Annexure IIB

This document provides a summary level schedule for the development of 2 x 2 strand slab casters (CC5 & CC6) from October 2022 through July 2025. It includes activities for general planning, basic engineering, detail engineering, procurement, fabrication, and installation with durations and responsibilities assigned. Key milestones include the kick-off meeting in October 2022, approval of layout drawings in November 2022, completion of basic engineering in October 2023, start of detail engineering in December 2022, and completion of detail engineering in October 2024.

Uploaded by

Madhur Taksali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
150 views

Annexure IIB

This document provides a summary level schedule for the development of 2 x 2 strand slab casters (CC5 & CC6) from October 2022 through July 2025. It includes activities for general planning, basic engineering, detail engineering, procurement, fabrication, and installation with durations and responsibilities assigned. Key milestones include the kick-off meeting in October 2022, approval of layout drawings in November 2022, completion of basic engineering in October 2023, start of detail engineering in December 2022, and completion of detail engineering in October 2024.

Uploaded by

Madhur Taksali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Activity ID Activity Name Duration Start Finish RESPONSIBILITY LD 2023 2024 2025

milestone S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S


-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
AMNS L2 Baseline 1019 07-Oct-22 22-Jul-25

GENERAL 45 07-Oct-22 20-Nov-22

AA00-G-0100 Coming Into Force of the Contract 0 07-Oct-22* AMNS/DAN

AA00-G-0200 Start of time schedule as per Contract 0 07-Oct-22 AMNS/DAN

AA00-G-0300 Preparation for Kick-off meeting 15 07-Oct-22 21-Oct-22 AMNS/DAN

AA00-G-0400 Kick-off meeting 15 22-Oct-22 05-Nov-22 AMNS/DAN

AA00-G-0500 Discussion of General Layout Drawing 15 22-Oct-22 05-Nov-22 AMNS/DAN

AA00-G-0600 Approval of layout drawing (Preliminary layout approval) 30 22-Oct-22 20-Nov-22 AMNS

BASIC ENGINEERING 365 07-Oct-22 06-Oct-23

AA00-BD-0100 GA Drawing for Ladle 31 07-Oct-22 06-Nov-22 AMNS

AA00-BD-0200 Basic data-Civil (Main load plan-for building column) 31 22-Oct-22 21-Nov-22 AMNS/DAN RD1

AA00-BD-0300 Basic data-Main process equipment Caster machine (load data in kN/m2) 61 07-Nov-22 06-Jan-23 DAN RD1

AA00-BD-0400 Basic data-Main process equipment Runout area (load data in kN/m2) 62 07-Dec-22 06-Feb-23 DAN RD1

AA00-BD-0500 Basic data-Building structure 30 22-Oct-22 20-Nov-22 AMNS

AA00-BD-0600 Basic data - Utility (Fluid balance table:Consumptions and TOPs) 90 07-Dec-22 06-Mar-23 DAN RD1

AA00-BD-0700 Basic Design-Civil for Caster machine area (1) 212 07-Nov-22 06-Jun-23 DAN RD1
(80% completion in 6m and rest 20% in 8m from zerodate)
AA00-BD-0800 Basic Design-Civil for Runout area (1) 90 07-Jan-23 06-Apr-23 DAN RD1

AA00-BD-0900 Basic Design-Civil for Caster Electrical & Hydraulic cabins (1) (80% completion in 7m and rest 20% in 150 07-Feb-23 06-Jul-23 DAN RD1
9m from zerodate)
AA00-BD-1000 Basic Design-Civil for Minor and Auxiliary equipment and final Elec bldg (maintenance area) 92 07-Jun-23 06-Sep-23 DAN RD1

AA00-BD-1100 Basic Design-Intermed. floors/platforms(incl. Major loads & fixing points for struct.)>>>Included in 0 07-Oct-22 DAN
caster machine area

