IPC-2Gondar Bahirdar Heavy Maintenance
IPC-2Gondar Bahirdar Heavy Maintenance
Prepared By: Nasir shifa ___________ Checked By : Eskinder Masresha_____________Certified By: Fentahun F._____________ Approved By: Wubante.J________________
Excluding VAT
- Advance repayment ( %)
- Penality
- Price Adjustment
- Others
-
-
- Sub Total 6,498,416.00
- VAT 15% 974,762.40
- This Certificate Net pay 7,473,178.40
-
TOTAL - -
With Out VAT With VAT NET CERTIFIED PAYMENT: Seven Million Four Hundred Eighty Four Thousand Five Hundred
Amount of Advance Taken (Birr) Thirty One and 74 /100 Birr
Amount of Advance Repaid Preveious (Birr) - -
Amount of Advance Repaid this month (Birr) - -
Amount of Advance Repaid to Date(Birr) - -
Amount of Advance Remaining to repaid(birr) - -
GD (MANEGER) Date:
Prepared By: Nasir shifa _______________ Date: Kalkidan Tashome
Gondar District
Enginering Service Team Leader
Certified by
Temesgen. _______________ Date: Resident Engineer Date:
Consultant Staff Fentahun Fikadu
Executed Station
Id Activity Unit Length (m) Width (m) Area (m2) TOTAL LITTRE Remark
From To
602+952 603+054 102 5 510 612.00
-
-
-
-
-
-
-
-
-
Prime Coat
-
2.4 -
-
-
-
-
-
-
-
-
This month Quantity 612.00
Previous Quantity -
Total 612.00
Date Date
Ethiopian Construction Works Corporation Gondar District
Employer: G/R/N/M/B/D
Consultant: Eng.Zewdie Eskinder with Ensired Civil System IPC-02
Contractor: ECWC Gondar District Sheet 4 of 5
Segment: Gondar-BahirDar Estimate No 2
Group : Pavement Month: February, 2019
Executed Station
Id Activity Unit Length (m) Width (m) Area (m2) Remark
From To
606+760 607+040 280 4.0 1,120.00
606+540 606+760 220 4.0 880.00
606+700 607+040 340 4.3 1,462.00
606+445 606+700 255 4.3 1,096.50
606+180 606+540 360 4.3 1,548.00
606+180 606+450 270 4.15 1,120.50
606+647 606+848 201 4.0 804.00
606+848 607+040 192 4.0 768.00
606+310 606+647 337 3.8 1,280.60
4.5cm thick 2nd layer 606+180 606+310 130 3.2 416.00
m2 903.00
Asphalt Surface 607+100 607+358 258 3.5
2.6.2 607+040 607+488 448 3.4 1,523.20
Date Date
Ethiopian Construction Works Corporation Gondar District
Employer: G/R/N/M/B/Employer: G/R/N/M/B/D
Consultant: Eng.Zewdie Eskinder with Ensired Civil System IPC-02
Contractor:ECWC Gondar District Sheet 5 of 5
Segment: Gondar-BahirDar Estimate No.2
Group : Pavement Month:February, 2019
Executed Station
Id Activity Unit Length (m) Width (m) Thickness (m) Volume Remark
From To
602+952 603+054 102 10 0.20 204.00
-
-
-
-
-
-
Base Course M3
-
2.2 -
-
-
-
-
This month Quantity 204.00
Previous Quantity -
Total 204.00
Date Date
Ethiopian Construction Works Corporation Gondar District
Employer: G/R/N/M/B/D
Consultant: Eng.Zewdie Eskinder with Ensired Civil System IPC-02
Contractor: ECWC Gondar District Sheet 1 of 5
Segment: Gondar-BahirDar Estimate No 2
Group : Pavement Month:February, 2019
Executed Station
Id Activity Unit Length (m) Width (m) Area (m2) side Area(m2) Total Area(m2) TOTAL LITTRE Days
From To
606+760 607+040 280 4.0 1,120 1,120 672 22/1/2019
606+540 606+760 220 4.0 880 880 528 23/1/2019
606+700 607+040 340 4.3 1,462 1,462 877.2 24/1/2019
606+445 606+700 255 4.3 1,096 1,096.5 657.9 25/1/2019
606+180 606+540 360 4.3 1,548 1,548 928.8 27/1/2019
606+180 606+450 270 4.15 1,121 1,120.5 672.3 30/1/2019
606+647 606+848 201 4.0 804 804 482.4 30/1/2019
606+848 607+040 192 4.0 768 768 460.8 11/2/2019
606+310 606+647 337 3.8 1,281 1,280.6 768.36 11/2/2019
Tack Coat RC-70 606+180 606+310 130 3.2 416 416 249.6 12/2/2019
Cutback Bitumen 607+100 607+358 258 3.5 903 903 541.8 12/2/2019
