Resumption Programme

The document outlines a resumption programme for a solid waste management project over 493 days. It includes preparatory work like equipment inspections, repairs, and assessments. It also includes various civil works like soil excavation, road works, and building rectifications.

Uploaded by

Planning HCEGC
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
24 views

Resumption Programme

The document outlines a resumption programme for a solid waste management project over 493 days. It includes preparatory work like equipment inspections, repairs, and assessments. It also includes various civil works like soil excavation, road works, and building rectifications.

Uploaded by

Planning HCEGC
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 11

ID Task Task Name Duration Start Finish % Complete Planned % Half 2, 2023 Half 1, 2024 Half 2, 2024

Mode Complete M J J A S O N D J F M A M J J A S O N D
1 Resumption Programme for Soild Waste Management Project 493 days Fri 6/2/23 Sun 10/6/24 0% 5%
2 Recommencement 0 days Fri 6/2/23 Fri 6/2/23 0% 100% 6/2
3 Preparatory work before resuming operations 171 days Fri 6/2/23 Sun 11/19/23 2% 13%
4 On-site equipment inspection before resumption of work (excluding 171 days Fri 6/2/23 Sun 11/19/23 3% 12%
insurance claims)
5 Mobilization 14 days Fri 6/2/23 Thu 6/15/23 40% 100%
6 Equipment check 30 days Fri 6/16/23 Sat 7/15/23 0% 23%
7 Preparation and Submission of the inventory check report 7 days Sun 7/16/23 Sat 7/22/23 0% 0%
8 Verification and approval of the inventory 30 days Sun 7/23/23 Mon 8/21/23 0% 0%
9 Procurement of lost and damaged equipment materials 30 days Tue 8/22/23 Wed 9/20/23 0% 0%
(compactors, gantry cranes)
10 Manufacturing and Trasportation of lost equipments 60 days Thu 9/21/23 Sun 11/19/23 0% 0%
11 ASL water-damaged equipment repair 97 days Fri 6/16/23 Wed 9/20/23 0% 5%
12 Southwest Institute's Asssesment 60 days Fri 6/16/23 Mon 8/14/23 0% 12%
13 Insurance Claims 90 days Fri 6/23/23 Wed 9/20/23 0% 0%
14 Specialized Works assesment 157 days Fri 6/16/23 Sun 11/19/23 0% 47%
15 Air Conditioner Repairs 15 days Fri 6/16/23 Fri 6/30/23 0% 47%
16 Weighing Bridge 15 days Fri 6/16/23 Fri 6/30/23 0% 47%
17 Condtions of the compactors 15 days Fri 6/16/23 Fri 6/30/23 0% 47%
18 Completion of Equipment assessment 0 days Sun 11/19/23 Sun 11/19/23 0% 0% 11/19
19 Civil Works 493 days Fri 6/2/23 Sun 10/6/24 1% 3%
20 ASL Area 493 days Fri 6/2/23 Sun 10/6/24 3% 2%
21 Soil Excavation ( Detention Pond) 108 days Fri 6/2/23 Sun 9/17/23 21% 19%
22 Dewatering 15 days Fri 6/2/23 Fri 6/16/23 100% 100%
23 Making Service Road 5 days Wed 6/14/23 Sun 6/18/23 95% 100%
24 Soil Excavation ( Detention Pond) 88 days Thu 6/22/23 Sun 9/17/23 3% 1%
25 Site cleaning and Earth Work (Roads) 12 days Mon 9/11/23 Fri 9/22/23 0% 0%
26 Surface Cleaning 12 days Mon 9/11/23 Fri 9/22/23 0% 0%
27 Demolishing (base failure and erosion area) 2 days Mon 9/11/23 Tue 9/12/23 0% 0%
28 Excavation (base failure and erosion area) 4 days Wed 9/13/23 Sat 9/16/23 0% 0%
29 Road Works (Base failure and erosion area) 24 days Sun 9/17/23 Tue 10/10/23 0% 0%
30 Sub Grade Preparation 5 days Sun 9/17/23 Thu 9/21/23 0% 0%
31 Sub Base Laying (425mm thick) 12 days Tue 9/19/23 Sat 9/30/23 0% 0%
32 ABC Laying (250mm thick) 14 days Wed 9/27/23 Tue 10/10/23 0% 0%
33 Structures 36 days Sat 10/21/23 Sat 11/25/23 0% 0%
34 Manhole Raise and Cover Placing 12 days Sat 10/21/23 Wed 11/1/23 0% 0%
35 Road Edge Kerbston placing 7 days Sun 11/19/23 Sat 11/25/23 0% 0%
36 Road Works 52 days Wed 10/11/23 Fri 12/1/23 0% 0%
37 Prime Coat (base failure and erosion area) 3 days Wed 10/11/23 Fri 10/13/23 0% 0%
38 60mm thickness Asphalt Binder Course Laying 18 days Sat 10/14/23 Tue 10/31/23 0% 0%
39 Tack Coat 19 days Thu 11/2/23 Mon 11/20/23 0% 0%
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Final-06.22.23.mpp
Milestone Inactive Summary Start-only Critical
Date: Thu 6/22/23
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 1
ID Task Task Name Duration Start Finish % Complete Planned % Half 2, 2023 Half 1, 2024 Half 2, 2024
Mode Complete M J J A S O N D J F M A M J J A S O N D
40 50mm thickness Asphalt Wearing Course Laying 19 days Thu 11/2/23 Mon 11/20/23 0% 0%
41 Road Marking 11 days Tue 11/21/23 Fri 12/1/23 0% 0%
42 Weight bridge control room rectification and balance works 59 days Sat 9/2/23 Mon 10/30/23 0% 0%
43 ASL Management building rectifications and balance works 180 days Sun 10/1/23 Thu 3/28/24 0% 0%
44 Comprehensive workshop 116 days Mon 1/29/24 Thu 5/23/24 0% 0%
45 Equipment room rectification and balance works 100 days Mon 3/25/24 Tue 7/2/24 0% 0%
46 Generator room rectification and balance works 58 days Mon 6/3/24 Tue 7/30/24 0% 0%
47 Storage room rectificaton and balance works 79 days Mon 7/1/24 Tue 9/17/24 0% 0%
48 Fuel tank rectification works 18 days Wed 9/18/24 Sat 10/5/24 0% 0%
49 Micellaneous works 19 days Wed 9/18/24 Sun 10/6/24 0% 0%
50 Completion of ASL Civil Works 0 days Sun 10/6/24 Sun 10/6/24 0% 0% 10/6
51 ATS Area 312 days Sat 9/2/23 Tue 7/9/24 0% 0%
52 Electric fence rectification 60 days Tue 1/2/24 Fri 3/1/24 0% 0%
53 Drain lines cleanning 80 days Sat 9/2/23 Mon 11/20/23 0% 0%
54 Sewage system including manholes 60 days Sat 3/2/24 Tue 4/30/24 0% 0%
55 Landscaping works 70 days Wed 5/1/24 Tue 7/9/24 0% 0%
56 Railway project management builidng rectification and balance 72 days Sat 9/2/23 Sun 11/12/23 0% 0%
works
57 Workshop and wokers rest room rectification and balance works 76 days Sat 10/14/23 Thu 12/28/23 0% 0%

