainage design, to be estimated from 24-hour rainfall of a known frequency (return period) by
applying the relationship
160
140
120
100
80
60
40
20
0
200 200 200 200 200 200 200 200 200 200 201 201 201 201 201
0 1 2 3 4 5 6 7 8 9 0 1 2 3 4
Pursat 125.3 85.6 83.6 109.8 58.9 76.4 80.1 70.2 77.2 64.8 57 71.7 103.3 76.4 60.2
Battambang 89 49.8 88.8 68.1 53.7 83.4 71 55.2 98.8 96.2 108 101.9 82.9 156.6 55
Banteay Meanchey 58.6 87.6 56.5 112.5 78.5 121.5 48.2
2.33 100
Rainfall Rainfall 10 year Rainfall 25 year Rainfall 50 year Rainfall
year year
Ratio Ratio return Ratio return Ratio return Ratio
return return
(RR2.33) (RR10) period (RR25) period (RR50) period (RR100)
period period
5mins 0.08 0.11 9.22 0.12 14.40 0.12 16.92 0.12 18.84 0.12 20.64
10mins 0.17 0.19 15.92 0.2 24.00 0.21 29.61 0.21 32.97 0.21 36.12
15mins 0.25 0.25 20.95 0.27 32.40 0.27 38.07 0.28 43.96 0.27 46.44
30mins 0.50 0.37 31.01 0.4 48.00 0.41 57.81 0.41 64.37 0.41 70.52
1h 1 0.49 41.06 0.53 63.60 0.55 77.55 0.55 86.35 0.55 94.60
2h 2 0.61 51.12 0.66 79.20 0.67 94.47 0.68 106.76 0.68 116.96
4h 4 0.72 60.34 0.76 91.20 0.78 109.98 0.79 124.03 0.79 135.88
8h 8 0.82 68.72 0.86 103.20 0.87 122.67 0.88 138.16 0.88 151.36
12h 12 0.89 74.58 0.91 109.20 0.92 129.72 0.92 144.44 0.93 159.96
18h 18 0.95 79.61 0.96 115.20 0.97 136.77 0.97 152.29 0.97 166.84
24h 24 1.00 83.80 1.00 120 1.00 141 1.00 157 1.00 172
2.33 10 25 50 100
Rainfall Rainfall Rainfall Rainfall Rainfall
year year year year year
Ratio Ratio Ratio Ratio Ratio
return return return return return
(RR2.33) (RR10) (RR25) (RR50) (RR100)
period period period period period
5mins 0.08 0.11 8.83 0.12 14.40 0.12 17.16 0.12 19.20 0.12 21.12
10mins 0.17 0.19 15.26 0.2 24.00 0.21 30.03 0.21 33.60 0.21 36.96
15mins 0.25 0.25 20.08 0.27 32.40 0.27 38.61 0.28 44.80 0.27 47.52
30mins 0.50 0.37 29.71 0.4 48.00 0.41 58.63 0.41 65.60 0.41 72.16
1h 1 0.49 39.35 0.53 63.60 0.55 78.65 0.55 88.00 0.55 96.80
2h 2 0.61 48.98 0.66 79.20 0.67 95.81 0.68 108.80 0.68 119.68
4h 4 0.72 57.82 0.76 91.20 0.78 111.54 0.79 126.40 0.79 139.04
8h 8 0.82 65.85 0.86 103.20 0.87 124.41 0.88 140.80 0.88 154.88
12h 12 0.89 71.47 0.91 109.20 0.92 131.56 0.92 147.20 0.93 163.68
18h 18 0.95 76.29 0.96 115.20 0.97 138.71 0.97 155.20 0.97 170.72
24h 24 1.00 80.30 1.00 120 1.00 143 1.00 160 1.00 176
i. Design rainfall-intensity-duration
15. The design rainfall-intensity-duration relationships are obtained directly from the time
distribution of rainfall, simply by converting the rainfall during a given duration to rainfall intensity in
millimeters per hour.
6.4.2 Methodology
16. There is a wide variation in the area of catchment. In addition, the road passes through different
vegetation and land use zones, although in hydrological terms there is little variation in relief, geology
and soil type, all of which affect the hydrological characteristics. There is no single method that
caters for all these variations. The followings are considerations for selecting any method to be
adopted for estimation of flood frequency and magnitude.
a. Design standard
17. The MPWT, Ministry of Public Work and Transports has a Design Standard for Drainage
produced in 1999 with the assistance of AusAID. The standard was later revised and updated in 2003.
