0% found this document useful (0 votes)
24 views10 pages

Group 2 - Activity 6

Uploaded by

Sieh Sieh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
24 views10 pages

Group 2 - Activity 6

Uploaded by

Sieh Sieh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 10

Prepared by: Group 2

Activity 6
EXPECTED
IMMEDIATE OPTIMISTIC MOST LIKELY PESSIMISTIC TIME
ACTIVITY PREDECESSOR a m b t = [(a + 4m +
b)/6]
A -- 2 5 8 5
B A 3 6 9 6
C A 4 7 10 7
D B 2 5 14 6
E D 3 3 3 3
F C 6 8 10 8
G E, F 1 1 1 1
H C 6 10 14 10
I G, H 3 4 5 4
Table 1

1) Draw the network for the activities in Table 1

B D

START A

2) State the critical path

EARLIEST EARLIEST LATEST


START FINISH START
EXPECTED
ACTIVITY IMMEDIATE TIME
PREDECESSOR t = [(a + 4m +
b)/6]
EXPECTED
IMMEDIATE TIME
ACTIVITY PREDECESSOR t = [(a + 4m +
b)/6] ES EF = ES + t LS = LF – t

A -- 5 0 5 0
B A 6 5 11 6
C A 7 5 12 5
D B 6 11 17 12
E D 3 17 20 18
F C 8 12 20 13
G E, F 1 20 21 21
H C 10 12 22 12
I G, H 4 22 26 22

Activity t
ES EF
LS LF B
5
6

A 5
0 5
0 5

C
5
5

Note: For Activit


smallest LS value
13 & H= 12, H ha
Answer: that is 12
The critical path is A--> C --> H ---> I

3)    Determine the expected completion time


The expected completion time is 26 weeks

4) Calculate the variance


VARIANCE
ACTIVITY
[(b-a)/6)]2
A 1.000
C 1.000
H 1.778
I 0.111
Total 3.889

Hence, the project variance is 3.889

5) Find the probability that the project will be completed in 28 weeks

= √3.889
= 1.972 weeks

Due date: 28 weeks


Expected date: 26 weeks

= (28 - 26)
1.972

Z = 1.014 ~ 1.01
From Z score table above, we find the probability of 0.84375 associated with this Z value.
That means the probability this project can be completed in 28 weeks or less is 0.84375 or 84.38%
The project’s expected completion date is 26 weeks.

Expected Time is 26 weeks

Probability 1.014 standard deviation


(T ≤ 26 weeks) is 84.38%

26 28
Weeks Weeks
VARIANCE
[(b-a)/6)]2

1.000
1.000
1.000
4.000
0.000
0.444
0.000
1.778
0.111

D E

G I FINISH

LATEST
FINISH SLACK

ON CRITICAL
PATH?
LF = Smallest ON CRITICAL
LS of LS - ES or LF – PATH?
following EF
activities

5 0 Yes
12 1 No
12 0 Yes
18 1 No
21 1 No
21 1 No
22 1 No
22 0 Yes
26 0 Yes
ES & EF Calculate forward

6 D 6 E
11 11 17 17
12 12 18 18

F 8
12 20
13 21
7
12
12 H 10
12 22
12 22

Note: For Activity C = LF take the


smallest LS values. Hence between F=
13 & H= 12, H have the smallest value
that is 12 LS & LF Calculate backward
this Z value.
is 0.84375 or 84.38%

014 standard deviation

Time
Note: For Activity I = ES take
the highest values EF. Hence
between G = 21 & H= 22, H
have the highest value that
is 22

3
20
21

G 1 I
20 21 22
21 22 22

lculate backward
e: For Activity I = ES take
highest values EF. Hence
ween G = 21 & H= 22, H
e the highest value that
2

4
26
26

Note:
Expected completion time
is 26

You might also like