Chapter 1 Intro To MCP
Chapter 1 Intro To MCP
Good project management is essential. In many developing The managerial cycle is shown in figure 1.2. Since changes often
countries construction alone accounts for about 10 percent of gross unforeseen, occur during the lifetime of a project, figure 1.2 represents a
national product, and 50 percent or more of the wealth invested in fixed continuous action aimed at achieving the best possible result.
assets.
Managing a project is quite different from managing a "steady-
state" organization. A project has a distinct beginning and end, whereas
steady-state organizations run continuously. Examples of the latter are
hospitals and mass production factories. In a hospital the basis of medical
care changes slowly, despite technological advances and the
administration works to a routine. In mass production industries the
routine of production proceeds continuously, except when new models
are being introduced.
1. 2. Managerial Cycle
Not every project requires all these people. On the other hand,
large and complex projects may require additional specialists, for
example, for heating and cooling, health and safety.
a) Purpose b) Activities
To complete the project brief and determine the layout, design,
methods of construction and estimate costs, in order to obtain the To obtain tenders from contractors: for the construction of the
necessary approvals from the client and authorities involved. building and to award the contract.
To prepare the necessary production information, including Government tendering procedures are particularly closely
working drawings and specifications and to complete all arrangements controlled to ensure that national contracts are awarded in an equitable
for obtaining tenders. and uniform way. In many cases tendering is the responsibility of a central
Tendering Board which is independent of either the client or the
b) Activities executing agency. Members of the project management team may be
Activities at this stage include required to provide the basic documentation to the central "Tendering
i) developing the project brief to final completion Board" and generally to provide technical assistance.
ii) investigating technical problems
c) Pre-Qualification iii) checking that the tenders are arithmetically correct
and conform to tender requirements.
To increase the probability that the client will get what is required,
it is usual to introduce some procedure to ensure that only experience and Government Tender Boards usually award the contract to the
competent contractors are allowed to tender. This procedure known as lowest bidder. In the case of private projects, the final choice of contractor
"pre-qualification", involves an investigation to the potential contractor's rests with the client, acting on the advice of the project management team.
financial, managerial and physical resources and of his experience of
similar projects and an assessment of the firm's integrity. 1.3.4. Constructing
The contract itself will be defined in a legal document which To construct the structure within the agreed limits of cost and
describes the duties and responsibilities of the parties to it. For time and to specified quality.
construction work, standard forms of contract have evolved in most
countries and it is usual for the central Tender Board to require the use of b) Activities
one of these standard forms with perhaps minor modifications to suit the
circumstances of a particular project. To plan, co-ordinate and control site operations. Production
planning includes the formulation of:
Other contract documents are those necessary to define in detail i) time-schedules,
the construction required by the client: drawings, specifications, ii) site organization,
schedules, bill of quantities, time-scale. These documents will have been iii)a manpower plan,
prepared during the design stage. iv) a plant and equipment plan
v) a materials delivery plan
Standard Forms of Contract:
Site operations include:
The use of standard forms of contract is recommended because: i) all temporary and permanent construction works and
i) their contents will be well known and understood by the the supply of all built-in furniture and equipment.
parties involved, ii) the co-ordination of subcontractors,
ii) their wording embodies much experience in resolving iii) general supervision.
difficulties of
interpretation and enforcement. The construction stage consists of a number interrelated a
iii) they will usually have been tested in law, activities. The failure of one activity can disrupt the entire production
iv) the preparation of new forms of contract is expensive schedule. Therefore, careful production planning is important.
and time-consuming
d) Participants
e.) Participants
The main participants are the project management team and the
In the case of government projects, the project management contractor. Normally, direct responsibility rests with the contractor. The
teams may be expected to give technical support by: project manager and his team must ·arrange for adequate supervision of
i) providing the necessary contract documents the work to ensure requirements.
ii) providing a basis for pre-qualification of tenderers,
1.3.5. Commissioning Stage
a) Purpose
b) Records
c) Activities
d) Participants