2.5 607+050 607+488 438 3.4 1,489 1,489.2 893.52 13/2/2019
- -
- -
- -
- -
- -
- -
- -
- -
This month Quantity 12,887.80 7,732.68
Previous Quantity 2,032.80
Total 9,765.48
IPC-02
Contractor: Gondar Road Maintenance Project Sheet 6 of 6
Route: Gondar-BahirDar Estimate No 2
Group : Haulage Month: February,2019
Item No.510 Over Haul
Station Unit Previous Quantity This Month Quantity To date Quantity Segment
m3 - - -
Gondar-BahirDar
Total - - -
Executed Station
Id Activity Unit Length (m) Width (m) Area (m2) Remark
From To
Date__________________
Checked by:
Work inspector Signature
Checked by: Ayenew Demisie
Material inspector Signature
Date__________________
Checked By : Fikadu
S.surveyor
Date :____________ Signature
Executed Station
Id Activity Unit Number Remark
From To
3.4
This month Quantity
Previous Quantity
Total
Date__________________
Checked by: Ayenew Demisie
Work inspector Signature
Date__________________
Checked By : Fikadu
S.surveyor
Date :____________ Signature
Date Date
Ethiopian Construction Works Corporation Gondar District
Employer: G/R/N/M/B/D
Consultant: Eng.Zewdie Eskinder wi IPC-03
Executed Station
Id Activity Unit Number Remark
From To
3.4
Date__________________
Checked by: Ayenew Demisie
Work inspector Signature
Date__________________
Checked By : Fikadu
S.surveyor
Date :____________ Signature
Executed Station
Id Activity Unit Length (km) Remark
From To
555+000 555+070 0.070
555+630 556+500 0.870
556+830 559+080 2.250
559+940 560+100 0.160
560+560 561+080 0.520
561+640 561+960 0.320
562+660 563+300 0.640
563+800 564+400 0.600
565+180 565+480 0.300
565+800 566+000 0.200
566+800 569+700 2.900
571+000 572+400 1.400
572+800 573+400 0.600
(Broken) 100mm width km 574+000 574+400 0.400
574+800 576+400 1.600
4.1 576+600 577+000 0.400
577+200 581+500 4.300
581+900 584+800 2.900
585+400 586+400 1.000
588+000 590+800 2.800
591+200 593+500 2.300
593+600 597+500 3.900
597+800 599+700 1.900
600+000 600+400 0.400
600+800 601+300 0.500
601+800 604+500 2.700
This month Quantity 35.03
Previous Quantity
Total
Date__________________
Checked by: Ayenew Demisie
Work inspector Signature
Date__________________
Checked By : Fikadu
S.surveyor
Date :____________ Signature
Nasir Shifa
Date Date
Ethiopian Construction Works Corporation Gondar District
Employer: G/R/N/M/B/D
Consultant: Eng.Zewdie Eskinder with Ensired Civil System IPC-03
Contractor: ECWC Gondar District Sheet 8 of 8
Route: Gonadr-Bahirdar Estimate No 8
Month: June, 2017
Item No.222 Gravel provision(Selected materials)
Executed Station
Id Activity Unit Length (km) Remark
From To
555+070 555+630 0.56
556+500 556+830 0.33
559+080 559+940 0.86
560+100 560+560 0.46
561+080 561+640 0.56
561+960 562+660 0.70
563+300 563+860 0.50
564+400 565+180 0.78
565+480 565+800 0.32
566+000 566+800 0.80
569+700 571+000 1.30
572+400 572+800 0.40
573+400 574+000 0.60
(UnBroken) 100mm width km 574+400 574+800 0.40
576+400 574+600 0.20
4.1.1 577+000 577+200 0.20
581+500 581+900 0.40
584+800 585+400 0.60
586+400 588+000 1.60
590+800 591+200 0.40
593+500 593+600 0.10
597+500 597+800 0.30
599+700 600+000 0.30
600+400 600+800 0.40
661+300 601+800 0.50
604+500 605+00 0.50
This month Quantity -
Previous Quantity
Total
Date__________________
Checked by: Ayenew Demisie
Work inspector Signature
Date__________________
Checked By : Fikadu
S.surveyor
Date :____________ Signature
Nasir Shifa
Date
Date
GONDAR ROAD NETWORK MANAGEMENT BRANCH DIRECTORATE (GRNMBD)
Station Unit Previous Quantity This Month Quantity To date Quantity Segment
14+000-25+500 m3 - - - Shehedi-Galego
Total - - -
Checked By :
Eng.
Alazar Malkie Signature
Date :____________
Checked By :
work inspector Signature
Sisay Hailemariam
Signed:_______________________________ Signed:_______________________________
G/D/R/M/P ENGINEERING SERVICE TEAM
LEADER G/R/N/M/B/D ENGINEERING TEAM LEADER
Nasir Shifa Alemayehu Teresa
Date Date
GONDAR ROAD NETWORK MANAGEMENT BRANCH DIRECTORATE (GRNMBD)
IPC-03
Contractor: Gondar Road Maintenance Project Sheet 2 of 3
Route: Shehedi-Galego Estimate No 2
Group : Drainage Month: October, 2015
Item No.230 Ditch Cleaning(Machine)
Station Unit Previous Quantity This Month Quantity To date Quantity Segment
19+200-25+500 some both side not all Km Err:509 Err:509 Err:509
Shehedi-Galego
Checked By :
Eng.
Alazar Malkie Signature
Date :____________
Checked By :
work inspector Signature
Sisay Hailemariam
Signed:_______________________________ Signed:_______________________________
G/D/R/M/P ENGINEERING SERVICE TEAM
LEADER G/R/N/M/B/D ENGINEERING TEAM LEADER
Nasir Shifa Alemayehu Teresa
Date Date
GONDAR ROAD NETWORK MANAGEMENT BRANCH DIRECTORATE (GRNMBD)
IPC-03
Contractor: Gondar Road Maintenance Project Sheet 3 of 3
Route: Shehedi-Galego Estimate No 3
Group : Pavement Month: October, 2015
Item No.418 Road Bed Preparation
Station Unit Previous Quantity This Month Quantity To date Quantity Segment
14+000-25+500 m3 Err:509 Err:509 Err:509
Shehedi-Gelego
Checked By :
Eng.
Alazar Malkie Signature
Date :____________
Checked By :
work inspector Signature
Sisay Hailemariam
Signed:_______________________________ Signed:_______________________________
G/D/R/M/P ENGINEERING SERVICE TEAM
LEADER G/R/N/M/B/D ENGINEERING TEAM LEADER
Nasir Shifa Alemayehu Teresa
Date Date
GONDAR ROAD NETWORK MANAGEMENT BRANCH DIRECTORATE (GRNMBD)
IPC-03
Contractor: Gondar Road Maintenance Project Sheet 4 of 4
Route: Hamusite-Este Estimate No 4
Group : Road side Month: October, 2015
Item No.121clearing &Grubing
Station Unit Previous Quantity This Month Quantity To date Quantity Segment
17+000-21+000 Ha - - -
Shehedi-Galego
Total - - -
Checked By :
Eng.
Date :____________
Checked By :
Signed:_______________________________ Signed:_______________________________
IPC-02
Contractor: Gondar Road Maintenance Project Sheet 1 of 6
Route: Hamusite-Este Estimate No 1
Group : Drainage Month: December, 2014
Item No.125 Mortared Masnory Repair
Station Unit Previous Quantity This Month Quantity To date Quantity Segment
51+000 m3 - - -
Hamusite-Este
Total - - -
Checked By :
Eng.
Alazar Malkie Signature
Date :____________
Checked By :
work inspector Signature
Sisay Hailemariam
Signed:_______________________________ Signed:_______________________________
G/D/R/M/P ENGINEERING SERVICE TEAM
LEADER G/R/N/M/B/D ENGINEERING TEAM LEADER
Nasir Shifa Alemayehu Teresa
Date Date
GONDAR ROAD NETWORK MANAGEMENT BRANCH DIRECTORATE (GRNMBD)
IPC-01
Contractor: Gondar Road Maintenance Project Sheet 4 of 7
Route: Hamusite-Este Estimate No 4
Group : General Month: November, 2014
Item No.411 Other Routine Maintenance
Station Unit Previous Quantity This Month Quantity To date Quantity Segment
51+000 m3 Err:509 - Err:509
Hamusite-Este
Checked By :
Eng.
