Time & Work Type - 7

These questions are related to time and work problems. There are multiple choice questions about how many people and time taken to complete work under different conditions. The key is to set up proper ratios and equations to solve for unknown values like number of people, time taken etc.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
44 views

Time & Work Type - 7

These questions are related to time and work problems. There are multiple choice questions about how many people and time taken to complete work under different conditions. The key is to set up proper ratios and equations to solve for unknown values like number of people, time taken etc.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

Maths • Time & Work

7
TYPE

1. If 8 men can do a piece of work in 14 days, 5. 38 men can complete a work by working 6
then in how much time (in days) will 7 men Hrs per day in 12 days then calculate in how
do the same piece of work? many days 51 men can do double of the work
by working 8 hrs per day?
38 6 12
(A) 12 (B) 16 51 8
(C) 18 (D) 20

2. x boys can do a piece of work in 24 days. Then (A) 56 days/


in how much time (in days) 2x boys will do 228
half of the work? (B) days/
17
x 24 2x
(C) 14 days/

(A) 6 (B) 8 128


(D) days/
(C) 10 (D) 12 17

3. A certain number of persons can complete a 6. 6 persons earn ` 8,400 in a week, if they work
piece of work in 55 days. If there were 6 per- 8 hours per day then how much amount would
sons more, the work could be finished 11 days be earned by 9 persons in a week if they do
earlier. How many persons were there when the work 6 hours per day?
the work started? 6 8 ` 8 400
55 6 9 6
11
(A) ` 9,450
(A) 17 (B) 24 (B) ` 1,350
(C) 30 (D) 22 (C) ` 9,000
(D) ` 7,200
4. A group of persons can do a work in 10 days.
If 5 persons remains absent from first day, then 7. If 12 carpenters working 6 hours a day can
the work is completed in 12 days by remain- make 460 chairs in 240 days, then find the
ing persons. Tell how many persons were in number of chairs made by 18 carpenters in
the group initially? 360 days each working 8 hours a day?
10 12 6 460 240
18 8 360
12
(A) 1320
(A) 20 (B) 25 (B) 1380
(C) 45 (D) 30 (C) 1260
(D) 920

Study Center : Jaipur • Gopalpura • Lalkothi • Jhotwara • Ambabari • Alwar • Udaipur 1


Mother's Maths
8. If x men working x hours per day can do x 11. 35 persons are engaged to complete a work in
units of works in x days, then y men working y 60 days. After 32 days it is observed that only
hours per day in y day would be able to do k (2/5)th part of the work has been done. The
units of work. What is the value of k ? number of persons to be engaged to complete

x x x x the remaining work in the said period is

y y y k 60 35

k 32

(CDS 2020(II)) (2/5)

(A) x²y–3 (B) x³y–2


(C) y²x–3 (D) y³x–2 (SSC CGL Mains 2016)

(A) 20 (B) 35
9. 40 persons can do a work in 15 days if they
(C) 30 (D) 25
work 8 hours per day, then in how many days
12. 38 man can complete a work in 12 days work-
60 persons can complete the double work if
ing 6 hour a day. In how many days 57 man
they work 4 hours per day? If the work done
can complete twice the work working 8 hours
by 3 persons of first type in 2 hours is same
as the work done by 4 persons of the second a day. If work done by 2 man of first group in

type in 3 hours. an hour is equal to work done by 3 man of


second group in 1.5 hour?
40 8 15
38 6 12
60 4
57 8
3 2
4 3
2 1 3 1.5

(A) 25 days/ (B) 30 days/


(A) 27 day/ (B) 28 day/
(C) 80 days/ (D) 35 days/
(C) 18 day/ (D) None of these
10. If 6 men and 8 women can do a piece of work
in 10 days; and 13 men and 24 women can do 13. 2 men can build a wall in 12 & 11 hrs respectively
the same work in 4 days, then what is the ra- but if they work together then they use 300 less bricks
tio of daily work done by a man to that of a per hour & build a wall in 6 hrs. Find the no. of bricks
woman? in the wall.

(CDS 2020(I))

(A) 2 : 1 (B) 1 : 2 (A) 41526 (B) 39600


(C) 4 : 3 (D) 3 : 4 (C) 25632 (D) 42600

2 HEAD OFFICE : 201, Himmat Nagar, Gopalpura Mode, Tonk Road, Jaipur-302018
0141-2711689, +91-7073909991 | www.motherseducationhub.org
Maths • Time & Work
14. 25 men can reap a field in 20 days. When 16. 250 persons can complete a work in 20 days
should 15 men leave the work, if the whole by working 5 hours a day. How many persons
are required to complete the same work in 10
1
field is to be reaped in 37 days after they days by working 8 hour per day?
2

leave the work ?


25 20
15
(A) 316 men/ (B) 320 men/
1 (C) 313 men/ (D) 310 men/
37
2
17. 4 girls can do a piece of work in 8 days, 3 boys
(A) After 4 days (B) After 6 days
can do the same piece of work in 2 days and 5
(C) After 5 days (D) After 3 days
women can do the same piece of work in 4
15. 30 men can complete a job in 40 days. How- days. Who is least efficient?
ever, after 24 days some men out of the as-
4 8 3
signed 30 left the job. The remaining people
2 5 4
took another 40 days to complete the job. The
number of men who left the job is.
30 40 24 (A) Boys / (B) Girls /

30 (C) Women / (D) Men /

40
(CDS 2017 (II))

(A) 24 (B) 18
(C) 12 (D) 6

Study Center : Jaipur • Gopalpura • Lalkothi • Jhotwara • Ambabari • Alwar • Udaipur 3


Mother's Maths

Solutions
1.(B) 8m × 14 = 7 × D 6 men and 8 women can do a piece of work
D = 16 days in 10 days
Work done by 6 men and 8 women in one
x 24 2x D
2.(A) = 1
1 1
day =
2 10
D = 6 days
1
6x + 8y = ……………..(1)
3.(B) x × 55 = (x + 6)44 10
Now, 13 men and 24 women can do the
5x = 4x + 24 x = 24 days
same work in 4 days.
4.(D) x × 10 = (x – 5) × 12 1
5x = 6x – 30 x = 30 = 13x + 24 y = …………….(2)
4
38m 6 12 51 8 D Multiply equation (1) by 3 and subtract from
5.(B) (2)
1 2

228 1 3 1
D= days = –5x = – =–
17 4 10 20
1
6m 8 9m 6 = x=
6.(A) 100
8400 x Put the value of x in (1)
9 8400 6 1 1
x= 9450 + 8y =  8y =
8 100 10 25
12 6 240 18 8 360 1
7.(B) =y=
460 x 200
x = 1380 Hence , Ratio of x and y = 2:1.
m1d1h1 m 2 d 2 h2 35 x 28
8.(D) 32 35
w1 w2 11.(D)
2 3
x³ × k = y³ × x 5 5

y3 3 × 16 × 35 = (35 + x)28
k=
x2 3 × 4 × 5 = 35 + x
k = y³x–2 60 = 35 + x
40m1 8 15 60m2 4D x = 25
9.(C)
1 2
3
3m1 × 2 = 4m2 × 3 12. (A) ATQ, 2M1 × 1 = 3M2 ×
2
m1 = 2m2
M1 9
 =
40 2 8 15 60 1 4 D M2 4
1 2
Men×Eff. Work Time
D = 80 days 38×9 1 6 × 12
10.(A) Let a man’s one day work = x unit 57×4 2 8×x
Woman’s one day work = y unit
4 HEAD OFFICE : 201, Himmat Nagar, Gopalpura Mode, Tonk Road, Jaipur-302018
0141-2711689, +91-7073909991 | www.motherseducationhub.org
Maths • Time & Work
2 × 38 × 9 × 6 × 12 = 57 × 4 × 8 × x 16. (C) Men Work Time
 x = 27 days 250 1 5 × 20
13.(B) 11 A 12 M 1 8 × 10
132
12 B 11 250 × 1 × 8 × 10 = M × 1 × 5 × 20
 M = 312.5  313
132 132
T(A+B) = 11 12 23 1 1
Let they put x bricks with full efficiency 17. (B) 1 girl's 1 days work =
8 4 32
So,
1 1
132 1 boy's 1 days work =
x = 6 [x – 300] 3 2 6
23
 22x = 23x – 6900 11
1 woman's 1 days work =
 x = 6900 bricks 5 4 20
So, Total bricks in wall = 6 [6900 – 300] Clearly, girls are less efficient i.e., they are
= 6 × 6600 taking the most time.
= 39,600 bricks
14.(C) Let efficiency of each men = 1
total work = 25 × 1 × 20 = 500
Let after x days 15 men left the work.
So,
75
25x + 10 × 1 = 500
2
 25x + 375 = 500
125
x= = 5 days
25
So, After 5 days 15 men left the work.

15. (C) Let number of men who left the job is x


1
Clearly, 1 day's work of 30 men =
40

1
1 day's work of 1 man =
30 40

24
24 day's work of 30 men =
40

40 x
and 40 days, work of x men =
30 40
The work is completed in 64 days
24 40x
 + =1
40 30 40

24 x x 16
 + = 1 =
40 30 30 40
x = 12
Thus, 12 men left the job