Amoingon Box Culvert
Amoingon Box Culvert
ANNEX 1
Schematic Diagram of
_________________________________Subproject
Qs 0.118 LPS
SPRING BOX
11 (elev = 750 m) (PUROK /SITIO__ 1
710 m.
j
9 F6
i 10 (elev = 730 m)
100 m. HH = 12
RESERVOIR
(elev = 735 m) 38
735 60 m.
h RH=.73
6 (elev = 733 m)
733
25 f 31
320 m. 240 m.
e
(elev = 709 m) 7 (elev = 710 m) RH=6.84 25
HH = 6 8 31 HH = 6 d
F5 g 200 m. F4 (elev = 720 m) 4 20 m. 5 F3
F3
720 (elev = 719 m)
HH = 10
(PUROK/SITIO____ 2
D=31
c 1,200 m.
19
RH=3.57 10 m. 705
(elev = 704 m) 2 b 3 F2
704 (elev = 703.5 m)
Preparation of schematic diagram as basis for pipeline design: HH = 6
Steps:
1. Locate tapstand and name it F1…n starting from farthest
to the reservoir and or water source.
2. Determine the number of nodes and name it in numbers a 500 m.
starting from farthest to the reservoir and or water source. D=31
3. Determine the number of sections and name it in letters
starting from farthest to the reservoir and or water source. (PUROK/SITIO 3
4. Indicate the number of HH per tapstand, the elevation of
the nodes, the length of the sections from survey results. HH = 10
5. Design for the pipe diameter of the sections (see pipeline analysis) 1 (elev = 700 m)
and indicate final pipe sizes in the schematic diagram. 700
F1
RH-1.2m
Rhwhole system=12.88m
KALAHI-CIDSS
Planning and Design WS
Schematic Diagram/Project Area Map
ANNEX 1
Prepare a map showing the area to be served and the location of the source(s) of water. It should be drawn to a
convenient scale or with measurements of distance between important structures along roads and pathways.
Include elevation. Indicate houses, schools, churches, markets, existing water systems, public faucets, reservoir
and other important land features.
Legend
House
School
Church
Public faucet
Existing pipeline
Proposed pipeline
R Reservoir
Gate valve
Check Valve
Reducer
Clinic
Contours
º123 Elevations
S Spring Box
KALAHI-CIDSS
Detailed Estimates
ANNEX 1a
FORMAT OF DETAILED COST ESTIMATES
The presentation of the materials, labor and equipment in details is helpful when implementing the subproject by community force
account.
ITEM RESERVOIR ( 8 cu.m. )
A. MATERIALS
1) Computation of Quantities and Costing
Particular Compu Material Quantity Unit TOTAL
Description Specs. Factor ted Compu- Say Unit Cost Cost
Volume ted (P) (P)
Concrete Class "A" (1:2:4) 3.26 cu.m
Plaster (1:2) 0.3 cu.m
Portland cement 40 kg. 38 bag 140.00 5,320.00
Sand 0.5 2.13 cu.m 250.00 532.50
Gravel 1 3.3 cu.m 350.00 1,155.00
Sahara compound D.C. 35 pack 22.00 770.00
RSB 10 mm x 6 m D.C. 41 pc. 70.00 2,870.00
12 mm x 6 m D.C. 23 pc. 77.00 1,771.00
G.I. wire Gauge # 16 D.C. 3 kg. 43.00 129.00
Marine plywood 1/4" x 4' x 8' D.C. 18 sheet 375.00 6,750.00
Rough lumber 2" x 2" x 8' D.C. 50 pc. 53.00 2,650.00
Common nails #4 D.C. 25 kg. 30.00 750.00
# 1-1/2 D.C. 3 kg. 35.00 105.00
TOTAL 22,802.50
B. LABOUR COST
Productivity rate ( Excavation ) 1.6 cu.m./m-day
Productivity rate ( Concrete works ) 0.14 cu.m./m-day
Particular Quantity Gang Activity Duration Rate Total
Description Manpower Required Output Compu- Say per Day Labour
ted Cost
Excavation 3.76
Supervisor 1 12.8 0.29375 1 250.00 250.00