Alazar Malkie Signature
Date :____________
Checked By :
work inspector Signature
Sisay Hailemariam
Signed:_______________________________ Signed:_______________________________
G/D/R/M/P ENGINEERING SERVICE TEAM
LEADER G/R/N/M/B/D ENGINEERING TEAM LEADER
Nasir Shifa Alemayehu Teresa
Date Date
GONDAR ROAD NETWORK MANAGEMENT BRANCH DIRECTORATE (GRNMBD)
IPC-02
Contractor: Gondar Road Maintenance Project Sheet 4 of 6
Route: Hamusite-Este Estimate No 4
Group : Drainage Month: December, 2014
Item No.417 Granular Backfill
Station Unit Previous Quantity This Month Quantity To date Quantity Segment
51+000 m3 - - -
Hamusite-Este
Total - - -
Checked By :
Eng.
Alazar Malkie Signature
Date :____________
Checked By :
work inspector Signature
Sisay Hailemariam
Signed:_______________________________ Signed:_______________________________
G/D/R/M/P ENGINEERING SERVICE TEAM
LEADER G/R/N/M/B/D ENGINEERING TEAM LEADER
Nasir Shifa Alemayehu Teresa
Date Date
Summary Of Payment For Operational Cost
Total
planned Previous Quantity to This Month
Activity ID Maintenance Activity Name Unit Unit Rate Date Quantity Total Quantity to Date Previous Amount to Date This Month Amount Total Amount to date
121 Culvert Cleaning M3 82.99 - 0.00 0.00 0.00 0.00 0.00 0.00
123.00 Repiar Erosion Damege M3 104.23 - 0.00 0.00 0.00 0.00 0.00 0.00
125 Mortared Masonary Repair M3 586.77 - 0.00 0.00 0.00 0.00 0.00 0.00
126 Dry Masonary Repair M3 314.30 - 0.00 972.75 972.75 0.00 305,735.32 305,735.32
127.00 Gabion structure M3 400.14 - 0.00 204.00 204.00 0.00 81,628.56 81,628.56
131 Bush Clearing M2 0.29 - 0.00 612.00 612.00 0.00 177.48 177.48
230 Ditch Cleaning (Machine) Km 4694.55 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
251 Concrete Construction (Class1) M3 2124.17 - 2,032.80 7,753.08 9,785.88 4,318,012.78 16,468,859.94 20,786,872.72
252 Concrete Construction (Class 2) M3 1626.45 - 0.00 0.00 0.00 0.00 0.00 0.00
253 Steel Reinforcement Kg 16.55 - 3,388.00 12,921.80 16,309.80 56,071.40 213,855.79 269,927.19
317 Gravel Resurfacing (Selected Material ) M3 136.85 - 0.00 0.00 0.00 0.00 0.00 0.00
318.00 Gravel Resurfacing(C.A) M3 248.42 - 0.00 0.00 0.00 0.00 0.00 0.00
410 Emergency Repair DWs 1012.50 - 0.00 0.00 0.00 0.00 0.00 0.00
411 Other Routine Maintenance DWs 1012.50 - 0.00 0.00 0.00 0.00 0.00 0.00
411(A) Clearing & Grubing Ha 4423.96 - 0.00 0.00 0.00 0.00 0.00 0.00
412B Commen Excavation to Embankment M3 44.23 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
415B Commen Excavation to Waste M3 61.59 - 0.00 0.00 0.00 0.00 0.00 0.00
417 Borrow Placing M3 87.43 - 0.00 0.00 0.00 0.00 0.00 0.00
414 Rock Excavation M3 34.00 - 0.00 0.00 0.00 0.00 0.00 0.00
417 Granular backfill M3 104.53 - 0.00 0.00 0.00 0.00 0.00 0.00
418 Road Bed Preparation Lm 56.26 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
453 Pipe Installation Lm 1388.89 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
461 Structural Excavation M3 56.38 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
471 Paved Waterway M2 168.57 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
510 Overhaul M3Km 5.99 - 0.00 0.00 0.00 0.00 0.00 0.00
Prepared By: __________________ Verified By: Mistr Shibeshi___________ Certified By: __________ Approved By: Abreham A._________
GONDER DISTRICT ROAD MAINTAINENCE GONDER DISTRICT ROAD MAINTAINENCE GONDER ROAD NETWORK MANAGEMENT TEAM GONDER ROAD NETWORK
PROJECT ENGINEERING SERVICE PROJECT MANAGER LEADER MANAGEMENT BRANCH DIRECTORATE
DIRECTOR
Project: Bahirdar -Gondar peroidic Project
Employer: Ethiopian Roads Authority IPC-03
Contractor: Ethiopian Construction works Corporation Sheet 3 of 3