58 Generator room rectifications and balance works 61 days Wed 11/29/23 Sun 1/28/24 0% 0%
59 Rectification works of the fuel tank 13 days Mon 1/29/24 Sat 2/10/24 0% 0%
60 Washing bay area cleaning and connecting 7 days Tue 12/26/23 Mon 1/1/24 0% 0%
61 Railway inspection pit cleaning 14 days Tue 11/21/23 Mon 12/4/23 0% 0%
62 Granty crane platform cleaning 21 days Tue 12/5/23 Mon 12/25/23 0% 0%
63 Completion of ATS works 0 days Tue 7/9/24 Tue 7/9/24 0% 0% 7/9
64 KTS Area 243 days Fri 6/2/23 Tue 1/30/24 0% 8%
65 Defects rectification 98 days Sat 9/2/23 Fri 12/8/23 0% 0%
66 Office builidng 14 days Sat 9/2/23 Fri 9/15/23 0% 0%
67 Workshop and wokers rest 14 days Sat 9/16/23 Fri 9/29/23 0% 0%
68 Generator distribution and control building 7 days Sat 9/30/23 Fri 10/6/23 0% 0%
69 Comprehensive workshop 14 days Sat 10/7/23 Fri 10/20/23 0% 0%
70 Equipment room 14 days Sat 10/21/23 Fri 11/3/23 0% 0%
71 Transfer station building 14 days Sat 11/4/23 Fri 11/17/23 0% 0%
72 Granty crane platform 21 days Sat 11/18/23 Fri 12/8/23 0% 0%
73 Bridges repair and balance work 14 days Sat 12/9/23 Fri 12/22/23 0% 0%
74 East road slope turfing & gate column construction 14 days Sat 12/23/23 Fri 1/5/24 0% 0%
75 Chainlink fence 25 days Sat 1/6/24 Tue 1/30/24 0% 0%
76 Storm water and sewage system balance works 14 days Sat 12/23/23 Fri 1/5/24 0% 0%
77 Marshy land resotration works 105 days Fri 6/2/23 Thu 9/14/23 0% 20%
78 Earth removal 60 days Fri 6/2/23 Mon 7/31/23 0% 35%
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Final-06.22.23.mpp
Milestone Inactive Summary Start-only Critical
Date: Thu 6/22/23
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 2
ID Task Task Name Duration Start Finish % Complete Planned % Half 2, 2023 Half 1, 2024 Half 2, 2024
Mode Complete M J J A S O N D J F M A M J J A S O N D
79 Canal excavation and restoration 45 days Tue 8/1/23 Thu 9/14/23 0% 0%
80 Completion of KTS Civil Works 0 days Fri 1/5/24 Fri 1/5/24 0% 0% 1/5
81 Machine flood damages rectification 126 days Fri 6/2/23 Thu 10/5/23 0% 7%
82 Cleaning of cable trenches 14 days Fri 7/21/23 Thu 8/3/23 0% 0%
83 Ordering switchinggear items 70 days Fri 6/2/23 Thu 8/10/23 0% 30%
84 Electrical switchboards 126 days Fri 6/2/23 Thu 10/5/23 0% 17%
85 LV Power distribution cabinet 98 days Fri 6/2/23 Thu 9/7/23 0% 44%
86 Dismantle the panel 14 days Fri 6/2/23 Thu 6/15/23 0% 100%
87 Clean & power coating the enclosure 21 days Fri 6/2/23 Thu 6/22/23 0% 100%
88 Reassemble the panel 28 days Fri 6/2/23 Thu 6/29/23 0% 75%
89 Wiring & assemble the components 42 days Fri 6/2/23 Thu 7/13/23 0% 50%
90 Testing 14 days Fri 7/14/23 Thu 7/27/23 0% 0%
91 Delivery to the site & Installation 14 days Fri 7/28/23 Thu 8/10/23 0% 0%
92 Power & Control Cable Termination 14 days Fri 8/4/23 Thu 8/17/23 0% 0%
93 Precommissioning 7 days Fri 8/11/23 Thu 8/17/23 0% 0%
94 Commissioning 21 days Fri 8/18/23 Thu 9/7/23 0% 0%
95 PLC CABINET 70 days Fri 7/21/23 Thu 9/28/23 0% 0%
96 Dismantle the Panel 7 days Fri 7/21/23 Thu 7/27/23 0% 0%
97 Clean & Powder Coating the Enclosure 7 days Fri 7/28/23 Thu 8/3/23 0% 0%
98 Reassemble the Panel 7 days Fri 8/4/23 Thu 8/10/23 0% 0%
99 Wiring & Assemble the Components 7 days Fri 8/11/23 Thu 8/17/23 0% 0%
100 Testing 7 days Fri 8/18/23 Thu 8/24/23 0% 0%
101 Deliver to Site 7 days Fri 8/25/23 Thu 8/31/23 0% 0%
102 Installation 7 days Fri 8/25/23 Thu 8/31/23 0% 0%
103 Power & Control Cable Termination 21 days Fri 8/25/23 Thu 9/14/23 0% 0%
104 Pre-Commissioning 7 days Fri 9/8/23 Thu 9/14/23 0% 0%
105 Commissioning 21 days Fri 9/8/23 Thu 9/28/23 0% 0%
106 ELECTRICAL CABINET FOR THE WHOLE SYSTEM 98 days Fri 6/2/23 Thu 9/7/23 0% 33%
107 Dismantle the Panel 28 days Fri 6/2/23 Thu 6/29/23 0% 75%
108 Clean & Powder Coating the Enclosure 35 days Fri 6/2/23 Thu 7/6/23 0% 60%
109 Reassemble the Panel 42 days Fri 6/2/23 Thu 7/13/23 0% 50%
110 Wiring & Assemble the Components 35 days Fri 6/16/23 Thu 7/20/23 0% 20%
111 Testing 7 days Fri 7/21/23 Thu 7/27/23 0% 0%
112 Deliver to Site 7 days Fri 7/28/23 Thu 8/3/23 0% 0%
113 Installation 7 days Fri 7/28/23 Thu 8/3/23 0% 0%
114 Power & Control Cable Termination 21 days Fri 7/28/23 Thu 8/17/23 0% 0%
115 Pre-Commissioning 7 days Fri 8/11/23 Thu 8/17/23 0% 0%
116 Commissioning 21 days Fri 8/18/23 Thu 9/7/23 0% 0%
117 MBR ULTRA FILTRATION SYSTEM UNIT 63 days Fri 7/28/23 Thu 9/28/23 0% 0%
118 Dismantle the Panel 7 days Fri 7/28/23 Thu 8/3/23 0% 0%

