FH Method Statement For Procurement Services
FH Method Statement For Procurement Services
FURNITURE, FITTINGS & EQUIPMENT (FF&E) AND OPERATING SUPPLY EQUIPMENT (OSE)
Contents
1 About Fino Hospitality 2
2 Our Services 2
2.1 Procurement Project Management 2
2.2 Custom Joinery 2
2.3 Custom Furniture 2
2.4 Operating Supplies and Equipment (OSE) 2
2.5 Logistics and Warehousing 2
3 Procurement Procedures 3
3.1 Pre-Tender 3
3.2 Tender Phase 3
3.3 Purchase Order 3
3.3.1 Supplier Payments 3
3.4 Delivery 4
3.5 Installation 4
3.6 Reporting 4
3.6.1. Asset Register 4
4 Consultancy Fee 4
4.1 Procurement Fee 4
4.2 Installation Fee 5
4.3 Travelling Expenses 5
4.4 Exclusions 5
Fino Hospitality (FH) was created to give owners, designers and developers a single solution for their
procurement needs. With our combined construction, procurement and hospitality operations experience we
can offer strategic advice and service. We aim to respect the design integrity, quality of products and project
budget to deliver a quality product and service to our clients.
Our passion for hospitality operations and design, combined with our keen understanding of quality
manufacturing processes guarantees that we offer our clients a smart solution for their projects’ needs.
2 OUR SERVICES
FH will source, deliver and install customs FF&E and OSE developed for individual projects or in accordance
with international hotel brand standards. All products sourced will be contract quality and the best possible
product in line with the project budget.
3 PROCUREMENT PROCEDURES
3.1 PRE-TENDER
• Review designer or operator specifications and issue Request for Information if needed
• Check layout drawings and/or BOQ’s
• Identify suitable suppliers and complete tender Terms & Conditions
• Compile Tender Packs
• Prepare provisional program and set critical path
• Agree and set client reporting and commercial requirements
• Agree client baseline budget
1. FH can invoice the Client in line with the cash flow and the Client makes a lump-sum
payment to FH, who in turn will distribute payments to the various suppliers. FH will add
a small margin to the payment applications to cover miscellaneous expenses such as bank
charges. This cost will be shown in the cash-flow projection to ensure full transparency.
2. FH will receive the invoices from the suppliers and after checking them for accuracy
submit a payment application to the Client. The Client will then be responsible to make
the individual payments to each supplier.
• Manage the shop drawing and material samples submittal process for FF&E items until approvals
are received from the interior designer.
• Once approvals for shop drawings and material samples are received issue a final production
program.
• Manage the production ensuring production is kept within the agreed program.
• Manage the quality control and quantity control of all items ensuring clients expectations are
met.
3
• Manage the packaging and packing of items suitable for the different modes of transport to
minimise the risk of damage during transport.
3.4 DELIVERY
• Manage the loading process to ensure containers are utilised properly and efficiently.
• Manage the necessary paperwork to avoid potential delays and penalties when it comes time
for customs clearance.
• Coordinate shipment schedule and estimated arrival at port with clearing agent, ensuring all the
necessary documents are received by them in time.
• Manage the local transport and delivery to the project site or designated warehousing facility.
• Check contents and report any damages or shortages to the client immediately.
• Arrange for repairs and/or replacement if required.
3.5 INSTALLATION
• Manage and coordinate the installation with the installation contractor.
• Ensure goods are installed or placed in the correct location in line with the designers FF&E
schedule
• Hand over all OSE items to the operator in the designated areas.
• Inspect the goods after installation and arrange for any necessary touch-ups if required.
• Prepare and update a detailed installation schedule and tracker to monitor progress and
highlight any delays for corrective action to be taken.
3.6 REPORTING
• Issue weekly FF&E and OSE tracking schedules
• Issue weekly Shop Drawing schedules
• Issue weekly Material Approval schedules
• Issue bi-weekly budget reports
• Issue monthly project update report
• Issue Asset Register at the end of the project
4 CONSULTANCY FEE
4
FH require payment by way of EFT into its nominated bank account nominated. Fee invoices shall be
submitted by the 25th day (or next working day) of each month and must be paid in line with the
agreed payment terms. Payments will be free from all fees, transfer charges or deductions. FH reserve
the right to suspend works due to non-payment.
If required, FH can provide a site manager to oversee the installation process. The associated costs
for accommodation, travelling, meals, etc. will be for the Clients account. Final fee structure to be
negotiated and agreed prior to mobilisation.
4.4 EXCLUSIONS
(a) VAT and withholding taxes are specifically excluded and shall be for the client’s account.
(b) Site offices and equipment. The client shall provide a suitable air-conditioned site office for the
duration that a site manager is based on site. The site manager will have unlimited internet and
telephone access as well printer facilities as required.