Consultant:Gondar Road Network Management Directorate Estimate No 3
Title: Takeoff Sheet Month: October, 2015
Executed Station
Id Activity Unit Length (m) Width (m) Thickness (m) Volume (m3) Remark
From To
589+289 589+604.4 315.4 9 1 2,838.60
1.1 Rock fill m3
Total 2,838.60
:_______________________________ Signed:_______________________________
Date Date
Project: Bahirdar -Gondar peroidic Project
Employer: Ethiopian Roads Authority
Contractor: Ethiopian Construction works Corporation IPC-03
Consultant:Gondar Road Network Management Directorate Sheet 3 of 3
Title: Takeoff Sheet Estimate No 3
Month: October, 2015
Executed Station
Id Activity Unit Length (m) Width (m) Thickness (m) Volume (m3) Remark
From To
589+289 589+604.4 315.4 9 0.3 851.58
1.2 Capping Layer m3
Total 851.58
Prepared by:Benti Kenasa Checked By: Alazar Malkie
Title: Project Engineer Title:Engineer
Signed:____________________ Signed:_________________
Date:______________________ Date:___________________
:_______________________________ Signed:_______________________________
Date Date
Executed Station
Id Activity Unit Length (m) Width (m) Thickness (m) Volume (m3) Remark
From To
589+289 589+604.4 315.4 9 0.2 567.72
Sub-Base m3
2.1
Total 567.72
:_______________________________ Signed:_______________________________
G/D/R/M/P ENGINEERING SERVICE
TEAM LEADER G/R/N/M/B/D ENGINEERING TEAM LEADER
Nasir Shifa Alemayehu Teresa
Date Date
Executed Station
Id Activity Unit Length (m) Width (m) Thickness (m) Volume Remark
From To
589+289 589+604.4 315.4 7.70 0.21 510.00
Base Course
:_______________________________ Signed:_______________________________
Date Date
Employer: Ethiopian Roads Authority
Contractor: Ethiopian Construction works Corporation IPC-03
Consultant:Gondar Road Network Management Directorate Sheet 3 of 3
Title: Takeoff Sheet Estimate No 3
Month: October, 2015
Executed Station
Id Activity Unit Length (m) Width (m) Area (m2) TOTAL LITTRE Remark
From To
589+289 589+537 248 3.725 923.80 1,108.56
589+537 589+604.4 67.4 3.725 251.07 301.28
589+402 589+604.4 202.4 3.725 753.94 904.73
Prime coat MC- 589+289 589+402 113 3.725 420.93 505.11
30 cutback Li
bitumen 603+500 603+577 77.00 3.47 267.19 320.63
2.4 601+494 601+581 87.00 4.2 365.40 438.48 App. Rate 1.2 liter
per m2
601+697 601+783 86.00 3.58 307.88 369.46
:_______________________________ Signed:_______________________________
G/D/R/M/P ENGINEERING SERVICE
TEAM LEADER G/R/N/M/B/D ENGINEERING TEAM LEADER
Nasir Shifa Alemayehu Teresa
Date Date
:_______________________________ Signed:_______________________________
G/D/R/M/P ENGINEERING SERVICE
TEAM LEADER G/R/N/M/B/D ENGINEERING TEAM LEADER
Nasir Shifa Alemayehu Teresa
Date Date
Project: Bahirdar -Gondar peroidic Project
Employer: Ethiopian Roads Authority IPC-03
Contractor: Ethiopian Construction works Corporation Sheet 3 of 3
Consultant:Gondar Road Network Management Directorate Estimate No 3
Title: Takeoff Sheet Month: October, 2015
Executed Station
Id Activity Unit Length (m) Width (m) Area (m2) Remark
From To
589+289 589+537 248 3.725 923.80
589+537 589+604.4 67.4 3.725 251.07
589+402 589+604.4 202.4 3.725 753.94
4.5cm thick 1st 589+289 589+402 113 3.725 420.93
layer Asphalt m2
Surface 603+500 603+577 77.00 3.47 267.19
2.6.1 601+494 601+581 87.00 4.2 365.40
601+697 601+783 86.00 3.58 307.88
:_______________________________ Signed:_______________________________
G/D/R/M/P ENGINEERING SERVICE
TEAM LEADER G/R/N/M/B/D ENGINEERING TEAM LEADER
Nasir Shifa Alemayehu Teresa
Date Date
Employer: Ethiopian Roads Authority
Contractor: Ethiopian Construction works Corporation IPC-03
Consultant:Gondar Road Network Management Directorate Sheet 3 of 3