However, this standard is of little relevance or use for this or other roads in floodplain and low relief
areas of Cambodia. This is because the standard has been based on methods appropriate to small
watercourses flowing in defined valleys, a situation rarely encountered in lowland Cambodia.
18. It describes only the use of the ‘Rational Method’. This method will not give reliable results for
the often-extensive flat catchments in lowland Cambodia, the Standard does warn of this limitation but
does not give useful guidance on an alternative.
19. For this hydrology study has demonstrated that the Rational Method is most applicable to much
catchments crossed by the project road except only the large catchment area.
b. Alternatives Methods of MPWT Design Standard
20. Many discussions explain why alternative methods of MPWT Standard were necessary and it
was given in consideration as:
1. Frequency analysis of continuous rainfall records from within the project area to
derive rainfall-intensity-duration curves for different return periods.
2. Rainfall-Ratio method to derive from 24-hour rainfall records from within the project
area rainfall intensity-duration curves for different return periods.
3. Correlation with gauge sites with continuous rainfall records analyzed by 1 above to
calibrate rainfall-intensity-duration curves derived by method 2 for different return
periods for sites with only 24-hour records.
4. For small catchments draining to normal culverts the Rational Method (i.e. the MPWT
method) to estimate discharge using the rainfall relationships from 1, 2 or 3 above.
5. For larger catchments draining to bridges or large culverts the United States Soil
Conservation Service Curve Number Method.
6. For larger catchments and those draining to bridges or large culverts a Generalized
Tropical Flood Model (GTFM) derived from the ORSTOM and TRRL methods.
7. For rivers where flow records are available, extreme value frequency analysis of peak
annual discharge.
21. The Rational Method (4) was introduced in the United States by Kuichling in 1886. Since then,
it has become the most widely used method for the analysis of runoff response from small catchments.
This method provides only the value of peak discharge. The peak discharge is primarily due to over
land flow rather than stream flow.
23. The time of concentration (tc) is the time required for water to flow from the hydraulically most
remote point of the drainage area to the point under investigation.
Time of concentration has been determined from the Kirpich Formula
b. Intensity of Rainfall ‘I ’
24. Intensity of rainfall ‘I’ in mm/h corresponding to the design return period and duration equal to
‘Tc’ is read from the rainfall-duration-frequency tables or curves.
25. The run-off coefficient ‘C’ is selected by reference to values in Table 05. This is based on the
table for rural areas in the Cambodian Standard Road Design Part 3 – Drainage, but with modified
descriptions more relevant to Cambodian conditions and more detailed definition of the relief
coefficient ‘A’ for flat areas. The runoff coefficient ‘C’ is equal to the sum of the coefficients from
columns A, B, C and D. The value of ‘C’ can vary from one moment to another according to changes,
especially soil moisture conditions.
Table 6-5. Values of Runoff Coefficient ‘C’ used in the Rational Formula
Watershed Characteristics
A B C D
Relief Soil Infiltration Vegetation Cover Surface Storage
e. Calculation of Discharge
27. The calculation of discharges using Rational Method is summarized in Annex.
C A xPxAxF
Qp = (eq.07)
360xTB
29. The values of the parameters required for the Generalised Tropical Flood Model have been
taken from the recommendations contained in Watkins and Fiddes.
31. It should be noted that the percentage runoff coefficient in the GTFM is different to that in the
Rational Method. This is because GTFM takes separate account of factors included in the Rational
Method runoff coefficient.
32. It was found that for the flat or very gently sloping catchments characteristic of Cambodia using
the banded Slope Class S.
33. It was found that presenting the slope classification in graphical form and using fractional slope
classes to remove the abrupt change between bands significantly improved estimates predicting flows
generally consistent with field observations.
CxA0.5
=TB + Ts (eq.09)
S2
Where C: is a constant, which is 30 for humid zone catchments.
A: is the catchment area in km2 .
S: is the Slope Class ‘S ’.
TS : is the surface cover flow time from Table 10.
36. This equation applies for storms of up to 8 hours duration. For longer durations on large
catchments the T = 8 value is adopted. The values adopted for design are presented in Table 6-6.
