This document is a construction turnover checklist for a project. It lists various construction works like facade works, wall works, floor works, and more. For each item, it indicates whether the work is completed ("√"), not completed ("x"), or not applicable ("none") and provides a remarks section. The checklist must be signed by the region representative, dealer representative, and contractor representative to verify completion and acceptance of the works. Photos of the turnover process must also be attached.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views

Region Construction Turnover Checklist-Final3

This document is a construction turnover checklist for a project. It lists various construction works like facade works, wall works, floor works, and more. For each item, it indicates whether the work is completed ("√"), not completed ("x"), or not applicable ("none") and provides a remarks section. The checklist must be signed by the region representative, dealer representative, and contractor representative to verify completion and acceptance of the works. Photos of the turnover process must also be attached.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

CONSTRUCTION

TURNOVER CHECKLIST

PROJECT: DATE:
LOCATION: DEALER/OWNER:

INSTRUCTIONS: MARK " √ " IF YES; MARK "×" IF NO; NONE MEANS NOW THIS WORK IN CHECKING PROJECT. NEED TO REMARK CLEAR REASON FOR NO
ACCEPTED?
NO WORK SCOPES NONE REMARKS
YES NO
FACADE WORKS
1 FRONT LOGO
2 GLASS WALL
3 ROLL-UP PORTAL
4 FROSTED STICKER
5 PAINT WORKS
6 ANTI-THEFT SYSTEM
7 ALUMINUM FLOOR STRIP
WALL WORKS
1 LIGHTED LETTERS
2 WOOD LAMINATES
3 CASHIER WALL ACP/BACKWALL
4 CASHIER WALL LOGO
5 CASHIER WALL LIGHTING
6 STAINLESS STEEL BASEBOARD
7 PAINT WORKS
FLOOR WORKS
1 TILES WORKS
2 POWER OUTLETS
3 CARPET WORKS
CEILING WORKS
1 LIGHTS PROPERLY INSTALLED
2 SMOKE DETECTORS
3 SPEAKERS
4 CCTV
5 WOOD LAMINATES
6 PAINT WORKS
7 VENTS
8 SPRINKLERS WITH ESCUTCHEON
ELECTRICAL WORKS
1 SWITCHES WITH TAGGING
2 PANELBOARD WITH TAGGING
3 3-PRONG POWER OUTLETS
4 EXIT SIGNAGE WORKING
5 LOGO/SIGNAGE TIMER SWITCH WORKING
6 PILOT LIGHTS WORKING
7 EMERGENCY LIGHTS CORRECT AND WORKING
MECHANICAL WORKS
1 AIRCON UNIT WORKING
2 RETURN AIR GRILL DIFFUSER WORKING
3 DUCTING SYSTEM WORKING
OSM INSTALLATION(for realme store)
1 CABINETS ARE ALL ALIGNED
2 LIGHTBOXES WORKING
3 TV CABINETS POWER WORKING
4 ACCESSORIES CABINETS POWER WORKING
5 TABLES POWER WORKING
6 CASHIER TABLE POWER WORKING
OSM INSTALLATION(for TechLife store)
1 TECHLIFE WALL RACKS ARE ALL ALIGNED
2 TECHLIFE APPLIANCE HEADER ALIGNED TO WALL RACKS
3 LIGHTBOXES WORKING
4 TECHLIFE WALL CABINETS POWER WORKING
5 TECHLIFE TV WALL RACK POWER WORKING
6 TECHLIFE HOME AND LIFESTYLE WALL RACK POWER WORKING
7 TABLES POWER WORKING
8 CASHIER TABLE POWER WORKING
OTHER WORKS
1
2
3
4
5
6
7
8

IMPORTANT NOTE:
ATTACH GPS PHOTOS OF ALL THE PARTIES PRESENT AND TURNOVER ON PROCESS, INCLUDING PUNCHLIST/FOR RECTIFICATION IF ANY.

Prepared By: RRM / Region Representative Witnessed By: OIC of Dealer / Dealer Representative
(Print Name and Signature) (Print Name and Signature)

Accepted By:Contractor Representative


(Print Name and Signature)

PLEASE ATTACH GPS PHOTOS OF ALL THE PARTIES PRESENT AND TURNOVER ON PROCESS;
INCLUDING PUNCHLIST/FOR RECTIFICATION IF ANY.

You might also like