3 Types of Estimates
3 Types of Estimates
0 Types of estimate
1) Plinth area:
Plinth area is the built up covered area of a building measured at floor level of any
storey. It is calculated by taking external dimensions of building at floor level
excluding the plinth offsets. The area of court yard, open area, balconies and
cantilever projection etc. shouldn't include in it.
Total area of floor in between walls i.e. Area of floor of all rooms, verandas, corridors,
entrance halls, staircase, kitchen, stores, toilet / bathroom etc is called floor area.
3) Circulation Area:
The floor area of verandas, corridors, entrance halls, staircase, room, balconies, and
lifts is known as circulation area because such area is used for the movement of
persons.
4) Carpet area:
The live able area of a building is called carpet area. It is the total floor area minus the
circulation area and minus the other unusable area such as of bathrooms, water
closets, air conditioning rooms etc. It should also exclude the kitchen, pantry, stores
and similar other rooms which are not used for living purpose in residential building.
This estimate is prepared from the practical knowledge and cost of similar works.
Such as estimate is framed by the use of any one of the following methods.
i) Unit rate method
ii) Plinth area estimate
iii) Cubic rate estimate
The plinth area is the built up area of external dimensions of a building. In other
words,
Plinth area = Carpet area + Circulation area + kitchen/Toilet etc + wall area
Q.1. Prepare a plinth area estimate of a building from the following data.
Carpet area = 250 sq. m.
Circulation area = 30% of plinth area
Walls = 10% of plinth area
Plinth area rate = Rs. 6000/m2
Solution:
Let us consider plinth area of building = PA
Hence,
Plinth area = Carpet area + Circulation area + walls
30 10
PA = 250 + × PA+ × PA
100 100
∴ PA = 416.67
∴ cost of building = PA x plinth area rate
= 416.67 x 6000
= Rs. 25,000020 Ans.
Q. 2 Prepare a preliminary estimate of a poly technique building for student no. 800 in order to
assess the amount for building, based on the following particulars.
a) Carpet area required per student = 1.2 sq. m.
b) Area of corridors, verandah etc = 20% of plinth area
c) Area of wall = 15% of plinth area
d) Plinth area rate = Rs 3500 per sq. m.
e) Cost of water supply work = 5% of building cost
f) Cost of sanitary = 7% of Building cost
g) Cost of electrification = 12% of building cost
h) Cost of approach road and boundary wall = 3% of building cost.
i) Contingencies and work charged establishment shall be 5% and 2.5% of the total cost
respectively.
Solution:
Let, plinth area be PA
Plinth area = carpet area + area of corridors, verandas + area of wall
20 15
PA = 1.2 x 800 + × PA + × PA
100 100
∴ PA = 1476.92m2
Building cost = 1476.92 x 3500 = 51,69,220
5
Cost of water supply work = 5% of 5169220 = x 51 , 692 ,20 = 258461
100
f) Cost of sanitary = 7% of 51,69,220
= 361845.4
g) Cost of electrification = 12% of 51,69,220
= 620306.4
h) Cost of approach road and boundary wall = 3% of 5169220
= 155076.6
Now,
Total cost = 5169220 + 258461 + 361845.4+620306.4+155076.6
= 6564909.4
i) Contingencies = 5% of 6564909.4
= 328245.47
Work charged establishment = 2.5% of 6564909.4
= 164122.73
Finally Grand total = 6564909.4+328245.47+164122.73
= Rs. 7057300 Answer
In order to keep the work (structure, road etc) in proper condition. Annual repairs
are carried out annually for which an estimate is prepared is known as repair and
maintenance estimate.
3.6 Complete estimate:
Detailed estimate is prepared in standard forms and the complete set of estimate
consist of:
1. Title page giving name of the Engineering Department, division, estimate no.,
District of sub-division, name of work and amount of estimate.
2. Index of content and plan and drawings.
3. Report
4. Design calculation
5. General Specification
6. Detailed Specification
7. Analysis of rates (If required)
8. Detailed measurement and calculation of quantities.
9. Abstract of estimated cost
10. General abstract of cost
11. Drawings: Plans, elevation, detailed drawing, site plan etc.
At the end of the abstract of estimated cost or summary of estimated cost there
should be signature of assistant engineer, executive engineer and superintending
engineer and on the back page head of account should be given.