Table 6-6. Areal Reduction Factors
8h 0.98 0.97 0.97 0.96 0.94 0.90 0.86 0.80 0.68 0.55 0.37
4h 0.97 0.96 0.96 0.94 0.92 0.87 0.82 0.75 0.60 0.44 0.20
2h 0.97 0.96 0.95 0.93 0.90 0.84 0.78 0.68 0.50 0.29
1h 0.96 0.94 0.93 0.91 0.87 0.80 0.72 0.60 0.37 0.11
30 min 0.95 0.93 0.91 0.89 0.84 0.75 0.64 0.50 0.20
d. Base Flow
37. Most watercourses crossed by the project roads are ephemeral (seasonally dry), and perennial
streams have small dry season flow. Design flood flows will however occur in the rainy season when
base flow may be more significant. But even then flows will be flashy and high discharges are not
sustained over long periods. Therefore, base flow has been neglected for the purpose of design
discharge estimates.
e. Calculation of discharge
Parameters for Generalised Tropical Flood Model
Very low permeability. Clay soils with high swelling potential; shallow soils
2
over largely impermeable layer, very high water table.
Very permeable. Soils with very high infiltration rates such as sands,
5
gravels and aggregated clays.
1 0 - 0.2
2 0.2 - 1.0
3 1.0 - 4.0
4 4.0 - 10.0
5 10.0 - 20.0
6 > 20.0
Table 6-9. Basic runoff coefficient for humid catchments (CS) (%)
1 48 36 23 11 0
2 55 43 30 18 6
3 62 50 37 25 13
4 69 57 45 32 20
5 76 64 52 39 27
6 83 71 59 46 34
Forest 1.7
41. This recommendation is appropriate for new construction. However, we have carefully
considered the justification for higher standards on parts of the road at locations where problems have
been reported. Conversely, for rehabilitation it is considered reasonable to accept slightly lower
standards, if the cost of achieving the proposed standards is too great.
43. Drainage structures are designed to accommodate a flow of a given return period
• For rural roads in the tropics it is usual to design culverts for a 1 in 25 year (or 5%
probability of occurrence event)
• Bridges for 1 in 50 or 100 years (or 2% or 1% respectively probability of occurrence).
44. During any given period of years there is a probability that the design flow will be equalled or
exceeded. The design life adopted for a road is commonly 20 years, and for a bridge 50 years. It can
be assumed that the project roads to the current alignment and levels are over 30 years old. On the
basis that the original drainage design was to the standards quoted above, it is a simple calculation to
estimate the probability that drainage capacity has been exceeded:
• During the design life of the road;
• Since it has been built; or
• For bridges by the time they reach their design life.
Table 6-6. Probability of design standards being exceeded during design life. (CDOT, 2004)
Return period‘T’
years 1 in 10 years 1 in 25 years 1 in 50 years 1 in 100 years
Design life ‘L’
(10% probability) (5% probability) (2% probability) (1% probability)
years
45. It can be seen that there is a 78% probability that each culvert on the road will have
experienced a flow equal or exceeding a designed capacity of 1 in 25 years during the last 30 years.
For bridges the corresponding probability is 45%. It should be understood that incidences of flooding
for more frequent events will not happen simultaneously at every location on the road, but will occur
randomly both temporally and spatially, dependant on the distribution of flood generating rainfall.
46. This should make it clear that if it is true that some drainage structures have failed under
extreme rainfall and floods, it does not mean that they have been under-designed.
observations highlight two major concerns related to current and future climate changes. Specifically,
there appears to be an overall increase in average total annual rainfall and, this increase is poorly
distributed over seasons, resulting in increased floods during the rainy season as well as increased
drought incidence during the dry season. Droughts are significant especially for unpaved roads as
dust levels increase and reduce visibility and create poor local air quality. Flooding and soil moisture
content is a primary concern for protecting investments in roadwork and will be addressed as a
priority in the climate change adaptation strategy to be implemented under the Project. The strategy
will seek to strengthen the overall objective of the Project to improve rural road mobility. It will do so by:
Protecting the road infrastructure from the impacts of climate change and,
Ensuring that the road infrastructure does not increase the vulnerability of the
surrounding area to climate change.
48. To address hydrological impacts, the project shall provide for appropriate design of roadside
and cross drainage systems, where necessary, to avoid flooding on project roads as well as in areas
surrounding the road embankment. The road embankment, bridges and drainage facilities shall be
designed based on the historical flood data and flood forecasting. Erosion control and slope
stabilization measures shall be included in the design, as appropriate, such as side ditches, berms,
stone ripraps, and gabions along the road, tree planting in areas of high erosion risk, cross drainage
to accommodate floodwater/run-off in case road sections are on elevated fills that will obstruct natural
drainage.
2. When the water level upstream and downstream are equalising, or during subsequent
rainfall during an on-going flood the depth of water is such that is water ponding or
backing-up from downstream submerging the culvert outlet, sometimes classified as
‘Type E’ culvert flow. Hydraulically the following applies:
• Culvert flows full;
• Culvert slope does not determine discharge;
• Flow control is wall friction and backwater from downstream;
• Culverts are hydraulically ‘Long’;
• Culvert inlet is submerged; and
• Culvert outlet is submerged.
51. The flow capacity is about 20% greater under Type F flow than Type E flow. Other flow types
could occur but only those critical for design have been considered.
52. It was necessary to decide which flow case to use for design. It was decided that Type F was
appropriate because:
• It is the condition most likely to apply at the onset of a flood when flow capacity is
most critical.
• It is the most damaging flow case with potential for scour because flow at the
outlet is super-critical.
53. The discharge equations for Type F and Type E culvert flow are described below.
The discharge equation used for ‘Type F’ outlet control is:
(eq.11)
𝑄𝑄 = 𝐴𝐴𝐴𝐴{2𝑔𝑔(𝑑𝑑1 + 𝑧𝑧 − 𝑘𝑘𝑘𝑘3)|(𝑘𝑘𝑘𝑘 + 𝑘𝑘𝑘𝑘 + 1)} 0.5
54. To permit calculation of Type F flow a general assumption has been made that at design flow
Where Q: discharge in m3/s
A0: culvert cross-sectional area in m2
g: acceleration due to gravity = 9.81 m2/s
d1: depth upstream of culvert in m
d3:: depth downstream of culvert in m
Z: Difference in inlet and outlet invert level, can be assumed = 0 for this
assessment.
K: A factor determined from model tests to be 0.75 for circular culverts and
0.65 for box culverts.
ke: entry loss coefficient:
• 0.50 for pipe culvert in vertical headwall without entrance
rounding
• 0.30 for box culvert with vertical head wall and 30° to 60° wing
walls
𝑛𝑛2 . 𝑙𝑙
𝐾𝐾𝐾𝐾 = 19.6
𝑅𝑅4/3
n: Manning’s ‘n’
L: culvert length in m
R: Hydraulic radius = wetted area / wetted perimeter
the upstream water depth d1 is 1.5 x the diameter of pipe culverts and + 0.5 m the height of box
culverts, this typically being the minimum design height of the road embankment.
55. To permit calculation of Type E flow a general assumption has been made that at design flow
the head loss through the culvert, d1 – d3, is 100 mm.
57. If the cross-section is complex it can be divided into vertical slices and the total flow obtained
by adding the flow calculated for each slice. This allows different values of roughness to be used, for
example gabions for the banks, sand for the bed. However for the purposes of the project the cross
section of all bridges has be reduced to an equivalent rectangular section to simplify the embedded
formula in the spread sheets.
63. The smallest pipe size recommended is 0.8 m diameter, this being the minimum practical safe
size for maintenance by man entry, but in fact, if we do not have enough existing level for 0.8m
diameter, we prefer to use 0.60m in double cell instead.
64. The sizes selected for culverts provide stepped increases in capacity. If additional capacity is
required, or where the vertical alignment of the road is a constraint on culvert height, then a multi-cell
arrangement is recommended.
Table 6-8. Recommended standard culvert dimensions and indicative discharge capacity
Indicative Capacity
Description Clear internal dimensions
m3/sec
pipe culvert 600 mm diameter 0.55
72. Map of Catchment Area and Hydraulic Calculation Sheets are attached in Appendix B.
1. Chow V T, A general formula for hydrological frequency analysis, Trans Am Geophys Un, 32,
231-237, April (1951).
2. Fiddes D, Flood estimation for small East African rural catchments, Proceeding Institution of
Civil Engineers, Part 2, 63, 21-34 (1977)
3. Kirpich Z P, Time of concentration of small agricultural watersheds, Civil Eng (NY) 10, 6, 362
pp, (1940)
4. Road Design Standard, Part 3 - Drainage, CAM PW.03.103.99, July 1999, produced as a joint
Australia-Cambodia project sponsored by the Australian Agency for International
Development (AusAID).
5. Soil Conservation Service, National Engineering Handbook (NEH), Section 4: Hydrology, Part
I: Watershed Planning, US Department of Agriculture, Washington DC (1964)
7. Watkins L H and Fiddes D, Highway and Urban Hydrology in the Tropics, Pentech Press,
London, 92-100 (1984).