Upda Set 3 Civil
Upda Set 3 Civil
Question # 02
What is the type of bond guarantees that if contractor goes
broke on a project, the surety will pay the necessary amount to
complete the job ?
A. Bed Bond.
B. Performance Bond.
C. Acceptance Bond
D. Payment Bond
1
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 03
When a T-Beam span over several supports continuously then
the beam at mid span should be designed as ?
A. Simply Supported.
B. Flanged Section.
C. Rectangular Section
D. Pre stressed Beam
Question # 04
Sand drains are used to ?
A. Help in Compacting of Sand Layers.
B. Increase Bearing Capacity of Dry Backfills.
C. Enhance the Permeability of Rock Masses
D. Accelerate the Consolidation Process Decreasing in Soil Volume
2
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 05
A formal CPM analysis for a project shows the planned costs to
date are $ 85,000 and accounting reports charges are $ 85,000
for work value of $ 70,000, the cost and schedule status for the
project are most nearly as?
A. ahead of schedule and over budget.
B. ahead of schedule and under budget.
C. behind schedule and over budget.
D. behind schedule and under budget
Question # 06
3
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 07
Consider the following statements
Entrainment of air in concrete is done so as to ?
1. Increase the workability.
2. Increase the strength.
3. Increase the resistance to freezing and thawing.
Which of the above statements is / are correct – select one :-
A. 1, 2 and 3
B. 1 only
C. 1 and 3 only
D. 3 only
4
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 08
The advantage of a Design and Build contractual arrangement is
(are) ?
A. Reduce project time.
B. Non adversary relationship among participants.
C. Known project cost before construction.
D. All of the above
Question # 09
5
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 10
Question # 11
If D is the duration, ES and EF are the earliest start and finish, LS
and LF are latest start and latest finish time, then the following
relation holds good
A. EF = ES + D
B. LS = LF – D
C. LF = LS + D
D. D = EF – ES
E. All Above 6
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 12
The goals of a quality management system ?
A. The ability of the product and services to meet customer expectations
can be
understood and evaluated on a continual basis
B. The effectiveness of systematic action can be measured on a regular
basis.
C. The quality of the products or services related to customer needs can
be continuously improved.
D. All the above
Question # 13
Contractor’s claims either extra cost or extra time should be
notice within :-
A. 45 days
B. 21 days
C. 14 days
D. 28 days
7
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 14
What are the main reasons for conducting pull-out tests for
soil nails?
A. To check if there is any slippage or creep occurrence.
B. To check compaction of the soil
C. To measure bearing capacity of the soil
D. All in the above
Question # 15
Increased water – cement ratio {W/C} in concrete mix :-
A. Results in decrease strength
B. Reduce workability
C. Decrease hydration
D. Reduce the slump value
8
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 16
Load path is one of the key considerations in structural design, and it is
about how to bring the load acting on the building
A. to the building façade.
B. to the ground / foundation.
C. to the columns.
D. to the beams
Question # 17
9
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 18
10
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 19
11
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 20
A tower crane with a 7000 Ib Counterweigh {A} is used to pick up {Load} with 15 ft.
boom extension as shown. The boom have weight of 1000 Ib {CG} shown in the figure.
The tower weigh is 3000Ib and the footing {6ft x 6 ft}weighs is 20,000 Ib. The
maximum load that the crane can lift without overturning is most near :
A. 7.50 kips
B. 10.75 kips
C. 13.25 kips
D. 11.00 kips
12
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 21
A precast wall panel 20 ft. long (perpendicular to drawing plane) x 14 ft. high x 4 Inches
thick is being tilted into position using single horizontal cable connected to the top of
the panel as shown in the figure below. The unit weight of the wall is 80 ib/ft³. At the
position showing the tension in the cable (Kips) is most nearly :-
A. 2.2
B. 3.6
C. 5.5
D. 4.8
13
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 22
The maximum moment in the beam is
A. 4200 N m
B. 5600 N m
C. 6400 N m
D. 6800 N m
Question # 23
A. 5 KN
B. 3 KN
C. 7 KN
D. 4 KN
14
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 24
15
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 25
Question # 26
16
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 27
17
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Hands Up !!!!
18
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # Correct Answer
1 B
2 D
3 B
4 D
5 C
6 A
7 C
Answers 8
9
D
E
10 B
11 E
12 D
13 D
14 A
15 B
16 B
17 C
18 D
19 D
20 D
21 A
22 B
23 A
24 A
25 D
26 C
27 D
19
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Exam # 02 (60 Minutes)
1
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
2
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
3
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 01
Question 01.1 –
What are the internal forces in section {1-1}
{axial, shear & moment} if the section is 2
m form the free end ?
A. 10, 10 & 20
B. 10, zero & 20
C. zero, 10 & 20
D. zero, zero & 20
Question 02.2 –
What are the internal forces in section {2-2}
{axial, shear & moment} if the section is 2
m form the free end ?
A. zero, zero & 20
B. zero, 10 & 20
C. 10, zero & 20
D. 10, 10 & 20
4
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question 01.3–
What are the internal forces in section {3-3}
{axial, shear & moment} if the section is 2
m form point {C} ?
A. 10, zero & 40
B. zero, 10 & 40
C. 10, 10 & 40
D. zero, zero & 40
Question 01.4 –
What are the internal forces in section {4-4}
{axial, shear & moment} if the section is 2
m form the fixed end ?
A. zero, zero & 80
B. 20, 20 & 80
C. 20, zero & 80
D. zero, 20 & 80
5
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question 01.5 –
What is the maximum design wind load which
keep the structure stable ?
A. 2.25 t/m
B. 1.65 t/m
C. 1.90 t/m
D. 5.35 t/m
6
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 02
In the beam loaded as shown what is
location of which zero shear force is
located ?
A. 10 ft from left support
B. 14 ft from left support
C. 17.5 from left support
D. 15 ft from left support
Question # 03
What is the maximum moment in the
shown loaded beam.
A. 239 kips ft
B. 325 kips ft
C. 288 kips ft
D. 128 kips ft
7
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 04
The frame shown in the figure have a
rigid support at {A} and hinged support at
{D} What is the most nearly reaction at
support {D} :
A. 20 kips
B. 32 kips
C. 40 kips
D. 36 kips
Question # 05
In the frame shown in the figure what is
the moment at {C} if it {C} is in the
middle of {BD} :
A. - 160 KN m
B. - 40 KN m
C. +160 KN m
D. + 40 KN m
8
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 06
What are the internal forces {axial, shear
& moment} the section {1-1}
A. zero, 1.66, 4.98
B. 1.66, zero & 6.68
C. zero, 1.66 & 6.68
D. zero, zero & 4.98
Question # 07
What is the force in member
{AB} ?
A. +188.87 kips
B. - 166.67 kips
C. + 166.67 kips
D. - 188.87 kips
9
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 08
Determine all the forces in all
members for the truss shown
in the figure ?
Question # 09
Determine all the forces in all
members for the truss shown
in the figure ?
10
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 10
Determine all the forces in all
members for the truss shown
in the figure ?
Question # 11
Determine all the forces in
all members for the truss
shown in the figure ?
Answers 11
11
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 12
Determine all the forces in
all members for the truss
shown in the figure ?
Answers # 12
Question # 13
Determine all the forces in
all members for the truss
shown in the figure ?
Answers # 13
12
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 14
Answers # 14
13
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 15
14
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 16
Question # 17
While working in final stages of a job, You noticed that a small clause in the
contract has been violated accidently, What should you do ?
A. Tell the client about the discrepancy and ask him/her/them what to do ?
B. Look for a loophole in the contract that would enable you to avoid re-doing the work.
C. Don’t worry about it, Let your boss or the client worry about it later, If it’s important…
they will address the subject.
D. Fire the person who caused the contract.
15
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 18
Value engineering can be described as ___________________
A. Reducing cost by reducing quality
B. Getting the best value for the least cost
C. Reducing scope to achieve budget
D. Reorganizing the project team to achieve the greatest efficiency
Question # 19
The intersection of WBS and OBS is the _______
A. Responsibility matrix
B. Functional matrix
C. Cost account
D. Sub-deliverable
E. Project overlap
Question # 20
The lowest element in hierarchical breakdown of WBS is_______
A. A deliverable
B. A work package
C. A cost account
D. A lowest sub-deliverable
E. An object
F. None of above
16
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 21
Use AOA method and define the total project duration :-
A. 9 Days
B. 8 Days
C. 10 Days
D. 11 Days
17
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 22
Using the PDM what is total float for activity {D}
A. 2 Days
B. 3 Days
C. 4 Days
D. 5 Days
18
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 23
Use AOA method and define the total project duration :-
A. 11 Days
B. 12 Days
C. 13 Days
D. 14 Days
19
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 24
The Work Breakdown Structure can BEST be thought of as an
effective aid for __________ communications.
A. Team
B. Project manager
C. Customer
D. Stakeholder
Question # 25
During project executing, a team member comes to project
manager because he is not sure of what work needs to be
accomplished on the project. Which of the following documents
contains the detailed description of work packages?
A. WBS dictionary.
B. Activity list.
C. Schedule baseline.
D. Scope definitions.
20
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 26
A detailed project schedule can be created only after creating
the:
A. Project budget.
B. Work breakdown structure.
C. Scope baseline
D. Detailed risk assessment.
Question # 27
You are a civil engineer who has never managed a work package
in project before. It would be BEST in this situation to rely on
_____ during planning in order to improve your chance of
success.
A) Your intuition and training
B) Stakeholder analysis
C) Historical information
D) Configuration management
21
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Hands Up !!!!
22
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # Correct Answer
1 As Shown in the Class
2 D
3 C
4 A
Answers 5 B
6 C
7 B
8 will solve in the Class
9 will solve in the Class
10 will solve in the Class
11 Given
12 Given
13 Given
14 Given
15 will solve in the Class
16 D
17 A { Will Discuss Again}
18 C
19 A
20 B
21 D
22 C
23 D
24 D
25 A
26 C
27 C
23
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Project Management Fondations
Introduction, Lifecycle & Organization
Dr. Akram Saad
PhD,MBA,PMP,CCP,MRICS
Segment
Two
Project Management Lifecycle
Segment
Three Project Organization & Key Roles
• Definition:
• “A project is a temporary endeavor undertaken to
create a unique product, service or result.”
• Individual Project:
• A temporary endeavor undertaken to create a unique
product, service or result
• Program:
– A collection of projects, sub-programs or other work
that are managed in a coordinated fashion in support
of a portfolio
• Portfolio:
– A collection of projects, programs, sub-portfolios and
operations managed as a group to achieve strategic
benefits
• Definition:
• “The application of knowledge, skills, tools and
techniques to project activities in order to meet
the defined project requirements.”
- OR -
• Scope
• Quality
• Schedule
• Budget
• Resources Changing any one factor will also change at
least one other factor…
• Risks/Issues
For example, shortening the Schedule will
likely increase cost or reduce scope/quality
Starting the Project Organizing and Preparing Carrying Out The Work Closing the Project
INITIATING
G
NNI
C LO
NG
CO
ING
N
T
TR
CU
O
X E
LL
E
IN
TIME
© Think For A Change, LLC.
Project Management Lifecycle
• Definition:
• “The Project Manager is the person assigned by
the performing organization to lead the team that
is responsible for achieving the project objectives.”
• Project Stakeholders
• Individuals, groups or organizations who may affect, be affected by, or
perceive itself to be affected by a decision, activity or outcome of a
project
• Stakeholders can take an active or passive role in guiding or
influencing the scope and outcome of the project effort
• Examples of “Stakeholders”:
• Project Team Resources (including leadership)
• Project Sponsor
• Customers/Users (internal and/or external)
• Business Partners
• Organizational Groups
• Functional Managers
• Government Regulators
• Consultants
• Project Teams
• The Project Team typically includes the project manager and the group
of individuals who act together in performing the work of the project
to achieve its objectives
• Traditional Project Team Roles:
• Project Management Staff
• Project Manager, Project Coordinator, PMO Staff, etc.
• Project Staff
• Tactical resources who identify and execute upon the tasks to be completed
• Subject Matter Experts (SMEs)
• Finance, Legal, HR, etc.
• Business Partners
• Line of business managers or individual contributors
• Project team members can either be “dedicated” or “shared” to
the Project
© Think For A Change, LLC.
Project Control
• Project Authority
• The oversight function aligned with the organization’s governance
model and the project life cycle and/or process methodology
• This framework provides the Project Team:
• Success and deliverable acceptance criteria
• Issue management and escalation protocols
• Communications management protocols
• Project decision-making processes
• Alignment of projects with corresponding programs or portfolios
• Stage-gate or phased review process management
• Change management review and approval protocols
• Internal stakeholder alignment
• Definition:
• “A management structure that standardizes the
project-related governance processes and
facilitates the sharing of resources,
methodologies, tools and techniques”
Question 1:
• How are projects
traditionally organized?
Question 1: Answer:
• How are projects • Individual Projects
traditionally organized? • Programs
• Portfolios
Question 2:
• What are the three (3)
common project
organizational
structures?
Question 2: Answer:
• What are the three (3) • Functional
common project • Projectized
organizational • Matrix
structures?
Question 3:
• Project team members
can either be ______ or
__________ to the
project?
Question 3: Answer:
• Project team members • Project team members
can either be ______ or can either be DEDICATED
__________ to the or SHARED to the
project? project?
Question 4:
• True or False? Projects end in
only one of two ways:
1. The project’s objectives
have been reached
2. The project is terminated
because its objectives will
not or cannot be met, or
when the need for the
project no longer exists.
Question 4: Answer:
• True or False? Projects end in • TRUE
only one of two ways:
1. The project’s objectives
have been reached
2. The project is terminated
because its objectives will
not or cannot be met, or
when the need for the
project no longer exists.
Question 5:
• The primary function of
a PMO is to support
_______________?
Question 5: Answer:
• The primary function of • Project Managers
a PMO is to support
_______________?
Pass Criteria =
27/27 = 100%
1
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 01
Separation of coarse aggregates from mortar during
transportation, is known
A. bleeding
B. creeping
C. segregation
D. shrinkage
E. none of these.
Question # 02
Grading of sand causes great variation in
A. workability of concrete
B. strength of concrete
C. durability of concrete
D. handing and placing of concrete
E. all the above.
2
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 03
Shrinkage in concrete can be reduced by using
A. low water cement ratio
B. less cement in the concrete
C. proper concrete mix
D. Pre saturated aggregates
E. all the above.
Question # 04
Too wet concrete may cause
A. weakness of concrete
B. excessive laitance
C. segregation
D. lower density
E. all the above.
3
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 05
Hardening of cement occurs at
A. rapid rate during the first few days and afterwards it continues to
increase at a decreased rate
B. slow rate during the first few days and afterwards it continues to increase
at a rapid rate
C .uniform rate throughout its age
D. none of these.
Question # 06
Pick up the correct statement from the following:
A. Lime in excess, causes the cement to expand and disintegrate
B. Silica in excess, causes the cement to set slowly
C. Alumina in excess, reduces the strength of the cement
D. Magnesium oxide in excess, remains in free state and makes the
cement unsound
E. All the above.
4
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 07
Pick up the correct statement from the following
A. Higher workability indicates unexpected increase in the moisture
content
B. Higher workability indicates deficiency of sand
C. If the concrete mix is dry, the slump is zero
D. Concrete mix having zero slump, is unsuitable for high strength.
E. All the above.
Question # 08
You are asked to construct a massive dam, the type of cement
you will use, is
A. ordinary Portland cement
B. rapid hardening cement
C. low heat cement
D. blast furnace slag cement
E. white cement
5
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 09
Water required per bag of cement, is
A. 7 kg
B. 14 kg
C. 21 kg
D. 28 kg
E. 35 kg
Question # 10
The process of hardening the concrete by keeping its surface
moist is known
A. placing
B. wetting
C. curing
D. compacting
E. none of these.
6
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 11
Workability of concrete for a given water content is good if the
aggregates, are
A. rounded aggregate
B. irregular aggregate
C. angular aggregate
D. flaky aggregates.
Question # 12
For compacting plain concrete road surface of thickness less
than 20 cm, we use
A. internal vibrator
B. screed vibrator
C. form vibrator
D. none of these
7
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 13
Pick up the correct statement from the following:
A. Construction joints are necessarily planned for their locations
B. Expansion joints are provided to accommodate thermal expansion
C. Construction joints are provided to control shrinkage cracks
D. Expansion joints need not be provided in foundation concrete
E. All the above.
Question # 14
Process of keeping Concrete moist for certain period after
casting is:
A - Finishing of Concrete
B - Curing of Concrete
C - Placing of Concrete
D - None of the above
8
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 15
Question # 16
Weight of reinforcement concrete in kg / m3 is:
A – 1500
B – 1600
C – 2000
D – 2400
9
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 17
Strength of concrete depends on:
A- Quality of water
B- Quality of aggregates
C- Quantity of cement
D- W / C ratio
E- All of the above
Question # 18
The compaction of concrete, improves
A. density
B. strength
C. durability
D. all the above.
10
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 19
Segregation is responsible for
A. honey-combed concrete
B. porous layers in concrete
C. surface scaling in concrete
D. sand streaks in concrete
E. all the above.
Question # 20
Addition of pozzolana to cement
A. decreases workability
B. increases strength
C. increases heat of hydration
D. decreases curing time
E. none of these.
11
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 21
Concrete gains strength due to
A. chemical reaction of cement with sand and coarse aggregates
B. evaporation of water from concrete
C. hydration of cement
D. All the above.
Question # 22
Expansion joints are provided if the length of concrete
structures exceeds
A. 10 m
B. 15 m
C. 25 m
D. 35 m
E. 45 m
12
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 23
Workability improved by adding
A. fly ash
B. hydrated lime
C. calcium chloride
D. bentonite
E. all the above.
Question # 24
If the slump of a concrete mix is 60 mm, its workability is
A. very low
B. low
C. medium
D. high
E. none of these.
13
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 25
Question # 26
Why steel reinforcement used in RCC structures
A. Steel gives high strength
B. The Co efficient of linear expansion of concrete and steel is same.
C. Easy to use and formed
D. Cost factors
14
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 27
Concrete slump tests, Steel Reinforcement sampling tests and
others materials tests for :-
A. To achieve high performance
B. For control quality
C. For achieving quality assurance plan
D. All above
15
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Hands Up !!!!
16
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # Correct Answer
1 C
2 E
3 E
4 E
5 D
6 E
7 E
8 C
Answers 9 E
10 C
11 A
12 B
13 E
14 B
15 A
16 D
17 E
18 D
19 E
20 B
21 C
22 E
23 E
24 C
25 D
26 B
27 B
17
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Time Management
6
4
Series 1
3
Series 2
2 Series 3
0
Category 1 Category 2 Category 3 Category 4
Green International
Green International Email:[email protected]
Email: [email protected] www.greenmtc-intl.com
www.greenmtc-intl.com ©2010
©2010 AllAll Rights
Rights Reserved
Reserved
Arrow Diagramming Method (ADM)
Precedence Diagramming Method
(PDM)
• The precedence diagramming method (PDM) is
what most management software programs use
to do activity sequencing.
• Precedence diagrams use boxes or circles to
represent the activities (called nodes).
• The nodes are connected with arrows showing
the dependencies between the activities. It is also
called activity on node (AON)
• PDM includes 4 types of dependencies
or precedence relationships.
PDM
The nodes are sketched large enough to include information about the activity. It is
common to show the following information for an activity :
activity description.
activity ID
activity duration(OD)
activity schedule dates
Precedence Diagramming Method
Precedence Diagraming Method
ES (early start):
EF (early finish) : earliest point in time that an activity can
finish based on the network relationships.
LS (late start): latest point in time that an activity must
start in order to avoid delaying the project’s completion.
LF (late finish): latest point in time that an activity
must finish in order to avoid delaying the project’s
completion.
activity float values: Total float is the amount of time that the completion of an
activity can be delayed without delaying the project’s completion.
Total float = LF – EF (or) LS – ES .
Precedence Network Activity
List
Stress is the internal resistance offered by the body per unit area. Stress is represented as force
per unit area. Typical units of stress are N/m2, ksi and MPa. There are two primary types of
stresses: normal stress and shear stress. Normal stress,, is calculated when the force is normal
to the surface area; whereas the shear stress, is calculated when the force is parallel to the
surface area.
Pparallel _ to _ area
A
Linear strain (normal strain, longitudinal strain, axial strain), , is a change in length per unit
length. Linear strain has no units. Shear strain, is an angular deformation resulting from shear
stress. Shear strain may be presented in units of radians, percent, or no units at all.
L
parallel _ to _ area
tan [ in radians]
Height
Hooke‘s law is a simple mathematical relationship between elastic stress and strain: stress is
proportional to strain. For normal stress, the constant of proportionality is the modulus of
elasticity (Young’s Modulus), E.
E
The deformation, , of an axially loaded member of original length L can be derived from Hooke’s
law. Tension loading is considered to be positive, compressive loading is negative. The sign of
the deformation will be the same as the sign of the loading.
PL
L L
E AE
This expression for axial deformation assumes that the linear strain is proportional to the
normal stress
E and that the cross-sectional area is constant.
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 62
Quick Refresher Guide Strength of Material
When an axial member has distinct sections differing in cross-sectional area or composition,
superposition is used to calculate the total deformation as the sum of individual deformations.
PL L
P
AE AE
When one of the variables (e.g., A), varies continuously along the length,
PdL dL
P
AE AE
Lf L
Hooke’s law may also be applied to a plane element in pure shear. For such an element, the shear
stress is linearly related to the shear strain, by the shear modulus (also known as the modulus of
rigidity), G.
G
The relationship between shearing deformation, s and applied shearing force, V is then
expressed by
VL
s
AG
Actual rupture
strength
Rupture
strength
Yield point
Elastic limit
Proportional limit
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 63
Quick Refresher Guide Strength of Material
Proportional Limit: It is the point on the stress strain curve up to which stress is proportional to
strain.
Elastic Limit: It is the point on the stress strain curve up to which material will return to its
original shape when unloaded.
Yield Point: It is the point on the stress strain curve at which there is an appreciable elongation
or yielding of the material without any corresponding increase of load; indeed the load actually
may decrease while the yielding occurs.
Poisson’s ratio, , is a constant that relates the lateral strain to the axial strain for axially loaded
members.
lateral
axial
Theoretically, Poisson’s ratio could vary from 0 to 0.5, but typical values are 0.33 for aluminum
and 0.3 for steel and maximum value of 0.5 for rubber.
Poisson’s ratio permits us to extend Hooke’s law of uniaxial stress to the case of biaxial stress.
Thus if an element is subjected simultaneously to tensile stresses in x and y direction, the strain
in the x direction due to tensile stress x is x/E. Simultaneously the tensile stress y will
produce lateral contraction in the x direction of the amount y/E, so the resultant unit
deformation or strain in the x direction will be
x y
x
E E
y x
y
E E
Hooke’s law can be further extended for three-dimensional stress-strain relationships and
written in terms of the three elastic constants, E, G, and . The following equations can be used to
find the strains caused due to simultaneous action of triaxial tensile stresses:
x
1
E
x y z
y
1
E
y z x
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 64
Quick Refresher Guide Strength of Material
z
1
E
z x y
xy
xy
G
yz
yz
G
zx
zx
G
For an elastic isotropic material, the modulus of elasticity E, shear modulus G, and Poisson’s
ratio are related by
E
G
21
E 2G1
The bulk modulus (K) describes volumetric elasticity, or the tendency of an object's volume to
deform when under pressure; it is defined as volumetric stress over volumetric strain, and is the
inverse of compressibility. The bulk modulus is an extension of Young's modulus to three
dimensions.
For an elastic, isotropic material, the modulus of elasticity E, bulk modulus K, and Poisson’s ratio
are related by
E 3K1 2
L L.α.t
Where, L is the length, α (/oC) is the coefficient of linear expansion, and t (oC) is the
temperature change.
ϵ= αt
If a temperature deformation is permitted to occur freely no load or the stress will be induced in
the structure. But in some cases it is not possible to permit these temperature deformations,
which results in creation of internal forces that resist them. The stresses caused by these
internal forces are known as thermal stresses.
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 65
Quick Refresher Guide Strength of Material
When the temperature deformation is prevented, thermal stress developed due to temperature
change can be given as:
σ E.α.t
Cylindrical shells
F 0 : 2 (2 rt ) p(2 r ) 0
2
x
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 66
Quick Refresher Guide Strength of Material
Spherical shells
F 0 : 2 (2 rt ) p(2 r ) 0
2
x
pr
1 2
Hoop stress = longitudinal stress = 2t
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 67
Quick Refresher Guide Strength of Material
The shear force, V at a section of a beam is the sum of all vertical forces acting on the beam
between that section and any one of its ends. It has units of Newtons, pounds, kips, etc. Shear
force is not the same as shear stress, since the area of the object is not considered.
The direction (i.e., to the left or right of the section) in which the summation proceeds is not
important. Since the values of shear will differ only in sign for summation to the left and right
ends, the direction that results in the minimum no. of calculations should be selected.
V F i
sec tion _ to
one _ end
Shear is positive when there is a net upward force to the left of a section, and it is negative when
there is a net downward force to the left of the section.
The bending moment, M, at a section of a beam is the algebraic sum of all moments and couples
located between the section and any one of its ends.
M F d i i
sec tion _ to
C i
sec tion _ to
one _ end one _ end
Bending moments in a beam are positive when the upper surface of the beam is in compression
and the lower surface is in tension. Positive moments cause lengthening of the lower surface and
shortening of the upper surface. A useful image with which to remember this convention is to
imagine the beam “smiling” when the moment is positive.
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 68
Quick Refresher Guide Strength of Material
The change in magnitude of the shear at any point is equal to the integral of the load function,
w(x), or the area under the load diagram up to that point.
x2
V2 V1 wxdx
x1
dV x
wx
dx
The change in magnitude of the moment at any point is equal to the integral of the shear
function, or the area under the shear diagram up to that point.
x2
M 2 M1 V xdx
x1
dM x
V x
dx
Both shear force and bending moment can be described mathematically for simple loadings by
the preceding equations, but the formulas become discontinuous as the loadings become more
complex. It is more convenient to describe complex shear and moment functions graphically.
Graphs of shear and moment as functions of position along the beam are known as shear force
and bending moment diagrams.
The following guidelines and conventions should be observed when constructing a shear
diagram.
The shear at any section is equal to the sum of the loads and reactions from the section to
the left end.
The magnitude of the shear at any section is equal to the slope of the moment function at
that section.
Loads and reactions to the left of the section acting upward are positive
The shear diagram is straight and sloping for uniformly distributed loads.
The shear diagram is straight and horizontal between concentrated loads.
The shear is undefined at points of concentrated loads.
The following guidelines and conventions should be observed when constructing a bending
moment diagram. By convention, the moment diagram is drawn on the compression side of the
beam.
The moment at any section is equal to the sum of the moments and couples from the
section to the left end.
The change in magnitude of the moment at any section is the integral of the shear
diagram, or the area under the shear diagram. A concentrated moment will produce a
jump or discontinuity in the moment diagram.
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 69
Quick Refresher Guide Strength of Material
The maximum or minimum moment occurs when the shear is either zero or changes its
sign.
The moment diagram is parabolic and is curved downward for downward uniformly
distributed loads.
Note:
If the external load is not at right angles to the axis of the beam, the loading can be resolved
axially and transversely to the beam
If there is any internal hinge in beam , bending moment will be zero at hinge point.
Variation of S.F. and B.M. for different loadings on spans of beams:
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 70
Quick Refresher Guide Strength of Material
For positive bending moment, the lower surface of the beam experiences tensile stress while the
upper surface of the beam experiences compressive stress. The bending stress distribution
passes through zero at the centroid, or neutral axis, of the cross section. The distance from the
neutral axis is y; and the distance from the neutral axis to the extreme fiber (i.e., the top or
bottom surface most distant from the neutral axis) is c.
Bending stress varies with location (depth) within the beam. It is zero at the neutral axis, and
increases linearly with distance from the neutral axis, as predicted by Equation,
My
b
I
In the above equation, I is the centroidal area moment of inertia of the beam. The negative sign
in the equation, required by the convention that compression is negative, is commonly omitted.
Since the maximum stress will govern the design, y can be set equal to c to obtain the extreme
fiber stress.
Mc
b,max
I
This equation shows that the maximum bending stress will occur at the section where the
moment is maximum. For standard structural shapes, I and c are fixed. Therefore, for design, the
elastic section modulus S, is often used.
I
S
c
M
b
S
For a rectangular b x h section, the centroidal moment of inertia and section modulus are
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 71
Quick Refresher Guide Strength of Material
bh3 bh 2
I Srec tan gular
12 6
Also, the strain in any fiber varies directly with its location y from the neutral axis and can be
found by the equation
y b y
b Or,
R E R
The transverse sections which are plane and normal before bending remain plane and
normal to the longitudinal fibres after bending (Bernoulli’s Assumption).
Material is homogeneous, isotropic and obeys Hook’s Law and limits of eccentricity are not
exceeded.
Every layer is free to expand or contract.
Modulus of elasticity has same value for tension and compression.
The beam is subjected to pure bending and therefore bends in an arc of a circle.
Points to remember:
Neutral Layer: The layer which does not undergo any change in length (N.A.)
Neutral axis: Line of intersection of Neutral Layer with plane of cross section. It passes through
C.G. of cross section. At this axis the strain changes its sign.
M/I=/y=E/R
Section Modulus ( I/c): It represents the strength of the section. Greater the value of ‘ ’,
stronger will be the section.
The shear stresses in a vertical section of a beam consist of both horizontal and transverse
(vertical) shear stresses.
The exact value of shear stress is dependent on the location, y, within the depth of the beam. The
shear stress distribution is given by equation shown below. The shear stress is zero at the top
and bottom surfaces of the beam. For a regular shaped beam, the shear stress is maximum at the
neutral axis
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 72
Quick Refresher Guide Strength of Material
QV
xy
Ib
In the above equation, I is the area moment of inertia, and b is the width or thickness of the beam
at the depth y within the beam where the shear stress is to be found. The first (or statical)
moment of the area of the beam with respect to the neutral axis, Q, is defined by,
c
Q ydA
y1
For rectangular beams, dA bdy. Then, the moment of the area A’ above 1ayer y is equa1 to the
product of the area and the distance from the centroidal axis to the centroid of the area.
Q y ' A'
For a rectangular beam, the equation for max, can be simplified. The maximum shear stress is 50
percent higher than the average shear stress.
3V 3V
max, rec tan gular 1.5 avg
2A 2bh
For a beam with a circular cross section, the maximum shear stress is
4V 4V 4
max,circular avg
3A 3r 2
3
For a steel beam with web thickness tweb and depth d, the web shear stress is approximated by
V V
avg
Aweb dtweb
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 73
Quick Refresher Guide Strength of Material
A composite structure is one in which two or more different materials are used. Each material
carries part of the applied load. Examples of composite structure include steel-reinforced
concrete and timber beams with bolted-on steel plates.
Most simple composite structures can be analyzed using the method of consistent deformations,
also known as the transformation method. This method assumes that the strains are the same in
both materials at the interface between them. Although the strains are the same, the stresses in
the two adjacent materials are not equal, since stresses are proportional to the modulus of
elasticity.
The transformation method starts by determining the modulus of elasticity for each (usually two
in number) of the materials in the composite beam and then calculating the modular ratio, n.
Eweaker is the smaller modulus of elasticity.
E
n
E wea ker
The area of the stronger material is increased by a factor of n. The transformed area is used to
calculate the transformed composite area, Ac,t , or transformed moment of inertia, Ic,t. For
compression and tension members, the stresses in the weaker and stronger materials are
F
wea ker
Ac,t
nF
stronger
Ac,t
For beams in bending, the bending stresses in the weaker and stronger materials are
Mcwea ker
wea ker
I c ,t
nMcstronger
stronger
I c,t
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 74
Quick Refresher Guide Strength of Material
The curvature of a beam caused by a bending moment is given by Eq. (1), where is the radius
of curvature, c is the largest distance from the neutral axis of the beam, and max is the maximum
longitudinal normal strain in the beam.
1 max M d 2 y d
2 ------- (1)
c EI dx dx
c ------- (2)
max
Using the preceding relationships, the deflection and slope of a loaded beam are related to the
moment M(x), shear V(x), and load w(x) by Eqs. (3) through (7).
dy
y' slope ------- (4)
dx
d 2 y Mx
y'' ------- (5)
dx2 EI
d 3 y Vx
y''' ------- (6)
dx3 EI
d 4 y wx
y'''' ------- (7)
dx 4 EI
If the moment function, M(x), is known for a section of the beam, the deflection at any point on
that section can be found from Eq. (8). The constants of integration are determined from the
beam boundary conditions in the table shown below.
Simple Support 0 0
Built-in Support 0 0
Free end 0 0 0
Hinge 0
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 75
Quick Refresher Guide Strength of Material
When multiple loads act simultaneously on a beam, all of the loads contribute to deflection. The
principle of superposition permits the deflections at a point to be calculated as the sum of the
deflections from each individual load acting individually. Superposition can also be used to
calculate the shear and moment at a point and to draw the shear and moment diagrams. This
principle is valid as long as the normal stress and strain are related by the modulus of elasticity,
E. Generally this is true when the deflections are not excessive and all stresses are kept below
the yield point of the beam material.
Points to be remembered
Theorem 1: The angle between tangents drawn at any two points on the deflected curve is equal
to the area of M / EI diagram between the two points.
∫ / / . A = area of B.M.D.
Theorem 2: The intercept on a vertical line made by two tangents drawn at the two points on the
deflected curve, is equal to the moment of M / EI diagram between the two points about the
vertical line.
= distance of C.G. of B.M.D.
e.g,: (Suitable for cantilevers) – from objective point of view.
A L B
x xL , x xLx
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 76
Quick Refresher Guide Strength of Material
Consider cantilever beam AB. Let ‘C’ be an intermediate point. Then the deflection at ‘C’ due to a
point load ‘P’ at B say , is equal to deflection at ‘B’ due to a point load ‘P’ at C i.e.,
A C B
∴
W
B
A
Slope
Maximum Deflection
W
a b
C B
A
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 77
Quick Refresher Guide Strength of Material
Slope
Maximum Deflection (3 )
w/unit run
B
A
Slope
Maximum Deflection
SL No. 4 Cantilever subjected to uniformly distributed load up to a certain length from fixed end
w/unit run
C B
A
-
a
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 78
Quick Refresher Guide Strength of Material
Slope ( ) where W =
Maximum Deflection * ( )+ * , ( -+
SL No. 5 Cantilever subjected to uniformly distributed load up to a certain length from free end
w/unit run
a ( )
B
A
Slope ( )
Maximum Deflection * (3 4 )+
B
A
Slope
Maximum Deflection
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 79
Quick Refresher Guide Strength of Material
/ run
B
A
Slope
Maximum Deflection
/ /
C
A B
Slope
Maximum Deflection ( )
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 80
Quick Refresher Guide Strength of Material
C
A B
( )
Slope
( )
/
( )
Maximum Deflection
√
. √ /
w/unit run
B
A
Slope ( )
( )
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 81
Quick Refresher Guide Strength of Material
Maximum Deflection * +
w/unit run
A B
C
Slope
Maximum Deflection
( at x 0 519 from A )
w/unit run
A B
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 82
Quick Refresher Guide Strength of Material
Slope
Maximum Deflection ( )
Counter- clockwise
Deflection : upwards
Downward
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 83
Quick Refresher Guide Strength of Material
Part3.5: Torsion
3.5.1 Torsion
If moment is applied in a plane perpendicular to the longitudinal axis of the beam (or) shaft, it
will be subjected to Torsion.
e.g.:
Torsion formula:
R = Radius of shaft
L = Length of shaft
( )
= for Hollow circular shaft
Assumptions:
Note:
The stress setup at any point in a cross section is one of pure shear or simple shear.
The longitudinal axis is neutral axis.
The shear stress will vary linearly from zero at the centre to maximum at the outer surface
(any point on periphery)
( )
For a hollow circular shaft,
Angle of Twist,
Composite Shafts: When two dissimilar shafts are connected together to form one shaft, the shaft
is known as composite shaft.
Shafts in Series: If the driving torque is applied at one end, and the resisting torque at the other
end, the shafts are said to have been connected in series.
( )
T ( )
Shafts in Parallel:
OR
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 86
Quick Refresher Guide Strength of Material
If the Torque ‘T’ is applied at the junction of two shafts and resisting Torque at their remote
ends, the shafts are said to be connected in parallel.
For such a case,
;
T=
. .,
If both the shafts are of same material
.
( )
Let a shaft be subjected to a bending moment of ‘M’ and twisting moment ‘T’ at a sector.
Shear stress,
16
√( /4) ( √ )
2
16
√( /4) ( √ )
2
2 16
2 √
2
Equivalent Torque: It is the twisting moment, which acting along produce the maximum shear
stress due to combined bending and Torsion.
Equivalent Bending Moment: The bending moment to produce the maximum bending stress
equal to greater principle stress ‘ ’.
1
( √ )
2
( ) /
/ .
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 87
Quick Refresher Guide Strength of Material
Assumptions:
Stresses at a section of a rod: A section of a rod is subjected to direct shear force (W) and a
Torque (T = WR)
,1 - …… (1)
16
∴
If m is small, then maximum shear stress can be calculated by A.M. Wahl’s formulae that takes
account for initial curvature of the spring wire:
.
Max. ( )
Twist 64 / , deflection
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 88
Quick Refresher Guide Strength of Material
Mohr's circle gives us a graphic tool by which, we can compare the different stress
transformation states of a stress cube to a circle. Each different stress combination is described
by a point around the circumference of the circle.
Compare the stress cube to a circle created using the circle offset
2
x y x y
a ave and R xy
2
2y 2
σy
τyx
σy
-τ y 2
x y
xy
2
R
B 2
(σx , -τxy )
σ
x y
(σx , τxy ) 2
A
σave
xy
+τ R
x
Notes:
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 89
Quick Refresher Guide Strength of Material
If the plane contain only shear and no normal stress (pure shear), then origin and centre of
the circle will coincide and maximum and minimum principal stress equal and opposite.
σ1 τ , σ2 -τ
The summation of normal stresses on any two mutually perpendicular planes remains
constant.
σx σy σ1 σ2
Cylindrical shells:
Longitudinal stress =
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 90
Quick Refresher Guide Strength of Material
( )
2 8
Spherical shells:
σ pd
τ
2 8t
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 91
Quick Refresher Guide Strength of Material
Strain energy, also known as internal energy per unit volume stored in a deformed material. The
strain energy is equivalent to the work done by the applied force. Simple work is calculated as
the product of a force moving through a distance.
For an axially loaded member below the proportionality limit, the total strain energy is given by,
1 P2 L
U P
2 2 AE
U 2
u
AL 2E
3.7.2 Elastic Strain Energy in Flexural Loading
In the beam shown in the figure consider a differential element isolated by two transverse
sections at a distance dx apart. Treating this element as an axially loaded bar, where P = dA =
(My/I)dA, the energy stored in it is
N.A.
y
P
dx
d y dA
M dx
∫
2EI
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 92
Quick Refresher Guide Strength of Material
For a circular bar of constant cross section, the strain energy stored in the body is equal to the
product of average torque and the angular deformation; that is
U = 1/2 T = T ( )
When the torque varies the result may be applied over a segment of length dx and integrated
over the length of the bar to obtain
T dx
∫
2GJ
It states that the deflection caused by any external force is equal to the partial derivative of the
strain energy with respect to that force.
Interpretation: The partial derivative of the strain energy with respect to one of the external
loads equals the displacement of the point of application of load in the direction of that load.
The problem of impact is analogous to that of a falling body stopped by spring. Let us consider a
free falling body of mass ‘m’ from a height h that produces a deflection in the spring.
Relationship between dynamic and static deflection can be obtained by equating the resultant
work done to the zero change in kinetic energy.
The ratio of the maximum dynamic deformation to the static deformation st can be given by
the equation
2h
1 √1
Also the stress due to gradually applied load may be applied by the impact factor to obtain the
maximum stress:
σ σ (1 √1 )
For sudden loading, free fall ‘h’ does not exist i.e., h 0. i.e., a suddenly applied load (dynamic
condition), produced a deflection which is twice as great as that obtained when the load is
applied gradually.
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 93
Quick Refresher Guide Strength of Material
Definitions:
Short Column: Short columns, called piers or pedestals, will fail by compression of the material.
These columns fail essentially by direct crushing at ultimate load.
Long columns: Long columns will buckle in the transverse direction that has the smallest radius
of gyration. Buckling failure is sudden, often without significant warning. If the material is wood
or concrete, the material will usually fracture (because the yield stress is low); however, if the
column is made of steel, the column will usually fail by local buckling, followed later by twisting
and general yielding failure. Intermediate length columns will usually fail by a combination of
crushing and buckling.
As slenderness ratio increases, permissible stress or critical stress reduces, consequently, load
carrying capacity also reduces.
X X
Y
For a given area, Tubular section will have maximum radius of gyration.
H-Section is more efficient than I-Section.
Equilibrium of a column: A column is said to have buckled or failed when it reaches “Neutral
Equilibrium”.
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 94
Quick Refresher Guide Strength of Material
Critical load: The load at which a long column fails is known as the critical load or Euler load. The
Euler load is the theoretical maximum load that an initially straight column can support without
transverse buckling. For column with frictionless or pinned ends, this load is given by Euler’s
formula shown below.
2 EI
Pcr 2 --------- (1)
L
The corresponding column stress is given by the equation shown below. This stress cannot
exceed the yield strength of the column material.
Pcr 2 E
cr [ ] --------- (2)
A L 2
r
L is the longest unbraced column length. If a column is braced against buckling at some point
between its two ends, the column is known as a braced column, and L will be less than the full
column height.
The quantity L/r is known as the slenderness ratio. Long columns have high slenderness ratios.
The smallest slenderness ratio for which Eq. (2) is valid is the critical slenderness ratio, which
can be calculated from the material’s yield strength and modulus of elasticity. Typical
slenderness ratios range from 80 to 120. The critical slenderness ratio becomes smaller as the
compressive yield strength increases.
Most columns have two radii of gyration, rx and ry, and therefore, have two slenderness ratios.
The largest slenderness ratio will govern the design.
The smallest force at which a buckled shape is possible. Prior to this load the column remains
straight. The columns buckle in the plane of the major axis of the cross section as shown below.
X X
X
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 95
Quick Refresher Guide Strength of Material
Assumptions:
Effective length and critical loads for various boundary conditions compared to a column whose
both ends are hinged.
L/2 4 EI/L
2. Both ends fixed
L
L/√2 2 EI/L
3. One end fixed and
other hinged
L
2L EI/4L
4. One end fixed and
other end free
L
L EI/L
5. One end fixed, at
other end only lateral
L
displacement and no
rotation
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 96
Quick Refresher Guide Strength of Material
2L EI/4L
6. One end pinned, at
other only lateral
L
displacement no
rotation
1.5L EI/2.5L
7. One end fixed, at
other end lateral
L
displacement and
partial rotation.
As and E are constant for a particular material, Euler’s formula is valid for a particular range of
slenderness ratio, for e.g. for mild steel whose = 3300 Kg/cm and E = 2.1 × 10 Kg/cm
Euler formula is not valid for slenderness ratio less than 80.
Euler’s formula is valid only up to proportional limit i.e., in inelastic zone, the formulae are not
valid
Note:
It is empirical formula
Takes into account both direct crushing (Pc) load and Euler critical load (P ).
1 1 1
i. e. ,
P P P
P .P
∴ P
P P
Basic Formula:
.
P ( / )
Where α Rankine’s constant
L = eff. Length
σ yield stress.
Rankine’s Co-efficient: is independent of geometry and end conditions, can be modified to
incorporate imperfections
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 97
Quick Refresher Guide Strength of Material
σ
α
E
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 98
Quick Refresher Guide Thermodynamics
Part – 4: Thermodynamics
Part 4.1: Basic Thermodynamics
Thermodynamic system is a quantity of matter or region in space considered for the analysis of a
problem.
Boundary
System
Surroundings
Classification of system:
Open system: Both energy and mass can transfer across the boundary e.g., Steam turbine,
centrifugal pump.
Energy in
Mass out
Mass in
Energy out
Closed system: Energy transfer occurs across the boundary. No mass transfer across the
boundary
Energy out
Energy in
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, [email protected] © Copyright reserved. Web: www.thegateacademy.com Page 99
Concrete Technology
presentation
Dr.Akram Saad
PhD,MBA,PMP,CCP,MRICS
Types of Cements
“OPC” Ordinary Portland Cement
“SRC“Sulphate Resistance Cement “SRC”
”PPC” Portland-Pozzolana Cement
“RHC” Rapid Hardening Cement
“LHC” Low Heat Cement
“PSC” Portland Slag Cement
White Cement
Cement
• Main two types are:
• Tricalcium silicate
• Di-calcium silicate
• Tri-calcium aluminate
• Tetra calcium alumino ferrite.
Important Notes
Ultimate strength to cement is provided by
- Di-calcium silicate
Setting time:
- Initial 45 minutes.
- Final 10 hours.
Portland Cement Setting Time
Time
Test Method Set Type
Specification
Initial ≥ 45 minutes
Vicat
Final ≤ 375 minutes
Soundness
• refers to the ability of cement paste to retain
its volume after it has get hardened.
... Soundness of cement is the property by
virtue of which the cement does not undergo
any significant expansion (or change in
volume) after it has set, thus eliminating any
chances of disrupting the mortar or concrete.
Bleeding
• Admixtures
Strength of concrete primarily depends on
- Quality of water
- Quality of aggregates
- Quantity of cement
- W / C ratio
Concrete hydration means
• Reaction between cement and water
Gradation
Describes the particle size distribution of the
aggregates
Why steel is used as reinforcement in R .Concrete
• Main bars in the slabs shall not be less than 8 mm (HYSD) or 10 mm (Plain
bars) and the distributors not less than 8 mm and not more than 1/8 of
slab thickness.
Important Notes
• Minimum thickness of slab is 125 mm.
• Dimension tolerance for cubes + 2 mm.
• Free fall of concrete is allowed maximum to 1.50m.
• Water absorption of bricks should not be more than 15 %.
• PH value of the water should not be less than 6.
• Compressive strength of Bricks is 3.5 N / mm2.
• In steel reinforcement binding wire required is 8 kg per MT.
• In soil filling as per IS code, 3 samples should be taken for
core cutting test for every 100m2.
Density of Materials
Material Density
Bricks 1600 – 1920 kg/m3
Concrete block 1920 kg/ m3
1 – 5 m3 1 No’s
6 -- 15 m3 2 No’s
16 – 30 m3 3 No’s
31 – 50 m3 4 No’s
3. For the manufacture of Portland cement, the proportions of raw materials used, are
A. lime 63%; silica 22 %; other ingredients 15%
B .lime 22 %; silica 63 %; other ingredients 15%
C. silica 40 %; lime 40 %; other ingredients 20%
D. silica 70 %; lime 20% ; other ingredients 10%.
4. Asbestos cement
A.is brittle
B. warps due to changes in humidity
C. strength is lowered when saturated by water.
D. All of the above.
5. Process of keeping Concrete moist for certain period after casting is:
A - Finishing of Concrete
B - Curing of Concrete
C - Placing of Concrete
D - None of the above
13. How many slump layers of concrete are required in slump test:
A- 4 layers
B- 2 layers
C- 3 layers
D- 7 layers
14. Air entrained concrete is used in lining walls and roofs to make them:
A - Heat insulated
B - Sound insulated
- None of the above
-A&B
Select one:
2. Stress means:
a) Is the internal forces developed in material due to external forces.
b) Ability to resist external forces
c) Deformation in material caused of external forces.
d) Forces applied perpendicular to the longitudinal axis of a member.
4. In above truss. If the temp of member B-C changed by 100 F°. the displacement of point E
is equal to :
a) 3.52 mm
b) 9.83 mm
c) 8.3 mm
d) None of the above.
9. For simply supported beam the shear and flexural stresses will equal to Zero at:
a) End supports.
b) Middle of the span and above neutral axis.
c) Middle of the span and on the neutral axis.
d) End Supports and below neutral axis.
11. Ministry of urban planning need to construct an exhibition center the location of this
center should be next to:
a) Airport
b) Buses stations.
c) In a high population area.
d) In a remote area.
21. 5 meter high retaining walls is back filled with sand (Unit weight = 19 KN/M3) with angle of
30°. Earth lateral pressure will equal to:
??? a) 95 KN/m.
b) 55 KN/m.
c) 45 KN/m.
d) None of the above.
22. A car going on a speed of 60 mile/Hr on a curve highway. After passing midpoint the driver
saw an accident in front of him. The distance that will be passed from the moment the
driver saw the accident until he hit the brakes equal to:
a) 45 ft
b) 90 ft
c) 180 ft
d) None of the above.
23. Moisture Content range for timber that Is used in construction is equal to:
a) 0 to 2%.
??? b) 2 to 4%.
c) 10%.
d) None of the above.
27. Minor limit design method for rectangular section will provide:
a) Minimum steel area, Minimum section dimension.
??? b) Minimum steel area, Maximum section dimension.
c) Maximum steel area, Maximum section dimension.
d) Maximum steel area, Minimum section dimension.
28. UPVC Pipe with station 0.00 and box culvert with station 163.666 ft. calculate the back
filling above the culvert:
a) 3 ft.
b) 4.7 ft.
??? c) 5.93 ft.
d) 2.5 ft.
29. Nominal moment for rectangular concrete cross section is given by:
a) = ( − )
b) = ( − )
c) = − + ( − )
d) = (1 − 0.59 )
30. A sample of 200 ml wastewater is given in a container (Weight of container = 22.00 g) and
was inserted in oven, after water evaporated the weight of sample was given as = 24.502 g
then the sample was inserted in a burning oven and the weight changed to = 22.606 g , the
??? volatile solids content for this sample is equal to:
a) 0.0095 g/ml.
b) 0.0584 g/ml.
c) 0.0081 g/ml.
d) None of the above.
31. The un-drained shear strength for clay is equal to:
a) Half of the unconfined compressive strength of clay.
b) Twice the unconfined compressive strength of clay.
c) One and a half the unconfined compressive strength of clay.
d) None of the above.
1. The strength of material is defined as:
a) Ability of material to resist external forces.
b) Ability of material to resist deformation.
c) Ability of material to with stand external loads.
d) None of the above.
2. Stress means:
a) Is the internal forces developed in material due to external forces.
b) Ability to resist external forces
c) Deformation in material caused of external forces.
d) Forces applied perpendicular to the longitudinal axis of a member.
4. In above truss. If the temp of member B-C changed by 100 F°. the displacement of point E
is equal to :
a) 3.52 mm
b) 9.83 mm
c) 8.3 mm
d) None of the above.
9. For simply supported beam the shear and flexural stresses will equal to Zero at:
a) End supports.
b) Middle of the span and above neutral axis.
c) Middle of the span and on the neutral axis.
d) End Supports and below neutral axis.
11. Ministry of urban planning need to construct an exhibition center the location of this
center should be next to:
a) Airport
b) Buses stations.
c) In a high population area.
d) In a remote area.
21. 5 meter high retaining walls is back filled with sand (Unit weight = 19 KN/M3) with angle of
30°. Earth lateral pressure will equal to:
a) 95 KN/m.
b) 55 KN/m.
c) 45 KN/m.
d) None of the above.
22. A car going on a speed of 60 mile/Hr on a curve highway. After passing midpoint the driver
saw an accident in front of him. The distance that will be passed from the moment the
driver saw the accident until he hit the brakes equal to:
a) 45 ft
b) 90 ft
c) 180 ft
d) None of the above.
23. Moisture Content range for timber that Is used in construction is equal to:
a) 0 to 2%.
b) 2 to 4%.
c) 10%.
d) None of the above.
27. Minor limit design method for rectangular section will provide:
a) Minimum steel area, Minimum section dimension.
b) Minimum steel area, Maximum section dimension.
c) Maximum steel area, Maximum section dimension.
d) Maximum steel area, Minimum section dimension.
28. UPVC Pipe with station 0.00 and box culvert with station 163.666 ft. calculate the back
filling above the culvert:
a) 3 ft.
b) 4.7 ft.
c) 5.93 ft.
d) 2.5 ft.
29. Nominal moment for rectangular concrete cross section is given by:
a) = ( − )
b) = ( − )
c) = − + ( − )
d) = (1 − 0.59 )
30. A sample of 200 ml wastewater is given in a container (Weight of container = 22.00 g) and
was inserted in oven, after water evaporated the weight of sample was given as = 24.502 g
then the sample was inserted in a burning oven and the weight changed to = 22.606 g , the
volatile solids content for this sample is equal to:
a) 0.0095 g/ml.
b) 0.0584 g/ml.
c) 0.0081 g/ml.
d) None of the above.
31. The un-drained shear strength for clay is equal to:
a) Half of the unconfined compressive strength of clay.
b) Twice the unconfined compressive strength of clay.
c) One and a half the unconfined compressive strength of clay.
d) None of the above.
MMUP Most Common Questions (CIVIL)
1. Strength of Material is Defined as :
Ability of Material to Resist External Forces (Ability of Material to Resist the Deformations due to external forces)
2. Stress Means:
Is the internal forces developed in material due to external loads
3. The SPT‐N (Soil Penetration Test ):
Indication of the relative density of granular deposits (for dense sand =20 ̴40)
4. Critical Path:
Longest sequence of activities path in a project
5. Add‐Mixture are Used in Concrete for :
Both (to increase workability of concrete + increase air content)
6. In PERT Chart the time estimate of activity is calculated by :
Probability (not normal or binomial or logarithmic)
7. The value of concrete cube strength is given at :
28 days
8. For simply supported beam the shear and flexural stresses will equal to zero at :
At mid span and neutral axe
9. The summation of internal angles at any polygon equal to :
=720=180 * (n‐2) , where “n” is the number of faces
10. ASGHAL is responsible for :
Urban Planning and public buildings
11. Compaction in backfilling is used for:
Reducing air content in backfilled material
12. Last component that is added to cement production process is :
Calcium sulfate (Gypsum)
13. Ultra Sonic pulse test is :
Both (Non destructive test, used in smooth concrete surfaces)
{It is used to inspect the depth and width of concrete, and detection of steel bars location in concrete}
14. Slump test is used for :
Testing of workability of concrete
15. No. of layers of concrete required in slump test:
3 layers
16. The following is not a gypsum board characteristic:
Fire resistance
17. Super elevation is used at:
Horizontal curves **to avoid centrifugal force at high speeds
18. Moisture content range for timber that is used in construction is equal to:
14‐18%
19. Plywood is preferred as construction material because :
The strength of the panel consistent across all directions
20. Fast Track project means:
Design/Built (Activities are parallel)
21. The meaning of crashing in project:
To increase project resource in order to reduce project total duration
22. The meaning of resource leveling :
Technique used to examine unbalanced use of resources over time
23. Minor limit design method for rectangular section will provide:
Minimum steel area, Maximum section dimension
24. Nominal moment for rectangular concrete cross section is given by :
Mn=Fs As (d‐a/2)
25. The un‐drained shear strength for clay is equal to :
One and a half the unconfined compressive strength of clay
26. Moment distribution method is devolved by :
Hardy Cross
27. The error in measuring tape due to shortage of tape is called:
Systematic error
28. Poisson’s Ratio is :
The transverse strain / the longitudinal strain
29. Initial setting time of cement for asbestos cement products should be not less than :
30 minutes
30. Type of cement using for canal lining is:
Sulphate resisting cement
31. If water required for 1 bag of cement is 30 liters , the water cement ratio is :
0.6
1800 kg
33. Mastic asphalt is normally used for :
Water proofing
34. Strength of cement concrete primarily depends upon:
Water‐Cement ratio
35. Soundness of cement is tested by:
Le‐chatelier apparatus
36. Slump test for concrete is carried out, to determine:
Workability
37. The foundations are placed below ground level, to increase:
Stability of structure
38. The loose pockets in soil mass can be bridged safely by providing a raft foundation provided the soft area is
smaller than:
One‐third the column spacing
39. The concrete slump recommended for beams and slabs is:
30 to 125 mm
40. The entrained concrete is used in lining walls and roofs for making:
Both (Heat insulated – sound insulated)
41. What is the maximum value of PHF (Peak Hour Factor):
1
42. What is the minimum value of PHF (Peak Hour Factor):
0.25
43. What is the factor not to be taken in consideration in mix design:
???????
44. What to take in consideration to safe design for long pile in a drilled rock soil:
Strength of concrete
45. What is the factor effecting the hardness of water?
Calcium &Magnesium
46. The road cross section is used for :
Cut and fills quantity
47. What is RQD 100% refer to : *RQD = Rock Quality Designation
High quality rock
48. Activity is followed by two activities is called:
Diversion activity
49. At project time frame , type of cost estimation is:
Budget cost
50. Maximum backfilling height for chambers and pit as per QCS is:
300mm
51. Amount of time that an activity may be delayed from early start without delaying the project is:
Total float Or Total Slack
52. Amount of time a task can be delayed without delaying the early start of its successor is:
Free float
53. What is hydration in concrete?
It is the reaction between cement and water
54. What is Project scope definition?
It is the sum total of all its product and their requirements or features
55. What is the yield strength of steel?
The ability of a metal to tolerate gradual progressive force without permanent deformation
56. Perfect sampling for Rock Soil:
Double Sleeve
57. What is the perception and reaction time for calculating the sight distance?
2.5 seconds, 1mile = 1.609344 KM, 60mile = 96.56 KM
58. For why steel is preferred as reinforcement in concrete?
Because it has the same coefficient of expansion of the concrete.
59. In infrastructure works , the utility with the lowest level is :
Drainage
60. Who makes the tests to ensure the reliability and suitability of the product?
Certified Testing Engineer.
61. Consolidation is aterm used to describe the volume reduction of?
Saturated Clay
62. Fundamental factor in creating durable concrete is …… and ………
Pozzolana, Ground granulated blast‐furnace slag
63. A project with CPI=0.95 and SPI=1.01 that means
The project runs with over cost and progress faster than plan
64. What is service Capacity of roads describes?
Capacity is defined as the maximum number of vehicles, passengers, or the like, per unit time, which can be
Accommodated under given conditions with a reasonable expectation of occurrence.
65. The levels of service of roads describe?
A term closely related to capacity and often confused with it is service volume. When capacity gives a
quantitative
Measure of traffic, level of service or LOS tries to give a qualitative measure. It divides the quality of tra_c into six
levels ranging from level A to level F.
66. Cohesionless backfill is usually layers thick ……?
30 CM
67. The main type of plastic moment into concrete is?
Plastic settlement Or Plastic shrinkage Or Both Or none of the above.
68. The legal area of piece of land is measured?
Vertically Or Horizontally Or Along ground Or Between the ellipsoid and geoid
69. What is proctor compactor test check?
Max Dry density
70. What does a burst activity mean?
A burst activity is an activity that is a predecessor to more than one activity
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
QCS: (2010): Qatar Construction Specification
QCS: (2007): Qatar Construction Standards
PERT: Program Evaluation and Review Technique
CPM: Critical Path Method
PWA: Public Works Affairs
AASHTO: American Association of State Highway & Transportation Officials
ASTM: American Society for Testing and Materials
QSAS: Qatar Sustainability Assessment System
BS: British Standards
ABET: Accreditation Board for Engineering and Technology
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Problems
71. A sample of 200 ml wastewater is given in a container (Weight of container = 22.00 g) and
was inserted in oven, after water evaporated the weight of sample was given as = 24.502 g
then the sample was inserted in a burning oven and the weight changed to = 22.606 g, the Volatile solids
content for this sample is equal to:
=24.502‐22.606=1.896 g
Volatile solids content= 1.896 g/200 ml =0.0095 g/ml
72. A car going on a speed of 60 mile/Hr on a curve highway. After passing midpoint the driver
saw an accident in front of him. The distance that will be passed from the moment the
driver saw the accident until he hit the brakes equal to:
‐ The perception and reaction time for calculating the sight distance=2.5 seconds
‐60 mile/hr *5280 ft/3600 seconds=88 ft/sec
‐ The distance that will be passed from the moment the driver saw the accident until he hit the brakes = 88 ft/sec
*2.5 sec = 220 ft
73. A flow in rectangular section 2 m wide as shown velocity equal to Y1/3 calculates the discharge.
V = Y 1/3
1 meter
30
Y
74. Calculate pressure at point A Water
Oil
S=0.9
0 5m
1.3 m
1m
A
Mercury
S=13.55
1. 100 Chord is mostly near to :
1/ 10.000
1/ 100.000 ???
1/ 200.000
Something I didn’t remember
2. Air entrained in concrete :
- Density concrete Decreases
- Workability Increases
- Segregation Decrease
- Durability Increases
- All of the above
3. Concrete Mix design; what is not to consider while preparing Mix design
- Initial setting time of cement
- Test control procedures
- Workability
- Compressive strength of concrete.
6. The truss shown in figure. If member AB is shorten by 3mm, applied force 25 KN, what is the
vertical displacement at point C? C
~3mm 25 E&A +
A B
3mm
7. Slope at C? 12 KN
A E
C
24m
– Zero
– 1666.66
– 3333.33
– 5555.55
HL
8.Given Q total (flow rate) Inflow Outflow
Head Loss
Friction Q
Diameter Pipe 1, 2 and 3
9. Given the following Weir; Head of water is 4 m, angle of Weir is 52 Degrees; Constant coefficient
0.06. What is the Flow rate =?
??? 52 h
Q =?
10. Question on Horizontal Curve:
Super elevation = 0.004; Friction = 0.016; Velocity = 55 mph. what is the minimum radius?
L
e + f = V2/127R
I R
LS =
LF
No question, only given the above table, and mentioned 4 multiple choice answers !
ACGF
CCCD
13. You have to make embankment V= 100,000cy material to be transported from near site.
Swell ratio material 20 %
Shrinkage value 15 %
How many cy to be excavated?
115,000
117,000
120,000
117,727
???
14. Concrete Sequence
1-Shutter erection
2- Concrete pouring
3- Curing
4-Shutter dismantling
The above rankine active retaining wall, given density of soil, angle of internal
friction, height of wall, angle of internal friction under wall base. Find out the factor
of safety against sliding?
– 3
– 1.23
– 2.5
– 3.5
18. Reynolds Coefficient Number is used for:
- Clay soil coefficient
- Fluid Mechanics close conduits
- Open Channel
- flow of traffic
Ans – 10 12%
2) The Delay Time for a Series of activities that would not effect if occurred the Project
timing Called.
• Total Slack
• Total Slag
• Critical Float
• Float Pad
• Critical Slag
• 1
• Less Than 1
• More Than 1
• Zero
Ans - 1
Public Work
Public Housings
2) Shutter Striking
3) Shutter Erection
4) Curing
Ans – 3-1-4-2
• 4 Layers
• 2 Layers
• 3 Layers
• 1 Layers
Ans – 3 Layers
• 0-20
• 20-40
• Large of 50
• 100
Ans – 20-40
Exam 20-Jan-2014 Civil
• Strength
• Durability
• Workability
• Water Content
Ans – Workability
2
9) For Isolated Foundation area of Foundation as per Calculation Required to be 2.25m
and the Colum Dimension is 0.25x0.8 what is the best Foundation Size
• 1.5mx1.5m
• 1mx2.25 m
• 1.25mx1.8m
Ans – 1.25mx1.8m
10) Separation of water or water sand cement from freshly concrete is known.
• Bleeding
• Creeping
• Segregation
• Flooding
Ans - Bleeding
Exam 20-Jan-2014 Civil
11) . P 4M
A 3m
No Reply
a) Speed
b) Progress
c) Quality
d) Repeating
Ans – Repeating
14) Car Speed 60 mile 1hr and f=2 and Road Radius=
• e = –f
• e = ‐f
Ans‐ e = –f
Exam 20-Jan-2014 Civil
15) AS Built Drawing Submitted For.
Construction
Additional Work
• 300 mm
• 500mm
• 250mm
• 150mm
Ans – 300 mm
Discipline.
b) All Engineer Should work and Cooperate Together and Solve all the
Engineering Issues.
c) .
d)
Ans - B
Exam 20-Jan-2014 Civil
1. 360
2. 540
3. 720
+
.&&
&
$&"&
%
/ $
#
3
4 0
4 0
4 )
4
4 2
!"#$$%
4 #
4 +
4 5+
4 )'+6()
7"$$!()
84 .&&
&$4!"
3$%$&&$
$
0
#&
%
*
'"()
"
0 "
3!
"
"&
#
0
#&
%
= .&&! .)
!
#
.%%
/$!
&$%
.&& &$4!"
*-.&?@
?""
!"$%"$&&
&
$@
$
/
1
.
+
$
/
PMP Questions with Answers for MME-Electrical – 2018
1. Information to develop a project network is collected from the
C. Budget
D. Project proposal
E. Responsibility matrix
2. Which of the following represents an activity on an AON (Activity on Node) project network?
A. An arrow
B. A line
C. A node
A node
A. An activity
B. Project flow
C. Dependency
A. A single activity
Page 1 of 12
C. A milestone
D. A critical path
E. An arrow
5. Which of the following is provided by a project network but not by the work breakdown structure?
A. Dependencies
B. Sequencing
C. Timing
B. Work packages
C. Budget
D. Project proposal
E. Responsibility matrix
Work packages
A. Event
B. Path
C. Activity
D. Node
E. Milestone
Activity
Page 2 of 12
8. An activity that has more than one dependency arrow flowing into it is termed a(n)
A. Parallel activity
B. Critical path
C. Burst activity
D. Merge activity
E. Independent activity
Merge activity
10. A/an _________ activity has more than one dependency arrow flowing from it.
A. Parallel
B. Critical path
C. Burst
D. Merge
E. Independent
Burst
11. An item on a project network is Design Software Completed. This is best described as a(n)
A. Event
B. Path
C. Activity
Page 3 of 12
D. Node
E. Milestone
Event
12. Activities which can take place at the same time are termed
A. Parallel activity
B. Critical path
C. Burst activity
D. Merge activity
E. Independent activity
Parallel activity
A. Critical path
B. Parallel path
C. Activity chain
D. Path
E. Dependent chain
Path
14. An AON project network uses which of the following basic building blocks?
A. Arrows
B. Bars
C. Nodes
15. Which of the following is not one of the basic rules to follow when developing project networks?
Page 4 of 12
A. An activity cannot begin until all preceding activities have been completed
C. Conditional statements are allowed but looping statements are not allowed
D. An activity identification number must be larger that that of any preceding activities
Conditional statements are allowed but looping statements are not allowed
A. Merge
B. Burst
C. Predecessor
D. Successor
E. Critical
Predecessor
A. Merge
B. Burst
C. Predecessor
D. Successor
E. Critical
Successor
Page 5 of 12
E. A, B, and C are all correct
C. Critical path
20. Which of the following correctly calculates the early finish for an activity?
A. LS + DUR
B. ES + DUR
C. LF +DUR
D. ES + SL
E. LF + SL
ES + DUR
21. Which of the following correctly calculates the late start for an activity?
A. EF - DUR
B. ES - DUR
C. LF - DUR
D. ES - SL
E. LF - SLACK
LF - DUR
22. The amount of time an activity can be delayed and yet not delay the project is termed
A. Total slack
Page 6 of 12
B. Free slack
C. Critical float
D. Float pad
E. Slip pad
Total slack
23. Which of the following will correctly calculate the total slack in an activity?
A. LS - ES
B. LF - EF
C. LS - LF
D. LF - ES
24. The laying pipe example in the text illustrates the concept of
A. Laddering
B. Hammock activities
C. Critical path
D. Concurrent engineering
E. Forward pass
Laddering
25. Using a special color copy machine for a tradeshow publication illustrates the concept of
A. Laddering
B. Hammock activities
C. Critical path
D. Concurrent engineering
E. Forward pass
Page 7 of 12
Hammock activities
26. If, for some reason, the project must be expedited to meet an earlier date, which of the following
actions would the project manager take first?
D. A sub-deliverable
E. A cost account
29. Which company utilized concurrent engineering to design a new line of cars and in the process
completed its development six months ahead of schedule?
A. General Motors
Page 8 of 12
B. Chrysler
C. Ford
D. Nissan
E. Toyota
Chrysler
30. The minimum amount of time a dependent activity must be delayed to begin or end is referred to as:
A. Hammock
B. Laddering
C. Lag
D. Cushion
E. Buffer
Lag
31. The requirement for a freshly poured foundation to cure before beginning construction is an
example of which of the following type of lag?
A. Start to Start
B. Start to Finish
C. Finish to Finish
D. Finish to Start
Finish to Start
Page 9 of 12
Start to Start lags
33. If testing cannot be completed any earlier than four days after the prototype is built, which of the
following type of lag exists?
A. Start to Start
B. Start to Finish
C. Finish to Finish
D. Finish to Start
Finish to Finish
34. Which of the following represents an activity on an AOA (Activity on Arrow) project network?
A. An arrow
B. A line
C. A node
A line
A. An activity
B. An event
C. Responsibility
An event
Activity
Task(s) of the project that consumes time while people/equipment either work or wait.
Activity-on-arrow
Page 10 of 12
(AOA)
Activity-on-arrow method for drawing project networks. The activity is shown as an arrow.
Activity-on-node
(AON)
Activity-on-node method for drawing project networks. The activity is on the node (rectangle).
Burst activity
An activity that has more than one activity immediately following it.
Concurrent engineering
Cross functional teamwork in new-product development projects that provides product design, quality
engineering, and manufacturing process engineering all at the same time.
Critical path
The longest activity path(s) through the network. The critical path can be distinguished by identifying the
collection of activities that all have the same minimum slack.
Gantt chart
Hammock activity
A special-purpose, aggregate activity that identifies the use of fixed resources or costs over a segment of
the project—e.g., a consultant. Derives its duration from the time span between other activities.
Lag relationship
The relationship between the start and/ or finish of a project activity and the start and/or finish of
another activity. The most common lag relationships are (1) finish-to-start, (2) finish-to-finish, (3) start-
to-start, and (4) start-to-finish.
Merge activity
An activity that has more than one activity immediately preceding it.
Parallel activity
Sensitivity
Page 11 of 12
The likelihood that the critical path(s) will change once the project begins to be implemented.
Page 12 of 12
PMP Questions with Answers for MME-Electrical – 2018
1. Information to develop a project network is collected from the
C. Budget
D. Project proposal
E. Responsibility matrix
2. Which of the following represents an activity on an AON (Activity on Node) project network?
A. An arrow
B. A line
C. A node
A node
A. An activity
B. Project flow
C. Dependency
A. A single activity
Page 1 of 12
C. A milestone
D. A critical path
E. An arrow
5. Which of the following is provided by a project network but not by the work breakdown structure?
A. Dependencies
B. Sequencing
C. Timing
B. Work packages
C. Budget
D. Project proposal
E. Responsibility matrix
Work packages
A. Event
B. Path
C. Activity
D. Node
E. Milestone
Activity
Page 2 of 12
8. An activity that has more than one dependency arrow flowing into it is termed a(n)
A. Parallel activity
B. Critical path
C. Burst activity
D. Merge activity
E. Independent activity
Merge activity
10. A/an _________ activity has more than one dependency arrow flowing from it.
A. Parallel
B. Critical path
C. Burst
D. Merge
E. Independent
Burst
11. An item on a project network is Design Software Completed. This is best described as a(n)
A. Event
B. Path
C. Activity
Page 3 of 12
D. Node
E. Milestone
Event
12. Activities which can take place at the same time are termed
A. Parallel activity
B. Critical path
C. Burst activity
D. Merge activity
E. Independent activity
Parallel activity
A. Critical path
B. Parallel path
C. Activity chain
D. Path
E. Dependent chain
Path
14. An AON project network uses which of the following basic building blocks?
A. Arrows
B. Bars
C. Nodes
15. Which of the following is not one of the basic rules to follow when developing project networks?
Page 4 of 12
A. An activity cannot begin until all preceding activities have been completed
C. Conditional statements are allowed but looping statements are not allowed
D. An activity identification number must be larger that that of any preceding activities
Conditional statements are allowed but looping statements are not allowed
A. Merge
B. Burst
C. Predecessor
D. Successor
E. Critical
Predecessor
A. Merge
B. Burst
C. Predecessor
D. Successor
E. Critical
Successor
Page 5 of 12
E. A, B, and C are all correct
C. Critical path
20. Which of the following correctly calculates the early finish for an activity?
A. LS + DUR
B. ES + DUR
C. LF +DUR
D. ES + SL
E. LF + SL
ES + DUR
21. Which of the following correctly calculates the late start for an activity?
A. EF - DUR
B. ES - DUR
C. LF - DUR
D. ES - SL
E. LF - SLACK
LF - DUR
22. The amount of time an activity can be delayed and yet not delay the project is termed
A. Total slack
Page 6 of 12
B. Free slack
C. Critical float
D. Float pad
E. Slip pad
Total slack
23. Which of the following will correctly calculate the total slack in an activity?
A. LS - ES
B. LF - EF
C. LS - LF
D. LF - ES
24. The laying pipe example in the text illustrates the concept of
A. Laddering
B. Hammock activities
C. Critical path
D. Concurrent engineering
E. Forward pass
Laddering
25. Using a special color copy machine for a tradeshow publication illustrates the concept of
A. Laddering
B. Hammock activities
C. Critical path
D. Concurrent engineering
E. Forward pass
Page 7 of 12
Hammock activities
26. If, for some reason, the project must be expedited to meet an earlier date, which of the following
actions would the project manager take first?
D. A sub-deliverable
E. A cost account
29. Which company utilized concurrent engineering to design a new line of cars and in the process
completed its development six months ahead of schedule?
A. General Motors
Page 8 of 12
B. Chrysler
C. Ford
D. Nissan
E. Toyota
Chrysler
30. The minimum amount of time a dependent activity must be delayed to begin or end is referred to as:
A. Hammock
B. Laddering
C. Lag
D. Cushion
E. Buffer
Lag
31. The requirement for a freshly poured foundation to cure before beginning construction is an
example of which of the following type of lag?
A. Start to Start
B. Start to Finish
C. Finish to Finish
D. Finish to Start
Finish to Start
Page 9 of 12
Start to Start lags
33. If testing cannot be completed any earlier than four days after the prototype is built, which of the
following type of lag exists?
A. Start to Start
B. Start to Finish
C. Finish to Finish
D. Finish to Start
Finish to Finish
34. Which of the following represents an activity on an AOA (Activity on Arrow) project network?
A. An arrow
B. A line
C. A node
A line
A. An activity
B. An event
C. Responsibility
An event
Activity
Task(s) of the project that consumes time while people/equipment either work or wait.
Activity-on-arrow
Page 10 of 12
(AOA)
Activity-on-arrow method for drawing project networks. The activity is shown as an arrow.
Activity-on-node
(AON)
Activity-on-node method for drawing project networks. The activity is on the node (rectangle).
Burst activity
An activity that has more than one activity immediately following it.
Concurrent engineering
Cross functional teamwork in new-product development projects that provides product design, quality
engineering, and manufacturing process engineering all at the same time.
Critical path
The longest activity path(s) through the network. The critical path can be distinguished by identifying the
collection of activities that all have the same minimum slack.
Gantt chart
Hammock activity
A special-purpose, aggregate activity that identifies the use of fixed resources or costs over a segment of
the project—e.g., a consultant. Derives its duration from the time span between other activities.
Lag relationship
The relationship between the start and/ or finish of a project activity and the start and/or finish of
another activity. The most common lag relationships are (1) finish-to-start, (2) finish-to-finish, (3) start-
to-start, and (4) start-to-finish.
Merge activity
An activity that has more than one activity immediately preceding it.
Parallel activity
Sensitivity
Page 11 of 12
The likelihood that the critical path(s) will change once the project begins to be implemented.
Page 12 of 12
work package
calculate pile
compressive strength
tensile strength =10%
compressive strength
soil
Exam # 9 (60 Minutes)
1
Question # 01
2 Minutes
2
Question # 02
6 Minutes
3
Question # 03
Question # 04
6 Minutes
4
Question # 05
Question # 06
4 Minutes
5
Question # 07
3 Minutes
Question # 08
6
Question # 09
2 Minutes
7
Question # 10
5 Minutes
Question # 11
8
Question # 12
3 Minutes
9
Question # 13
3 Minutes
Question # 14
10
Question # 15
Question # 16
3 Minutes
11
Question # 17
3 Minutes
Question # 18
12
Question # 19
3 Minutes
13
Question # 20
Question # 21
3 Minutes
14
Question # 22
4 Minutes
Question # 23
15
Question # 24
4 Minutes
Question # 25
16
Question # 26
4 Minutes
Question # 27
17
Hands Up !!!!
18
Question # Correct Answer
1 B
2 D
3 A
4 D
5 C
6 B
7 A
Answers 8
9
B
D
10 A
11 A
12 C
13 A
14 A
15 A
16 A
17 A
18 C
19 B
20 B
21 D
22 D
23 D
24 B
25 D
26 C
27 A
19
Answer # 01
Answer # 02
20
Answer # 03
Answer is A
21
Answer # 04
Answer is D
22
Answer # 05
Answer is C
23
Answer # 10
Answer is A
Answer # 11
Answer is A
24
Answer # 12
25
Answer # 18
Answer # 19
26
Answer # 20
Answer # 22
27
Answer # 23
Answer # 24
28
Answer # 26
29
Answer # 27
30