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Final-06.22.23.mpp
Milestone Inactive Summary Start-only Critical
Date: Thu 6/22/23
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 3
ID Task Task Name Duration Start Finish % Complete Planned % Half 2, 2023 Half 1, 2024 Half 2, 2024
Mode Complete M J J A S O N D J F M A M J J A S O N D
119 Clean & Powder Coating the Enclosure 7 days Fri 8/4/23 Thu 8/10/23 0% 0%
120 Reassemble the Panel 7 days Fri 8/11/23 Thu 8/17/23 0% 0%
121 Wiring & Assemble the Components 7 days Fri 8/18/23 Thu 8/24/23 0% 0%
122 Testing 7 days Fri 8/25/23 Thu 8/31/23 0% 0%
123 Deliver to Site 7 days Fri 8/25/23 Thu 8/31/23 0% 0%
124 Installation 7 days Fri 8/25/23 Thu 8/31/23 0% 0%
125 Power & Control Cable Termination 21 days Fri 8/25/23 Thu 9/14/23 0% 0%
126 Pre-Commissioning 7 days Fri 9/8/23 Thu 9/14/23 0% 0%
127 Commissioning 21 days Fri 9/8/23 Thu 9/28/23 0% 0%
128 NANO FILTRATION SYSTEM 70 days Fri 7/28/23 Thu 10/5/23 0% 0%
129 Dismantle the Panel 7 days Fri 7/28/23 Thu 8/3/23 0% 0%
130 Clean & Powder Coating the Enclosure 7 days Fri 8/4/23 Thu 8/10/23 0% 0%
131 Reassemble the Panel 7 days Fri 8/11/23 Thu 8/17/23 0% 0%
132 Wiring & Assemble the Components 7 days Fri 8/18/23 Thu 8/24/23 0% 0%
133 Testing 7 days Fri 8/25/23 Thu 8/31/23 0% 0%
134 Deliver to Site 7 days Fri 9/1/23 Thu 9/7/23 0% 0%
135 Installation 7 days Fri 9/1/23 Thu 9/7/23 0% 0%
136 Power & Control Cable Termination 21 days Fri 9/1/23 Thu 9/21/23 0% 0%
137 Pre-Commissioning 7 days Fri 9/15/23 Thu 9/21/23 0% 0%
138 Commissioning 21 days Fri 9/15/23 Thu 10/5/23 0% 0%
139 ELECTRICAL CONTROL CABINET INCLUDING PLC 77 days Fri 6/16/23 Thu 8/31/23 0% 7%
140 Dismantle the Panel 14 days Fri 6/16/23 Thu 6/29/23 0% 50%
141 Clean & Powder Coating the Enclosure 7 days Fri 6/30/23 Thu 7/6/23 0% 0%
142 Reassemble the Panel 7 days Fri 7/7/23 Thu 7/13/23 0% 0%
143 Wiring & Assemble the Components 7 days Fri 7/14/23 Thu 7/20/23 0% 0%
144 Testing 7 days Fri 7/21/23 Thu 7/27/23 0% 0%
145 Deliver to Site 7 days Fri 7/28/23 Thu 8/3/23 0% 0%
146 Installation 7 days Fri 7/28/23 Thu 8/3/23 0% 0%
147 Power & Control Cable Termination 21 days Fri 7/28/23 Thu 8/17/23 0% 0%
148 Pre-Commissioning 7 days Fri 8/11/23 Thu 8/17/23 0% 0%
149 Commissioning 21 days Fri 8/11/23 Thu 8/31/23 0% 0%
150 ELECTRICAL CABINET - SLUDGE TREATMENT SYSTEM 77 days Fri 6/16/23 Thu 8/31/23 0% 7%
151 Dismantle the Panel 14 days Fri 6/16/23 Thu 6/29/23 0% 50%
152 Clean & Powder Coating the Enclosure 7 days Fri 6/30/23 Thu 7/6/23 0% 0%
153 Reassemble the Panel 7 days Fri 7/7/23 Thu 7/13/23 0% 0%
154 Wiring & Assemble the Components 7 days Fri 7/14/23 Thu 7/20/23 0% 0%
155 Testing 7 days Fri 7/21/23 Thu 7/27/23 0% 0%
156 Deliver to Site 7 days Fri 7/28/23 Thu 8/3/23 0% 0%
157 Installation 7 days Fri 7/28/23 Thu 8/3/23 0% 0%
158 Power & Control Cable Termination 21 days Fri 7/28/23 Thu 8/17/23 0% 0%

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Final-06.22.23.mpp
Milestone Inactive Summary Start-only Critical
Date: Thu 6/22/23
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 4
ID Task Task Name Duration Start Finish % Complete Planned % Half 2, 2023 Half 1, 2024 Half 2, 2024
Mode Complete M J J A S O N D J F M A M J J A S O N D
159 Pre-Commissioning 7 days Fri 8/11/23 Thu 8/17/23 0% 0%
160 Commissioning 21 days Fri 8/11/23 Thu 8/31/23 0% 0%
161 ELECTRICAL CABINET - OXIDATION SYSTEM 77 days Fri 6/16/23 Thu 8/31/23 0% 7%
162 Dismantle the Panel 14 days Fri 6/16/23 Thu 6/29/23 0% 50%
163 Clean & Powder Coating the Enclosure 7 days Fri 6/30/23 Thu 7/6/23 0% 0%
164 Reassemble the Panel 7 days Fri 7/7/23 Thu 7/13/23 0% 0%
165 Wiring & Assemble the Components 7 days Fri 7/14/23 Thu 7/20/23 0% 0%
166 Testing 7 days Fri 7/21/23 Thu 7/27/23 0% 0%
167 Deliver to Site 7 days Fri 7/28/23 Thu 8/3/23 0% 0%
168 Installation 7 days Fri 7/28/23 Thu 8/3/23 0% 0%
169 Power & Control Cable Termination 21 days Fri 7/28/23 Thu 8/17/23 0% 0%
170 Pre-Commissioning 7 days Fri 8/11/23 Thu 8/17/23 0% 0%
171 Commissioning 21 days Fri 8/11/23 Thu 8/31/23 0% 0%
172 PLC CABINET FOR THE WHOLE SYSTEM 70 days Fri 6/30/23 Thu 9/7/23 0% 21%
173 Dismantle the Panel 7 days Fri 6/30/23 Thu 7/6/23 0% 100%
174 Clean & Powder Coating the Enclosure 7 days Fri 7/7/23 Thu 7/13/23 0% 100%
175 Reassemble the Panel 7 days Fri 7/14/23 Thu 7/20/23 0% 100%
176 Wiring & Assemble the Components 7 days Fri 7/21/23 Thu 7/27/23 0% 0%
177 Testing 7 days Fri 7/28/23 Thu 8/3/23 0% 0%
178 Deliver to Site 7 days Fri 8/4/23 Thu 8/10/23 0% 0%
179 Installation 7 days Fri 8/4/23 Thu 8/10/23 0% 0%
180 Power & Control Cable Termination 21 days Fri 8/4/23 Thu 8/24/23 0% 0%
181 Pre-Commissioning 7 days Fri 8/18/23 Thu 8/24/23 0% 0%
182 Commissioning 21 days Fri 8/18/23 Thu 9/7/23 0% 0%
183 PUMPS AND MOTORS 63 days Tue 7/4/23 Mon 9/4/23 0% 0%
184 CENTRIFUGAL FAN : 41000M3/H, 75KW, 3200PA, IP55 35 days Tue 8/1/23 Mon 9/4/23 0% 0%
185 Testing 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
186 Deliver to Site 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
187 Installation 21 days Tue 8/1/23 Mon 8/21/23 0% 0%
188 Pre-Commissioning 7 days Tue 8/15/23 Mon 8/21/23 0% 0%
189 Commissioning 21 days Tue 8/15/23 Mon 9/4/23 0% 0%
190 CIRCULATING WATER PUMP: Q=16M3/H, N=3.0KW, H=30-40M, 35 days Tue 8/1/23 Mon 9/4/23 0% 0%
IP55
191 Testing 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
192 Deliver to Site 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
193 Installation 21 days Tue 8/1/23 Mon 8/21/23 0% 0%
194 Pre-Commissioning 7 days Tue 8/15/23 Mon 8/21/23 0% 0%
195 Commissioning 21 days Tue 8/15/23 Mon 9/4/23 0% 0%
196 SPRINKLING WATER PUMP Q=16 M3/H, N=3.0KW, H=30-40M, 35 days Tue 8/1/23 Mon 9/4/23 0% 0%
IP55
197 Testing 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Final-06.22.23.mpp
Milestone Inactive Summary Start-only Critical
Date: Thu 6/22/23
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 5
ID Task Task Name Duration Start Finish % Complete Planned % Half 2, 2023 Half 1, 2024 Half 2, 2024
Mode Complete M J J A S O N D J F M A M J J A S O N D
198 Deliver to Site 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
199 Installation 21 days Tue 8/1/23 Mon 8/21/23 0% 0%
200 Pre-Commissioning 7 days Tue 8/15/23 Mon 8/21/23 0% 0%
201 Commissioning 21 days Tue 8/15/23 Mon 9/4/23 0% 0%
202 CHEMICAL SORUBBER TOWER DIA. 3.2MM X 6.6M 35 days Tue 8/1/23 Mon 9/4/23 0% 0%
203 Testing 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
204 Deliver to Site 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
205 Installation 21 days Tue 8/1/23 Mon 8/21/23 0% 0%
206 Pre-Commissioning 7 days Tue 8/15/23 Mon 8/21/23 0% 0%
207 Commissioning 21 days Tue 8/15/23 Mon 9/4/23 0% 0%
208 SPRINKLING WATER PUMP Q=60M3/H, H=25M 35 days Tue 8/1/23 Mon 9/4/23 0% 0%
209 Testing 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
210 Deliver to Site 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
211 Installation 21 days Tue 8/1/23 Mon 8/21/23 0% 0%
212 Pre-Commissioning 7 days Tue 8/15/23 Mon 8/21/23 0% 0%
213 Commissioning 21 days Tue 8/15/23 Mon 9/4/23 0% 0%
214 PUMP 35 days Tue 8/1/23 Mon 9/4/23 0% 0%
215 Testing 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
216 Deliver to Site 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
217 Installation 21 days Tue 8/1/23 Mon 8/21/23 0% 0%
218 Pre-Commissioning 7 days Tue 8/15/23 Mon 8/21/23 0% 0%
219 Commissioning 21 days Tue 8/15/23 Mon 9/4/23 0% 0%
220 FLAME ARRESTOR 49 days Tue 7/18/23 Mon 9/4/23 0% 0%
221 Dismantle & Clean the Motor 14 days Tue 7/18/23 Mon 7/31/23 0% 0%
222 Service & Assemble the Motor 14 days Tue 7/25/23 Mon 8/7/23 0% 0%
223 Testing 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
224 Deliver to Site 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
225 Installation 21 days Tue 8/1/23 Mon 8/21/23 0% 0%
226 Pre-Commissioning 7 days Tue 8/15/23 Mon 8/21/23 0% 0%
227 Commissioning 21 days Tue 8/15/23 Mon 9/4/23 0% 0%
228 DIVING MIXER FOR BALANCING TANK 63 days Tue 7/4/23 Mon 9/4/23 0% 0%
229 Dismantle & Clean the Motor 14 days Tue 7/4/23 Mon 7/17/23 0% 0%
230 Service & Assemble the Motor 14 days Tue 7/11/23 Mon 7/24/23 0% 0%
231 Testing 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
232 Deliver to Site 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
233 Installation 21 days Tue 8/1/23 Mon 8/21/23 0% 0%
234 Pre-Commissioning 7 days Tue 8/15/23 Mon 8/21/23 0% 0%
235 Commissioning 21 days Tue 8/15/23 Mon 9/4/23 0% 0%
236 DIVING MIXTURE OF CARBON SOURCE TANK 63 days Tue 7/4/23 Mon 9/4/23 0% 0%
237 Dismantle & Clean the Motor 14 days Tue 7/4/23 Mon 7/17/23 0% 0%

