Boq For Asphalt Roads & Parking 1
Boq For Asphalt Roads & Parking 1
A
TCF SITE - 1 (CAMP & SITE OFFICE)
ASPHALT WORKS for Roads & Car Parking. Total Area for Type I, II, II & IV = 60,970
m2
Ref Dwg. S-CI-DAL-1002 sht 001 & S-CI-DRD-1001 sht 001
Civil Works
Civil Works
Civil Works
Page 1 of 8
SAUDI ARAMCO
TEMPORARY CONSTRUCTION FACILITIES - TCF -1, TCF2 & TCF 3
FIELD GAS COMPRESSION PROJECT
HARADH & HAWIYAH - KSA
Amount
Item Description Unit Qty Rate
S.R
4 230mm thk Aggregate base course m3 2,662 40.00 106,480.00
Civil Works
A5 ASPHALT WORKS for Roads & Car Parking. Total Area for Type I & II = 68,341 m2
Ref Dwg. S-CI-DAL-1002 sht 001 & S-CI-DRD-1001 sht 001
Type I - 15m wide Road ( Area = 8,383 m2)
Page 2 of 8
SAUDI ARAMCO
TEMPORARY CONSTRUCTION FACILITIES - TCF -1, TCF2 & TCF 3
FIELD GAS COMPRESSION PROJECT
HARADH & HAWIYAH - KSA
Amount
Item Description Unit Qty Rate
S.R
3 230mm thk Sub-base Course m3 16,171 40.00 646,840.00
Summary of TCF1
1 600mm thk Excavation m3 212,799.00 10.00 2,127,990.00
2 Disposal of Excavated Soil Materials m3 212,799.00 5.00 1,063,995.00
3 230mm thk Sub-base Course m3 77,017.00 40.00 3,080,680.00
4 230mm thk Aggregate base course m3 71,071.00 40.00 2,842,840.00
Page 3 of 8
SAUDI ARAMCO
TEMPORARY CONSTRUCTION FACILITIES - TCF -1, TCF2 & TCF 3
FIELD GAS COMPRESSION PROJECT
HARADH & HAWIYAH - KSA
Amount
Item Description Unit Qty Rate
S.R
5 Prime Coat Liquid Asphalt -MC - 70 m2 283,782.00 3.00 851,346.00
6 90mm thick Asphalt Binder Course Class A m3 32,331.00 380.00 12,285,780.00
7 Tack Coat RC - 250 m2 283,782.00 3.00 851,346.00
8 50mm thk Asphalt Wearing Course Class A m3 14,190.00 380.00 5,392,200.00
Total for Asphalt Roads & Parking - TC1 28,496,177.00
Page 4 of 8
SAUDI ARAMCO
TEMPORARY CONSTRUCTION FACILITIES - TCF -1, TCF2 & TCF 3
FIELD GAS COMPRESSION PROJECT
HARADH & HAWIYAH - KSA
Amount
Item Description Unit Qty Rate
S.R
Page 5 of 8
SAUDI ARAMCO
TEMPORARY CONSTRUCTION FACILITIES - TCF -1, TCF2 & TCF 3
FIELD GAS COMPRESSION PROJECT
HARADH & HAWIYAH - KSA
Amount
Item Description Unit Qty Rate
S.R
Asphalt Paving for External Roads & Roundabout
(15m Wide Roads)
B3
Total Area = 132,228 m2
(Drawing S-CI-DRD-1001-001)
1 600mm thk Excavation m3 79,337 10.00 793,368.00
2 Disposal of Scraped Soil materials m 3
79,337 5.00 396,684.00
3 230mm thk Sub Base Materials with Aggregates having grading (Class A & B) m3 30,412 40.00 1,216,497.60
4 230mm thk Aggregate Base Course (Class B) m3 30,412 40.00 1,216,497.60
5 Prime Coat M-70 m 2
132,228 3.00 396,684.00
6 90mm thk Asphalt Concrete Binder Course m 3
11,901 380.00 4,522,197.60
7 Tack Coat m2 132,228 3.00 396,684.00
8 50mm thk Asphalt Surface/Wearing Course m3 6,611 380.00 2,512,332.00
Summary of TCF2
Excavtion for (230mm thk Sub Base, 230mm thk Aggregate Base
1 m3 175,262 10.00
Course,90mm thk Binder Course & 50mm thk Wearing Course)
1,752,618.00
2 Disposal of Scraped Soil materials m3 175,262 5.00 876,309.00
3 230mm thk Sub Base Materials with Aggregates having grading (Class A & B) m3 67,184
40.00 2,687,347.60
4 230mm thk Aggregate Base Course (Class B) m3 67,184 40.00 2,687,347.60
5 Prime Coat M-70 m2 298,103 3.00 894,309.00
6 90mm thk Asphalt Concrete Binder Course m 3
26,289 380.00 9,989,922.60
7 Tack Coat m2 298,103 3.00 894,309.00
8 50mm thk Asphalt Surface/Wearing Course m3 14,605 380.00 5,549,957.00
Total for Asphalt Roads & Parking - TC2 25,332,119.80
Page 6 of 8
SAUDI ARAMCO
TEMPORARY CONSTRUCTION FACILITIES - TCF -1, TCF2 & TCF 3
FIELD GAS COMPRESSION PROJECT
HARADH & HAWIYAH - KSA
Amount
Item Description Unit Qty Rate
S.R
3 230mm thk Sub Base Materials with Aggregates having grading (Class A & B) m3 11,127 40.00 445,086.80
3 230mm thk Sub Base Materials with Aggregates having grading (Class A & B) m3 12,731 40.00 509,247.60
Page 7 of 8
SAUDI ARAMCO
TEMPORARY CONSTRUCTION FACILITIES - TCF -1, TCF2 & TCF 3
FIELD GAS COMPRESSION PROJECT
HARADH & HAWIYAH - KSA
Amount
Item Description Unit Qty Rate
S.R
3 230mm thk Sub Base Materials with Aggregates having grading (Class A & B) m3 30,204 40.00 1,208,153.20
3 230mm thk Sub Base Materials with Aggregates having grading (Class A & B) m3 13,877 40.00 555,063.60
Summary of TCF3
1 Excavation m3 177,232 10.00 1,772,316.00
3 230mm thk Sub Base Materials with Aggregates having grading (Class A & B) m3 67,939 40.00 2,717,551.20
Page 8 of 8