ESTIMATE
ESTIMATE
This Detailed estimate for the construction of proposed Police Chowki at Rajepur( Unnao ), U.P has been
prepared as per letter no.
Dated
REQUIREMENTS:
This proposed building will investigate criminal’s activities, decrease the crime rate, which helps us to feel safe.
PROVISION:
Provision of Building =Building Civil work, Drain along Boundary wall, Road, Electrification, Plumbing & Rain water
harvesting, are also part of estimate.
The above works are proposed to be carried out at campus Rajepur, U.P (U.P.)
TYPE OF STRUCTURE:
The proposed building will be framed structure. This will be designed according to I.S. code 456 – 2000.
RATES:
The Detailed estimate has been prepared on the basis of S.O.R. 2022 & 2023, D.S.R 2021 and current market rate.
Conclusion:
With the above remark the detailed estimate for construction of proposed Cyber Thana building at Rajepur,
U.P(U.P.), amounting to RS 10.49 Cr is here by submitted for approval and allotment of funds.
DETAIL ESTIMATE FOR PROPOSED ADMINISTRATIVE BLOCK FOR ZONAL
POLICE CHOWKI AT RAJEPUR, U.P.
FORM - J
FORM WORK
Centering and shuttering including strutting, propping etc. and removal
7 DSR-5.9 of form for
Foundations, footings, bases of columns, etc. for mass
5.9.1 concrete
102.37 SQM 267.34 27,368.51
5.9.3 Suspended floors, roofs, landings, balconies and access platform 715.83 SQM 665.46 4,76,358.95
Lintels, beams, plinth beams, girders, bressumers and
5.9.5 1,115.69 SQM 528.13 5,89,224.79
cantilevers
5.9.6 Columns, Pillars, Piers, Abutments, Posts and Struts 683.90 SQM 698.19 4,77,493.28
BRICK WORK
PWD - Class-150 (Non Modular) brick work in 1:6 cement and Coarse sand
10 303+307- mortar in foundation and plinth including supply of all materials, labour 28.00 Cum 4,805.00 1,34,542.40
306 and T&P etc. required for proper completion of the work.
Class -150 (non modular ) brick work in 1:6 cement and coarse sand
mortar above for super structure above plinth level up to floor five level
PWD-307-
11 including necessary cutting and moulding of brick work as required and 132.54 Cum 5,425.00 7,19,037.46
306+310
also including honey combed brick work in thickness of wall more than
12 cm .
Half brick masonry with common burnt clay F.P.S. (non modular) bricks
PWD-307- of class designation 7.5 in superstructure above plinth level up to floor V
12 306+310+3 level. Half brick masonry with common burnt clay F.P.S. (non modular) 267.46 Sqm 5,580.00 14,92,426.80
10A bricks of class designation 7.5 in superstructure above plinth level up to
floor V level.
Extra for providing and placing in position 2 Nos 6mm dia. M.S. bars
12.1 DSR-6.15 at every third course of half brick masonry. 267.46 Sqm 75.05 20,072.76
Casement door with top hung ventilator with 3D and S.S. friction hinges
(400 x 19 x 1.9 mm) made of (big series) frame 67 x 64 mm, sash 67 x
110 mm & mullion 67 x 80 mm all having wall thickness of 2.3 ±. 0.2 mm
DSR-9.147
and single glazing bead / double glazing bead of appropriate 69.00 Sqm 9,073.62 6,26,079.89
c.2
dimension.(Area of door upto 2.50 sqm)
Providing and fixing factory made uPVC white colour sliding glazed
window upto
1.50 m in height dimension comprising of uPVC multi-chambered frame
with in_x005f built roller track and sash extruded profiles duly
reinforced with 1.60 ± 0.2 mm
thick galvanized mild steel section made from roll forming process of
required
length (shape & size according to uPVC profile), appropriate dimension
of uPVC
extruded glazing beads and uPVC extruded interlocks, EPDM gasket,
wool pile,
zinc alloy (white powder coated) touch locks with hook, zinc alloy body
with single
DSR 9.147 nylon rollers (weight bearing capacity to be 40 kg), G.I fasteners 100 x 8
mm size
14 D
for fixing frame to finished wall and necessary stainless steel screws etc.
Profile of
frame & sash shall be mitred cut and fusion welded at all corners,
including drilling
of holes for fixing hardware's and drainage of water etc. After fixing
frame the gap
between frame and adjacent finished wall shall be filled with weather
proof silicon
sealent over backer rod of required size and of approved quality, all
complete as per
approved drawing & direction of Engineer-in-Charge. (Single / double
glass panes,
wire mesh and silicon sealent shall be paid separately). Variation in
profile
dimension in higher side shall be accepted but no extra payment on this
Two track two panels sliding window made of (big series) frame 67 x 50
DSR 9.147 mm & sash 46 x 62 mm both having wall thickness of 2.3 ± 0.2 mm and
(D).3 single glazing bead / double glazing bead of appropriate dimension . 69.20 SQM 6,789.75 4,69,839.00
(Area of window above 1.75 sqm upto 2.50 sqm).
Provinding and fixing glass panes with putty and glazing clips in steel
DSR- doors,
15 69.20 SQM 1,079.52 74,700.63
10.30.2 windows,clerestory windows all complete with : 6.0 mm thick panes.
Providing and fixing stainless steel fancy handle of approved make fixed
DSR-
17 with SS screws etc. complete as per direction of Engineer-in-charge. 4.00 Each 132.95 531.81
9.170.1 200MM
Providing and fixing aluminium die cast body tubular type universal
hydraulic door closer (having brand logo with ISI, IS : 3564, embossed
18 DSR- 9.84 20.00 Each 890.39 17,807.89
on the body, door weight upto 35 kg and door width upto 700 mm), with
necessary accessories and screws etc. complete.
Providing and fixing bright finished brass 100 mm mortice latch and
lock, ISI
19 DSR- 9.103 marked, with six levers and a pair of anodised (anodic coating not less 20 Each 642.24 12,844.81
than grade AC 10 as per IS : 1868) aluminium lever handles of approved
quality with necessary screws etc. complete
FLOORING WORK
Providing and fixing 18 mm thick Granite (gang saw cut), mirror
polished, premoulded and prepolished, machine cut for kitchen
platforms, vanity counters, window sills, facias and similar locations, of
required size, approved shade, colour and texture laid over 20 mm thick
23 DSR-8.2
base cement mortar 1:4 (1 cement : 4 coarse sand), joints treated with
white cement, mixed with matching pigment, epoxy touch ups, including
rubbing, curing, moulding and polishing to edges to give high glossy
finish etc. complete at all levels.
Granite stone slab colour black, Cherry/Ruby red
8.2.2.1 (a) Slab area upto 0.50 Sqm 33.75 Sqm 4062.27 1,37,101.64
8.2.2.2 (b) Slab area Above 0.50 Sqm 11.69 Sqm 3841.77 44,925.62
Providing and laying rectified Glazed Ceramic floor tiles of size 300x300
mm or more (thickness to be specified by the manufacturer), of 1st
quality conforming to IS : 15622, of approved make, in all colours,
26 DSR-11.40 shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick 39.84 Sqm 1063.54 42,367.82
Cement Mortar 1:4 (1 Cement : 4 Coarse sand), jointing with grey cement
slurry @ 3.3 kg/ sqm including pointing the joints with white cement
and matching pigments etc., complete.
-
Providing and fixing Ist quality ceramic glazed wall tiles conforming to
IS: 15622 (thickness to be specified by the manufacturer), of approved
make, in all colours, shades except burgundy, bottle green, black of any
size as approved by Engineer-in-Charge, in skirting, risers of steps and
27 DSR-8.31 184.37 Sqm 923.21 1,70,210.35
dados, over 12 mm thick bed of cement mortar 1:3 (1 cement : 3 coarse
sand) and jointing with grey cement slurry @ 3.3kg per sqm, including
pointing in white cement mixed with pigment of matching shade
complete.
-
Providing and laying vitrified floor tiles in different sizes (thickness to be
specified by the manufacturer) with water absorption less than 0.08%
and conforming to IS: 15622, of approved make, in all colours and
DSR-
28 shades, laid on 20mm thick cement mortar 1:4 (1 cement : 4 coarse -
11.41.2 sand), jointing with grey cement slurry @ 3.3 kg/ sqm including grouting
the joints with white cement and matching pigments etc., complete.
Size of Tile 600x600 mm 182.64 Sqm 1229.83 2,24,616.58
-
Providing and laying Vitrified tiles in different sizes (thickness to be
specified by manufacturer), with water absorption less than 0.08 % and
conforming to I.S. 15622, of approved make, in all colours & shade, in
DSR-
29 skirting, riser of steps, over 12 mm thick bed of cement mortar 1:3 (1 18.45 Sqm 1273.11 23,488.85
11.46.2 cement: 3 coarse sand), jointing with grey cement slurry @ 3.3 kg/sqm
including grouting the joint with white cement & matching pigments etc.
complete. Size of Tile 600x600 mm
-
Kota stone slab flooring over 20 mm (average) thick base laid over and
DSR- jointed with grey cement slurry mixed with pigment to match the shade
30 65.02 Sqm 1481.55 96,322.70
11.26.1 of the slab, including rubbing and polishing complete with base of
cement mortar 1 : 4 (1 cement : 4 coarse sand) : 25 mm thick
-
Kota stone slabs 20 mm thick in risers of steps, skirting, dado and pillars
laid on 12 mm (average) thick cement mortar 1:3 (1 cement: 3 coarse
31 DSR-11.27 6.64 Sqm 1769.72 11,746.52
sand) and jointed with grey cement slurry mixed with pigment to match
the shade of the slabs, including rubbing and polishing complete.
Stone work, plain in copings, cornices, string courses and plinth courses,
upto 75 mm thick in Cement mortar 1:6 (1 cement : 6 coarse sand),
including pointing with white cement mortar 1:2 (1 white cement : 2
32 DSR- 7.32.1 2.33 Cum 62583.59 1,46,065.40
stone dust) with an admixture of pigment matching the stone shade. Red
sand stone
ROOFING WORK
Providing and laying integral cement based water proofing treatment
including preparation of surface as required for treatment of roofs,
balconies, terraces etc consisting of following operations: (a) Applying a
slurry coat of neat cement using 2.75 kg/sqm of
cement admixed with water proofing compound conforming
to IS. 2645 and approved by Engineer-in-charge over the RCC
slab including adjoining walls upto 300 mm height including
cleaning the surface before treatment.
(b) Laying brick bats with mortar using broken bricks/brick bats
25 mm to 115 mm size with 50% of cement mortar 1:5 (1
cement : 5 coarse sand) admixed with water proofing
compound conforming to IS : 2645 and approved by Engineer in-charge
over 20 mm thick layer of cement mortar of mix 1:5
(1 cement :5 coarse sand ) admixed with water proofing
DSR- compound conforming to IS : 2645 and approved by Engineer in-charge
33 330.00 Sqm 1322.11 4,36,297.70
12.21.1 to required slope and treating similarly the adjoining
walls upto 300 mm height including rounding of junctions of
walls and slabs.
(c) After two days of proper curing applying a second coat of
cement slurry using 2.75 kg/ sqm of cement admixed with
water proofing compound conforming to IS : 2645 and
approved by Engineer-in-charge.
(d) Finishing the surface with 20 mm thick jointless cement mortar
of mix 1:4 (1 cement :4 coarse sand) admixed with water
proofing compound conforming to IS : 2645 and approved by
Engineer-in-charge including laying glass fibre cloth of
approved quality in top layer of plaster and finally finishing
the surface with trowel with neat cement slurry and making
pattern of 300x300 mm square 3 mm deep.
(e) The whole terrace so finished shall be flooded with water for a
FINISHING WORK
PWD
35 586+583- 12 mm thick plaster in 1:6 cement & coarse sand mortar. 290.31 Sqm 165.00 47,901.74
582
Providing and fixing on wall face unplasticised Rigid PVC rain water
pipes
45 DSR-12.41 conforming to IS : 13592 Type A, including jointing with seal ring 47.00 Rm 277.58 13,046.43
conforming to IS : 5382, leaving 10 mm gap for thermal expansion, (i)
Single socketed pipes.110 MM DIA
Mild Steel Iron Grill of a approved qualitiy and drawing including supply
PWD SOR
47 of all materials, fabrication, labour, T&P in all respect as per direction of 1,729.96 Kg 71.500 1,23,691.87
Ch-10 _ 502
Engineer-in-charge for proper completion of work at sit
TOTAL 30,24,997.85 1,36,14,250.28
Deduction 5% Over head charge in DSR ITEM Only 30,24,997.85 1,29,33,537.77
G.TOTAL 1,59,58,535.62
DETAIL ESTIMATE FOR PROPOSED ADMINISTRATIVE BLOCK FOR ZONAL POLICE CHOWKIAT
RAJEPUR, U.P.
Details of Meaurement
Sl. No. Description Nos. L B H Qty UNIT
1 Excavation Work
Excavation (0 mtr to 1.5mtr )
FT1 1 1.950 2.250 1.500 6.58
FT2 3 2.100 2.400 1.500 22.68
FT3 2 2.250 2.550 1.500 17.21
FT4 11 1.350 1.650 1.500 36.75
FT5 2 1.500 1.800 1.500 8.10
CFT1 1 3.365 1.350 1.500 6.81
CFT2 1 4.532 1.650 1.500 11.22
CFT2 1 4.878 1.650 1.500 12.07
CFT3 1 13.146 2.100 1.500 41.41
CFT4 2 4.000 1.950 1.500 23.40
CFT4 1 3.585 1.950 1.500 10.49
CFT5 1 13.146 2.250 1.500 44.37
CFT5 1 5.000 2.250 1.500 16.88
CFT6 1 3.000 2.550 1.500 11.48
CFT6 1 5.000 2.550 1.500 19.13
CFT6 1 4.000 2.550 1.500 15.30
R1-R1 1 1.171 1.350 1.500 2.37
R1-R1 1 1.660 1.350 1.500 3.36
R1-R1 1 0.963 1.350 1.500 1.95
Total 311.55 Cum
2 Filling Available Earth
Excavated Earth 311.55
Foundation -87.12
P.C.C. -52.17
Column -8.04
Into Plinth 1 334.35 0.400 133.74
Filling Required 297.96 Cum
5 PCC (1:4:8)
Under footing
FT1 1 1.950 2.250 0.100 0.44
FT2 3 2.100 2.400 0.100 1.51
FT3 2 2.250 2.550 0.100 1.15
FT4 11 1.350 1.650 0.100 2.45
FT5 2 1.500 1.800 0.100 0.54
CFT1 1 3.365 1.350 0.100 0.45
CFT2 1 4.532 1.650 0.100 0.75
CFT2 1 4.878 1.650 0.100 0.80
CFT3 1 13.146 2.100 0.100 2.76
CFT4 2 4.000 1.950 0.100 1.56
CFT4 1 3.585 1.950 0.100 0.70
CFT5 1 13.146 2.250 0.100 2.96
CFT5 1 5.000 2.250 0.100 1.13
CFT6 1 3.000 2.550 0.100 0.77
CFT6 1 5.000 2.550 0.100 1.28
CFT6 1 4.000 2.550 0.100 1.02
R1-R1 1 1.171 1.350 0.100 0.16
R1-R1 1 1.660 1.350 0.100 0.22
R1-R1 1 0.963 1.350 0.100 0.13
Under floor
Office 1 4.000 3.700 0.100 1.48
Malkhana 1 4.000 6.200 0.100 2.48
Mandir 1 5.800 2.650 0.100 1.54
Armoury 1 7.000 3.800 0.100 2.66
Pantry 1 2.760 1.300 0.100 0.36
Double ht. Entrance Lobby 1 9.900 4.400 0.100 4.36
Entrance Lobby 1 9.500 3.700 0.100 3.52
lock up 1 3.650 2.300 0.100 0.84
Hall for inspector 1 5.500 3.700 0.100 2.04
Sweeper Toilet 1 1.700 1.200 0.100 0.20
Male Toilet 1 2.500 2.500 0.100 0.63
Corridor 1 3.700 1.200 0.100 0.44
Staircase 1 6.000 2.600 0.100 1.56
Record Room 1 6.000 2.400 0.100 1.44
Conference Room 1 6.000 4.815 0.100 2.89
Office 1 6.000 1.800 0.100 1.08
Corridor 1 3.700 1.200 0.100 0.44
Lobby 1 26.250 0.100 2.63
Femail Toilet 1 3.600 2.300 0.100 0.83
TOTAL 52.17 Cum
7 D.P.C.
Office 2 4.000 0.230 1.84
2 3.700 0.230 1.70
Malkhana 2 4.000 0.230 1.84
2 6.200 0.230 2.85
Mandir 2 5.800 0.230 2.67
2 2.650 0.230 1.22
Armoury 2 7.000 0.230 3.22
2 3.800 0.230 1.75
Pantry 2 2.760 0.230 1.27
2 1.300 0.230 0.60
Double ht. Entrance Lobby 2 9.900 0.230 4.55
2 4.400 0.230 2.02
Entrance Lobby 2 9.500 0.230 4.37
2 3.700 0.230 1.70
lock up 2 3.650 0.230 1.68
2 2.300 0.230 1.06
Hall for inspector 2 5.500 0.230 2.53
2 3.700 0.230 1.70
Sweeper Toilet 2 1.700 0.230 0.78
2 1.200 0.230 0.55
Male Toilet 2 2.500 0.230 1.15
2 2.500 0.230 1.15
Corridor 2 3.700 0.230 1.70
2 1.200 0.230 0.55
Staircase 2 6.000 0.230 2.76
2 2.600 0.230 1.20
Record Room 2 6.000 0.230 2.76
2 2.400 0.230 1.10
Conference Room 2 6.000 0.230 2.76
2 4.815 0.230 2.21
Office 2 6.000 0.230 2.76
2 1.800 0.230 0.83
Corridor 2 3.700 0.230 1.70
2 1.200 0.230 0.55
Femail Toilet 2 3.600 0.230 1.66
2 2.300 0.230 1.06
Deduction (-)
D1 -1 1.800 0.230 -0.41
D2 -10 1.200 0.230 -2.76
D3 -1 1.050 0.230 -0.24
D4 -1 0.900 0.230 -0.21
TOTAL 62.19 Sqm
8 Form work
Foundation
Shuttering for P.C.C. work 33.43
Shuttering for footing work 68.94
TOTAL 102.37 Sqm
SLAB
Bottom 1 828.703 828.70
Side 1 52.277 52.28
Deduction of beam bottom -1 191.493 -191.49
TOTAL 689.49 Sqm
Beam
Plinth Beam 135.19
Lintel 43.05
TOTAL 1115.69 Sqm
Column 683.90
TOTAL 683.90 Sqm
Stairs 26.34
TOTAL 26.34 Sqm
9 REINFORCEMENT WORK
R.C.C. Qty. Coeff. Perc.
Foundation 87.12 7850.00 1.50% 10258.54
Slab 96.28 7850.00 1.00% 7558.00
Beam 112.10 7850.00 2.50% 22000.51
Lintel 2.88 7850.00 1.50% 338.54
Column 62.85 7850.00 3.00% 14801.51
Stairs 4.45 7850.00 1.50% 524.10
Total Concrete 365.68 TOTAL 55481.19 Kg
10 R.C.C. Work
R.C.C. Work below Plinth
Trapezoidal footing
FT1 1 1.800 2.100 0.200 0.76
FT2 3 1.950 2.250 0.200 2.63
FT3 2 2.100 2.400 0.200 2.02
FT4 11 1.200 1.500 0.150 2.97
FT5 2 1.350 1.650 0.150 0.67
CFT1 1 3.365 1.350 0.150 0.68
CFT2 1 4.532 1.650 0.200 1.50
CFT2 1 4.878 1.650 0.200 1.61
CFT3 1 13.146 2.100 0.450 12.42
CFT4 2 4.000 1.950 0.200 3.12
CFT4 1 3.585 1.950 0.200 1.40
CFT5 1 13.146 2.250 0.200 5.92
CFT5 1 5.000 2.250 0.200 2.25
CFT6 1 3.000 2.550 0.200 1.53
CFT6 1 5.000 2.550 0.200 2.55
CFT6 1 4.000 2.550 0.200 2.04
R1-R1 1 1.171 1.350 0.250 0.40
R1-R1 1 1.660 1.350 0.250 0.56
R1-R1 1 0.963 1.350 0.250 0.33
V= No. x (A1+ A2+ Sqrt(A1xA2)) x H/3
FT1 1 3.780 0.350 1.150 0.70 0.133
FT2 3 4.388 0.350 1.239 2.39 0.133
FT3 2 5.040 0.350 1.328 1.79 0.133
FT4 11 1.800 0.350 0.794 3.78 0.117
FT5 2 2.228 0.350 0.883 0.81 0.117
CFT1 1 4.543 2.356 3.271 1.02 0.100
CFT2 1 7.478 3.172 4.871 1.81 0.117
CFT2 1 8.049 3.415 5.242 1.95 0.117
CFT4 2 7.800 2.800 4.673 3.56 0.117
CFT4 1 6.991 2.510 4.188 1.60 0.117
CFT5 1 29.579 9.202 16.498 6.45 0.117
CFT5 1 11.250 3.500 6.275 2.45 0.117
CFT6 1 7.650 2.100 4.008 1.61 0.117
CFT6 1 12.750 3.500 6.680 2.68 0.117
CFT6 1 10.200 2.800 5.344 2.14 0.117
FT1 1 0.500 0.700 0.200 0.07
FT2 3 0.500 0.700 0.200 0.21
FT3 2 0.500 0.700 0.200 0.14
FT4 11 0.500 0.700 0.200 0.77
FT5 2 0.500 0.700 0.200 0.14
CFT1 1 3.365 0.700 0.150 0.35
CFT2 1 4.532 0.700 0.150 0.48
CFT2 1 4.878 0.700 0.150 0.51
CFT4 2 4.000 0.700 0.150 0.84
CFT4 1 3.585 0.700 0.150 0.38
CFT5 1 13.146 0.700 0.150 1.38
CFT5 1 5.000 0.700 0.150 0.53
CFT6 1 3.000 0.700 0.150 0.32
CFT6 1 5.000 0.700 0.150 0.53
CFT6 1 4.000 0.700 0.150 0.42
TOTAL 87.12 Cum
Plinth Beam
TB1 1 4.000 0.230 0.350 0.32
TB1 1 3.700 0.230 0.350 0.30
TB1 1 4.000 0.230 0.350 0.32
TB1 1 3.700 0.230 0.350 0.30
TB2 1 4.000 0.230 0.600 0.55
TB3 2 6.200 0.230 0.350 1.00
TB4 1 2.760 0.230 0.350 0.22
TB5 1 1.300 0.230 0.450 0.13
TB5 1 5.600 0.230 0.450 0.58
TB5 1 4.400 0.230 0.450 0.46
TB6 1 6.900 0.115 0.350 0.28
TB6 1 3.650 0.115 0.350 0.15
TB6 1 2.300 0.115 0.350 0.09
TB6 1 3.650 0.115 0.350 0.15
TB7 1 2.300 0.230 0.450 0.24
TB7 1 5.500 0.230 0.450 0.57
TB7 2 3.700 0.230 0.450 0.77
TB7 1 5.500 0.230 0.450 0.57
TB7 2 1.700 0.230 0.450 0.35
TB7 1 1.200 0.230 0.450 0.12
TB7 2 2.500 0.230 0.450 0.52
TB7 1 2.500 0.230 0.450 0.26
TB7 1 1.300 0.230 0.450 0.13
TB7 2 6.000 0.230 0.450 1.24
TB7 2 2.600 0.230 0.450 0.54
TB7 1 6.000 0.230 0.450 0.62
TB7 2 2.400 0.230 0.450 0.50
TB7 1 6.000 0.230 0.450 0.62
TB8 2 4.815 0.230 0.350 0.78
TB8 1 6.000 0.230 0.350 0.48
TB8 2 1.800 0.230 0.350 0.29
TB8 1 3.700 0.230 0.350 0.30
TB8 2 1.200 0.230 0.350 0.19
TB8 1 3.600 0.230 0.350 0.29
TB8 1 2.300 0.230 0.350 0.19
TB8 1 3.600 0.230 0.350 0.29
TB8 1 2.300 0.230 0.350 0.19
TOTAL 14.88 Cum
Column footing to plinth 1.5-0.10-0.373
C1 6 0.300 0.300 1.027 0.55
C2 5 0.300 0.450 1.027 0.69
C3 8 0.300 0.450 1.027 1.11
C4 3 0.300 0.450 1.027 0.42
C5 16 0.300 0.450 1.027 2.22
C6 2 0.300 0.450 1.027 0.28
C7 15 0.300 0.600 1.027 2.77
TOTAL 8.04 Cum
TOTAL 110.05 Cum
Beam
F.F.
B1 2 7.500 0.230 0.450 1.55
B2 2 2.400 0.350 0.600 1.01
B3 1 8.600 0.230 0.450 0.89
B3 1 8.200 0.230 0.450 0.85
B4 4 7.500 0.230 0.450 3.11
B5 2 7.500 0.230 0.450 1.55
B5 1 6.000 0.230 0.450 0.62
B5 1 7.600 0.230 0.450 0.79
B6 6 2.400 0.230 0.600 1.99
B7 8 7.500 0.230 0.600 8.28
B7 1 8.800 0.230 0.450 0.91
B8 2 2.145 0.115 0.450 0.22
B9 2 5.000 0.230 0.450 1.04
B10 2 7.300 0.230 0.450 1.51
B10 4 7.200 0.230 0.450 2.98
B11 6 4.200 0.230 0.450 2.61
B11 6 4.000 0.230 0.450 2.48
B11 2 5.000 0.230 0.450 1.04
B12 2 5.000 0.230 0.450 1.04
B13 2 4.200 0.230 0.450 0.87
B14 2 7.300 0.230 0.450 1.51
B15 1 5.200 0.230 0.450 0.54
B15 1 5.300 0.230 0.450 0.55
B16 1 9.900 0.115 0.350 0.40
B16 2 7.700 0.115 0.350 0.62
S.F.
B1 2 7.500 0.230 0.450 1.55
B1 2 6.800 0.230 0.450 1.41
B2 2 2.400 0.350 0.600 1.01
B3 1 8.600 0.230 0.450 0.89
B3 1 8.200 0.230 0.450 0.85
B4 4 7.500 0.230 0.450 3.11
B4 1 6.800 0.230 0.450 0.70
B5 2 7.500 0.230 0.450 1.55
B5 1 6.000 0.230 0.450 0.62
B5 1 7.600 0.230 0.450 0.79
B6 6 2.400 0.230 0.600 1.99
B7 8 7.500 0.300 0.450 8.10
B7 1 8.800 0.300 0.450 1.19
B8 2 2.145 0.115 0.450 0.22
B9 2 5.000 0.230 0.450 1.04
B10 2 7.300 0.350 0.600 3.07
B10 4 7.200 0.350 0.600 6.05
B10 1 7.500 0.350 0.600 1.58
B11 6 4.200 0.350 0.600 5.29
B11 6 4.000 0.350 0.600 5.04
B11 2 5.000 0.350 0.600 2.10
B12 2 5.000 0.350 0.600 2.10
B13 2 4.200 0.350 0.600 1.76
B14 2 7.300 0.350 0.600 3.07
B15 1 5.200 0.350 0.600 1.09
B15 1 5.300 0.350 0.600 1.11
B16 1 9.900 0.115 0.350 0.40
B16 2 7.700 0.115 0.350 0.62
TOTAL 97.22 Cum
R.C.C. Lintel
G.F.
D1 7 1.250 0.230 0.175 0.35
D2 5 1.000 0.230 0.150 0.17
D3 5 0.750 0.115 0.150 0.06
W1 16 0.650 0.230 0.150 0.36
W2 1 2.400 0.230 0.200 0.11
W3 4 1.250 0.230 0.175 0.20
W4 1 0.825 0.230 0.150 0.03
W5 1 1.700 0.230 0.200 0.08
W6 1 1.800 0.230 0.200 0.08
V1 1 0.825 0.230 0.150 0.03
V2 1 0.500 0.230 0.150 0.02
V3 1 1.615 0.230 0.175 0.07
First Floor
D1 4 1.250 0.230 0.175 0.20
D2 4 1.000 0.230 0.150 0.14
D3 3 0.750 0.115 0.150 0.04
W1 8 0.650 0.230 0.150 0.18
W3 11 1.250 0.230 0.175 0.55
W6 1 1.800 0.230 0.200 0.08
W7 1 1.400 0.230 0.175 0.06
V3 1 1.615 0.230 0.175 0.07
TOTAL 2.88 Cum
Column
G.F. to F.F.
C1 6 0.300 0.300 3.500 1.89
C2 5 0.300 0.450 3.500 2.36
C3 8 0.300 0.450 3.500 3.78
C4 3 0.300 0.450 3.500 1.42
C5 16 0.300 0.450 3.500 7.56
C6 2 0.300 0.450 3.500 0.95
C7 15 0.300 0.600 3.500 9.45
F.F. to S.F.
C1 6 0.300 0.300 3.500 1.89
C2 5 0.300 0.450 3.500 2.36
C3 8 0.300 0.450 3.500 3.78
C4 3 0.300 0.450 3.500 1.42
C5 16 0.300 0.450 3.500 7.56
C6 2 0.300 0.450 3.500 0.95
C7 15 0.300 0.600 3.500 9.45
TOTAL 54.81 Cum
Stairs
G.F. to F.F.
Waist slab 2 1.300 1.800 0.175 0.82
Landing 1 2.500 1.800 0.175 0.79
Landing 1 2.500 1.800 0.175 0.79
F.F. to S.F.
Waist slab 2 1.300 1.800 0.175 0.82
Landing 1 1.800 1.800 0.175 0.57
Landing 1 2.130 1.800 0.175 0.67
TOTAL 4.45 Cum
TOTAL 255.64 Cum
0.00
TOTAL 0.00 Sqm
Plaster work
Ground Floor 3.6-0.15
Office 1 4.000 3.500 14.00
Office 1 3.700 3.500 12.95
Pantry 1 2.760 3.500 9.66
Pantry 1 1.300 3.500 4.55
lock up 1 3.650 3.500 12.78
lock up 1 2.300 3.500 8.05
Hall for inspector 1 5.500 3.500 19.25
Sweeper Toilet 1 1.200 3.500 4.20
Male Toilet 1 2.500 3.500 8.75
Record Room 1 6.000 3.500 21.00
Conference Room 1 6.000 3.500 21.00
Office 1 6.000 3.500 21.00
Femail Toilet 1 3.600 3.500 12.60
Femail Toilet 1 2.300 3.500 8.05
Office 1 4.000 3.050 12.20
Office 1 3.700 3.050 11.29
Malkhana 1 4.000 3.050 12.20
Malkhana 2 6.200 3.050 37.82
Double ht. Entrance Lobby 1 5.600 3.050 17.08
Double ht. Entrance Lobby 1 4.400 3.050 13.42
Entrance Lobby 1 6.900 3.050 21.05
lock up 1 3.650 3.050 11.13
lock up 1 2.300 3.050 7.02
Hall for inspector 1 5.500 3.050 16.78
Hall for inspector 2 3.700 3.050 22.57
Sweeper Toilet 2 1.700 3.050 10.37
Male Toilet 2 2.500 3.050 15.25
Corridor 1 1.300 3.050 3.97
Staircase 2 6.000 3.050 36.60
Staircase 2 2.600 3.050 15.86
Record Room 2 2.400 3.050 14.64
Conference Room 2 4.815 3.050 29.37
2 1.800 3.050 10.98
Corridor 1 3.700 3.050 11.29
2 1.200 3.050 7.32
Femail Toilet 1 3.600 3.050 10.98
Femail Toilet 1 2.300 3.050 7.02
Deduction (-)
G.F.
D1 -2 1.250 2.400 -6.00
D2 -2 1.000 2.400 -4.80
D1 5 1.250 2.400 15.00
D2 3 1.000 2.400 7.20
D3 5 0.750 2.400 9.00
W1 -16 0.650 1.500 -15.60
W2 -1 2.400 1.500 -3.60
W3 -4 1.250 1.500 -7.50
W4 -1 0.825 1.500 -1.24
W5 -1 1.700 1.500 -2.55
W6 -1 1.800 1.500 -2.70
V1 -1 0.825 0.650 -0.54
V2 -1 0.500 0.300 -0.15
V3 -1 1.615 0.650 -1.05
F.F.
Multipurpose hall 2 8.000 0.230 3.050 11.22
Multipurpose hall 2 4.600 0.230 3.050 6.45
Entrance Lobby 1 6.900 0.230 3.050 4.84
Barrack 1 5.500 0.230 3.050 3.86
Barrack 2 3.700 0.230 3.050 5.19
Sweeper Toilet 2 1.700 0.230 3.050 2.39
Male Toilet 2 2.500 0.230 3.050 3.51
Corridor 1 1.300 0.230 3.050 0.91
Staircase 2 6.000 0.230 3.050 8.42
Staircase 2 2.600 0.230 3.050 3.65
Dinnig hall 2 2.400 0.230 3.050 3.37
Store 2 4.815 0.230 3.050 6.76
Store 2 1.800 0.230 3.050 2.53
Corridor 1 3.700 0.230 3.050 2.60
2 1.200 0.230 3.050 1.68
Femail Toilet 1 3.600 0.230 3.050 2.53
Femail Toilet 1 2.300 0.230 3.050 1.61
Deduction (-)
D1 -2 1.250 0.230 2.400 -1.38
D2 -2 1.000 0.230 2.400 -1.10
W1 -8 0.650 0.230 1.500 -1.79
W3 -11 1.250 0.230 1.500 -4.74
W6 -1 1.800 0.230 1.500 -0.62
W7 -1 1.400 0.230 1.500 -0.48
V3 -1 1.615 0.230 0.650 -0.24
TOTAL 580.63 Sqm
BILL OF QUANTITY
S. PWD/ Items No. L B H Qty. Unit Rate Amount
Amount As
N. DSR As Per MR &
Per DSR
PWD SOR
1- PWD- Excavation in foundation in ordinary soil
251 (Loam, Clay or Sand) including lift upto
1.50 m and lead upto 30m and including
filling watering and ramming of excavated
earth into the trenches or into the space
between the building and the sides of
foundation trenches or into the plinth and
removal and disposal of surplus earth as
directed by the Engineer In-charge upto a
distance of 30m from the foundation
trenches.
For Septic Tank 1 9.92 5.62 3.40 189.55
For chambers 2 0.83 1.06 1.30 2.29
191.84 Cum. 135.00 25898.40
1.5m to 3.0m
For Septic Tank 1 9.92 5.62 1.500 83.63
3.0m to 4.5m
For Septic Tank 2 9.92 5.62 0.40 44.60
128.23 Cum 150.00 19234.50
DS
R-
6 Steel reinforcement for R.C.C. work 1.5% 78.50 4.51 5.31 Qtl. 77.83 413.26
- DS including straightening, cutting,
R- bending, placing in position and
5.22 binding all complete upto plinth level &
A.6 above plinth level. Thermo-
Mechanically Treated bars of grade Fe-
500D or more.
DSR 2021 23.7 Supplying, filling, spreading & leveling coarse sand of
size range 1.5 mm to 2 mm in recharge pit, in required
4 thickness over gravel layer for all leads & lifts, all
complete as per direction of Engineer -
incharge. 5.28 Cum 1309.00 6905.24
DSR 2021 23.13.3 Providing and fixing suitable size threaded mild steel
cap or spot welded plate to the top of bore well
7
housing/ casing pipe, removable as per
requirement, all complete for borewell of: 1 Each 280.95 280.95
DSR 2021 23.14.3 Providing and fixing M.S. clamp of required dia to the top
of casing/ housing pipe of tubewell as per IS: 2800 (part I),
8
including necessary bolts & nuts
of required size complete. 1 Each 1586.02 1586.02
DSR 2021 23.15.3 Providing and fixing Bail plug/ Bottom plug of
9 required dia to the bottom of pipe assembly of
tubewell as per IS:2800 (part I). 1 Each 308.55 308.55
DSR 2021 23.11 Supplying, assembling, lowering and fixing in vertical
position in bore well, ERW (Electric Resistance
Welded) FE 410 plain slotted (having slot of size
1.6/3.2 mm) mild steel threaded and socketed/ plain
bevel ended pipe (type A) of required dia,
conforming to IS: 8110, of reputed and approved make,
10 having wall thickness not less than 5.40 mm, including
painted with outside surface with two coats of
anticorrosive bitumestic paint of approved brand
and manufacture, including hire & labour charges,
fittings & accessories, all complete, for all depths, as
per
direction of Engineer -in-charge.
10.1 DSR 2021 Providing and fixing M.S. Tubular frames for doors,
5.1 windows, ventilators and cupboard with rectangular/ L-
Type sections, made of 1.60 mm thick M.S. Sheet, joints
mitred, welded and grinded finish, with profiles of required
size, including fixing of necessary butt hinges and screws
13 and applying a priming coat of approved steel primer.
Fixing with 15x3 mm lugs 10 cm long embedded in
cement concrete block 15x10x10 cm of C.C. 1:3:6 (1
Cement : 3 coarse sand : 6 graded stone
aggregate 20 mm nominal size)