Maintenance Optimization of Centrifugal Pumps - A Case Study
Maintenance Optimization of Centrifugal Pumps - A Case Study
Abstract
Maintenance has gained credit over the past decades. The oil and gas industry requires
efficient maintenance programs due to the hazardousness surrounding the industry. Crude
oil margins are also dropping and maintenance yields high controllable costs. Therefore,
safety and economy are the driving forces of maintenance optimisation. Refineries have to
operate when margins are the most profitable so reliability is crucial.
Centrifugal pumps are essential features of the refining process. Due to limited resources,
maintenance work is prioritised according to the operating context and risks. Criticality
analysis is a widespread tool in the industry which supports the resource allocation decision.
The criticality level has, thus, to be highly accurate and adapted to the plant situation since it
influences the overall maintenance system efficiency. Maintenance plans must be properly
designed and implemented to enhance reliability.
Andreï LAQUET
Master Thesis
Acknowledgment
I would like to thank my supervisor Jerzy Mikler, for his help and advices given
during the thesis.
Donges, FRANCE
2015-07-07
Andreï LAQUET
Andreï LAQUET
Content Master Thesis
Content
1 Introduction ....................................................................................... 1
1.1 Presentation ............................................................................................................... 1
1.2 Scientific objective and aim ..................................................................................... 2
1.3 Structure and methodology .................................................................................... 2
Andreï LAQUET
Content Master Thesis
Andreï LAQUET
Content Master Thesis
Appendixes
Andreï LAQUET
Introduction Master Thesis
1 Introduction
1.1 Presentation
Over the past decades, the industry has been constantly evolving. The challenges
emerging from both market and society have matured and depict now an entire
different situation and framework. The concerns and focus of 1950’s which have
constructed the old industrial paradigm are now obsolete or at least irrelevant today.
The evolution of the society and the economical changes that the world has been
experiencing build the cornerstones of the maintenance philosophy change. Indeed,
new trade-offs and new challenges have revolutionised the industry and
maintenance work is now granted with higher merit.
For years, production has been the greatest endeavour of the industry. Nearly every
organisation focused on the adding value part of the processes. In other word
everything was set up in order to improve the product production processes. Thus,
maintenance has for long been seen as a necessary evil [1] that had to be fulfilled in
order to keep its great brother, the production, running. Through the past decade,
this feeling has been evolving. Maintenance has gained credits and is seen as a high
leverage business function which generates large controllable operating costs. Since
these costs are controllable maintenance leaves room for improvements and
industries are now trying to exploit it.
Andreï LAQUET 1
Introduction Master Thesis
strategy to the two maintenance practices is the best way to go deeper into the
optimisation of the maintenance work.
Several maintenance methodologies are formalised and exist to do so. The most
common ones are Reliability Centred Maintenance (RCM), Total Productive
Maintenance (TPM) and other Preventive Maintenance Optimisation (PMO). These
methodologies will be developed later on.
A clear methodology has been developed to conduct the study. This guideline is
described in the following section.
Andreï LAQUET 2
Maintenance evolution and scope Master Thesis
The first generation is the symbol of old industrial manners, it covers the period up
to World War II during which maintenance was not be carried out until the event of
failure [4]. The run-to-failure strategy was the only way to proceed. It might seem
archaic nowadays but it suited perfectly equipment lifecycle. At that time there was
no high technology or mechanised process and the equipments were simple and
usually over-designed. Downtime was not important and so was the failure
prevention. In other words, maintenance seemed to be set apart in this generation.
However, it is interesting to understand that before 1940’s industrials did not invest
in maintenance because there was no need to do so.
The second generation was driven by the industrial changes that World War II had
brought. The balance between supply and demand drastically changed during the
war. Workforce was scarce while demand was increasing. This led to a need for
mechanisation which entailed higher plant availability. Industries had to develop
quickly new solutions in order to be able to meet the demand. These new challenges
had a huge impact on how maintenance was seen by industrial managers. Indeed,
preventive maintenance concept made its first appearance in the sixties to tackle
plant downtime.
The strategy switched during the second generation from systematic run-to-failure
maintenance plans to preventive maintenance plans based on fixed intervals
overhauls. After some years, cost of maintenance began to be too high to keep
maintaining equipments with that strategy. Nevertheless, the trend was not to give
up and go back to a run-to-failure methodology but quite the opposite. Plants needed
and still need even higher availability due to lower margins and a fierce competition.
The third and current generation began in the mid-seventies. Moubray characterises
the changes to this third generation as changes driven by “new expectations, new
Andreï LAQUET 3
Maintenance evolution and scope Master Thesis
researches and new techniques”. These adjectives summarise the main spirit
conveyed by the current society. New expectations triggered by growing concerns in
the society. Indeed, safety and environmental standards are ones of the driven forces
which motivate, not to say force, managers to improve their maintenance efficiency.
The production cost which includes maintenance cost but also production
profits
𝑈𝑝𝑡𝑖𝑚𝑒
System availability defined by: 𝐴𝑣𝑎𝑙𝑖𝑎𝑏𝑙𝑖𝑡𝑦 = 𝑈𝑝𝑡𝑖𝑚𝑒+𝐷𝑜𝑤𝑛𝑡𝑖𝑚𝑒
So breakdowns and unplanned maintenance operations have an important
impact on the global availability which emphasises the role for an efficient
maintenance program.
Andreï LAQUET 4
Maintenance evolution and scope Master Thesis
Safety level and potential risks for workers, machines and environment.
Reduce unavailability
Ensure product and services quality
Master the costs linked to the maintenance program
Protect the key actors of the maintenance action: persons, environment and
the machines involved in the scope
Particular attention has to be put on the word system to properly understand this
chart. Maintenance system is included in the production system because it is a
Andreï LAQUET 5
Maintenance evolution and scope Master Thesis
prerequisite for the production to have a maintenance system around. However, this
does not mean that maintenance department in terms of hierarchy is encompassed in
the production department. The trend conveyed by the third generation of
maintenance is to put on an equal footing maintenance and production departments
in order to maximise the enterprise system efficiency.
Nevertheless, TPM and RCM are not antinomic concepts. Indeed, RCM conducts a
solid way to improve and master preventive maintenance which can enhance TPM
implementation. [11]
RCM methodology takes its origin in the aviation sector with Nowlan and Heap [12]
in the 1960’s. Their work takes place in the second maintenance generation when the
Boeing 747, amongst others, has been introduced. In the 1960’s, periodic overhauls
aimed to guarantee the required safety and availability level. Actually, their research
emphasises quite the opposite of what was targeted. In most cases, periodic
overhauls had no effect on reliability and safety of the equipments even if the
periodicity of the maintenance work was changed. RCM is defined by its creators as
“a scheduled-maintenance program designed to realise the inherent reliability
capabilities of equipment” [12]. John Moubray refined RCM into RCMII based on the
principles of the two American engineers. He defined its version of RCM as “a
process used to determine the maintenance requirements of any physical asset in its
operating context” [3]. His work focuses on the potential consequences more than on
the failure itself. In that way Moubray modernised the concept and opened it to new
horizons wider than the initial aviation scope. Through 7 basic questions the purpose
of RCM is to mitigate failure consequences in order to ensure reliability of the
equipments.
Andreï LAQUET 6
Maintenance evolution and scope Master Thesis
RCM is nowadays one of the most popular methodologies used to implement and
develop maintenance plans. One of the key features of RCM is that it focuses on the
functional requirements, on what the user wants it to do. It is a highly valuable
methodology which could contribute to develop a cost-effective maintenance
program. Nevertheless applying RCM is a complex and time-consuming labour and
industrials might be reluctant to opt for this technique. To tackle this problem,
several attempts have been carried on to build RCM framework in order to simplify
the use of RCM. They will be discussed later on in this paper.
Andreï LAQUET 7
Maintenance evolution and scope Master Thesis
In TPM, operators are involved and play an active role in maintenance detections
and small repairs. It focuses on the six following equipment losses [13]:
Breakdowns
Setup and alignment
Idling and minor stoppages
Reduced speed
Defects in process
Reduced yield
Operators are in charge of carrying some controls during the equipment operating
time to prevent one of the losses depicted above to happen.
It is a real challenge to motivate industries to use RCM, to name only Nowlan and
Heap’s work. To motivate the use of such complex tools, benefits have to be proven
beforehand. Improvements are proven but every sector has its own specific
challenges or at least the priorities are different. Some will emphasise the security
aspect of their equipment while others will put pressure on reducing costs and then
lower the maintenance costs. The framework in which the study takes place is thus
crucial and need to be narrowed down in order to identify the potential benefits of
improving maintenance.
Andreï LAQUET 8
Maintenance evolution and scope Master Thesis
The following case study takes place in a European refinery. The maintenance
management organisation differs from the one of our case study. However, the
outcomes can be spread to a wider range than only the plant studied because
European refineries are similar and have similar challenges to overcome.
2.3.2 Economy
The economic impact of maintenance management ineffectiveness in oil and gas
companies has been studied by Aoudia, Belmokhtar and Zwingelstein in 2008 [14]. In
order to prove and highlight the importance of maintenance they chose to
demonstrate the contrary of their theory in order to strengthen their words. By
developing the financial losses brought by maintenance management ineffectiveness,
they underlined the potential strength of maintenance improvements.
Moreover, the oil and gas industry is now suffering from the drop in crude oil price
which thwarted companies’ forecasts. It would be yet inaccurate to affirm that the
increasing need for higher maintenance efficiency comes from that drop. However,
economical savings are topical and optimised-cost maintenance plans are welcomed.
Their demonstration relies on two steps. First, ineffectiveness causes due to poor
maintenance management are identified and then evaluated in terms of financial
losses. As mentioned before, the implementation and the importance that
maintenance is granted in the organisation is one of the key of success. The study has
been conducted in a refinery built more than 50 years ago with a large number of
equipment and manufacturers. This description could nearly describe any European
refinery so the challenges are quite similar to a general case in which European
refineries after World War II are considered. They identified three main facts which
point up maintenance management ineffectiveness: Cancellation of preventive
maintenance programs, delays in the implementation of corrective maintenance
actions and number of accidents.
Andreï LAQUET 9
Maintenance evolution and scope Master Thesis
Andreï LAQUET 10
Maintenance evolution and scope Master Thesis
Nowadays the third point tends to be avoided during TAM period. The operating
loss generated by the shutdown time is so important that managers try to reduce it. It
comes together with the spirit of maintaining assets efficiently. It would be
nonsensical to reduce cost by optimising maintenance system and at the same time
extend shutdown periods.
TAM cost is, thus, reduced without being deleted. This shows once more that safety
is the most important challenge in that industry. Risks of major catastrophes are not
annihilated because it is impossible to have zero risk, but potential safety exposure is
reduced drastically thanks to TAM. However, as pointed out by Duffuaa and Ben
Andreï LAQUET 12
Maintenance evolution and scope Master Thesis
Daya [16], TAM is “a hazardous event” since the accident risk increases due to the
nature of the work. Therefore, on one hand it helps to enhance plant safety while on
the other hand it might cause accidents. It is management staff’s role to emphasise
safety importance during TAM. This will be developed further later on.
The time between the equipment interruption and the corrective maintenance
execution is highly important and impacts the production. The figures of Table 1
depict the preventive and corrective maintenance proportion in terms of hours of
work for the maintenance staff and unproductive time. It highlights the idea that
planning is the key for efficiency.
Preventive Corrective
Total
Maintenance Maintenance
Proportion of time
85% 15% 100%
spent by workers
Proportion of
7% 66% 73%
unproductive time
Number of accidents
A low accident rate is one of the biggest targets in refineries. Maintenance is one of
the greatest generators of accidents due to the variety of the job and the environment
it takes place. To avoid accidents to occur the most important aspect is to plan and
prepare carefully what has to be done and how it will be done. The preparation of
Andreï LAQUET 13
Maintenance evolution and scope Master Thesis
work is hardly perfect in corrective maintenance and people are often under pressure
due to urgent operating needs. This worsen working conditions and lead to
negligence because people involved can hardly step back and think of the best
method to proceed. In the case study, 51% of accidents of 2005 were due to human
errors. The only way to reduce this negligence is by better planning and less pressure
on the teams which is only possible with preventive maintenance or at least early
failure detection.
Inadequate tools 4
Outdated equipments 4
Defect in equipment 4
design
Others 4
The safety working routine is highly important in order to protect workers against
potential hazards. This type of safety plan brings a huge amount of administrative
tasks to fulfil and breaks maintenance productivity due to coordination problem,
Andreï LAQUET 14
Improvement methodologies Master Thesis
work stopped due to missing signature, etc. However, managers all agree that even if
the safety plans brings some unproductive points it cannot be infringed and
overstepped. These points accentuate the close relationship that maintenance has
with the cornerstones of a plant: safety, productivity and environment. An effective
maintenance program is needed and it can be designed and implemented through
well-known maintenance improvement methodologies.
3 Improvement methodologies
3.1 RCM and its limitations
The challenges that petrochemical industries face towards an efficient preventive
maintenance plan are now clearly identified. Different maintenance methodologies
have been described and the industry is now disposed to implement a way to
improve the maintenance efficiency. Nevertheless, methods like RCM are time
consuming and the benefits are not directly perceptible. Preventive maintenance
activities provide in essence long term benefits and it can be hard to convince the
actors to opt for a painful method during months without any positive outcome.
Conventional RCM approach has some limitations regarding its implementation in
refineries. These limitations have been pinpointed by Deepak and Jagathy in 2013
[17] to justify the need for a new model for RCM in petroleum refineries. The
limitations do not discredit the methodology. The implementation of the method
could be slightly modified in order to easier meet the industrial requirements.
The RCM approach is developed with a design approach which gives an accurate
picture of the situation but is hard to implement and need long analysis. In a
refinery, similar to the one in which our case study has been performed, the
important number of equipment entails too many time-consuming FMECA to be
performed. Deepak and Jagathy assessed 50000 failure modes to analyse taking into
account 2000 rotating machines. Our case study refinery has 1934 rotating machines,
of which 684 are pumps, so the approximation can be used in our case. Due to
limited manpower and time, refiners are not willing to apply the methodology as it
is. One way to deal with that issue is to rank equipment by criticality in order to
prioritise their study. This methodology is applicable to industries and is known as
Sub-Optimal RCM. However, this methodology has been criticised because it
concentrates on critical equipment which sometimes does not affect global reliability.
Andreï LAQUET 15
Improvement methodologies Master Thesis
The spirit of the methodology is to carry out Failure Mode and Effect Analysis on
critical equipment.
This step focuses on the potential consequences of the failure and on the best way to
keep the equipment away from it.
Andreï LAQUET 16
Improvement methodologies Master Thesis
provide high improvements. The main focus that Moubray express is related to the
protection devices such as spare equipment installed. Considering the retroactive
approach it is true that there might be a gap in the maintenance program if every
failure mode is not analysed. Many of current maintenance policies do not consider
spare equipment as maintainable equipment. If so, the new maintenance program
would continue to spread the gap in this area and be either inexistent or, at least,
poorly sized. If used, Streamlined RCM must consider protective devices carefully.
They often result in no planned maintenance tasks for these machines which
discredit the method and make it “completely indefensible” [18]
Every method has its benefits and its drawbacks. The most important is to master the
subject by a proper review of what exists and what could have been done. As
explained above Streamlined RCM suffers from the lack of maintenance for
equipment and failure modes which do not have direct operational consequences:
the hidden failures. It is explained by the fact that SRCM starts with current
maintenance program. It is actually a problem when reviewing the maintenance
tasks but nothing prevents the person in charge of the analysis from adding these
types of failure modes to the future maintenance program. Moreover, when the
equipment is standard and well-known it is easier to find the gaps of an existing
program. In fact, PMO methodology includes that failure mode gap to the current
practices. The challenge is to fully complete the list in order to develop an accurate
program. And this is not easy to do when the whole range of failures are not covered.
These two methodologies are appealing to companies because they use the concrete
controls and the current program in order to carry out the analysis. It is more about
reviewing and improving the current maintenance program than redesigning it
which contributes to be easily accepted by maintenance staff.
Andreï LAQUET 17
Case study scope Master Thesis
The fluids and the operating context have different specificities that need to be taken
into account when choosing the right pump to be implemented. Indeed, the fluid
circulating in the centrifugal pump induces a large range of flow phenomena which
have a “profound impact on design and operation through the achieved efficiency,
the stability of the head-capacity characteristic, vibration, noise, component failure
due to fatigue, as well as material damage caused by cavitation, hydro-abrasive wear
or erosion corrosion.” [19]
These parameters have to be taken into account when the maintenance task selection
is determined. According to Gülich, life cycle costs and operation efficiency of the
machine highly rely on these parameters, their interaction and also on the
understanding of the relation between the pump and its operating context. Within
the same area of expertise, Azadeh, Ebrahimpour and Bavar [20] developed an entire
system to improve pump failure diagnosis through analysis of the parameter
interaction. They created a range of linguistic rules which “approximate human
reasoning” through If-Then rules. Inputs are the variation of the operating
parameters. Their work emphasises the importance of parameters interrelation.
Putting together all variations lead directly to a diagnosis. This is useful to get
directly to the most likely failure causes and might lead to lower delay of action by
providing conclusion faster.
Even if there are many centrifugal pumps in a refinery, they are nearly all different
due to different operating range and conditions. It can be hard to know where to
Andreï LAQUET 18
Case study scope Master Thesis
start with maintenance optimisation in big plants. Indeed, the review process has to
be carried for every single machine in order to be accurate and enhance its reliability.
One way to prioritise the work is commonly done through a criticality analysis.
Before developing the technical methods to evaluate equipment criticality level it is
important to clarify how this parameter influences the maintenance decision process.
Resources cover both tangible resources such as financial resources and intangible
resources like human resources. Applying RCM concept does not necessarily means
invest a lot of money but it needs significant start-up expenses in terms of human
resources.
Due to the number of pumps in the plant and for economical purpose the criticality
of each rotating machine has to be evaluated. Several approaches have been
developed in order to assess criticality to equipment.
The authors use the model developed for nuclear power plant in order to perform
safety assessment. However, the industries are quite different and the challenges and
available information are slightly distinct. Historical information is often not as
Andreï LAQUET 19
Case study scope Master Thesis
accurate in the oil and gas industry as in the nuclear sector. As in Bevilacqua et al.
study [1] fault tree logic is developed to link the production losses to component
failures. This methodology suits the purpose of linking a component failure to an
event. However the level of detail of the tree lies on the criticality of the machine. So
the criticality is implicitly taken into account but not evaluated as a proper ranking
system.
Qi et al. [22] And Gomez et al. [23] developed two criticality assessment approaches
which answer to the industrial need of ranking machines according to their financial,
safety and environment impact. The multi-criterion of Gomez et al. [23] encompasses
12 criteria ranked from 0 to 4 grouped in the three main categories:
After evaluating all these parameters, the criticality is given by weighting criteria
that takes into account the operational importance of the machines. This assignment
of weight evaluation is hardly easy to do because people from production or
maintenance department have different vision of which challenges are the most
important. Weighting factors will, then, seldom coincide since they have different
point of view. The method faces again the same problem between balancing several
points of view in a criticality analysis. Moreover, the high number of criteria slows
down the process which makes it difficult to implement. However, the criterions
cover all the relevant information needed for a criticality level, from the impact that a
failure might have to the maintenance requirements and likelihood of failure.
Andreï LAQUET 20
Case study scope Master Thesis
Qi et al. [22] opted for a method with fewer criterions. Only three criteria, ranked
from 0 to 4, are used with fixed weighting criteria
The impacts can be inaccurate for equipment with redundancy. Indeed, the loss of a
machine will be considered as not critical if it is doubled because the direct impact is
null. So every machine that has a standby pump would be considered as non critical
with this strategy. If the loss is considered for the function which is covered by the
pump and its stand by then they will be highly critical. The analysis requires a
method to take redundancies as an operating parameter and must be expressed and
not only hidden in the impact reflexion. For that purpose Gomez et al.’s
methodology was better, because it is explicitly one of the criteria, but their strategy
is highly time-consuming which may repel industrials.
Scientists agree that maintenance strategies, for example RCM, are highly valuable
and induce strong improvements if applied correctly. Partial of prioritised strategies
are said to look for economical savings more than global reliability improvements.
However, the current industrial situation forces oil and gas companies to optimise
their strategy in order to allocate resources as clever and accurate as possible.
Criticality assessment is, thus, criticised for granting an asset more resources than
another. This choice will impact the reliability of other machines. Nevertheless,
industrial managers do not look for the concept of reliability itself. The main goal is
to maximise economical profitability in order to ensure the highest possible safety
level. These two targets are, of course, provided by a strong maintenance plan and
high reliability levels but not necessarily for every asset.
Andreï LAQUET 21
Maintenance of centrifugal pumps: a case study Master Thesis
Andreï LAQUET 22
Maintenance of centrifugal pumps: a case study Master Thesis
The mechanical seal is an external device which prevents leakage between the pump
and the environment. It is an essential part of the pump especially with hazardous
product which, in case of leakage, can engender safety and environmental problems.
Andreï LAQUET 23
Maintenance of centrifugal pumps: a case study Master Thesis
Corrective
Maintenance
RCFA
Criticality
Preventive Predictive
Maintenance Maintenance
Plan Plan
Control list and frequency
Andreï LAQUET 24
Criticality analysis Master Thesis
6 Criticality analysis
6.1 The current situation
Evaluate the criticality of the machines is not a new concept in Total organisation.
Actually each pump has its criticality assessed in the business management software,
SAP in that case. As mentioned in the first part of this paper criticality assessment is
an important part for maintenance managers. Indeed, it is often related to the
machine criticality that resources will, or will not, be allocated in order to improve its
reliability. In theory, reliability should not be linked to criticality but in practice
prioritisation is needed and it allocates resources according to criticality levels.
Criticality is central and linked to every maintenance task. The place of criticality
level in the organisation is highlighted in Figure 7 and Appendix 2.
In most cases the machine ends up in the medium/high criticality category and the
prioritisation is impossible among each category, so in that case for more than half of
the machines. Such system must spread out the most critical machines into several
categories to be efficient.
Andreï LAQUET 25
Criticality analysis Master Thesis
SAP distribution
71 pumps 46 pumps
10% 7%
High
220 pumps
32% Medium/High
347 pumps
51%
Medium
Low
The need for a new criticality assessment is motivated by the ineffectiveness of the
system caused by the distribution as explained above. The second reason why a new
criticality assessment needs to be carried out is the obsolescence of the current
classification. Processes have changed through the years and some machines even
stopped to operate. The update is needed to keep the coherence between reality and
decision making strategies. To reach a useful distribution the methodology has to be
clear and parameters have to be quantified.
Andreï LAQUET 26
Criticality analysis Master Thesis
A criticality level relies on the potential risk that equipment might engender. As
shown in the literature review the three parameters which matter the most in
industrial environment are: economical, safety and environmental. Considering that
quality is covered by the economical risks because quality problems imply sales
decreases or production loss. The fuzzy criticality assessment system gives a method
on how to evaluate the impact according to these criterions.
On one hand, the impact generated by losing the function fulfilled by the group of
machines is crucial to assess the criticality. On the other hand, in a refinery, the worst
case scenario often leads to high risks which would lead to assess a high criticality to
an important number of machines. A second parameter has to be set regarding the
likelihood of the functional loss. This second parameter has to take into account the
operating context which surrounds the equipment. One or a combination of
production system outputs has to be gathered in order to evaluate this parameter.
The criticality levels are defined by Total through the matrix below, Figure 9. The
boundaries have been changed for confidentiality purpose. The use of criticality
matrix is common in chemical industry. A complete inventory of petrochemicals
companies’ policies towards criticality assessment has been carried by the ministry of
sustainable development in 2004. [24] The economical levels are not given due to
confidentiality issues but it does not impact the comprehension of the method used.
Andreï LAQUET 27
Criticality analysis Master Thesis
Andreï LAQUET 28
Criticality analysis Master Thesis
Andreï LAQUET 29
Criticality analysis Master Thesis
6.5 Results
The combination of both criterions linked to the criticality matrix gives directly the
new criticality of the equipments. The new criticality method spreads out the most
critical equipment into several sectors. It is better for the use that the company target.
However, there are an important number of NA (Non Acceptable) criticality levels.
Andreï LAQUET 30
Criticality analysis Master Thesis
Results
39; 6%
73; 10%
321; 44%
166; 23%
125; 17%
6.6 Limits
The method of probability assessment has a great output and summarises the
situation clearly. However, MTTR of machines are set according to the power of the
machine. It is not a precise measurement but, as pointed out in the literature study, in
petroleum refineries, databases are not as precise as in nuclear power plants and it
was not possible to evaluate the real MTTR. Due to that problem MTTR are broadly
over evaluated and so is the criticality.
The risk assessment method induces also some limitations. They are the same than
the ones pointed out by Qi et al. [22]. Potential imprecision can be induced by
gathering personal viewpoint on a machine. Moreover, the method is not flexible and
the risk levels are integers which can be a problem if the risk is close to a boundary.
For example, if a breakdown is estimated to generate 0.95 M€ loss then it would be
consider as intermediate level, the same level as if it was 0.15M€ even if it is 7 times
greater. A ranking system with progressive scale and not only integers could be more
accurate to understand what is hidden behind the risk. Moreover, it would be useful
to be able to rank the machines within a same criticality level. By developing a more
flexible model this could also be done.
Andreï LAQUET 31
Corrective maintenance system Master Thesis
All these limits give credit to the persons who disregard the criticality assessment in
terms of reliability improvements. Nevertheless, due to the important number of
equipment it would be hardly possible to equally allocate resources to every
machine. For preventive maintenance purpose the criticality assessment should not
be the principal parameter to be used. However criticality is a powerful tool to
support task prioritisation and, thus, to manage emergencies.
Task prioritisation is executed every day to analyse the risk and the urgency of the
situation. This component is a pure managerial issue and not technical. It transposes
the resource limitation dilemma to the daily work. The prioritisation methodology
will not be developed in this paper because it has been reviewed within the
company.
Andreï LAQUET 32
Corrective maintenance system Master Thesis
The global stock level of the plant is too high to be kept. Indeed, high profits and old
habits led over the years to store an important number of components. The total
amount exclusively linked to pump components stored is 2.5M€. Even if the stock is
high some key components have been identified as missing so this indicates that,
apart from the stock level, there might be a mismatch between what is stored and
what should be stored.
In France, companies pay taxes according to the spare parts stock. So the higher the
stock level the more expensive the annual taxes. The implementation of stock
changes has to take that into account. Indeed, if every missing item is purchased at
once then the stock level would increase which would generate an important tax
increase.
The strategy is based upon experience of technicians and machine criticality. The
table summarising the strategy is given in Appendix 3. During revision (partial or
general), some components are replaced. Wear parts, are systematically changed and
the other ones are inspected and then replaced if necessary. When a piece is replaced
by a spare it is not always scraped. The repairable parts are repaired, if possible and
economically viable, and then stored again in the warehouse.
Wear parts category contains: wearing rings, coupling repair kit and gaskets. For
other machines, the “big” components, such as impeller and complete rotor, are
stored only for the most critical machines. Together with the criticality-based
strategy, an economy of scale strategy is also recommended. For example if there are
ten identical pumps in the refineries the stock levels will not just be summed. The ten
identical machines will be considered as if there were only 3 of them considering the
most critical ones as references. This logic aims to reduce cost without interfering in
the repair delay.
even if the strategy is interesting in a cost perspective it only has an effect on pumps
with redundancies.
Figure 13 shows the stock evolution due to the new criticality levels and the new
strategy. The difference between what is stored and what need to be stored in order
to respect the specifications has to be explained. It is important to highlight, once
again, that the delta is given only to provide a numerical idea of the difference
between the stock levels.
1400
1200
1000
800
600
Current level
200
These results lead to a decrease of the spare parts by 31.1% which represents around
0.9M€. It is a great economical savings but it has to be carefully implemented because
Andreï LAQUET 34
Corrective maintenance system Master Thesis
this strategy might worsen the situation if not implemented carefully. Indeed, one
day of stoppage for the distillation unit generates to 1M€ of loss. Therefore, it is
obvious that savings and improvements can disappear in a flash.
The stock optimisation needs new maintenance philosophy too. The stock level of
rotor, which includes impeller and shaft, highlights that need. In the current system,
shaft and impeller are nearly always available in warehouse. 65% of parts included in
the rotor category have spare stored in the warehouse. However, the new strategy
states that only levels 1 and 2, 39% of the pumps, must have spare rotor.
Maintenance technicians are used to have spare parts for these components.
Therefore, the working methods need to change. When a wearing is suspected an
order has to be considered because the delivery time is often important.
Components age has not been taken into account when designing this strategy.
Particular attention has to be put on components’ obsolescence. Indeed, some
components are not being produced anymore. Therefore, a parallel review and
criticality analysis of the components has to be carried out in order to identify which
are critical due to the market and not only the operating conditions.
Andreï LAQUET 35
Preventive maintenance: review and progress Master Thesis
The method is articulated over four major phases. First, a general overview of the
common failure modes identified in the art is gathered. Then, the current preventive
tasks are formalised through a PMO like approach and completing with the missing
failure modes. Finally, the current strategy will be criticised and improvement hints
will be proposed.
Andreï LAQUET 36
Preventive maintenance: review and progress Master Thesis
is the variety that a single failure mode can induce. Problems have from 4 possible
causes up to 20 for vibrations the mean being 10 potential causes for a single
problem. It underlines what has been depicted in the literature study, the parameters
interaction is highly important in order to detect the functional failure. The
mechanical seal has also the same type of root cause failure analysis table.
In Mobley’s diagram only common and principal failure modes are listed. Hidden
failures are not mentioned here and the methodology used needs a special treatment
for them.
Operators control it through the manometer they control that it is not null and that it
does not fluctuate “too much”. There is a lack of quantification in two ways. First,
admissible pressure fluctuation needs to be quantified in order to set an alarm level.
Second, operating range is often not known neither by the operator nor the
maintenance method staff. Machines are old and the operating conditions have
evolved and they are might have undergone a change of their working range. An
evaluation of the operating range needs to be implemented in order to control
machines use. Once the range is known a visual marker can be put on every
manometer so that the control is simple and fast.
Vibration
The vibration can be induced by nearly every failure mode. In Mobley’s table 20 out
of 31 common failure modes provoke vibration. Operator control aims only to report
that a defect is already in the machine. The precision is low and it is more of a default
observation than a preventive control. However this control is easy to perform and
can be useful as it is carried out three times a day.
Andreï LAQUET 37
Preventive maintenance: review and progress Master Thesis
long time before it wears every mechanical part in the machine. Controls according
to criticality are useful in that case. Nevertheless, it would be useful to have at least
one vibration route for every machine so that if a problem is detected the vibration
route taken can be compared to one taken in good conditions.
All these controls are done by the operator thanks to his senses. They are not precise
and in some cases a finer measure can be performed if needed.
Leakage for mechanical seal is a functional feature so there must be one. When a
quench is installed (steam sweeping of the dirt) the flow rate must be 0.2 bar which
corresponds to a drop by drop leakage. Installing a manometer to clearly quantify
and adjust that rate would be easier than train all operators to sense when the
quench needs to be adjusted. This kind of improvement comes from the review of the
preventive controls by balancing experts’ point of view and operators’ manners of
controlling. It is important to give the suitable tools to operators to improve
parameters control.
Missing controls
As expected by John Moubray theoretical assertions some hidden failures are forgot
in operators’ check list. Mobley’s tables do not list them neither because they are not
identified as key failure modes because they are safety devices which prevent a
common failure mode to happen.
There are two kinds of hidden failures which are identified as missing here, the
functional holes cleaning and the quench setting. The quench setting has already
been discussed in the previous paragraph. Concerning functional holes, in a pump
and mechanical seal design there are three main holes that needs to be clean to
operate properly.
o Pump drain hole to eliminate gas and water before starting the pump
o Air vent on bearing to equilibrate pressure in the bearings to avoid high
pressure to destroy the balls and the
o Mechanical seal drain oil collector which if clogged might stock water in
the cavity and then bring water in the mechanical seal which can induce
grafoil gaskets destruction.
Andreï LAQUET 38
Preventive maintenance: review and progress Master Thesis
The problem comes from the fact that most of the operators are not aware of these
small details that highly lower MTBF. Training and explanation is needed in order to
implement correctly the cleaning of these holes.
Other missing actions are listed in green in Appendix 5. They have lower impact on
pump breakdowns so they are not discussed in the core of the paper even if they are
proposed as improvement controls.
In order to comprehend and fully optimise the pump functioning all operating
parameter are useful to follow. However the methodology used suffer from one
major gap, it does not take into account the evolution of a machine through the time.
If a parameter has been detected as out of range, for example a drop of discharge
pressure, and then came back to normal then it will be simply ignored and
considered as solved. This is one of the major inconvenient that determines why
FMCA is difficult to carry out and needs a long period of time and several failures in
order to identify the cause. The interaction of parameters, as pointed out in several
pump scientific studies [19] [20], is highly valuable for pump failure diagnosis.
However the problems often come from operational and short phenomenon which
cannot be seen by measuring only once per shift. Therefore continuous monitoring
finds its full interest in these cases but it is impossible to implement continuous
monitoring for more than a thousand machines so another proposal is explained.
Andreï LAQUET 39
Preventive maintenance: review and progress Master Thesis
Andreï LAQUET 40
Preventive maintenance: review and progress Master Thesis
range period. The control can be added to the operator list and then it works with the
same logic than all other control.
Information provided by the sensor can be added to the current manners of detecting
failure cause in particular cases. However, the real target is to detect the failure
before it occurs. It is possible if the organisation is formalised, mastered and driven
by managers’ commitment because the analysis of a red light event has to be done
quickly after the arrival to avoid losing information on the process conditions.
Andreï LAQUET 41
Conclusion and further studies Master Thesis
Further study could be to carry proper FMECA on critical machines especially on the
one categorised as Non Acceptable. Criticality assessment is static so it must be
updated to be effective. Either the criticality must be reviewed periodically or a
dynamic model has to be developed to solve the problem.
Research findings raised great improvement ideas and this paper highlights the
potential improvement hints possible to put in practice for maintenance plans even
in mature plants. However, it is the economical context and safety policy which drive
companies’ strategy. Equipment reliability itself is not the target. Therefore, money
and time will be allocated for reliability improvement only if the gain is nearly
guaranteed which is difficult to demonstrate in most preventive actions.
Andreï LAQUET 42
References Master Thesis
10 References
[1] Bevilacqua Maurizio, Braglia Marcello, Montanari Roberto. “The classification
and regression tree approach to pump failure rate analysis”; Reliability Engineering
System and Safety, 79, pp. 59-67; 2003
[2] Turner Steve. “PM Optimisation – Maintenance analysis of the future”; ICOMS
Annual conference Melbourne; 2001
[5] Oke Sunday Ayoola. “An analytical model for the optimisation of maintenance
profitability”; International Journal of Productivity and Performance Management,
Vol.54 No. 2, pp 113-36; 2005
[10] Jardine Andrew K.S., Tsang Albert H.C. “Maintenance, Replacement, and
Reliability: Theory and Applications, Second Edition”; CRC Press; 2005
[11] Ben-Daya Mohamed. “You may need RCM to enhance TPM implementation”;
Journal of Quality in Maintenance Engineering, Vol.6 No.2 pp. 82-85, 2000.
Andreï LAQUET 43
References Master Thesis
[15] Arts R.H.P.M., Knapp Gerald M., Mann Jr Lawrence, "Some aspects of measuring
maintenance performance in the process industry", Journal of Quality in
Maintenance Engineering, Vol. 4, pp. 6 – 11; 1998
[17] Deepak Prabhakar P., Jagathy Raj V. P. “A New Model For Reliability Centered
Maintenance In Petroleum Refineries”; International Journal of Scientific &
Technology Research V. 2; 2013
[20] Azadeh A., Ebrahimipour V., Bavar P. “A fuzzy inference system for pump
failure diagnosis to improve maintenance process: The case of a petrochemical
industry”; Elsevier; 2009
[21] Torabi KK, Karimi B., Parmar R., Oliverio M., Dinnie K.“Quantitative risk
assessment for process design modification and maintenance optimization in
refineries and petrochemical plants”; The Canadian journal of chemical engineering,
V. 84; 2006
[22] Qi H.S., Alzaabi R.N., Wood A.S. and Jani M. M. "A fuzzy criticality assessment
system of process equipment for optimised maintenance management"; International
Journal of Computer Integrated Manufacturing, pp. 112-125; 2015
Andreï LAQUET 44
References Master Thesis
[23] Gomez de Leon Hijes Felix C., Cartagena Jose Javier Ruiz. “Maintenance strategy
based on a multicriterion classification of equipments”; Reliability Engineering
System and Safety, 91, pp. 444-451; 2006
[24] Merad M.M. « Analyse de l’état de l’Art sur les grilles de criticité » ; Ministère de
l’Ecologie et du Développement Durable ; 2004
Andreï LAQUET 45
Appendix 1: Refineries general process description Master Thesis
11 Appendixes
11.1 Appendix 1: Refineries general process description
The chart below is a simplified chart of refining processes. It is not particularly describing the
case study plant.
Source: ExxonMobil
Andreï LAQUET 46
Appendix 1: Refineries general process description Master Thesis
Distillation: First stage of the reining process. The crude oil is boiled and condensed
again to fractionate the different hydrocarbon components by using the difference
between boiling points. Heavier components will be collected in the lower part of the
column and lighter ones, such as Liquefied Petroleum Gas (LPG), in the lower part.
Fluid Catalytic Cracking Unit: uses heat and catalyst to break or “crack” large gas
oil molecules into a range of smaller ones.
Reformer Unit: The molecular structures of crude and coker naphthas are
transformed using heat, catalyst and moderate pressure. It aims to produce a high
octane primary gasoline blend stock called reformate.
Alkylation Unit: acid catalyst is combined with small molecules to produce larger
ones collectively called alkylate. Alkylate has a high octane and is the cleanest
burning of the gasoline blendstocks.
Economical impact
Catalytic Reforming
>30 days >3 days
stoppage
Andreï LAQUET 47
Appendix 2: Maintenance actors and criticality scope diagram Master Thesis
Andreï LAQUET 48
Appendix 3: Spare parts strategy and results Master Thesis
Balancing drum and liner / balancing disk and counter disk (if applicable) 1 1 0 0 0
Shaft sleeve 2 2 1 1 0
Gaskets: pump casing, flat, O-ring, Bearing Housing, stuffing box, etc. 2 2 1 1 1
Andreï LAQUET 50
Appendix 4: Mobley’s root cause failure analysis Master Thesis
Andreï LAQUET 51
Appendix 4: Mobley’s root cause failure analysis Master Thesis
Andreï LAQUET 52
Appendix 5: List of control for pump, mechanical seal and motor Master Thesis
11.5 Appendix 5: List of control for pump, mechanical seal and motor
Andreï LAQUET 53
Appendix 5: List of control for pump, mechanical seal and motor Master Thesis
If low suction
15 Strainer control Suction volume problem
pressure
16 Gas pressure in accumulator Weekly round Greaser Pressure in envelope seal too low
17 Programmed revision 5 or 10 years / Turnaround maintenance
Missing controls
18 Quench flow control Every shift Operator Seal clogged
To be determined
Unblock or control cooling
19 upon machine Increase of temperature
pipes
context
Cleaning of functional holes Mechanical seal drain: water in the seal (destruction);
Operator/
20 (pump and seal drain, air Every shift/Weekly Pump drain: liquid in the pump (increased wearing or impeller destruction)
Greaser
vent) Air vent, pressure too high in the bearing (ball wear increase)
Fin cleaning for gas
21 Every year Eiffel Defect in the cooling system of pressurised seals
pressurised seals
Andreï LAQUET 54