AA00-BD-1200 Basic Design - Utility-Media consumption list and P&ID 243 07-Dec-22 06-Aug-23 DAN RD1

AA00-BD-1300 Basic Design - Equipment, Hydraulic and Lubrication systems 182 07-Dec-22 06-Jun-23 DAN

AA00-BD-1400 Basic Design - E&I (Including cable engineering & internal E-bldg layout) 214 07-Mar-23 06-Oct-23 DAN

AA00-BD-1500 Basic Design-Utility piping 153 07-Mar-23 06-Aug-23 DAN

AA00-BD-1600 Basic Design-Automation 273 07-Jan-23 06-Oct-23 DAN

AA00-BD-1700 Basic Design-AMNSI scope 0 07-Oct-22 DAN

DETAIL ENGINEERING 655 22-Dec-22 06-Oct-24

AA00-DD-0100 Detail Design-Piling 183 22-Dec-22 22-Jun-23 AMNS

AA00-DD-0200 Detail Design-Civil for all Buildings 212 07-Feb-23 06-Sep-23 AMNS

AA00-DD-0300 Detail Design-Civil for all Equipment 337 07-Mar-23 06-Feb-24 AMNS

AA00-DD-0400 Detail Design-Structure for Building 425 07-Jan-23 06-Mar-24 AMNS

AA00-DD-0500 Detail Design-Equipment related structure 244 07-Apr-23 06-Dec-23 AMNS

Actual Work Critical Milestone Doc. No : DPC6V4-AA00-N0000-AV002


Actual Milestone
2 X 2 STRAND SLAB CASTERS CC5 & CC6 Date Revision Checked Approved
28-Oct-22 First Issue SX MR
Activity - OVERALL LEVEL 2 SCHEDULE - 23-Nov-22 Revised SX MR
Milestone Page 1 of 3
Critical Activity
Activity ID Activity Name Duration Start Finish RESPONSIBILITY LD 2023 2024 2025
milestone S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
AA00-DD-0600 Detail Design-OEM scope Major equipment 303 07-Feb-23 06-Dec-23 DAN

AA00-DD-0700 Detail Design-OEM scope Structures 303 07-Feb-23 06-Dec-23 DAN RD2

AA00-DD-0800 Detail Design-OEM scope Auxiliary equipment 184 07-Jul-23 06-Jan-24 DAN

AA00-DD-0900 Detail Design-OEM scope Utility piping CC5 183 07-Jun-23 06-Dec-23 DAN RD2

AA00-DD-1000 Detail Design-OEM scope Utility piping CC6 184 07-Aug-23 06-Feb-24 DAN RD2

AA00-DD-1100 Detail Design-OEM scope E&I (incl. Cable routing and tray engineerig) for CC5. Data fo CC5 will be 214 07-May-23 06-Dec-23 DAN RD2
used also for CC6

AA00-DD-1200 Detail Design-Automation 244 07-Jul-23 06-Mar-24 DAN RD2

AA00-DD-1300 Detail Design-Balance shop piping/cabling 215 07-Jul-23 06-Feb-24 AMNS

AA00-DD-1400 DD-Balance civil/structure (Roads, drain, platforms handrails. Etc) 335 07-Nov-23 06-Oct-24 AMNS

PROCUREMENT 151 07-Nov-22 06-Apr-23

AA00-PR-0100 Procurement of AMNSI scope items (Cranes, Structures, Water, E&A etc.) 151 07-Nov-22 06-Apr-23 AMNS

MANUFACTURING & SUPPLY 672 07-Apr-23 06-Feb-25

AA00-MF-0100 Manufacturing of Sellers imported equipment 427 07-Apr-23 06-Jun-24 DAN


(FOB acc. INCOTERMS 2020) wihtout OCP for CC5
AA00-MF-0200 Manufacturing of Sellers imported equipment 428 07-Jul-23 06-Sep-24 DAN
(FOB acc. INCOTERMS 2020) wihtout OCP for CC6

AA00-MF-0300 Manufacturing of Sellers imported equipment 427 07-Aug-23 06-Oct-24 DAN


(FOB acc. INCOTERMS 2020) OCP for CC5

AA00-MF-0400 "Manufacturing of Sellers imported equipment 427 07-Oct-23 06-Dec-24 DAN


(FOB acc. INCOTERMS 2020) OCP for CC6"
AA00-MF-0500 Manufacturing of Seller's local equipment CC5&CC6 519 07-Apr-23 06-Sep-24 DAN

AA00-MF-0600 FOB delivery of Online-Segments for CC5 (from end of 18m to 20m) (3) 61 07-Apr-24 06-Jun-24 DAN RD3

AA00-MF-0700 FOB delivery of Online-Segments for CC6 (from end of 21m to 23m) (3) 62 07-Jul-24 06-Sep-24 DAN RD3

AA00-MF-0800 Transport of Seller's imported equipment CC5&CC6 457 07-Sep-23 06-Dec-24 AMNS

AA00-MF-0900 Arrival at site of Seller's imported equipmetn CC5&CC6 458 07-Nov-23 06-Feb-25 AMNS

AA00-MF-1000 DAP delivery of Seller's local equipment (FOT at site) CC5 198 22-Nov-23 06-Jun-24 DAN

AA00-MF-1100 DAP delivery of Ladle turret (FOT at site) for CC5 (subject to receiving Ladle GA dwg in 1month from 0 07-Jan-24 DAN RD3
zero date, item2.0)

AA00-MF-1200 DAP delivery of Segment support frame (FOT at site) for CC5 (from end of 15m to 16m) 31 07-Jan-24 06-Feb-24 DAN RD3

AA00-MF-1300 DAP delivery of Seller's local equipment (FOT at site) CC6 259 22-Jan-24 06-Oct-24 DAN

AA00-MF-1400 DAP delivery of Ladle turret (FOT at site) for CC6 (subject to receiving Ladle GA dwg in 1month from 0 07-Mar-24 DAN RD3
zero date, item2.0)
AA00-MF-1500 DAP delivery of Segment support frame (FOT at site) for CC6 (from end of 17m to 18m) 31 07-Mar-24 06-Apr-24 DAN RD3

AA00-MF-1600 DAP delivery of OCP Seller's local equipment (FOT at site) CC5 92 07-Jul-24 06-Oct-24 DAN

AA00-MF-1700 DAP delivery of OCP Seller's local equipment (FOT at site) CC6 91 07-Sep-24 06-Dec-24 DAN

AA00-MF-1800 DAP delivery of interconnecting piping by Seller local (FOT at site) CC5 77 22-Mar-24 06-Jun-24 DAN RD3

AA00-MF-1900 DAP delivery of interconnecting piping by Seller local (FOT at site) CC6 77 22-May-24 06-Aug-24 DAN RD3

CONSTRUCTION 790 07-Jan-23 06-Mar-25

Actual Work Critical Milestone Doc. No : DPC6V4-AA00-N0000-AV002


Actual Milestone
2 X 2 STRAND SLAB CASTERS CC5 & CC6 Date Revision Checked Approved
28-Oct-22 First Issue SX MR
Activity - OVERALL LEVEL 2 SCHEDULE - 23-Nov-22 Revised SX MR
Milestone Page 2 of 3
Critical Activity
Activity ID Activity Name Duration Start Finish RESPONSIBILITY LD 2023 2024 2025
milestone S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
AA00-CS-0100 Piling 212 07-Jan-23 06-Aug-23 AMNS

AA00-CS-0200 Civil work - Execution of bulding columns, equipment foundation , electrical room, casting platforms 382 22-Mar-23 06-Apr-24 AMNS

AA00-CS-0300 Structural steel work-Major execution of bay structure 321 22-Jul-23 06-Jun-24 AMNS

AA00-CS-0400 Structural steel work-Balance execution of bay structure(roof and wall cladding) 123 07-May-24 06-Sep-24 AMNS

AA00-CS-0500 Erection of caster Mechanical equipment CC5 260 22-Dec-23 06-Sep-24 AMNS

AA00-CS-0800 Erection of caster Electrical equipment CC5 214 07-Apr-24 06-Nov-24 AMNS

AA00-CS-0900 Utility piping CC5 244 07-Apr-24 06-Dec-24 AMNS

AA00-CS-1000 Hydraulics, Lubrication CC5 214 07-May-24 06-Dec-24 AMNS

AA00-CS-1100 Cabling CC5 306 07-Mar-24 06-Jan-25 AMNS

AA00-CS-1200 Instrumentation CC5 306 07-Mar-24 06-Jan-25 AMNS

AA00-CS-1300 Automation CC5 92 07-Jul-24 06-Oct-24 AMNS

AA00-CS-1400 Erection of caster Mechanical equipment CC6 259 22-Feb-24 06-Nov-24 AMNS

AA00-CS-1500 Erection of caster Electrical equipment CC6 214 07-Jun-24 06-Jan-25 AMNS

AA00-CS-1600 Utility piping CC6 273 07-Jun-24 06-Mar-25 AMNS

AA00-CS-1700 Hydraulics, Lubrication CC6 215 07-Jul-24 06-Feb-25 AMNS

AA00-CS-1800 Cabling CC6 304 07-May-24 06-Mar-25 AMNS

AA00-CS-1900 Instrumentation CC6 304 07-May-24 06-Mar-25 AMNS

AA00-CS-2000 Automation CC6 92 07-Nov-24 06-Feb-25 AMNS

COLD START AND INTEGRATED TEST 151 07-Nov-24 07-Apr-25

AA00-CT-0100 CC5 92 07-Nov-24 06-Feb-25 AMNS/DAN

AA00-CT-0200 R.F.I.O (Ready for Initial Operation) CC5 0 07-Feb-25 AMNS/DAN

AA00-CT-0300 CC6 90 07-Jan-25 06-Apr-25 AMNS/DAN

AA00-CT-0400 R.F.I.O (Ready for Initial Operation) CC6 0 07-Apr-25 AMNS/DAN

INDUSTRIAL COMMISSIONING AND ACCEPTANCE 165 07-Feb-25 22-Jul-25

AA00-IC-0100 Start of Industrial Commissioning / Hot start CC5 0 07-Feb-25 AMNS/DAN

AA00-IC-0200 Industrial Commissioning Certificate (I.C.) - Caster 5 15 07-Feb-25 21-Feb-25 AMNS/DAN LD4

AA00-IC-0300 Acceptance Testing CC5 89 22-Feb-25 21-May-25 AMNS/DAN

AA00-IC-0400 Provision Acceptance - Caster 5 0 22-May-25 AMNS/DAN

AA00-IC-0500 Start of Industrial Commissioning / Hot start CC6 0 07-Apr-25 AMNS/DAN

AA00-IC-0600 Industrial Commissioning Certificate (I.C.) - Caster 6 15 07-Apr-25 21-Apr-25 AMNS/DAN RD4

AA00-IC-0700 Acceptance Testing CC6 91 22-Apr-25 21-Jul-25 AMNS/DAN

AA00-IC-0800 Provision Acceptance - Caster 6 0 22-Jul-25 AMNS/DAN

Actual Work Critical Milestone Doc. No : DPC6V4-AA00-N0000-AV002


Actual Milestone
2 X 2 STRAND SLAB CASTERS CC5 & CC6 Date Revision Checked Approved
28-Oct-22 First Issue SX MR
Activity - OVERALL LEVEL 2 SCHEDULE - 23-Nov-22 Revised SX MR
Milestone Page 3 of 3