Laborer 8 1 150.00 1,200.00
Form works
Supervisor 1 6 250.00 1,500.00
Carpenter 2 6 225.00 2,700.00
Laborer 8 6 150.00 7,200.00
Steel works
Supervisor 1 3 250.00 750.00
Steelperson 2 3 225.00 1,350.00
Laborer 8 3 150.00 3,600.00
Concrete works 3.26
Supervisor 1 1.4 2.328571429 3 250.00 750.00
Mason 2 3 225.00 1,350.00
Laborer 8 3 150.00 3,600.00
TOTAL 13 24,250.00
KALAHI-CIDSS PROJECT 3 of 7
Detailed Estimates
A. MATERIALS
1) Computation of Quantities and Costing
Particular Compu Material Quantity Unit TOTAL
Description Specs. Factor ted Compu- Say Unit Cost Cost
Volume ted (P) (P)
Concrete Class "A" (1:2:4) 0.224
Portland cement 40 kg. 9 2.016 2.5 bag 140.00 350.00
Sand 0.5 0.112 0.15 cu.m 250.00 37.50
Gravel 1 0.224 0.25 cu.m 350.00 87.50
Sahara compund D.C. 2 pack 22.00 44.00
RSB 10 mm x 6 m D.C. 6 pc. 70.00 420.00
G.I. Tie wire Gauge # 16 D.C. 0.5 kg. 43.00 21.50
Forms Re-use from reservoir construction
Common nail Re-use from reservoir construction
TOTAL 960.50
B. LABOUR COST
Particular Quantity Gang Activity Duration Rate Total
Description Manpower Required Output Compu- Say per Day Labour
ted Cost
Form works
Supervisor 1 1 250.00 250.00
Carpenter 1 1 225.00 225.00
Laborer 4 1 150.00 600.00
Steel works
Supervisor 1 1 250.00 250.00
Steelperson 1 1 225.00 225.00
Laborer 4 1 150.00 600.00
Concrete works
Supervisor 1 2 250.00 500.00
Mason 1 2 225.00 450.00
Laborer 4 2 150.00 1,200.00
Removal of old pipe,
installation of new
Supervisor 1 1 250.00 250.00
Mason 1 1 225.00 225.00
Laborer 4 1 150.00 600.00
Ditching
Supervisor 1 1 250.00 250.00
Laborer 4 1 150.00 600.00
TOTAL 6 6,225.00
KALAHI-CIDSS PROJECT 4 of 7
Detailed Estimates
ITEM PIPELINE
A. MATERIALS
1) Computation of Quantities and Costing
Particular Pipeline Section Quantity Unit Total
Unit Section/ Length Compu- Cost Cost
Description Specs. Location ted Say
(m) (P) (P)
Pipes and fittings
G.I. Pipe, sched. 40 31 mm x 6 m pc. a 500 83.33 84 550.00 46,200.00
G.I. Union patente 31 mm pc. a 7.33 8 88.00 704.00
G.I. Coupling 31 mm pc. a 75 32.00 2,400.00
G.I. Tee 31 x 31 mm pc. a 1 42.00 42.00
G.I. Reducer Bushing 31 x 13 mm pc. a 1 30.00 30.00
G.I. Plug 31 mm pc. a 1 20.00 20.00
G.I. Pipe, sched. 40 13 mm x 6 m pc. a 0.5 184.00 92.00
G.I. Coupling 13 mm pc. a 1 12.00 12.00
G.I. Elbow, 90 degrees 13 mm pc. a 2 15.00 30.00
Brass Gate valve 13 mm pc. a 1 65.00 65.00
KALAHI-CIDSS PROJECT 5 of 7
Detailed Estimates
KALAHI-CIDSS PROJECT 6 of 7
Detailed Estimates
B. LABOUR COST
Particular Quantity Gang Activity Duration Rate Total
Description Manpower Required Output Compu- Say per Day Labour
ted Cost
Pipe Threading 559.5
Supervisor 1 200 2.7975 3 250.00 750.00
Plumber 2 3 225.00 1,350.00
Laborer 8 3 150.00 3,600.00
Excavation, Laying
& Installation and
Backfilling 559.5
Supervisor 1 60 9.325 10 250.00 2,500.00
Plumber 2 10 225.00 4,500.00
Laborer 8 10 150.00 12,000.00
TOTAL 13 24,700.00
KALAHI-CIDSS PROJECT 7 of 7
Detailed Estimates
A. MATERIALS
1) Computation of Quantities and Costing
Particular Compu Material Quantity Unit TOTAL
Description Specs. Factor ted Compu- Say Unit Cost Cost
Volume ted (P) (P)
Concrete Class "A" (1:2:4) 0.48
Portland cement 40 kg. D.C. 5 bag 140.00 700.00
Sand D.C. 0.25 cu.m. 250.00 62.50
Gravel D.C. 0.5 cu.m. 350.00 175.00
G.I. Wire Gauge # 4 D.C. 1 roll 1,500.00 1,500.00
Gauge # 16 D.C. 2 kg. 43.00 86.00
RSB 12 mm x 6 m D.C. 10 pc. 77.00 770.00
16 mm x 6 m D.C. 8 pc. 103.00 824.00
Steel angle bar 1-1/2 x 1-1/2 D.C. 2 pc. 250.00 500.00
x 1/8 x 6 m
TOTAL 4,617.50
B. LABOUR COST
Particular Quantity Gang Activity Duration Rate Total
Description Manpower Required Output Compu- Say per Day Labour
ted Cost
(suspended)
Form & steel works
Supervisor 1 1 250.00 250.00
Laborer 6 1 150.00 900.00
Concrete casting
Supervisor 1 1 250.00 250.00
Laborer 6 1 150.00 900.00
Installation
Supervisor 1 3 250.00 750.00
Laborer 6 3 150.00 2,700.00
Instn. (submerged)
Supervisor 1 1 250.00 250.00
Laborer 6 1 150.00 900.00
TOTAL 6 6,900.00
KALAHI-CIDSS PROJECT 8 of 7
Detailed Estimates
A. MATERIALS
1) Computation of Quantities and Costing
Particular Compu Material Quantity Unit TOTAL
Description Specs. Factor ted Compu- Say Unit Cost Cost
Volume ted (P) (P)
Concrete Class "B" (1:2.5:5) 1.218
Portland cement 40 kg. 7.5 9.135 9.5 bag 140.00 1,330.00
Sand 0.5 0.609 0.7 cu.m. 250.00 175.00
Gravel 1 1.218 1.3 cu.m. 350.00 455.00
RSB 10 mm x 6 m D.C. 15 pc. 70.00 1,050.00
G.I. wire Gauge # 16 D.C. 1.5 kg. 43.00 64.50
Forms Re-use from reservoir construction
Common nails Re-use from reservoir construction
TOTAL 3,074.50
B. LABOUR COST
Particular Quantity Gang Activity Duration Rate Total
Description Manpower Required Output Compu- Say per Day Labour
ted Cost
Concrete 1.218
Supervisor 1 1.5 0.812 1 250.00 250.00
Mason 1 1 225.00 225.00
Laborer 4 1 150.00 600.00
Form, Steelwork,
Excavation
Supervisor 1 3 250.00 750.00
Carpenter 1 3 225.00 675.00
Laborer 4 3 150.00 1,800.00
TOTAL 4 4,300.00
KALAHI-CIDSS PROJECT 9 of 7
IMPLEMENTATION SCHEDULE WS
Noted:
Approved by: _____________________________ _____________________
BSPMC Chairperson Deputy Area Coordinator Regional Infrastructure Engineer
Note: Attach Material Records Sheet if physical accomplishment lags behind financial disbursements.
ANNEX 1
Design criteria
The pipeline must be designed to handle the maximum hour demand or Peak Flow (PF)=2.5ADD of the area to be served
Minimun pressure at the remotest end of the system should be 3.0 meters (Approx. 4.26 psi) and 7.0 meters at the
mainline
Maximum Velocity of flow in the pipes:
a. Main pipes… 3.0 meters per second
b. Distribution pipes… 1.5 meters per second
Water flow per tapstand ranges from 0.125 lps to 0.225 lps
Column Description:
Column Description
a Pipe section under consideration
b-c Node section under consideration
d Length of pipe section under consideration (meter)
e Number of household served
f Computed Peak Flow (liter per second)
g Difference in elevation between nodes under consideration (meter)
h Computed Pipe Diameter (mm), using the Darcy Weisbach Formula
i Nominal Diameter available in the market (mm)
j Headloss per 100 meters (refer to table 9.1 or 9.2)
k Actual Headloss
Formula:
Column f:
Where:
PF = Peak flow.
GRF = Growth rate factor (1+GR)^life span
N = Total number of household served by the pipe section.
PCWC = Per capita water consumption.
Column h:
HF = (8)(f)(L)(Q)^2/D^5(g)(pi)^2
D^5 =(8)(f)(L)(Q)^2/HF(g)(pi)^2
Where:
Simplifying:
Column j:
Column k:
The total headloss is less than the elevation head and therefore accept adjusted size but there are still critical nodes
Pipeline Section Household Peak Node Pipe Pipe Headloss Actual Hydraulic
Section Node Length Served Flow Elev. Diameter Diameter per Headloss Gradeline Available Total
from to Difference Option 100 m. Pipe Point Ground Head per Residual
(m) (no.) (lps) (m) (mm) (mm) (m) (m) Elevation Elevation Elevation section Head
a b c d e f g h i j k masl masl masl
a 1 2 500 10 ### 4 #VALUE! 31 0.4525 2.2625 700.00 701.74 699.50 1.7375 12.879
c 2 4 1200 16 ### 16 #VALUE! 31 1.036 12.432 704.00 707.57 708.00 3.568 11.1415
e 4 6 240 26 ### 13 #VALUE! 31 2.5655 6.1572 720.00 726.84 720.00 6.8428 7.5735
h 6 9 60 38 ### 2 #VALUE! 38 2.1155 1.2693 733.00 733.73 733.00 0.7307 0.7307
9 Reservoir 735.00 735.00 732.00 0 0
740.00
Reservoir
730.00
720.00
680.00
1 2 3 4 5
Contract I.D. :
no
of CALENDAR DAYS
Item No. DESCRIPTION wt % day 9 18 27 39
s
###
#########
######
######
######
######
######
### #########
######
I (a) Mobilization/Demobilization 1.27% 20
0 0 0 0 0
II (b) Project Billboard/ Signboard 0.74% 5
0 0 0 0
III (c ) Structure Excavation (Common Soil) 7.30% 4
0
IV (d) Embankment from Borrow 13.64% 1
0 0 0 0 0
V(e) Reinforcing Steel Bar, Grade 40 (minor structures) 34.98% 5
Quarterly Accomplishment 0.57% 0.83% 28.23% 28.30%
100%
Cumulative Quarterly Accomplishment 0.57% 1.40% 29.63% 57.93%
Quarterly Cash Flow 22,375.32 19,590.83 419,860.43 532,632.03
Cumulative Quarterly Cashflow 22,375.32 41,966.15 461,826.58 994,458.61
Contract I.D. :
P E R T C P M
Business Name : SKYSCRAPER CONSTRUCTION AND ENGINEERING SERVICES
Business Address: Brgy. 1, Buenavista, Marinduque
no
of CALENDAR DAYS
Item No. DESCRIPTION wt % day 9 18 27 39
s
I (a) Mobilization/Demobilization 1.27% 20
GENERAL REQUIREMENTS / MOBILIZATION and DEMOBILIZATION
II (b) Project Billboard/ Signboard 0.74% 5
Project Name:
Furnishing Labor, Materials and Equipment Rental for the CONSTRUCTION
OF BOX CULVERT, Brgy. Amoingon, Boac, Marinduque (Rebidding)
(Rebidding)
no of
CALENDAR DAYS
Item No. DESCRIPTION wt % days
11 22 33 45
0 0 0 0 0 0
Mobilization/Demobilization 1.27% 6
0
Project Billboard/ Signboard 0.74% 1
0 0 0 0 0 0
Structure Excavation (Common Soil) 7.30% 6
0 0 0 0 0 0 0 0
Embankment from Borrow 13.64% 8
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Reinforcing Steel Bar, Grade 40 (minor structures) 34.98% 18
####################################
Structural Concrete Class A (minor structures) 42.07% 12
Project Name: Furnishing Labor, Materials and Equipment Rental for the CONSTRUCTION
OF BOX CULVERT, Brgy. Amoingon, Boac, Marinduque (Rebidding)
(Rebidding)
P E R T C P M
Business Name : SKYSCRAPER CONSTRUCTION AND ENGINEERING SERVICES
Business Address: Brgy. 1, Buenavista, Marinduque
CALENDAR DAYS
no of
Item No. DESCRIPTION wt % days 11 22 33 45
a Mobilization/Demobilization 1.27% 6
GENERAL REQUIREMENTS / MOBILIZATION and DEMOBILIZATION
DELIVERY OF MATERIALS
f Structural Concrete Class A (minor structures) 42.07% 12
Project Name: Furnishing Labor, Materials and Equipment Rental for the CONSTRUCTION
OF BOX CULVERT, Brgy. Amoingon, Boac, Marinduque (Rebidding)
(Rebidding)
CALENDAR DAYS
Item No. DESCRIPTION
11 22 33 45
4 Vibratory Roller
6 Bar Cutter
7 Bar Bender
9 Minor Tools
MANPOWER SCHEDULE
Business Name : SKYSCRAPER CONSTRUCTION AND ENGINEERING SERVICES
Business Address: Brgy. 1, Buenavista, Marinduque
CALENDAR DAYS
Item No. DESCRIPTION
11 22 33 45
1 PROJECT MANAGER
2 PROJECT ENGINEER
3 MATERIALS ENGINEER
4 PROJECT SUPERVISOR
5 FOREMAN
6 SKILLED
7 UNSKILLED
Scope of Work %
Item No. Quantity Unit Unit Price Total
(Direct Cost) Wt.
SUMMARY OF ESTIMATES
Item No. DESCRIPTION AMOUNT
Summary of Work
Mobilization/Demobilization 12,626.00
Equipment Rental
Various Tools and Equipment 10,000.00 10,000.00
sub-total 10,000.00
Direct Labor
Foreman 1.00 day 1.00 500.00 500.00
Skilled 1.00 day 1.00 400.00 400.00
Unskilled 1.00 day 1.00 350.00 350.00
sub-total 1,250.00
Equipment Rental
Minor Tools (10% of Labor Cost) 125.00
sub-total 125.00
Materials
Good Lumber 45.00 bd.ft 70.00 3,150.00
4'x8' Tarpaulin 32.00 ft2
35.00 1,120.00
Assorted CW Nail 2.00 kg 100.00 200.00
sub-total 4,470.00
Direct Labor
Project Supervisor 2.00 days 1.00 600.00 1,200.00
Foreman 3.00 days 1.00 500.00 1,500.00
Skilled 4.00 days 3.00 400.00 4,800.00
Unskilled 6.00 days 4.00 350.00 8,400.00
sub-total 15,900.00
Equipment Rental
Backhoe (0.8 cu.m.) 20.00 hours 1,000.00 20,000.00
Dump Truck (10 cu.m.) 20.00 hours 1,000.00 20,000.00
Minor Tools (10% of Labor Cost) 1,590.00
sub-total 41,590.00
Direct Labor
Project Supervisor 3.00 days 1.00 600.00 1,800.00
Foreman 4.00 days 1.00 500.00 2,000.00
Skilled 7.00 days 3.00 400.00 8,400.00
Unskilled 8.00 days 4.00 350.00 11,200.00
sub-total 23,400.00
Equipment Rental
Dump Truck (10 cu.m.) 8.00 hours 1,000.00 8,000.00
Vibratory Roller 8.00 hours 1,000.00 8,000.00
Motorized Road Grader 8.00 hours 1,000.00 8,000.00
sub-total 24,000.00
Materials
Common Borrow (w/ 25% Shrinkage Factor) 120.00 cu.m. 500.00 60,000.00
sub-total 60,000.00
Direct Labor
Project Supervisor 8.00 days 1.00 600.00 4,800.00
Foreman 13.00 days 1.00 500.00 6,500.00
Skilled 15.00 days 3.00 400.00 18,000.00
Unskilled 18.00 days 4.00 350.00 25,200.00
sub-total 54,500.00
Equipment Rental
Bar Cutter 15.00 hours 500.00 7,500.00
Bar Bender 15.00 hours 500.00 7,500.00
Minor Tools (10% of Labor) 5,450.00
sub-total 20,450.00
Materials
RSB, Grade 40 (w/ 5% Shrinkage) 3,234.71 kg 60.00 194,082.60
Tie Wire (2% of RSB) 65.00 kg 100.00 6,500.00
sub-total 200,582.60
Direct Labor
Project Supervisor 5.00 days 1.00 600.00 3,000.00
Foreman 6.00 days 1.00 500.00 3,000.00
Skilled 10.00 days 3.00 400.00 12,000.00
Unskilled 12.00 days 4.00 350.00 16,800.00
sub-total 34,800.00
Equipment Rental
Water Truck (1000 gal) 12.00 hours 1,000.00 12,000.00
One bagger Mixer 12.00 hours 800.00 9,600.00
Minor Tools (10% of Labor) 3,480.00
sub-total 25,080.00
Materials
Ordinary Gravel 38.00 cu.m 1,200.00 45,600.00
Ordinary Sand 19.00 cu.m 1,200.00 22,800.00
Cement 486.00 bags 280.00 136,080.00
Steel Wire Mesh 1.00 ln.m. 1,000.00 1,000.00
Assorted CW Nail 8.00 kg 100.00 800.00
Weep Hole (75mmø) 1.00 ln.m. 200.00 200.00
Phenolic Board 35.00 pcs 1,000.00 35,000.00
Lumber - 4 uses 600.00 bd.ft. 50.00 30,000.00
sub-total 271,480.00
Project Name: Furnishing Labor, Materials and Equipment Rental for the CONSTRUCTION
OF BOX CULVERT, Brgy. Amoingon, Boac, Marinduque (Rebidding)
(Rebidding)
SUMMARY SHEET
DESCRIPTION UNIT PRICE / RENTAL
MATERIALS
EQUIPMENT
Minor Tools
LABOR
SCOPE OF WORK:
Submitted by: