The document is an inventory list of assets at the Piayu WTP in Batam. It contains details of 9 intake pumps, chemical dosing pumps, mixers, storage tanks, and distribution pumps across three phases. The list includes information on the manufacturer, type, specifications, quantity, location, and condition of each item. Several pumps are noted as functioning properly while others are damaged or undergoing repairs.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
63 views7 pages

Aset WTP Piayu

The document is an inventory list of assets at the Piayu WTP in Batam. It contains details of 9 intake pumps, chemical dosing pumps, mixers, storage tanks, and distribution pumps across three phases. The list includes information on the manufacturer, type, specifications, quantity, location, and condition of each item. Several pumps are noted as functioning properly while others are damaged or undergoing repairs.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

SPAM BATAM

Inventaris Aset WTP Piayu

NO Description Merk Type Spesifikasi Qty Units Remarks Lokasi Notes

I INTAKE
1 Phase 1
a Pompa Intake Grundfoss Submersible Pump 30 KW Unit 1 Berfungsi Baik Intake Didalam Air
b Pompa Intake Grundfoss Submersible Pump 30 KW Unit 1 Dalam PerbaikanMukakuning Rusak
c Pompa Intake Grundfoss Submersible Pump 37 KW Unit 1 Berfungsi Baik Intake Didalam Air
d Pompa Intake Grundfoss Submersible Pump 18,5 KW Unit 1 Berfungsi Baik Intake Didalam Air
e Panel Kelistrikan Intake (MCC) Star delta 37 KW Set 1 Berfungsi Baik Intake
f Panel Kelistrikan Intake (MCC) Star delta 55 KW Set 1 Berfungsi Baik Intake
g Valve Arita Check Valve 200 MM Unit 4 Berfungsi Baik Intake
h Valve AVK Gate Valve 200 MM Unit 5 Berfungsi Baik Intake
i Flexible Joint Tozen 300 MM Unit 8 Berfungsi Baik Intake
j Valve (Bypass) AVK Gate Valve 400 MM Unit 3 Berfungsi Baik Intake
2 Phase 2
a Pompa Intake Grundfoss Submersible 18,5 KW Unit 2 Berfungsi Baik Intake Didalam Air
b Pompa Intake Grundfoss Submersible 18,5 KW Unit 2 Dalam PerbaikanMukakuning Rusak
c Panel Kelistrikan Intake (MCC) Star delta 18.5 KW Set 4 Berfungsi Baik Intake
d Valve Arita Check Valve 250 MM Unit 4 Berfungsi Baik Intake
e Valve AVK Gate Valve 250 MM Unit 6 Berfungsi Baik Intake
f Valve AVK Gate Valve 200 MM Unit 1 Berfungsi Baik Intake
g Flexible Joint Tozen 400 MM Unit 12 Berfungsi Baik Intake
h Valve (Bypass) AVK Gate Valve 400 MM Unit 3 Berfungsi Baik Intake
3 Penyalur Petir Area Intake Thomas 125 Tower Cakupan Area 125 Set 1 Berfungsi Baik Intake
4 Ruang Panel Intake Kongkrit (Dinding Pasang Bata) 7 M x 5,3 M x 3,7 M Unit 1 Berfungsi Baik Intake Ada As Build Drawing
5 Ponton Steel Plat (6 mm) 5Mx4Mx1M Unit 1 Berfungsi Baik Intake Ada As Build Drawing
6 PJU Philips IP 67 Tinggi tiang 7 mtr, 150 watt Titik 8 Berfungsi Baik Intake
7 Lampu Sorot / Mercury Solar Lite Floodlight 500 watt Titik 2 Berfungsi Baik Intake
8 Stabilizer Ph1 Yoritsu Digital Set 1 Berfungsi Baik Ruang Stabilizer Intake Phase 1
9 Stabilizer Ph2 Yoritsu Digital Set 1 Berfungsi Baik Ruang Stabilizer Intake Phase 2

II GEDUNG CHEMICAL Kongkrit (Struktur Baja) 15 M x 14 M x 5,88 M Unit 1 Berfungsi Baik Ruang Chemical Ada As Build Drawing
1 POMPA DOSSING
a Pompa Dosing Jesco Memdos MR 980 0,55 KW Set 3 Berfungsi Baik Ruang Chemical PW 55
b Pompa Dosing Jesco Memdos MR 980 0,75 KW Unit 1 Berfungsi Baik Ruang Chemical PW 55
c Pompa Dosing Milton Roy GB 1000 KP1MNN 0,55 KW Unit 2 Berfungsi Baik Ruang Chemical Allum
d Pompa Dosing Milton Roy GB 1000 0,55 KW Unit 2 Berfungsi Baik Ruang Chemical
e Pompa Dosing Milton Roy GB 1000 0,75 KW Unit 1 Berfungsi Baik Ruang Chemical
2 MIXER
a Mixer Teco Motor 2,2 KW Unit 5 Berfungsi Baik Ruang Chemical
b Panel Kelistrikan Mixer dan Dosing Pump Direct Online Set 1 Berfungsi Baik Ruang Chemical
3 Penampungan Kapur Kongkrit 6 M x 5 M x 1,5 M Unit 1 Berfungsi Baik Ruang Chemical Ada As Build Drawing
5 Panel PH Online (VSD) ABB 380 V Set 1 Berfungsi Baik Ruang Chemical
6 Exhaust Fan Wington Mounted Wall 24 Inchi Unit 2 Berfungsi Baik Ruang Chemical
7 Eye Wash Arboles Navaez 10-08191 Rubi Spin Unit 1 Berfungsi Baik Ruang Chemical

III RUANG POMPA DISTRIBUSI


A PHASE 1 Kongkrit 28 M x 10 M x 7,9 M Unit 1 Berfungsi Baik Ruang Distribusi Pump Phase 1 Ada As Build Drawing
1 POMPA DOSTRIBUSI Struktur Beton Bertulang, Atap Baja
22,5 M x 17,1 M x 8,8 M Unit 1 Berfungsi Baik Ruang Pompa Disribusi Phase 1 & 2 Lantai Atas 5 M, Lantai Bawah 3,8 M
a Pompa Distribusi Sothern Cross Centrifugal 110 KW Unit 4 Berfungsi Baik Ruang Distribusi Pump Phase 1 1 Dalam proses Install
b Valve Inlet DP AVK Gate Valve 150 MM Unit 4 Berfungsi Baik Ruang Distribusi Pump Phase 1
c Valve Outlet DP AVK Gate Valve 150 MM Unit 6 Berfungsi Baik Ruang Distribusi Pump Phase 1
d Valve DP AVK Check Valve 150 MM Unit 6 Berfungsi Baik Ruang Distribusi Pump Phase 1
e Flexible Joint DP Tozen 150 MM Unit 8 Berfungsi Baik Ruang Distribusi Pump Phase 1
f Panel kelistrikan Pompa DP,Back Wash dan Blower Start Delta Set 1 Berfungsi Baik Ruang Distribusi Pump Phase 1
g Panel kelistrikan Pompa Dist. ABB VSD 110 KW Unit 1 Berfungsi Baik Ruang Distribusi Pump Phase 1
h Residual (Microchem) SEVERN TRENT KC 4000 WP70CV32 Unit 1 Rusak Ruang Distribusi Pump
i Crane Gedung Pompa Dist Phase 1 - Chain Block 2 Ton Set 1 Berfungsi Baik Ruang Distribusi Pompa Phase 1
j Lampu Sorot / Mercury Solar Lite Floodlight 500 watt Titik 3 Berfungsi Baik Ruang Distribusi Pump Phase 1
k Pompa Water Level Control Grundfoss Submersible 1,30 KW Unit 1 Berfungsi Baik Ruang Ditribution Pump Phase 1
l Panel Water Level Control Unit 1 Berfungsi Baik Ruang Ditribution Pump Phase 1
SPAM BATAM
Inventaris Aset WTP Piayu

NO Description Merk Type Spesifikasi Qty Units Remarks Lokasi Notes

m Exhaust Fan Wington Mounted Wall 24 Inchi Unit 3 Berfungsi Baik Ruang Distribution Pump Phase 1
n Capasitor Bank Unit 1 Berfungsi Baik Ruang Distribution Pump Phase 1
2 BLOWER Struktur Beton Bertulang, Atap Baja
22,5 M x 17,1 M x 8,8 M Unit 1 Berfungsi Baik Ruang Pompa Disribusi Phase 1 & 2 Lantai Atas 5 M, Lantai Bawah 3,8 M
a Blower Shinmaywa Centrifugal 22 KW Unit 2 Berfungsi Baik Ruang Distribusi Pump Phase 1
b Valve Outlet Blower AT Gate Valve 100 MM Unit 2 Berfungsi Baik Ruang Distribusi Pump Phase 1
c Valve Otomatis Blower AT Gate Valve 50 MM Unit 1 Berfungsi Baik Ruang Distribusi Pump Phase 1
3 BACKWASH Struktur Beton Bertulang, Atap Baja
22,5 M x 17,1 M x 8,8 M Unit 1 Berfungsi Baik Ruang Pompa Disribusi Phase 1 & 2 Lantai Atas 5 M, Lantai Bawah 3,8 M
a Pompa Backwash Grundfoss Centrifugal 15 KW Unit 3 Berfungsi Baik Ruang Distribusi Pump Phase 1
b Valve Inlet Backwash AT Gate Valve 100 MM Unit 3 Berfungsi Baik Ruang Distribusi Pump Phase 1
c Valve Outlet Backwash AVK Gate Valve 100 MM Unit 3 Berfungsi Baik Ruang Distribusi Pump Phase 1
d Valve Backwash - Check Valve 100 MM Unit 3 Berfungsi Baik Ruang Distribusi Pump Phase 1
e Flexible Joint Backwash Tozen 100 MM Unit 6 Berfungsi Baik Ruang Distribusi Pump Phase 1

B PHASE 2
1 POMPA DOSTRIBUSI Kongkrit (Struktur Baja) 20 M x 8,20 M x 8,8 M Unit 1 Berfungsi Baik Ruang Distribusi Pump Phase 2 Ada As Build Drawing
a Pompa Distribusi KSB Splitcase 250 KW Unit 3 Berfungsi Baik Ruang Distribusi Pump Phase 2
b Pompa Distribusi Sothern Cross Centrifugal 132 KW Unit 1 Berfungsi Baik Ruang Distribusi Pump Phase 2
c Valve Inlet DP AVK Gate Valve 250 MM Unit 4 Berfungsi Baik Ruang Distribusi Pump Phase 2 1 Dalam proses Install
d Valve Outlet DP Keystone Butterfly Valve 200 MM Unit 4 Berfungsi Baik Ruang Distribusi Pump Phase 2 1 Dalam proses Install
e Valve Outlet DP Arita Check Valve 200 MM Unit 4 Berfungsi Baik Ruang Distribusi Pump Phase 2 1 Dalam proses Install
f Flexible Joint Inlet DP Tozen 250 MM Unit 4 Berfungsi Baik Ruang Distribusi Pump Phase 2 1 Dalam proses Install
g Flexible Joint Outlet DP Tozen 200 MM Unit 4 Berfungsi Baik Ruang Distribusi Pump Phase 2 1 Dalam proses Install
h Valve Water Service AVK Gate Valve 100 MM Unit 2 Berfungsi Baik Ruang Distribusi Pump Phase 2
i PRV Singer 50 MM Unit 2 Berfungsi Baik Ruang Distribusi Pump Phase 2
j Valve Water Hammer AVK Gate Valve 200 MM Unit 1 Berfungsi Baik Ruang Distribusi Pump Phase 2
k SARV (Water Hammer) Singer 200 MM Unit 1 Berfungsi Baik Ruang Distribusi Pump Phase 2
l Flanged Adaptor Synchong 450 MM Unit 3 Berfungsi Baik Ruang Distribusi Pump Phase 2
m Panel kelistrikan Pompa Dist. Dunfoss VSD 250 KW Unit 1 Berfungsi Baik Ruang Distribusi Pump Phase 2
n Panel kelistrikan Pompa Dist. Dunfoss Soft Starter 185 KW Unit 2 Berfungsi Baik Ruang Distribusi Pump Phase 2
o Panel kelistrikan back wash dan blower Start Delta 18.5 KW Set 1 Berfungsi Baik Ruang Distribusi Pump Phase 2
p Flow Meter Distribusi SIEMENS MAG 5000 DN 400 mm Set 1 Berfungsi Baik Jalur Pipa 400 Distribusi Ph 2, Ruang Distribusi Pump Phase 2
q Residual (Microchem) SEVERN TRENT KC 4000 WP70CV32 Unit 1 Rusak Ruang Distribusi Pump
r Crane Gedung Pompa Dist Phase 2 HYUNDAI Electric chain Hoist 2,5 Ton Set 1 Berfungsi Baik Ruang Distribusi Pompa Phase 2
s Lampu Sorot / Mercury Solar Lite Floodlight 500 watt Titik 3 Berfungsi Baik Ruang Distribusi Pump Phase 2
t Control Panel Intake Ph2 Set 1 Berfungsi Baik Ruang Distribusi Pump Phase 2 4 DP, 3 Backwash & 2 Blower
u Panel Alarm / Sirine Set 1 Berfungsi Baik Ruang Distribusi Pump Phase 2
v Panel Capasitor Bank Set 1 Berfungsi Baik Ruang Distribusi Pump Phase 2
w Panel RTU Set 1 Berfungsi Baik Ruang Distribusi Pump Phase 2 PH Online, F/M Intake & F/M Distribusi
x Pompa Water Level Control Grundfoss Submersible 1,30 KW Unit 1 Berfungsi Baik Ruang Ditribution Pump Phase 2
y Panel Water Level Control Unit 1 Berfungsi Baik Ruang Ditribution Pump Phase 2
z Exhaust Fan Wington Mounted Wall 24 Inchi Unit 3 Berfungsi Baik Ruang Distribution Pump Phase 2
2 BLOWER Struktur Beton Bertulang, Atap Baja
22,5 M x 17,1 M x 8,8 M Unit 1 Berfungsi Baik Ruang Pompa Disribusi Phase 1 & 2 Lantai Atas 5 M, Lantai Bawah 3,8 M
a Blower Shinmaywa Centrifugal 18,5 KW Unit 2 Berfungsi Baik Ruang Distribusi Pump Phase 2
3 BACKWASH Struktur Beton Bertulang, Atap Baja
22,5 M x 17,1 M x 8,8 M Unit 1 Berfungsi Baik Ruang Pompa Disribusi Phase 1 & 2 Lantai Atas 5 M, Lantai Bawah 3,8 M
a Pompa Backwash Grundfoss Centrifugal 18,5 KW Unit 3 Berfungsi Baik Ruang Distribusi Pump Phase 2
b Valve Inlet Backwash AVK Gate Valve 200 MM Unit 3 Berfungsi Baik Ruang Distribusi Pump Phase 2
c Valve Outlet Backwash Kent Butterfly Valve 200 MM Unit 3 Berfungsi Baik Ruang Distribusi Pump Phase 2
d Valve Backwash Tozen Check Valve 200 MM Unit 3 Berfungsi Baik Ruang Distribusi Pump Phase 2
e Flexible Joint Backwash Tozen 200 MM Unit 6 Berfungsi Baik Ruang Distribusi Pump Phase 2
f Valve Pembuangan Angin Backwash AVK Gate Valve 50 MM Unit 1 Berfungsi Baik Ruang Distribusi Pump Phase 2

IV GEDUNG GENSET DAN TRAFO


1 GEDUNG GENSET Struktur Baja 11,2 M x 8,3 M x 7,22 M Unit 1 Berfungsi Baik Ruang Genset Ada As Build Drawing
a Genset Cummins Open 880 KVA Unit 2 Berfungsi Baik Ruang Genset
b Panel Kelistrikan Genset Deepsea ATS 1600 A Set 2 Berfungsi Baik Ruang Genset
c Panel Load Sharing Set 1 Stanby Ruang Genset
d Main Panel LVMDP 2 1600 A Set 1 Berfungsi Baik Ruang Genset
e Lampu Sorot / Mercury Solar Lite Floodlight 250 watt Titik 2 Berfungsi Baik Ruang Genset
f Lampu Sorot / Mercury Solar Lite Floodlight 250 watt Titik 6 Tidak Berfungsi Ruang Genset
SPAM BATAM
Inventaris Aset WTP Piayu

NO Description Merk Type Spesifikasi Qty Units Remarks Lokasi Notes

2 GEDUNG TRAFO Kongkrit 12 M x 3,6 M x 3,4 M Unit 1 Berfungsi Baik Ruang Trafo Phase 1 Ada As Build Drawing
Phase 1 Cummins Open 880 KVA Unit 2 Berfungsi Baik Ruang Genset
a Trafo Star Lite Step Down 1600 KVA Unit 1 Berfungsi Baik Ruang Trafo Phase 1
b Panel Kelistrikan Trafo Schneider Kubikal TM / QM 20 KV Set 1 Berfungsi Baik Ruang Trafo Phase 1
c Main panel LVMDP 1 Schneider 2.000 A Set 1 Berfungsi Baik Ruang Trafo Phase 1
d Exhaust Fan Wington Mounted Wall 24 Inchi Unit 1 Berfungsi Baik Ruang Travo Phase 1
Phase 2 Kongkrit 8 M x 6,5 M x 4,1 M Unit 1 Berfungsi Baik Ruang Trafo Phase 2 Ada As Build Drawing
a Trafo Star Lite Step Down 1000 KVA Unit 1 Tidak berfungsi Ruang Trafo Phase 2
b Panel Kelistrikan Trafo Schneider Kubikal TM / QM 20 KV Set 1 Tidak berfungsi Ruang Trafo Phase 2
c Exhaust Fan Wington Mounted Wall 24 Inchi Unit 1 Berfungsi Baik Ruang Travo Phase 2

V GEDUNG CHLORINE Kongkrit (Struktur Baja) 12 M x 5,20 M x 5,3 M Unit 1 Berfungsi Baik Ruang Chlorine Ada As Build Drawing
1 PHASE 1
a Vaccum Regulator NXt 3000 10 Kg/Jam Unit 1 Berfungsi Baik Ruang Chlorine
b Vaccum Ejector SEVERN TRENT 200 PPD 4 Kg/Jam Unit 1 Berfungsi Baik Ruang Chlorine
c Vaccum Ejector SEVERN TRENT 100 PPD 2 Kg/Jam Unit 1 Berfungsi Baik Ruang Chlorine
d Remote Meter SEVERN TRENT 200 PPD 4 Kg/Jam Unit 1 Berfungsi Baik Ruang Chlorine
e Remote Meter SEVERN TRENT 100 PPD 2 Kg/Jam Unit 1 Berfungsi Baik Ruang Chlorine
2 PHASE 2
a Vaccum Regulator NXt 3000 10 Kg/Jam Unit 1 Berfungsi Baik Ruang Chlorine
b Vaccum Ejector SEVERN TRENT 200 PPD 4 Kg/Jam Unit 1 Berfungsi Baik Ruang Chlorine
c Vaccum Ejector SEVERN TRENT 100 PPD 2 Kg/Jam Unit 1 Berfungsi Baik Ruang Chlorine
d Remote Meter SEVERN TRENT 200 PPD 4 Kg/Jam Unit 1 Berfungsi Baik Ruang Chlorine
e Remote Meter SEVERN TRENT 100 PPD 2 Kg/Jam Unit 1 Berfungsi Baik Ruang Chlorine
3 ABSORBER
a Pompa Blower SEVERN TRENT 3000 m3/jam Unit 1 Berfungsi Baik Ruang Chlorine
b Pompa Soda Caustic HANS PUMP 4 m3/jam Unit 1 Berfungsi Baik Ruang Chlorine
c Gas Detector SEVERN TRENT 1610B - 1620 B Unit 1 Berfungsi Baik Ruang Chlorine
4 Penyalur Petir Gedung Chlorine Thomas 125 Tower Cakupan Area 125 Set 1 Berfungsi Baik Ruang Chlorine Diatas Gedung
5 Crane Gedung Ruang Chlorine HYUNDAI Electric chain Hoist 2,5 Ton Set 1 Berfungsi Baik Ruang Chlorine
6 Panel Chlorine Set 1 Berfungsi Baik Ruang Chlorine
7 Panel Netralisir & Absorber Set 1 Berfungsi Baik Ruang Chlorine

VI RUANG OPERATOR Kongkrit 8 M x 4 M x 5,2 M Unit 1 Berfungsi Baik Ruang Operator / SPV Ada As Build Drawing
a PH Meter on line Evoqua W3T158816 Set 1 Berfungsi Baik Ruang Operator
b Jart Test Stuart SW6 Set 1 Berfungsi Baik Ruang Operator
c PH Meter WTW pH 3210 WTW 82362 Set 2 Berfungsi Baik Ruang Operator
d Turbidimeter EUTECH TN-100 Set 1 Berfungsi Baik Ruang Operator

VII BANGUNAN MODUL


I MODUL PHASE 1
a Valve Drain Floculator TEK Gate Valve 100 MM Unit 1 Berfungsi Baik Module Phase 1
b Valve Inlet CW No.1 sd 6 AVK Butterfly Valve 300 MM Unit 6 Berfungsi Baik Module Phase 1
c Valve Drain CW No.1 sd 6 AVK Gate Valve 150 MM Unit 6 Berfungsi Baik Module Phase 1
d Valve Drain CW Eurovalve Butterfly Valve 150 MM Unit 1 Berfungsi Baik Module Phase 1
e Valve Outlet CW No.1 sd 3 (Balancing) Keystone Butterfly Valve 250 MM Unit 3 Berfungsi Baik Module Phase 1
f Valve Drain Balncing No 1 sd 3 AT Gate Valve 50 MM Unit 3 Berfungsi Baik Module Phase 1
g Valve Inlet filter 1 s/d 7 Keystone Butterfly Valve 200 MM Unit 7 Berfungsi Baik Module Phase 1
h Valve Drain filter 1 s/d 7 (Main hole) AT Gate Valve 50 MM Unit 7 Tidak Berfungsi Module Phase 1
i Valve Drain filter 1 s/d 7 Keystone Butterfly Valve 200 MM Unit 7 Berfungsi Baik Module Phase 1
j Valve Outlet filter 1 s/d 7 Keystone Butterfly Valve 200 MM Unit 7 Berfungsi Baik Module Phase 1
k Valve Back Wash Filter 1 s/d 7 Keystone Butterfly Valve 200 MM Unit 7 Berfungsi Baik Module Phase 1
l Valve Back Wash AVK Gate Valve 200 MM Unit 2 Berfungsi Baik Module Phase 1
m Flow Meter Backwash Kent Turbin 200 MM Unit 1 Berfungsi Baik Module Phase 1
n Valve Blower Filter 1 s/d 7 Keystone Butterfly Valve 100 MM Unit 7 Berfungsi Baik Module Phase 1
o Flanged Adaptor Synchong Steel Flange Adaptor, PN 10/14 300 MM Unit 6 Berfungsi Baik Module Phase 1
p Flanged Adaptor Synchong Steel Flange Adaptor, PN 10/15 200 MM Unit 6 Berfungsi Baik Module Phase 1
q Flanged Adaptor Synchong Steel Flange Adaptor, PN 10/16 400 MM Unit 2 Berfungsi Baik Open Yard Phase 1
r Pompa Pembuangan Sedimen Submersible 3 Phase Unit 1 Berfungsi Baik Module Phase 1
s Lamella Tubedek Polycarbonate 5,90 m x 3,95 m Unit 6 Berfungsi Baik Module Phase 1 Sedimen No 1 sd 6 Phase 1
SPAM BATAM
Inventaris Aset WTP Piayu

NO Description Merk Type Spesifikasi Qty Units Remarks Lokasi Notes

t PJU Philips IP 67 Tinggi tiang 12 mtr, 150 watt Titik 18 Berfungsi Baik Phase 1
u Lampu Module Philips Cup IP 67 250 watt Titik 12 Berfungsi Baik Diatas Module Phase 1
FILTER Phase 1 Package (Struktur Baja) 4,25 M x 3,4 M & Tinggi 3,5 M Unit 7 Berfungsi Baik Module Phase 1 Ada As Build Drawing
a Gravel batuan 3.98 x 2.98 x 0,1 m Unit 7 Berfungsi Baik Module Phase 1 Filter No 1 sd 7 Phase 1
b Nozel Filter Nozzle B-19 Type: NPT ukuran 0.5 inc mash 0.5mm. Bahan PE Unit 7 Berfungsi Baik Module Phase 1 jumlah nozzle per filter: 520 pcs
c Silica Sand Pasir Silica uk 2.36 mm - 1.18mm 3.98 x 2.98 x 1 m Unit 7 Berfungsi Baik Module Phase 1 Filter No 1 sd 7 Phase 1
d Pipa Header AW PVC 300 MM unit 7 Berfungsi Baik Module Phase 1
e Pipa Lateral AW PVC 100 MM UNIT 7 Module Phase 1

2 MODUL PHASE 2
a Valve Drain Floculator 1 s/d 5 AVK Gate Valve 100 MM Unit 5 Berfungsi Baik Module Phase 2
b Valve Over Flow Floculator 1 s/d 2 AVK Gate Valve 100 MM Unit 2 Berfungsi Baik Module Phase 2
c Valve Inlet Flocculator Keystone Butterfly Valve 400 MM Unit 1 Berfungsi Baik Module Phase 2
d Valve Inlet CW No.1 sd 6 Keystone Butterfly Valve 300 MM Unit 6 Berfungsi Baik Module Phase 2
e Valve Drain CW No,1 sd 6 AVK Gate Valve 100 MM Unit 6 Berfungsi Baik Module Phase 2
f Valve Inlet filter 1 s/d 6 Keystone Butterfly Valve 200 MM Unit 6 Berfungsi Baik Module Phase 2
g Valve Drain filter 1 s/d 6 Main hole Arita Gate Valve 38 MM Unit 6 Tidak Berfungsi Module Phase 2
h Valve Drain filter 1 s/d 6 Keystone Butterfly Valve 200 MM Unit 6 Berfungsi Baik Module Phase 2
i Valve Outlet filter 1 s/d 6 Keystone Butterfly Valve 200 MM Unit 6 Berfungsi Baik Module Phase 2
j Valve Back Wash Filter 1 s/d 6 Keystone Butterfly Valve 200 MM Unit 6 Berfungsi Baik Module Phase 2
k Valve Blower Filter 1 s/d 6 Keystone Butterfly Valve 125 MM Unit 6 Berfungsi Baik Module Phase 2
l Flanged Adaptor Outlet Sedimen Synchong Steel Flange Adaptor, PN 10/15 150 MM Unit 12 Berfungsi Baik Module Phase 2
m Flanged Adaptor Inlet Clearwell AVK DI Flange Adaptor 300 MM Unit 2 Berfungsi Baik Module Phase 2
n Lamella Tubedek PVC 5,90 m x 3,95 m Unit 6 Berfungsi Baik Sedimen Sedimen No 1 sd 6 Ph 2
o PJU Philips IP 67 Tinggi tiang 9 mtr, 150 watt Titik 9 Berfungsi Baik Phase 2
p Lampu Module Philips Cup IP 67 250 watt Titik 13 Berfungsi Baik Diatas Module Phase 2
FILTER Phase 2 Struktur Baja 4 M x 3 M x 3,4 M Unit 6 Berfungsi Baik Module Phase 2 Ada As Build Drawing
a Gravel batuan 3.98 x 2.98 x 0,1 m Unit 7 Berfungsi Baik Module Phase 2 Filter No 1 sd 7 Phase 1
b Nozel Filter Nozzle B-19 Type: NPT ukuran 0.5 inc mash 0.5mm. Bahan PE Unit 7 Berfungsi Baik Module Phase 1 jumlah nozzle per filter: 540 pcs
c Silica Sand Pasir Silica uk 2.36 mm - 1.18mm 3.98 x 2.98 x 1 m Unit 7 Berfungsi Baik Module Phase 2 Filter No 1 sd 7 Phase 1
d Pipa Header AW PVC 300 MM unit 7 Berfungsi Baik Module Phase 2
e Pipa Lateral AW PVC 100 MM UNIT 7 Module Phase 2

3 AERATOR PHASE 1 Package (Struktur Baja) 7,8 M x 7,2 M x 10,6 M Unit 1 Berfungsi Baik Module Phase 1 Ada As Build Drawing
a Valve Drain Aerator IBS Gate Valve 100 MM Unit 1 Berfungsi Baik Module Phase 1

4 AERATOR PHASE 2 Ground tank (Struktur Baja) 7,15 M x 7,15 M x 9,9 M (2000 m3) Unit 1 Berfungsi Baik Module Phase 2 Ada As Build Drawing
a Valve Inlet Aerator 1 s/d 3 (Bypass) AVK Gate Valve 200 MM Unit 3 Berfungsi Baik Module Phase 2
b Valve Drain Aerator 1 s/d 2 AVK Gate Valve 100 MM Unit 2 Berfungsi Baik Module Phase 2

5 CLEARWELL PHASE 1 Kongkrit (Beton) 25 M x 13 M x 4,8 M (1000 M3) Unit 1 Berfungsi Baik Module Phase 1 Ada As Build Drawing
a Valve Inlet Clearwell AVK Gate valve 400 MM Unit 1 Berfungsi Baik Clearwell Phase 1
b Valve Out Let Clearwell 1 s/d 2 Keystone Butterfly valve 400 MM Unit 2 Berfungsi Baik Ruang Distribusi Pump Phase 1
c Valve Drain Clearwell 1 s/d 2 AT Gate valve 250 MM Unit 2 Berfungsi Baik Ruang Distribusi Pump Phase 1
d Valve Inlet Suplai From DK AVK Gate valve 200 MM Unit 1 Berfungsi Baik Clearwell Phase 1
e Valve Distribusi AVK Gate valve 400 MM Unit 1 Berfungsi Baik Open Yard Samping Gardu PLN
f Valve Clearwell Blakeborough Gate valve 250 MM Unit 2 Berfungsi Baik Module Phase 1

6 CLEARWELL PHASE 2 Kongkrit 31 M x 24,6 M x 4,8 M (2000 M3) Unit 1 Berfungsi Baik Module Phase 2 Ada As Build Drawing
a Valve Inlet Clearwell 1 dan 2 Keystone Butterfly valve 300 MM Unit 2 Berfungsi Baik Clearwell Phase 2
b Valve Out Let Clearwell 1 s/d 2 Keystone Butterfly valve 450 MM Unit 3 Berfungsi Baik Ruang Distribusi Pump Phase 2
c Valve Drain Clearwell 1 s/d 2 AVK Gate valve 300 MM Unit 2 Berfungsi Baik Ruang Distribusi Pump Phase 2
d Valve Balancing Tank AVK Gate valve 300 MM Unit 1 Berfungsi Baik Ruang Distribusi Pump Phase 2
e Valve Distribusi AVK Gate valve 400 MM Unit 1 Berfungsi Baik Ruang Distribusi Pump Phase 2
7 Koagulator/Floculator Package (Struktur Baja) 12 M x 4,55 M x 4,5 M Unit 1 Berfungsi Baik Module Phase 1 Ada As Build Drawing
8 Sedimen / Clarifier Package (Struktur Baja) 4 M x 6 M & Tinggi 8,2 M Unit 6 Berfungsi Baik Module Phase 1 Ada As Build Drawing
9 Balance Tank Package (Struktur Baja) 2,1 M x 2,2 M & Tinggi 3,8 M Unit 3 Berfungsi Baik Module Phase 1 Ada As Build Drawing
10 Koagulator/Floculator Ground tank (Struktur Baja) 14,6 M x 4,5 M x 5,4 M (250 m3) Unit 1 Berfungsi Baik Module Phase 2 Ada As Build Drawing
11 Sedimen / Clarifier Kongkrit (Struktur Baja) 6 M x 4 M x 8,7 M Unit 6 Berfungsi Baik Module Phase 2 Ada As Build Drawing
SPAM BATAM
Inventaris Aset WTP Piayu

NO Description Merk Type Spesifikasi Qty Units Remarks Lokasi Notes

VIII PIPA
I INTAKE
Phase 1
a Pipa Header Galvanis 300 mm Meter 8,9 Berfungsi Baik Intake
b Pipa Intake ke Header Galvanis 200 mm Meter 12 Berfungsi Baik Intake 4 Unit, 2 Dalam Perbaikan
c Pipa Transmisi Intake ke Aerator Galvanis 400 mm Meter 11,2 Berfungsi Baik Intake
d Pipa Transmisi Intake ke Aerator Steel Pipe 400 mm Meter 281 Berfungsi Baik Intake
e Pipa Transmisi Intake ke Aerator DCIP 400 mm Meter 27 Berfungsi Baik Intake
Phase 2
a Pipa header Galvanis 400 mm Meter 3,9 Berfungsi Baik Intake
b Pipa Intake ke Header Galvanis 250 mm Meter 14,8 Berfungsi Baik Intake 4 Unit, 2 Dalam Perbaikan
c Pipa Transmisi Intake ke Aerator DCIP 200 mm Meter 336,4 Berfungsi Baik Intake
d Pipa Transmisi Intake ke Aerator PE 315 mm Meter 19,68 Berfungsi Baik Intake
2 MODUL
Phase 1
a Pipa dari Aerator ke Koagulator Steel Pipe 400 mm Meter 5 Berfungsi Baik Module Phase 1
b Pipa dari Floculator ke Sedimen Steel Pipe 500 mm Meter 28 Berfungsi Baik Module Phase 1
c Pipa dari Floculator ke Sedimen Steel Pipe 300 mm Meter 6 Berfungsi Baik Module Phase 1 6 Unit
d Pipa dari Sedimen ke Balance Tank Sintec DCIP 450 mm Meter 25 Berfungsi Baik Module Phase 1
e Pipa dari Sedimen ke Balance Tank DCIP 200 mm Meter 18 Berfungsi Baik Module Phase 1 6 Unit
f Pipa dari Sedimen ke Balance Tank DCIP 250 mm Meter 5,1 Berfungsi Baik Module Phase 1 3 Unit
g Pipa dari Balance tank ke filter + Drain DCIP 200 mm Meter 45,7 Berfungsi Baik Module Phase 1
h Pipa dari filter ke Clearweell + Backwash DCIP 200 mm Meter 69,9 Berfungsi Baik Module Phase 1
i Pipa dari filter ke Clearweell DCIP 450 mm Meter 25 Berfungsi Baik Module Phase 1
j Pipa Drain clearwell DCIP 250 mm Meter 30 Berfungsi Baik Module Phase 1
k Pipa Drain clearwell DCIP 400 mm Meter 100 Berfungsi Baik Module Phase 1
l Pipa header Aerator DCIP 400 mm Meter 8 Berfungsi Baik Module Phase 1
m Overflow dan Drain Flocculator Galvanis 100 mm Meter 12,5 Berfungsi Baik Module Phase 1
n Pipa Balance tank DCIP 250 mm Meter 14 Berfungsi Baik Module Phase 1
o Pipa dari Filter ke Clearwell DCIP 400 mm Meter 4 Berfungsi Baik Module Phase 1
p Pipa dari Filter ke Clearwell DCIP 250 mm Meter 40 Berfungsi Baik Module Phase 1
Phase 2
a Pipa header Aerator Galvanis 300 mm Meter 8,9 Berfungsi Baik Module Phase 2
b Pipa drain Aerator Galvanis 100 mm Meter 20,6 Berfungsi Baik Module Phase 2
c Pipa dari Aerator ke Koagulator Steel Pipe 400 mm Meter 4 Berfungsi Baik Module Phase 2
d Pipa dari Floculator ke Sedimen DCIP 500 mm Meter 27,6 Berfungsi Baik Module Phase 2
e Pipa dari Sedimen Ke Filter DCIP 500 mm Meter 29,2 Berfungsi Baik Module Phase 2
f Pipa dari Sedimen Ke Filter DCIP 300 mm Meter 3 Berfungsi Baik Module Phase 2
g Pipa dari Sedimen Ke Filter DCIP 200 mm Meter 30 Berfungsi Baik Module Phase 2 6 Unit
h Pipa dari Sedimen Ke Header DCIP 150 mm Meter 30 Berfungsi Baik Module Phase 2 12 Unit
i Pipa dari filter ke Clearweell DCIP 200 mm Meter 34,8 Berfungsi Baik Module Phase 2 6 Unit
j Pipa dari filter ke Clearweell DCIP 450 mm Meter 26 Berfungsi Baik Module Phase 2
k Pipa dari filter ke Clearweell PE 300 mm Meter 8 Berfungsi Baik Module Phase 2 2 Unit
l Pipa Drain clearwell DCIP 300 mm Meter 30 Berfungsi Baik Module Phase 2
m Overflow Flocculator DCIP 100 mm Meter 10,6 Berfungsi Baik Module Phase 2
n Pipa Drain Flocculator DCIP 100 mm Meter 31 Berfungsi Baik Module Phase 2
o Pipa dari Balance Tank ke Clearwell DCIP 300 mm Meter 30 Berfungsi Baik Module Phase 2
p Pipa dari Balance Tank ke Clearwell DCIP 500 mm Meter 30 Berfungsi Baik Module Phase 2
3 RUANG POMPA DISTRIBUSI
Phase 1
a Pipa Inlet Pompa Distribusi ke Header Steel Pipe 450 mm Meter 9,5 Berfungsi Baik Ruang Distribusi Pump Phase 1
b Pipa Header Distribusi Steel Pipe 400 mm Meter 7,9 Berfungsi Baik Ruang Distribusi Pump Phase 1
c Pipa dari Header ke Flow Meter Distribusi DCIP 400 mm Meter 30 Berfungsi Baik Ruang Distribusi Pump Phase 1
d Pipa Blower Filter Galvanis 100 mm Meter 84,9 Berfungsi Baik Ruang Distribusi Pump Phase 1
e Pipa Backwash Galvanis 250 mm Meter 3,5 Berfungsi Baik Ruang Distribusi Pump Phase 1
f Pipa Backwash Galvanis 100 mm Meter 5,4 Berfungsi Baik Ruang Distribusi Pump Phase 1
g Pipa Backwash Galvanis 150 mm Meter 4,2 Berfungsi Baik Ruang Distribusi Pump Phase 1
Phase 2
a Pipa Inlet Pompa Distribusi ke Header DCIP 250 mm Meter 5,1 Berfungsi Baik Ruang Distribusi Pump Phase 2 2 Unit
b Pipa Inlet Pompa Distribusi ke Header Pompa dan Backwash DCIP 450 mm x 14 m Meter 14 Berfungsi Baik Ruang Distribusi Pump Phase 2
SPAM BATAM
Inventaris Aset WTP Piayu

NO Description Merk Type Spesifikasi Qty Units Remarks Lokasi Notes

c Pipa Header Distribusi Steel Pipe 200 mm Meter 3,9 Berfungsi Baik Ruang Distribusi Pump Phase 2 3 Unit
d Header Distribusi Outlet DCIP 400 mm Meter 6,4 Berfungsi Baik Ruang Distribusi Pump Phase 2
e Header Distribusi Outlet DCIP 300 mm Meter 12,5 Berfungsi Baik Ruang Distribusi Pump Phase 2
f Pipa dari Header ke Flow Meter Distribusi DCIP 400 mm Meter 70 Berfungsi Baik Ruang Distribusi Pump Phase 2
g Pipa Distribusi Piayu ke Duriangkang DCIP 200 mm Meter 70 Berfungsi Baik Ruang Distribusi Pump Phase 2
h Header Distribusi DCIP 400 mm Meter 17,5 Berfungsi Baik Ruang Distribusi Pump Phase 2
i Pipa Distribusi Inlet Steel Pipe 250 mm Meter 5,5 Berfungsi Baik Ruang Distribusi Pump Phase 2 Proses Install
j Pipa Distribusi Outlet Steel Pipe 200 mm Meter 11 Berfungsi Baik Ruang Distribusi Pump Phase 2 Proses Install
k Pipa Backwash Inlet Galvanis 200 mm Meter 4,8 Berfungsi Baik Ruang Distribusi Pump Phase 2
l Pipa Backwash Outlet Galvanis 200 mm Meter 6 Berfungsi Baik Ruang Distribusi Pump Phase 2
m Pipa Backwash Outlet DCIP 200 mm Meter 60,85 Berfungsi Baik Ruang Distribusi Pump Phase 2
n Pipa Blower Galvanis 100 mm Meter 100,6 Berfungsi Baik Ruang Distribusi Pump Phase 2

VIII OPEN YARD


Flow Meter Intake Phase 1 SIEMENS MAG 5000 DN 400 mm Set 1 Berfungsi Baik Open Yard Belakang bangunan aerator Ph 1
Flow Meter Distribusi Phase 1 SIEMENS MAG 6000 DN 400 mm Set 1 Berfungsi Baik Open Yard Jalur Pipa 400 Distribusi Ph 1, Samping Mushallah
Flow Meter Intake Phase 2 SIEMENS MAG 5000 DN 200 mm Set 1 Berfungsi Baik Open Yard Belakang bangunan aerator Ph 2
Chlorine Residual Control Phase 1 Set 1 Rusak Open Yard Samping Ruangan DP Phase 1
Chlorine Residual Control Phase 2 Set 1 Rusak Open Yard Depan Ruangan DP Phase 2
Meter Listrik Itron ACE6000 Set 7 Berfungsi Baik R.Genset,R Mainpanel ,R DP Phase 1 dan2
Gravel Stanby batuan Berfungsi Baik Open Yard Samping Tempat penyimpanan Pasir Kapur
Ruang Security Kongkrit 4 M x 4 M x 4,6 M Unit 1 Berfungsi Baik Pos Security Ada As Build Drawing
Penyalur Petir Depan Ruang Chemical Thomas 125 Tower Cakupan Area 125 Set 1 Berfungsi Baik Open Yard Depan ruang Chemical
Tanki Solar Utama Steel Cylinder Tank 5 Ton Unit 1 Berfungsi Baik Open Yard Samping Ruang Genset
Tanki Solar Harian Stell Cube tank 1,8 Ton Unit 1 Berfungsi Baik Open Yard Samping Ruang Genset
Lampu Sorot / Mercury Solar Lite Floodlight 500 watt Titik 4 Berfungsi Baik Open Yard Lapangan Volley
Pagar Keliling Harmonica Kawat Hijau Meter 487 Berfungsi Baik Open Yard Tiang Siku Besi (50 M x 50 M)
Jalan Beton 2 M x 12 M Meter 57 Berfungsi Baik Open Yard Belakang Gedung Genset
Eye Wash & Body Wash Arboles Navaez 10-08191 Rubi Spin Unit 1 Berfungsi Baik Open Yard Disamping Ruang Chlorine
Pipa Drain WTP DCIP 400 mm Meter 176 Berfungsi Baik Open Yard Depan Ruang DP Phase 1 s/d Pintu Masuk WTP
Pompa Transfer Kapur Grundfoss Submersible 780watt Unit 1 Berfungsi Baik Open Yard Belakang Gedung Chemical

IX RUANG MAIN PANEL


Control Panel Intake Ph1 Set 1 Berfungsi Baik Ruang Main Panel
Panel Lampu PJU Phase 1 Set 1 Berfungsi Baik Ruang Main Panel
Panel Workshop Maintenance Set 1 Berfungsi Baik Ruang Main Panel

X KABEL
A RUANG GARDU PLN PHASE 1
1 Kubikal TM 20 KV ke Trafo 1600 KVA Supreme N2XSY 1 C x 50 x 3 Tarikan Meter 7 Berfungsi Baik Ruang Gardu PLN Phase 1
2 Trafo 1600 KVA ke Box ACB TR 2000 A Supreme NYY 1 C x 400 x 13 Tarikan Meter 4 Berfungsi Baik Ruang Gardu PLN Phase 1
3 Box ACB TR 2000 A ke Main Panel Genset 1600 A Supreme NYY 1 C x 400 x 13 Tarikan Meter 27 Berfungsi Baik Ruang Gardu PLN Phase 1

B RUANG GENSET
1 Main Panel Genset 1600 A ke Panel Genset Phase 1Taisin (Electrical Cable) NYY 1 C x 240 x 7 Tarikan Meter 3,2 Berfungsi Baik Ruang Genset
2 Main Panel Genset 1600 A ke Panel Genset Phase 2Taisin (Electrical Cable) NYY 1 C x 400 x 10 Tarikan Meter 5,1 Berfungsi Baik Ruang Genset
3 Alternator Genset Phase 1 ke Panel Genset Phase 1Taisin (Electrical Cable) NYY 1 C x 400 x 10 Tarikan Meter 11,3 Berfungsi Baik Ruang Genset
4 Alternator Genset Phase 2 ke Panel Genset Phase 2Taisin (Electrical Cable) NYY 1 C x 400 x 10 Tarikan Meter 9,1 Berfungsi Baik Ruang Genset
5 Panel Genset Phase 1 ke LVMDP Phase 1 Supreme NYY 1 C x 240 x 7 Tarikan Meter 24 Berfungsi Baik Ruang Genset
6 Panel Genset Phase 2 ke LVMDP Phase 2 Supreme NYY 1 C x 400 x 10 Tarikan Meter 76 Berfungsi Baik Ruang Genset

C INTAKE
1 LVMDP Phase 1 ke Main Breaker Stabilizer Phase 1Supreme
Intake NYFGBY 4 C x 185 x 1 Tarikan Meter 365,5 Berfungsi Baik Intake
2 Main Breaker Stabilizer Phase 1 ke Stabilizer PhaseSupreme
1 NYFGBY 1 C x 185 x 4 Tarikan Meter 5,8 Berfungsi Baik Intake
3 Main Breaker Stabilizer Phase 2 ke Stabilizer PhaseSupreme
2 NYFGBY 4 C x 70 x 1 Tarikan Meter 343,4 Berfungsi Baik Intake
4 Main Breaker Stabilizer ke Stabilizer Phase 2 Supreme NYY 1 C x 120 x 4 Tarikan Meter 5,8 Berfungsi Baik Intake
5 Stabilizer Phase 1 Ke Panel MCC Phase 1 Intake Supreme NYY 1 C x 185 x 4 Tarikan Meter 8,8 Berfungsi Baik Intake
6 Stabilizer Phase 2 Ke Panel MCC Phase 2 Intake Supreme NYY 1 C x 120 x 4 Tarikan Meter 8,3 Berfungsi Baik Intake
7 Panel MCC Intake Phase 1 Ke Junction Box Pompa Intake
Supreme
Phase 1 NYY 4 C x 16 x 10 Tarikan Meter 69,5 Berfungsi Baik Intake
8 Panel MCC Intake Phase 2 Ke Junction Box Pompa Intake
Supreme
Phase 2 NYY 4 C x 16 x 8 Tarikan Meter 66,7 Berfungsi Baik Intake

D LVMDP PHASE 1 DAN 2


1 LVMDP Phase 1 ke Panel MCC DP Phase 1 Supreme NYFGBY 4 C x 240 x 2 Tarikan Meter 11,5 Berfungsi Baik Ruang LVMDP Phase 1
2 LVMDP Phase 1 ke Panel MCC DP Phase 1 Supreme NYY 1 C x 240 x 4 Tarikan Meter 11,5 Berfungsi Baik Ruang LVMDP Phase 1
3 LVMDP Phase 1 ke Box Panel Ruang Chlorine Supreme NYFGBY 4 C x 10 x 1 Tarikan Meter 40,3 Berfungsi Baik Ruang LVMDP Phase 1
4 LVMDP Phase 1 ke Box Panel Ruang Dossing Supreme NYFGBY 4 C x 16 x 1 Tarikan Meter 105 Berfungsi Baik Ruang LVMDP Phase 1
5 LVMDP Phase 2 ke Panel MCC DP Phase 2 Supreme NYY 1 C x 240 x 12 Tarikan Meter 5 Berfungsi Baik Ruang LVMDP Phase 2

E MCC KE POMPA
Phase 1
SPAM BATAM
Inventaris Aset WTP Piayu

NO Description Merk Type Spesifikasi Qty Units Remarks Lokasi Notes

1 Panel MCC DP Phase 1 ke Motor Pompa 4 Supreme NYY 4 C x 95 x 2 Tarikan Meter 19 Berfungsi Baik Ruang Panel MCC DP Phase 1
2 Panel MCC DP Phase 1 ke Motor Pompa 3 Supreme NYY 4 C x 95 x 2 Tarikan Meter 20,6 Berfungsi Baik Ruang Panel MCC DP Phase 1
3 Panel MCC DP Phase 1 ke Motor Pompa 2 Supreme NYY 4 C x 95 x 2 Tarikan Meter 21,9 Berfungsi Baik Ruang Panel MCC DP Phase 1
4 Panel MCC DP Phase 1 ke Motor Pompa 1 Supreme NYY 4 C x 95 x 2 Tarikan Meter 22,8 Berfungsi Baik Ruang Panel MCC DP Phase 1
5 Panel MCC Phase 1 ke Motor Backwash 1 Supreme NYY 4 C x 4 x 2 Tarikan Meter 18 Berfungsi Baik Ruang MCC Phase 1
6 Panel MCC Phase 1 ke Motor Backwash 2 Supreme NYY 4 C x 4 x 2 Tarikan Meter 17 Berfungsi Baik Ruang MCC Phase 1
7 Panel MCC Phase 1 ke Motor Backwash 3 Supreme NYY 4 C x 4 x 2 Tarikan Meter 16 Berfungsi Baik Ruang MCC Phase 1
8 Panel MCC Phase 1 ke Motor Blower 1 Supreme NYY 4 C x 6 x 2 Tarikan Meter 15 Berfungsi Baik Ruang MCC Phase 1
9 Panel MCC Phase 1 ke Motor Blower 2 Supreme NYY 4 C x 6 x 2 Tarikan Meter 14 Berfungsi Baik Ruang MCC Phase 1

Phase 2
1 Panel MCC DP Phase 2 ke Motor Pompa 1 Supreme NYY 1 C x 150 x 6 Tarikan Meter 17 Berfungsi Baik Ruang MCC DP Phase 2
2 Panel MCC DP Phase 2 ke Motor Pompa 2 Supreme NYY 1 C x 150 x 6 Tarikan Meter 19 Berfungsi Baik Ruang MCC DP Phase 2
3 Panel MCC DP Phase 2 ke Motor Pompa 3 Supreme NYY 1 C x 150 x 6 Tarikan Meter 21 Berfungsi Baik Ruang MCC DP Phase 2
4 Pompa Backwash Phase 2 ke Panel Distribusi 1 Supreme NYY 4 C x 10 x 2 Tarikan Meter 15,8 Berfungsi Baik Ruang Panel MCC DP Phase 2
5 Pompa Backwash Phase 2 ke Panel Distribusi 2 Supreme NYY 4 C x 10 x 2 Tarikan Meter 17,9 Berfungsi Baik Ruang Panel MCC DP Phase 2
6 Pompa Backwash Phase 2 ke Panel Distribusi 3 Supreme NYY 4 C x 10 x 2 Tarikan Meter 20 Berfungsi Baik Ruang Panel MCC DP Phase 2
7 Pompa Blower Phase 2 ke Panel Distribusi 1 Supreme NYY 4 C x 10 x 2 Tarikan Meter 25 Berfungsi Baik Ruang Panel MCC DP Phase 2
8 Pompa Blower Phase 2 ke Panel Distribusi 2 Supreme NYY 4 C x 10 x 2 Tarikan Meter 22,3 Berfungsi Baik Ruang Panel MCC DP Phase 2

XI SYSTEM GROUNDING
1 System grounding Panel Kelistrikan DP Phase 1 < 1 ohm Lot 1 Berfungsi Baik Ruang Distibusi Pump Phase 2
2 System grounding Panel Kelistrikan DP Phase 2 < 1 ohm Lot 1 Berfungsi Baik Ruang Distibusi Pump Phase 2
3 System grounding Panel Kelistrikan RTU < 0,8 ohm Lot 1 Berfungsi Baik Ruang Distibusi Pump Phase 2
4 System Grounding Panel Kelistrikan Intake < 1 ohm Lot 1 Berfungsi Baik Ruang Panel Pompa Intake
5 System Grounding Panel Kelistrikan Genset < 1 ohm Lot 1 Berfungsi Baik Ruang Genset
6 System Grounding Panel Kelistrikan Trafo Phase 1 < 1 ohm Lot 1 Berfungsi Baik Ruang Gardu PLN Phase 1
7 System Grounding Panel Kelistrikan Dosing Pump Phase 1 < 1 ohm Lot 1 Berfungsi Baik Ruang Chemical