Title: Takeoff Sheet Estimate No 3
Month: October, 2015
Executed Station
Id Activity Unit Length (m) Width (m) Area (m2) Remark
From To
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
4.5cm thick 2nd -
layer Asphalt m2 -
Surface -
2.6.2
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Date Date
Project: Bahirdar -Gondar peroidic Project
Employer: Ethiopian Roads Authority
Contractor: Ethiopian Construction works Corporation
Consultant:Gondar Road Network Management Directorate
Title: Takeoff Sheet IPC-03
Sheet 3 of 3
Estimate No 3
Month: October, 2015
Executed Station
Id Activity Unit Quantity (no.) Remark
From To
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
Traffic Sign no 0 0 0
0 0 0
3.5
0 0 0
0 0 0
0 0 0
0 0 0
This month Quantity
Previous Quantity
Total
:_______________________________ Signed:_______________________________
G/D/R/M/P ENGINEERING SERVICE
TEAM LEADER G/R/N/M/B/D ENGINEERING TEAM LEADER
Nasir Shifa Alemayehu Teresa
Date Date
0
940.01
1,928.81
Summary Of Payment For Replacment Cost
Previous
Total
Activity ID Maintenance Activity Name Unit Unit Rate Quantity to This Month Total Quantity to Previous Amount to
planned
Date Quantity Date Date This Month Amount Total Amount to date
121 Culvert Cleaning M3 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00
123.00 Repiar Erosion Damege M3 15.04 - 0.00 0.00 0.00 0.00 0.00 0.00
125 Mortared Masonary Repair M3 9.88 - 0.00 0.00 0.00 0.00 0.00 0.00
126 Dry Masonary Repair M3 0.00 - 0.00 972.75 972.75 0.00 0.00 0.00
127.00 Gabion structure M3 30.09 - 0.00 204.00 204.00 6,138.36 6,138.36 6,138.36
131 Bush Clearing M2 0.00 - 0.00 612.00 612.00 0.00 0.00 0.00
230 Ditch Cleaning (Machine) Km 0.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
251 Concrete Construction (Class1) M3 70.70 - 2,032.80 7,753.08 9,785.88 691,830.76 548,118.23 691,830.76
252 Concrete Construction (Class 2) M3 115.72 - 0.00 0.00 0.00 0.00 0.00 0.00
253 Steel Reinforcement Kg 0.00 - 3,388.00 12,921.80 16,309.80 0.00 0.00 0.00
317 Gravel Resurfacing (Selected Material ) M3 20.51 - 0.00 0.00 0.00 0.00 0.00 0.00
318.00 Gravel Resurfacing(C.A) M3 255.88 - 0.00 0.00 0.00 0.00 0.00 0.00
410 Emergency Repair DWs 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00
411 Other Routine Maintenance DWs 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00
411(A) Clearing & Grubing Ha 2292.00 - 0.00 0.00 0.00 0.00 0.00 0.00
412B Commen Excavation to Embankment M3 5.63 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
415B Commen Excavation to Waste M3 9.37 - 0.00 0.00 0.00 0.00 0.00 0.00
417 Borrow Placing M3 6.97 - 0.00 0.00 0.00 0.00 0.00 0.00
414 Rock Excavation M3 7.54 - 0.00 0.00 0.00 0.00 0.00 0.00
417 Granular backfill M3 19.65 - 0.00 0.00 0.00 0.00 0.00 0.00
418 Road Bed Preparation Lm 14.12 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
453 Pipe Installation Lm 165.83 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
461 Structural Excavation M3 0.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
471 Paved Waterway M2 0.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
510 Overhaul M3Km 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00
Total Err:509 Err:509 Err:509
Prepared By: __________________ Verified By: Mistr Shibeshi___________ Certified By: __________ Approved By: Abreham A._________
GONDER DISTRICT ROAD MAINTAINENCE GONDER DISTRICT ROAD MAINTAINENCE GONDER ROAD NETWORK MANAGEMENT GONDER ROAD NETWORK
PROJECT ENGINEERING SERVICE PROJECT MANAGER TEAM LEADER MANAGEMENT BRANCH DIRECTORATE
DIRECTOR
breham A._________
DER ROAD NETWORK
T BRANCH DIRECTORATE
DIRECTOR