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Final-06.22.23.mpp
Milestone Inactive Summary Start-only Critical
Date: Thu 6/22/23
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 6
ID Task Task Name Duration Start Finish % Complete Planned % Half 2, 2023 Half 1, 2024 Half 2, 2024
Mode Complete M J J A S O N D J F M A M J J A S O N D
238 Service & Assemble the Motor 14 days Tue 7/11/23 Mon 7/24/23 0% 0%
239 Testing 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
240 Deliver to Site 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
241 Installation 21 days Tue 8/1/23 Mon 8/21/23 0% 0%
242 Pre-Commissioning 7 days Tue 8/15/23 Mon 8/21/23 0% 0%
243 Commissioning 21 days Tue 8/15/23 Mon 9/4/23 0% 0%
244 DIVIDING MIXTURE 63 days Tue 7/4/23 Mon 9/4/23 0% 0%
245 Dismantle & Clean the Motor 14 days Tue 7/4/23 Mon 7/17/23 0% 0%
246 Service & Assemble the Motor 14 days Tue 7/11/23 Mon 7/24/23 0% 0%
247 Testing 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
248 Deliver to Site 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
249 Installation 21 days Tue 8/1/23 Mon 8/21/23 0% 0%
250 Pre-Commissioning 7 days Tue 8/15/23 Mon 8/21/23 0% 0%
251 Commissioning 21 days Tue 8/15/23 Mon 9/4/23 0% 0%
252 INLET PUMP OF MBR 49 days Tue 7/18/23 Mon 9/4/23 0% 0%
253 Dismantle & Clean the Motor 14 days Tue 7/18/23 Mon 7/31/23 0% 0%
254 Service & Assemble the Motor 14 days Tue 7/25/23 Mon 8/7/23 0% 0%
255 Testing 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
256 Deliver to Site 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
257 Installation 21 days Tue 8/1/23 Mon 8/21/23 0% 0%
258 Pre-Commissioning 7 days Tue 8/15/23 Mon 8/21/23 0% 0%
259 Commissioning 21 days Tue 8/15/23 Mon 9/4/23 0% 0%
260 PRIMARY SECONDARY NITRIFICATION PUMP 63 days Tue 7/4/23 Mon 9/4/23 0% 0%
261 Dismantle & Clean the Motor 14 days Tue 7/4/23 Mon 7/17/23 0% 0%
262 Service & Assemble the Motor 14 days Tue 7/11/23 Mon 7/24/23 0% 0%
263 Testing 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
264 Deliver to Site 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
265 Installation 21 days Tue 8/1/23 Mon 8/21/23 0% 0%
266 Pre-Commissioning 7 days Tue 8/15/23 Mon 8/21/23 0% 0%
267 Commissioning 21 days Tue 8/15/23 Mon 9/4/23 0% 0%
268 ROOTS BLOWER 49 days Tue 7/18/23 Mon 9/4/23 0% 0%
269 Dismantle & Clean the Motor 14 days Tue 7/18/23 Mon 7/31/23 0% 0%
270 Service & Assemble the Motor 14 days Tue 7/25/23 Mon 8/7/23 0% 0%
271 Testing 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
272 Deliver to Site 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
273 Installation 21 days Tue 8/1/23 Mon 8/21/23 0% 0%
274 Pre-Commissioning 7 days Tue 8/15/23 Mon 8/21/23 0% 0%
275 Commissioning 21 days Tue 8/15/23 Mon 9/4/23 0% 0%
276 COOLING SLUDGE PUMP; CENTRIFUGAL PUMP 63 days Tue 7/4/23 Mon 9/4/23 0% 0%
277 Dismantle & Clean the Motor 14 days Tue 7/4/23 Mon 7/17/23 0% 0%

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Final-06.22.23.mpp
Milestone Inactive Summary Start-only Critical
Date: Thu 6/22/23
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 7
ID Task Task Name Duration Start Finish % Complete Planned % Half 2, 2023 Half 1, 2024 Half 2, 2024
Mode Complete M J J A S O N D J F M A M J J A S O N D
278 Service & Assemble the Motor 14 days Tue 7/11/23 Mon 7/24/23 0% 0%
279 Testing 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
280 Deliver to Site 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
281 Installation 21 days Tue 8/1/23 Mon 8/21/23 0% 0%
282 Pre-Commissioning 7 days Tue 8/15/23 Mon 8/21/23 0% 0%
283 Commissioning 21 days Tue 8/15/23 Mon 9/4/23 0% 0%
284 DEFOAMER CIRCULATION PUMP: CENTRIFUGAL PUMP 63 days Tue 7/4/23 Mon 9/4/23 0% 0%
285 Dismantle & Clean the Motor 14 days Tue 7/4/23 Mon 7/17/23 0% 0%
286 Service & Assemble the Motor 14 days Tue 7/11/23 Mon 7/24/23 0% 0%
287 Testing 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
288 Deliver to Site 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
289 Installation 21 days Tue 8/1/23 Mon 8/21/23 0% 0%
290 Pre-Commissioning 7 days Tue 8/15/23 Mon 8/21/23 0% 0%
291 Commissioning 21 days Tue 8/15/23 Mon 9/4/23 0% 0%
292 MBR ULTRAFILTRATION PROCESSING UNIT 63 days Tue 7/4/23 Mon 9/4/23 0% 0%
293 Dismantle & Clean the Motor 14 days Tue 7/4/23 Mon 7/17/23 0% 0%
294 Service & Assemble the Motor 14 days Tue 7/11/23 Mon 7/24/23 0% 0%
295 Testing 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
296 Deliver to Site 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
297 Installation 21 days Tue 8/1/23 Mon 8/21/23 0% 0%
298 Pre-Commissioning 7 days Tue 8/15/23 Mon 8/21/23 0% 0%
299 Commissioning 21 days Tue 8/15/23 Mon 9/4/23 0% 0%
300 NANOFILTRATION SYSTEM 63 days Tue 7/4/23 Mon 9/4/23 0% 0%
301 Dismantle & Clean the Motor 14 days Tue 7/4/23 Mon 7/17/23 0% 0%
302 Service & Assemble the Motor 14 days Tue 7/11/23 Mon 7/24/23 0% 0%
303 Testing 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
304 Deliver to Site 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
305 Installation 21 days Tue 8/1/23 Mon 8/21/23 0% 0%
306 Pre-Commissioning 7 days Tue 8/15/23 Mon 8/21/23 0% 0%
307 Commissioning 21 days Tue 8/15/23 Mon 9/4/23 0% 0%
308 FLOCCULANT DOSING PUMP 63 days Tue 7/4/23 Mon 9/4/23 0% 0%
309 Dismantle & Clean the Motor 14 days Tue 7/4/23 Mon 7/17/23 0% 0%
310 Service & Assemble the Motor 14 days Tue 7/11/23 Mon 7/24/23 0% 0%
311 Testing 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
312 Deliver to Site 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
313 Installation 21 days Tue 8/1/23 Mon 8/21/23 0% 0%
314 Pre-Commissioning 7 days Tue 8/15/23 Mon 8/21/23 0% 0%
315 Commissioning 21 days Tue 8/15/23 Mon 9/4/23 0% 0%
316 PUMP 63 days Tue 7/4/23 Mon 9/4/23 0% 0%
317 Dismantle & Clean the Motor 14 days Tue 7/4/23 Mon 7/17/23 0% 0%

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Final-06.22.23.mpp
Milestone Inactive Summary Start-only Critical
Date: Thu 6/22/23
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 8
ID Task Task Name Duration Start Finish % Complete Planned % Half 2, 2023 Half 1, 2024 Half 2, 2024
Mode Complete M J J A S O N D J F M A M J J A S O N D
318 Service & Assemble the Motor 14 days Tue 7/11/23 Mon 7/24/23 0% 0%
319 Testing 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
320 Deliver to Site 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
321 Installation 21 days Tue 8/1/23 Mon 8/21/23 0% 0%
322 Pre-Commissioning 7 days Tue 8/15/23 Mon 8/21/23 0% 0%
323 Commissioning 21 days Tue 8/15/23 Mon 9/4/23 0% 0%
324 PAC DOSING DEVICE 49 days Tue 7/18/23 Mon 9/4/23 0% 0%
325 Dismantle & Clean the Motor 14 days Tue 7/18/23 Mon 7/31/23 0% 0%
326 Service & Assemble the Motor 14 days Tue 7/25/23 Mon 8/7/23 0% 0%
327 Testing 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
328 Deliver to Site 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
329 Installation 21 days Tue 8/1/23 Mon 8/21/23 0% 0%
330 Pre-Commissioning 7 days Tue 8/15/23 Mon 8/21/23 0% 0%
331 Commissioning 21 days Tue 8/15/23 Mon 9/4/23 0% 0%
332 ROOTS BLOWER 63 days Tue 7/4/23 Mon 9/4/23 0% 0%
333 Dismantle & Clean the Motor 21 days Tue 7/4/23 Mon 7/24/23 0% 0%
334 Service & Assemble the Motor 28 days Tue 7/11/23 Mon 8/7/23 0% 0%
335 Testing 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
336 Deliver to Site 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
337 Installation 21 days Tue 8/1/23 Mon 8/21/23 0% 0%
338 Pre-Commissioning 7 days Tue 8/15/23 Mon 8/21/23 0% 0%
339 Commissioning 21 days Tue 8/15/23 Mon 9/4/23 0% 0%
340 AEREATORS 42 days Tue 7/25/23 Mon 9/4/23 0% 0%
341 Dismantle & Clean the Motor 21 days Tue 7/25/23 Mon 8/14/23 0% 0%
342 Service & Assemble the Motor 28 days Tue 8/1/23 Mon 8/28/23 0% 0%
343 Testing 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
344 Deliver to Site 7 days Tue 8/1/23 Mon 8/7/23 0% 0%
345 Installation 21 days Tue 8/1/23 Mon 8/21/23 0% 0%
346 Pre-Commissioning 7 days Tue 8/15/23 Mon 8/21/23 0% 0%
347 Commissioning 21 days Tue 8/15/23 Mon 9/4/23 0% 0%
348 Commencing on-site work after preparatory works 201 days Mon 11/20/23 Fri 6/7/24 0% 0%
349 Activated Sludge Liquid(ASL) work schedule 119 days Mon 11/20/23 Sun 3/17/24 0% 0%
350 Retrial of ASL infiltrate operation 119 days Mon 11/20/23 Sun 3/17/24 0% 0%
351 Trial run preparation stage 56 days Mon 11/20/23 Sun 1/14/24 0% 0%
352 Equipment defect rectification and chemical procurement 30 days Mon 11/20/23 Tue 12/19/23 0% 0%

353 Inoculation of activated sludge 7 days Wed 12/20/23 Tue 12/26/23 0% 0%


354 Domestication of sludge with infiltrate 16 days Wed 12/27/23 Thu 1/11/24 0% 0%
355 Low-load continuous operation for 72 hours 3 days Fri 1/12/24 Sun 1/14/24 0% 0%
356 Phase 1 of trial operation 26 days Mon 1/15/24 Fri 2/9/24 0% 0%

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Final-06.22.23.mpp
Milestone Inactive Summary Start-only Critical
Date: Thu 6/22/23
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 9
ID Task Task Name Duration Start Finish % Complete Planned % Half 2, 2023 Half 1, 2024 Half 2, 2024
Mode Complete M J J A S O N D J F M A M J J A S O N D
357 Gradually ramp up to full load 26 days Mon 1/15/24 Fri 2/9/24 0% 0%
358 Phase 2 of trial operation 37 days Sat 2/10/24 Sun 3/17/24 0% 0%
359 Reliability test 30 days Sat 2/10/24 Sun 3/10/24 0% 0%
360 Employer's Acceptance 7 days Mon 3/11/24 Sun 3/17/24 0% 0%
361 Retrial of ASL deodorization project operation 77 days Wed 12/20/23 Tue 3/5/24 0% 0%
362 Equipment defect rectification and chemical procurement 30 days Wed 12/20/23 Thu 1/18/24 0% 0%

363 Inoculation of microbial strains 7 days Fri 1/19/24 Thu 1/25/24 0% 0%


364 Continuous operation at low load for 72 hours 3 days Fri 1/26/24 Sun 1/28/24 0% 0%
365 Reliability test 30 days Mon 1/29/24 Tue 2/27/24 0% 0%
366 Employer's Acceptance 7 days Wed 2/28/24 Tue 3/5/24 0% 0%
367 ASL sluice gates and water pumps 30 days Sat 2/10/24 Sun 3/10/24 0% 0%
368 Finishing of remaining tasks 30 days Sat 2/10/24 Sun 3/10/24 0% 0%
369 Rectification of minor issues in ASL 30 days Wed 12/20/23 Thu 1/18/24 0% 0%
370 Defect rectification 30 days Wed 12/20/23 Thu 1/18/24 0% 0%
371 ATS work plan 44 days Mon 11/20/23 Tue 1/2/24 0% 0%
372 Installation of ATS gantry crane 44 days Mon 11/20/23 Tue 1/2/24 0% 0%
373 On-site installation 30 days Mon 11/20/23 Tue 12/19/23 0% 0%
374 Commissioning 14 days Wed 12/20/23 Tue 1/2/24 0% 0%
375 Installation of ATS air conditioning 44 days Mon 11/20/23 Tue 1/2/24 0% 0%
376 Procurement 30 days Mon 11/20/23 Tue 12/19/23 0% 0%
377 Installation 14 days Wed 12/20/23 Tue 1/2/24 0% 0%
378 ASL&ATS fire protection 37 days Mon 11/20/23 Tue 12/26/23 0% 0%
379 Defect rectification and commissioning 30 days Mon 11/20/23 Tue 12/19/23 0% 0%
380 Employer acceptance of fire safety system 7 days Wed 12/20/23 Tue 12/26/23 0% 0%
381 KTS work plan 201 days Mon 11/20/23 Fri 6/7/24 0% 0%
382 KTS leachate trial run 201 days Mon 11/20/23 Fri 6/7/24 0% 0%
383 Trial run preparation phase 56 days Sat 2/10/24 Fri 4/5/24 0% 0%
384 Equipment defect rectification and chemical procurement 30 days Sat 2/10/24 Sun 3/10/24 0% 0%

385 Inoculation of activated sludge 7 days Mon 3/11/24 Sun 3/17/24 0% 0%


386 Inoculation of sludge with leachate for acclimation 16 days Mon 3/18/24 Tue 4/2/24 0% 0%
387 Continuous operation at low load for 72 hours 3 days Wed 4/3/24 Fri 4/5/24 0% 0%
388 First stage of trial run 26 days Sat 4/6/24 Wed 5/1/24 0% 0%
389 Gradually ramp up to full load 26 days Sat 4/6/24 Wed 5/1/24 0% 0%
390 Second stage of trial operation 37 days Thu 5/2/24 Fri 6/7/24 0% 0%
391 Reliability test 30 days Thu 5/2/24 Fri 5/31/24 0% 0%
392 Employer's Acceptance 7 days Sat 6/1/24 Fri 6/7/24 0% 0%
393 Electrical Works 201 days Mon 11/20/23 Fri 6/7/24 0% 0%
394 Generator commissioning 22 days Mon 11/20/23 Mon 12/11/23 0% 0%
395 Defect rectification 15 days Mon 11/20/23 Mon 12/4/23 0% 0%
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Final-06.22.23.mpp
Milestone Inactive Summary Start-only Critical
Date: Thu 6/22/23
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 10
ID Task Task Name Duration Start Finish % Complete Planned % Half 2, 2023 Half 1, 2024 Half 2, 2024
Mode Complete M J J A S O N D J F M A M J J A S O N D
396 Testing 7 days Tue 12/5/23 Mon 12/11/23 0% 0%
397 KTS automation and control engineering 37 days Mon 11/20/23 Tue 12/26/23 0% 0%
398 Fiber optic cabling 15 days Mon 11/20/23 Mon 12/4/23 0% 0%
399 Security system testing 7 days Tue 12/5/23 Mon 12/11/23 0% 0%
400 Full-site commissioning 15 days Tue 12/12/23 Tue 12/26/23 0% 0%
401 KTS odor control 77 days Wed 2/28/24 Tue 5/14/24 0% 0%
402 Equipment defect rectification and chemical procurement 30 days Wed 2/28/24 Thu 3/28/24 0% 0%

403 Inoculation of microbial strains 7 days Fri 3/29/24 Thu 4/4/24 0% 0%


404 Continuous operation at low load for 72 hours 3 days Fri 4/5/24 Sun 4/7/24 0% 0%
405 Reliability testing 30 days Mon 4/8/24 Tue 5/7/24 0% 0%
406 Employer acceptance 7 days Wed 5/8/24 Tue 5/14/24 0% 0%
407 KTS compactor installation 75 days Mon 11/20/23 Fri 2/2/24 0% 0%
408 Mobilization 30 days Mon 11/20/23 Tue 12/19/23 0% 0%
409 Defect rectification 30 days Wed 12/20/23 Thu 1/18/24 0% 0%
410 Installation 30 days Wed 12/20/23 Thu 1/18/24 0% 0%
411 Adjusting and fixing errors 15 days Fri 1/19/24 Fri 2/2/24 0% 0%
412 Installation of KTS gantry crane 44 days Wed 1/3/24 Thu 2/15/24 0% 0%
413 Installation 30 days Wed 1/3/24 Thu 2/1/24 0% 0%
414 Adjusting and fixing errors 14 days Fri 2/2/24 Thu 2/15/24 0% 0%
415 Installation of KTS weighbridge 44 days Mon 11/20/23 Tue 1/2/24 0% 0%
416 Installation 30 days Mon 11/20/23 Tue 12/19/23 0% 0%
417 Adjusting and fixing errors 14 days Wed 12/20/23 Tue 1/2/24 0% 0%
418 Installation of KTS air conditioning 157 days Wed 1/3/24 Fri 6/7/24 0% 0%
419 Procurement 60 days Wed 1/3/24 Sat 3/2/24 0% 0%
420 Installation 14 days Sun 3/3/24 Sat 3/16/24 0% 0%
421 Completion of commencement 0 days Fri 6/7/24 Fri 6/7/24 0% 0% 6/7

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Final-06.22.23.mpp
Milestone Inactive Summary Start-only Critical
Date: Thu 6/22/23
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress