Estimating Assignment Final
Estimating Assignment Final
Total Marks
TOTAL /80
TABLE OF CONTENT
CONTENT PAGE
Question 1 :
Introduction 3
Conclusion 64
Appendix 65-67
Question 2 68-71
Question 3 72-75
Reference 76-78
Introduction
The project we have found to be applied into this assignment is a project about a
single-story bungalow. The information we have collected about this project is the
Bill of Quantities (BQ). The information, which is unobtainable are the tendering
documents, contract documents, etc. The dimension of the components and the
works included in this project which were shown in the BQ, are the excavation
works, works below lowest floor finishes, frames, roofs, walls, doors, windows,
floors, ceilings and plumbing. Based on the BQ and the estimations, there are rates
of each work based on the assumptions and costs of labor during each process,
starting from excavation for pad footings with depth not exceeding 1.50m deep,
until the application of the finishing coats onto the surface of the ceilings. Each of
the estimating calculation was assumptions-included and the assumptions were
consistent throughout the entire construction period. There are some works that
may have a slight alternation compared to the pre- construction designs when it
was being measured or constructed on the actual work, which they will be
measured as “Provisional Measurement”.
The build-up rate in the construction works shows how fast the parts of the
construction can be done, and it can be influenced by several factors as the rate was
based on some principles. Take the excavation works in the first step in a
construction, for instance, it will be affected primarily by the labors, construction
materials and the plants/machines. The factors changing the labor rates include the
different procuring way of a labor on the site, which was either in-house, supply
only, or supply and install. The rate of labor also depends on the skill efficiency of
the certain worker towards the works in a construction. Workers with higher skills
will result in higher cost per hour and that increases the total cost consumed during
the construction period. On the other hand, however, workers with higher skills
also usually have a higher output of productivity and the quality of finish, which in
the meantime, decreasing the time used on construction.
The second principle, which relates to the building material, comes with
various circumstances which need to be encountered. Some materials require extra
works than other materials after the delivery, unloading, stacking, handling and
protection costs, which increase the material cost in overall. For example, there are
bending works and binding works on the reinforcement bars, and there are mixing
works and formworks on the concrete installation. Some other components such as
slabs, windows, and doors will require higher skill level workers to execute out the
works, will also indirectly increase the cost used.
The third principle of the build-up rate, states that it also can be influenced
by the plants and machines used on the site. This is because the contractor may not
have the ownership on some plants, in result they will have extra payments for the
plants to execute certain construction works, to speed up the build-up rate. Some
of the plants and machines will have a shorter expected lifespan, hance the
contractor will have to take in consideration before conducting the works, because
when a plant needs maintenance and repairing, it decreases the build-up rate, and
it can slow down or delay the entire construction works.
In the BQ below in our assignment, we will show what are the components
needed in the project and the costs to be paid for each component after the
estimating calculations.
BQ With Rates
SHOW UNIT
Item BILL NO. 3 Unit Rate Qty. Amount (RM)
SINGLE STOREY BUNGALOW
Notes
B The words "as described" where used in this Bill shall mean as
described in the above documents.
C The quantities in this Bill are for Contractor's guidance only and shall not
form part of the Contract; except for works where quantities measured as
"PROVISIONAL" are subject to remeasurement based on actual work
executed.
D Contractor shall fill in details any item or quantity not included in this Bill
but necessary for the satisfactory completion of the works as shown in
the Drawings.
F The description in this Bill shall form an integral part of the Specification.
In case of discrepancy, difference or divergence between the Drawings
and the Specification, Contractor shall report to the Architect or Quantity
Surveyor for decision.
H This Bill is for one (1) no. of Bungalow Show Unit (Type 1) and one (1)
no. of Typical Bungalow (Type 1). Contractor is deemed to have allowed
for all additional works for non-typical units.
To Collection RM : -
Item WORK BELOW LOWEST FLOOR FINISH Unit Rate Qty. Amount (RM)
Excavation commencing from reduced level and get out, fill in and ram;
remove surplus excavated materials from site:-
1 Excavate for pad footings; not exceeding 1.50m deep. M3 14.95 2 29.90
2 Ditto; exceeding 1.50m but not exceeding 3.00m deep. M3 26.45 0.5 13.23
3 Excavate for ground beams; not exceeding 1.50m deep. M3 15.70 1 15.70
6 150mm (finished) Bed under ground slabs and thickenings. M2 9.26 171 1,583.46
7 150mm (finished) Bed under apron, terrace, car porch slabs and M2 9.26 98 907.48
driveway.
To Collection RM : 3,725.78
Item WORK BELOW LOWEST FLOOR FINISH (CONT'D) Unit Rate Qty. Amount (RM)
8 600mm x 600mm x 75mm Thick concrete slab with fibre mesh and M2 93.95 56 5,261.20
including 25mm gap fill with aggregate and sand. (Car Porch & Master
Bedroom Terrace)
To Collection RM : 25,710.49
Item WORK BELOW LOWEST FLOOR FINISH (CONT'D) Unit Rate Qty. Amount (RM)
Pad footings
Column stumps
Ground beams
Pad footings
Column stumps
Ground beams
To Collection RM : 1,027.94
Item WORK BELOW LOWEST FLOOR FINISH (CONT'D) Unit Rate Qty. Amount (RM)
Ground Slabs
9 Edge of concrete; exceeding 200mm but not exceeding 300mm high. M 20.02 58 1,161.16
10 -
To Collection RM : 10,267.38
Item WORK BELOW LOWEST FLOOR FINISH (CONT'D) Unit Rate Qty. Amount (RM)
COLLECTION
COLLECTION
Columns
Stiffeners
Columns
Stiffeners
To Collection RM : 3,300.71
Item FRAME (CONT'D) Unit Rate Qty. Amount (RM)
To Collection RM : 1,923.40
COLLECTION
FRAME RM 5,224.11
Total Carried To End of this Bill
1 Half brick walls (115mm thick); reinforced with and including course M2 32.45 60 1,947.00
reinforcement as described at every fourth course, well lapped.
2 100mm Thick "Acotec" precast panel setting on and filled with "Acofix" M2 92.87 110 10,215.70
jointing compound to all joints, anchor bar and fixing accessories
inclusive of necessary starter bar, reinforcement and cement and sand
infill, all as per manufacturer's specification.
3 100mm Thick "Acotec" fire-rated precast panel setting on and filled with M2 114.61 5 573.05
"Acofix" jointing compound to all joints, anchor bar and fixing
accessories inclusive of necessary starter bar, reinforcement and cement
and sand infill, all as per manufacturer's specification. (To bath 2)
Galvanised iron gauge 26; soldered 25mm seams and 100mm joints:-
To Collection RM : 13,414.67
Item EXTERNAL WALLS (CONT'D) Unit Rate Qty. Amount (RM)
Prepare and apply one coat of "Nippon Vinilex 5100 Sealer" and two
finishing coats of "Nippon" Weatherbond or approved equivalent weather-
resisting acrylic paint externally on:-
Supply and install cement sand brick copings, complete with supporting
and all ancillary works; all as shown in the drawings:-
To Collection RM : 2,044.32
1 100mm x 100mm Thick copings; including reinforcement. and all M 21.46 4 85.84
additional formwork.
To Collection RM : 85.84
COLLECTION
1 Half brick walls (115mm thick); reinforced with and including course M2 32.45 5 162.25
reinforcement as described at every fourth course, well lapped.
3 100mm Thick "Acotec" precast panel setting on and filled with "Acofix" M2 92.87 96 8,915.52
jointing compound to all joints, anchor bar and fixing accessories
inclusive of necessary starter bar, reinforcement and cement and sand
infill, all as per manufacturer's specification.
4 100mm Thick "Acotec" fire-rated precast panel setting on and filled with M2 114.61 18 2,062.98
"Acofix" jointing compound to all joints, anchor bar and fixing
accessories inclusive of necessary starter bar, reinforcement and cement
and sand infill, all as per manufacturer's specification. (To bath 2)
To Collection RM : 7,694.99
Tender Addendum No. 2
Item INTERNAL WALL FINISHES (CONT'D) Unit Rate Qty. Amount (RM)
Prepare and apply one coat of "Nippon Vinilex 5100 Sealer" and two
finishing coats of "Nippon Matex Pro" or approved equivalent emulsion
paint internally on:-
To Collection RM : 4,981.19
Tender Addendum No. 2
Item INTERNAL WALL FINISHES (CONT'D) Unit Rate Qty. Amount (RM)
COLLECTION
To Collection RM : 16,827.20
Item INTERNAL FLOOR FINISHES (CONT'D) Unit Rate Qty. Amount (RM)
Prepare and clean surface, supply and apply two coats of "SikaTop Seal
107" or approved equivalent cementitious waterproofing coating, at the
rate of 1.0kg/m2 per coat, including all necessary angle fillet at edges;
laid all in accordance to the manufacturer's printed instruction and
specification including 5 years warranty for product and workmanship:-
5.26 24 126.24
5.26 4 21.04
To Collection RM : 1,218.29
Item INTERNAL FLOOR FINISHES (CONT'D) Unit Rate Qty. Amount (RM)
COLLECTION
- -
Labour cost
To excavate
General worker = 2 hours x (RM40.00/8 hours) = RM 10.00
Boards and struts, say = RM3.00
Total cost = RM13.00
15% profit and overhead = RM1.95
Price/m3 = RM14.95
2. Excavate for pad footings; exceeding 1.50m but not exceeding 3.00m deep. – m3
Assumption:
Hours to excavate = 4 hours
Labour cost
To excavate
General worker = 4 hours x (RM40.00/8 hours) = RM20.00
Boards and sturts, say = RM3.00
Total cost = RM23.00
15% profit and overhead = RM3.45
Price/m3 = RM26.45
Labour cost
To excavate
General worker = 2 hours x (RM40.00/ 8 hours) = RM10.00
Boards and sturts = RM3.00
Wastage 5% = RM0.65
Total cost = RM13.65
15% profit and overhead = RM2.05
Price/m3 = RM15.70
4. Excavate for thickenings; including forming sloping sides; not exceeding 1.50m deep.
– m3
Assumption:
Output for general workers = 2 hours
Wastage 5 %
Labour cost
To excavate
General worker = 2 hours x (RM40.00/ 8 hours) = RM10.00
Boards and sturts = RM3.00
Wastage 5% = RM0.65
Total cost = RM13.65
15% profit and overhead = RM2.05
Price/m3 = RM15.70
5. Lean concrete (Grade 15) as described 50mm Blinding under pad footings – m2
Assumptions
Concrete Grade 15 = Concrete mix 1 : 2 : 4
Cost for cement = RM15.45/bag (50kg)
Cost for sand = RM32.00/m3
Cost for aggregate = RM41.00/m3
Material cost
1 m3 cement = 30 bags x RM15.45 = RM463.50
2 m3 sand = 2m3 x RM32.00 = RM64.00
4 m3 aggregate = 4m3 x RM41.00 = RM164.00
Subtotal = RM691.50
50% for shrinkage, compaction, and wastage = RM345.75
Material cost for 7.00m3 = RM1037.25
Material cost/m3 = RM148.18
Material cost for m2 = RM148.18 x (50/1000) = RM7.41
Labour cost
To mix
General worker = 2.00 hours x (RM40.00/8 hours) = RM10.00
To transport and place
General worker = 8.00 hours x (RM40.00/8 hours) = RM40.00
Total cost = RM57.41
15% profit and overhead = RM8.61
Price/m2 = RM66.02
7. 150mm (finished) Bed under apron, terrace, car porch slabs and driveway – m2
Assumption:
Wastage = 7.5%
Output for general worker = 1.05 hours
Labour cost
General worker = 1.05 hours x (RM40.00/8 hours) = RM5.25
Boards and struts = RM3.00
Wastage 5 % = RM0.15
Total = RM8.40
15% profit and overbed = RM1.26
Price/m2 = RM9.26
8. 0.3mm thick polythene sheet damp-proofing membrane; well lapped at joints under
side of ground slabs and thickenings – m2
Assumption:
Price of polythene sheet = RM2.04/m2
Overlapping and wastage = 5%
Material cost
Polythene sheet = RM2.04
5% overlapping and wastage = RM0.10
Labour cost
Bricklayer = 0.02 hour x (RM60.00/8 hours) = RM0.15
General worker = 0.01 hour x (RM40.00/8 hours) = RM0.05
Total cost = RM2.34
15% profit and overhead = RM0.35
Price/m2 = RM2.69
9. 0.3mm thick polythene sheet damp-proofing membrane; well lapped at joints under
side of apron and terrace – m2
Assumption:
Price of polythene sheet = RM2.04/m2
Overlapping and wastage = 5%
Material cost
Polythene sheet = RM2.04
5% overlapping and wastage = RM0.10
Labour cost
Bricklayer = 0.02 hour x (RM60.00/8 hours) = RM0.15
General worker = 0.01 hour x (RM40.00/8 hours) = RM0.05
Total cost = RM2.34
15% profit and overhead = RM0.35
Price/m2 = RM2.69
Material Cost
1m3 cement = 28 bags x RM15.45 = RM432.60
1m3 sand = RM32.00 x 1m3 = RM32.00
2m3 aggregate = RM41.00 x 2m3 = RM82.00
Subtotal = RM546.60
50% for shrinkage, compaction, and wastage = RM273.30
Material cost for 4.00m3 = RM819.90
Material cost/m3 = RM204.98
Labour cost
To mix
General worker = 2.00 hours x (RM40.00/8 hours) = RM10.00
To transport and place
General worker = 8.00 hours x (RM40.00/8 hours) = RM40.00
Total cost = RM254.98
15% profit and overhead = RM38.25
Price/m3 = RM293.23
Material Cost
1m3 cement = 28 bags x RM15.45 = RM432.60
1m3 sand = RM32.00 x 1m3 = RM32.00
2m3 aggregate = RM41.00 x 2m3 = RM82.00
Subtotal = RM546.60
50% for shrinkage, compaction, and wastage = RM273.30
Material cost for 4.00m3 = RM819.90
Material cost/m3 = RM204.98
Labour cost
To mix
General worker = 2.00 hours x (RM40.00/8 hours) = RM10.00
To transport and place
General worker = 8.00 hours x (RM40.00/8 hours) = RM40.00
Total cost = RM254.98
15% profit and overhead = RM38.25
Price/m3 = RM293.23
14. Vibrated reinforced concrete (Grade 25) in 125mm thick ground slabs – m2
Assumption:
Reinforced concrete Grade 25 = Concrete mix 1 : 1 : 2
Cost for cement = RM15.45/bag (50kg)
Cost for sand = RM32.00/m3
Cost for aggregate = RM41.00/m3
Material Cost
1m3 cement = 28 bags x RM15.45 = RM432.60
1m3 sand = RM32.00 x 1m3 = RM32.00
2m3 aggregate = RM41.00 x 2m3 = RM82.00
Subtotal = RM546.60
50% for shrinkage, compaction, and wastage = RM273.30
Material cost for 4.00m3 = RM819.90
Material cost/m3 = RM204.98
Material cost/m2 = RM204.98 x (125mm/1000m) = RM25.62
Labour cost
To mix
General worker = 2.50 hours x (RM40.00/8 hours) = RM12.50
To transport and place
General worker = 8.00 hours x (RM40.00/8 hours) = RM40.00
Total cost = RM78.12
15% profit and overhead = RM11.72
Price/m2 = RM89.84
15. Vibrated reinforced concrete (Grade 25) in 100mm thick ground slabs – m2
Assumption:
Reinforced concrete Grade 25 = Concrete mix 1 : 1 : 2
Cost for cement = RM15.45/bag (50kg)
Cost for sand = RM32.00/m3
Cost for aggregate = RM41.00/m3
Material Cost
1m3 cement = 28 bags x RM15.45 = RM432.60
1m3 sand = RM32.00 x 1m3 = RM32.00
2m3 aggregate = RM41.00 x 2m3 = RM82.00
Subtotal = RM546.60
50% for shrinkage, compaction, and wastage = RM273.30
Material cost for 4.00m3 = RM819.90
Material cost/m3 = RM204.98
Material cost/m2 = RM204.98 x (100mm/1000m) = RM20.50
Labour cost
To mix
General worker = 2.50 hours x (RM40.00/8 hours) = RM12.50
To transport and place
General worker = 8.00 hours x (RM40.00/8 hours) = RM40.00
Total cost = RM73.00
15% profit and overhead = RM10.95
Price/m2 = RM83.95
16. Vibrated reinforced concrete (Grade 25) in 100mm thick ground slabs – m2
Assumption:
Reinforced concrete Grade 25 = Concrete mix 1 : 1 : 2
Cost for cement = RM15.45/bag (50kg)
Cost for sand = RM32.00/m3
Cost for aggregate = RM41.00/m3
Material Cost
1m3 cement = 28 bags x RM15.45 = RM432.60
1m3 sand = RM32.00 x 1m3 = RM32.00
2m3 aggregate = RM41.00 x 2m3 = RM82.00
Subtotal = RM546.60
50% for shrinkage, compaction, and wastage = RM273.30
Material cost for 4.00m3 = RM819.90
Material cost/m3 = RM204.98
Material cost/m2 = RM204.98 x (100mm/1000m) = RM20.50
Labour cost
To mix
General worker = 2.50 hours x (RM40.00/8 hours) = RM12.50
To transport and place
General worker = 8.00 hours x (RM40.00/8 hours) = RM40.00
Total cost = RM73.00
15% profit and overhead = RM10.95
Price/m2 = RM83.95
17. Precast concrete (Grade 25) of 600mm x 600mm x 75mm thick concrete slab with
fibre mesh and including 25mm gap fill with aggregate and sand. – m2
Assumption:
Reinforced concrete Grade 25 = Concrete mix 1 : 1 : 2
Cost for cement = RM15.45/bag (50kg)
Cost for sand = RM32.00/m3
Cost for aggregate = RM41.00/m3
Material Cost
1m3 cement = 28 bags x RM15.45 = RM432.60
1m3 sand = RM32.00 x 1m3 = RM32.00
2m3 aggregate = RM41.00 x 2m3 = RM82.00
Subtotal = RM546.60
50% for shrinkage, compaction, and wastage = RM273.30
Material cost for 4.00m3 = RM819.90
Material cost/m3 = RM204.98
Material cost/m2 = RM204.98 x (100mm/1000m) = RM20.50
Labour cost
To mix
General worker = 2.50 hours x (RM40.00/8 hours) = RM12.50
To transport and place
General worker = 8.00 hours x (RM40.00/8 hours) = RM40.00
Total cost = RM73.00
15% profit and overhead = RM10.95
Price/m2 = RM83.95
18. 10mm Diameter mild steel rod reinforcement in links, stirrups, and binders in pad
footings - kg
Assumptions:
Cost for 10 mm Diameter mild steel rod reinforcement = RM2,850.00/tonne
Cost for tying wire = RM4.00/kg
Wages of bar bender = RM55.00/day
Quotation for reinforcement work by labour – only subcontractor = RM350.00/tonne
19. 10mm Diameter mild steel rod reinforcement in links, stirrups, and binders in column
stumps - kg
Assumptions:
Cost for 10 mm Diameter mild steel rod reinforcement = RM2,850.00/tonne
Cost for tying wire = RM4.00/kg
Wages of bar bender = RM55.00/day
Quotation for reinforcement work by labour – only subcontractor = RM350.00/tonne
20. 6mm Diameter mild steel rod reinforcement in links, stirrups, and binders in ground
beam - kg
Assumptions:
Cost for 6 mm Diameter mild steel rod reinforcement = RM2,900.00/tonne
Cost for tying wire = RM4.00/kg
Wages of bar bender = RM55.00/day
Quotation for reinforcement work by labour – only subcontractor = RM350.00/tonne
21. 12mm Diameter high tensile steel rod reinforcement in pad footings - kg
Assumptions:
Cost for 12 mm Diameter high tensile steel rod reinforcement = RM2,850.00/tonne
Cost for tying wire = RM4.00/kg
Wages of bar bender = RM55.00/day
Quotation for reinforcement work by labour – only subcontractor = RM350.00/tonne
23. 16mm Diameter high tensile steel rod reinforcement in ground beam. - kg
Assumptions:
Cost for 16 mm Diameter high tensile steel rod reinforcement = RM2,700.00/tonne
Cost for tying wire = RM4.00/kg
Wages of bar bender = RM55.00/day
Quotation for reinforcement work by labour – only subcontractor = RM350.00/tonne
24. 10mm Diameter high tensile steel rod reinforcement in ground beam - kg
Assumptions:
Cost for 10 mm Diameter high tensile steel rod reinforcement = RM2,850.00/tonne
Cost for tying wire = RM4.00/kg
Wages of bar bender = RM55.00/day
Quotation for reinforcement work by labour – only subcontractor = RM350.00/tonne
25. 10mm Diameter high tensile steel rod reinforcement in apron and terrace slabs - kg
Assumptions:
Cost for 10 mm Diameter high tensile steel rod reinforcement = RM2,850.00/tonne
Cost for tying wire = RM4.00/kg
Wages of bar bender = RM55.00/day
Quotation for reinforcement work by labour – only subcontractor = RM350.00/tonne
Material cost
BRC A6 = RM6.75
Labour cost
To unload and arrange
General worker = 1.50 x (RM40.00/8 hours) = RM7.50
To install
Labour – only subcontractor = 1 hour x (RM55/8 hours) = RM6.88
Total cost = RM21.13
15% profit and overbend = RM3.17
Price/m2 = RM24.30
Material cost
BRC A6 = RM6.75
Labour cost
To unload and arrange
General worker = 1.50 x (RM40.00/8 hours) = RM7.50
To install
Labour – only subcontractor = 1 hour x (RM55/8 hours) = RM6.88
Total cost = RM21.13
15% profit and overbend = RM3.17
Price/m2 = RM24.30
Material cost
BRC A6 = RM6.75
Labour cost
To unload and arrange
General worker = 1.50 x (RM40.00/8 hours) = RM7.50
To install
Labour – only subcontractor = 1 hour x (RM55/8 hours) = RM6.88
Total cost = RM21.13
15% profit and overbend = RM3.17
Price/m2 = RM24.30
Material cost
Plywood/m2 = RM17.48
0.06m3 struts = 0.06m3 x (RM960.00/1.40) = RM41.14
Subtotal = RM58.62
Cost for formwork for 1 time usage = RM58.62/5 times = RM11.72
0.35 kg nails = 0.35 x RM4.50 = RM1.58
Subtotal = RM13.30
10% wastage = RM1.33
Labour cost
To prepare and fix
Carpenter = 1.00 hour × (RM50.00/8 hours) = RM6.25
General worker = 0.75 hour × (RM40.00/8 hours) = RM3.75
To dismantle and keep
General worker = 0.75 hour × (RM40.00/8 hours) = RM3.75
Total cost = RM28.35
15% price and overbend = RM4.25
Price/m2 = RM32.60
30. Formwork to sides of column stumps – m2
Material cost
Plywood/m2 = RM17.48
0.06m3 struts = 0.06m3 x (RM960.00/1.40) = RM41.14
Subtotal = RM58.62
Cost for formwork for 1 time usage = RM58.62/5 times = RM11.72
0.35 kg nails = 0.35 x RM4.50 = RM1.58
Subtotal = RM13.30
10% wastage = RM1.33
Labour cost
To prepare and fix
Carpenter = 1.00 hour × (RM50.00/8 hours) = RM6.25
General worker = 0.75 hour × (RM40.00/8 hours) = RM3.75
To dismantle and keep
General worker = 0.75 hour × (RM40.00/8 hours) = RM3.75
Total cost = RM28.35
15% price and overbend = RM4.25
Price/m2 = RM32.60
Material cost
Plywood/m2 = RM17.48
0.06m3 struts = 0.06m3 x (RM960.00/1.40) = RM41.14
Subtotal = RM58.62
Cost for formwork for 1 time usage = RM58.62/5 times = RM11.72
0.35 kg nails = 0.35 x RM4.50 = RM1.58
Subtotal = RM13.30
10% wastage = RM1.33
Labour cost
To prepare and fix
Carpenter = 1.00 hour × (RM50.00/8 hours) = RM6.25
General worker = 0.75 hour × (RM40.00/8 hours) = RM3.75
To dismantle and keep
General worker = 0.75 hour × (RM40.00/8 hours) = RM3.75
Total cost = RM28.35
15% price and overbend = RM4.25
Price/m2 = RM32.60
Material cost
Plywood/m2 = RM17.48
0.06m3 struts = 0.06m3 x (RM960.00/1.40) = RM41.14
Subtotal = RM58.62
Cost for formwork for 1 time usage = RM58.62/5 times = RM11.72
0.35 kg nails = 0.35 x RM4.50 = RM1.58
Subtotal = RM13.30
10% wastage = RM1.33
Labour cost
To prepare and fix
Carpenter = 1.00 hour × (RM50.00/8 hours) = RM6.25
General worker = 0.75 hour × (RM40.00/8 hours) = RM3.75
To dismantle and keep
General worker = 0.75 hour × (RM40.00/8 hours) = RM3.75
Total cost = RM28.35
15% price and overbend = RM4.25
Price/m2 = RM32.60
33.
34. Formwork to edge of concrete; not exceeding 100mm high – m
Material cost
Plywood = RM17.48
0.06m3 struts = 0.06m3 x (RM960.00/1.40) = RM41.14
Subtotal = RM58.62
Cost for formwork for 1 time usage = RM58.62/5 times = RM11.72
0.35 kg nails = 0.35 x RM4.50 = RM1.58
Subtotal = RM13.30
10% wastage = RM1.33
Total cost/m2 = RM14.63
Total cost/m = RM14.63 x (100mm/ 1000mm) = Rm1.46
Labour cost
To prepare and fix
Carpenter = 1.00 hour × (RM50.00/8 hours) = RM6.25
General worker = 0.75 hour × (RM40.00/8 hours) = RM3.75
To dismantle and keep
General worker = 0.75 hour × (RM40.00/8 hours) = RM3.75
Total cost = RM15.21
15% price and overbend = RM2.28
Price/m = RM17.49
35. Formwork of concrete; exceeding 200mm but not exceeding 300mm high – m
Material cost
Plywood = RM17.48
0.06m3 struts = 0.06m3 x (RM960.00/1.40) = RM41.14
Subtotal = RM58.62
Cost for formwork for 1 time usage = RM58.62/5 times = RM11.72
0.35 kg nails = 0.35 x RM4.50 = RM1.58
Subtotal = RM13.30
10% wastage = RM1.33
Total cost/m2 = RM14.63
Total cost/m = RM14.63 x (250mm/ 1000mm) = Rm3.66
Labour cost
To prepare and fix
Carpenter = 1.00 hour × (RM50.00/8 hours) = RM6.25
General worker = 0.75 hour × (RM40.00/8 hours) = RM3.75
To dismantle and keep
General worker = 0.75 hour × (RM40.00/8 hours) = RM3.75
Total cost = RM17.41
15% price and overbend = RM2.61
Price/m = RM20.02
FRAME
1. Vibrated reinforced concrete (Grade 25) in columns – m3
Assumption:
Reinforced concrete Grade 25 = Concrete mix 1 : 1 : 2
Cost for cement = RM15.45/bag (50kg)
Cost for sand = RM32.00/m3
Cost for aggregate = RM41.00/m3
Material Cost
1m3 cement = 28 bags x RM15.45 = RM432.60
1m3 sand = RM32.00 x 1m3 = RM32.00
2m3 aggregate = RM41.00 x 2m3 = RM82.00
Subtotal = RM546.60
50% for shrinkage, compaction, and wastage = RM273.30
Material cost for 4.00m3 = RM819.90
Material cost/m3 = RM204.98
Labour cost
To mix
General worker = 2.00 hours x (RM40.00/8 hours) = RM10.00
To transport and place
General worker = 8.00 hours x (RM40.00/8 hours) = RM40.00
Total cost = RM254.98
15% profit and overhead = RM38.25
Price/m3 = RM293.23
Material Cost
1m3 cement = 28 bags x RM15.45 = RM432.60
1m3 sand = RM32.00 x 1m3 = RM32.00
2m3 aggregate = RM41.00 x 2m3 = RM82.00
Subtotal = RM546.60
50% for shrinkage, compaction, and wastage = RM273.30
Material cost for 4.00m3 = RM819.90
Material cost/m3 = RM204.98
Labour cost
To mix
General worker = 2.00 hours x (RM40.00/8 hours) = RM10.00
To transport and place
General worker = 8.00 hours x (RM40.00/8 hours) = RM40.00
Total cost = RM254.98
15% profit and overhead = RM38.25
Price/m3 = RM293.23
3. 10mm Diameter mild steel rod reinforcement in links, stirrups, and binders in
columns - kg
Assumptions:
Cost for 10 mm Diameter mild steel rod reinforcement = RM2,850.00/tonne
Cost for tying wire = RM4.00/kg
Wages of bar bender = RM55.00/day
Quotation for reinforcement work by labour – only subcontractor = RM350.00/tonne
4. 6mm Diameter mild steel rod reinforcement in links, stirrups, and binders in columns
- kg
Assumptions:
Cost for 6 mm Diameter mild steel rod reinforcement = RM2,900.00/tonne
Cost for tying wire = RM4.00/kg
Wages of bar bender = RM55.00/day
Quotation for reinforcement work by labour – only subcontractor = RM350.00/tonne
5. 6mm Diameter mild steel rod reinforcement in links, stirrups, and binders in stiffeners
- kg
Assumptions:
Cost for 6 mm Diameter mild steel rod reinforcement = RM2,900.00/tonne
Cost for tying wire = RM4.00/kg
Wages of bar bender = RM55.00/day
Quotation for reinforcement work by labour – only subcontractor = RM350.00/tonne
Material cost
Plywood/m2 = RM17.48
0.06m3 struts = 0.06m3 x (RM960.00/1.40) = RM41.14
Subtotal = RM58.62
Cost for formwork for 1 time usage = RM58.62/5 times = RM11.72
0.35 kg nails = 0.35 x RM4.50 = RM1.58
Subtotal = RM13.30
10% wastage = RM1.33
Labour cost
To prepare and fix
Carpenter = 1.00 hour × (RM50.00/8 hours) = RM6.25
General worker = 0.75 hour × (RM40.00/8 hours) = RM3.75
Material cost
Plywood/m2 = RM17.48
0.06m3 struts = 0.06m3 x (RM960.00/1.40) = RM41.14
Subtotal = RM58.62
Cost for formwork for 1 time usage = RM58.62/5 times = RM11.72
0.35 kg nails = 0.35 x RM4.50 = RM1.58
Subtotal = RM13.30
10% wastage = RM1.33
Labour cost
To prepare and fix
Carpenter = 1.00 hour × (RM50.00/8 hours) = RM6.25
General worker = 0.75 hour × (RM40.00/8 hours) = RM3.75
To dismantle and keep
General worker = 0.75 hour × (RM40.00/8 hours) = RM3.75
Total cost = RM28.35
15% price and overbend = RM4.25
Price/m2 = RM32.60
EXTERNAL WALL
1. Cement and sand brick in cement mortar(1:3) of half bricks walls (115mm thick);
reinforced with and course reinforcement as described at every fourth course, well
lapped. – m2
Assumption:
Width of brick = 210mm
Wastage 5 %
Cost for cement = RM15.45/bag (50kg)
Cost for sand = RM32/m3
Cost for cement and sand brick = RM0.27/no
Material cost
Bricks = 45 No x RM0.27 = RM12.15
Mortar = 0.025m3 x RM186.20 = RM4.66
Brick reinforcement = 3.60m x RM0.60 = RM2.16
Subtotal = RM18.97
Labour cost
Bricklayer = 1.00 hour × (RM60.00/8 hours) = RM7.50
General worker = 0.35 hour × (RM40.00/8 hours) = RM1.75
Subtotal = RM9.25
Total cost = RM28.22
15% profit and overhead = RM4.23
Price/m2 = RM32.45
Material cost
Price of wall panel = RM42.00
Nails = 0.35 x RM4.50 = RM1.58
Wastage of 5% = RM2.18
Subtotal = RM45.76
Labour cost
Layer of skilled worker = 2 hours x (RM60.00/8 hours) = RM15.00
2 general worker = 2 hours x (RM40.00/8 hours) x 2 = RM20.00
Total = RM80.76
15% profit and overhead = RM12.11
Price/m2 = RM92.87
Material cost
Price of wall panel = RM60.00
Nails = 0.35 x RM4.50 = RM1.58
Wastage of 5% = RM3.08
Subtotal = RM64.66
Labour cost
Layer of skilled worker = 2 hours x (RM60.00/8 hours) = RM15.00
2 general worker = 2 hours x (RM40.00/8 hours) x 2 = RM20.00
Total = RM99.66
15% profit and overhead = RM14.95
Price/m2 = RM114.61
Labour cost
1 skilled worker = 1.5 x (RM60.00/8 hours) = 11.25
2 general worker = 2 hours x (RM40.00/8 hours) x 2 = RM20
Total = RM75.32
15% profit and overhead = RM11.30
Price/m2 = RM86.62
Material cost
Price of cement board = RM40.00
Nail = 0.35 x RM4.50 = RM1.58
Wastage of 6%= RM2.49
Subtotal = RM44.07
Labour cost
1 skilled worker = 1.5 x (RM60.00/8 hours) = 11.25
2 general worker = 2 hours x (RM40.00/8 hours) x 2 = RM20
Total = RM75.32
15% profit and overhead = RM11.30
Price/m2 = RM86.62
6. Galvanised iron gauge 26, soldered 25mm seams and 100mm joints flashing to
cement board – m2
Assumption:
Price for galvanised iron gauge 26 = RM30.00/m2
Wastage and spacing = 5%
Output of rebar bender = 2 hours
Output of general worker = 2.5 hours
Material cost
Price of iron gauge = RM30.00
Labour cost
Rebar bender = 2 hours x (RM65.00/8 hours) = RM16.25
2 General worker = 2.5 x (RM40.00/8 hours) x 2 = RM25.00
Total = RM71.25
15% profit and overhead = RM10.69
Price/m2 = RM81.94
7. Apply one coat of zinc chromate primer and two finishing coats of “Nippon 9000” or
approved equivalent gloss enamel paint on steelwork on exposed surfaces of flashing.
– m2
Prepare surface, stirring paint
Materials, say = RM0.50
Ladders, brushes, etc, say = RM0.10
Subtotal RM0.60
5% wastage = RM0.03
Painter = 0.03 hour x (RM40.00/8 hours) = RM0.15
Zinc chromate primer
Paint = 0.057 litres x (RM98.00/5 litres) = RM1.12
5% wastage = RM0.06
Painter = 0.025 hour × (RM40.00/8 hours) = RM0.13
First coat
Paint = 0.063 litres × (RM135.00/5 litre) = RM1.70
5% wastage = RM0.09
Painter = 0.025 hour × (RM40.00/8 hours) = RM0.13
Second coat
Paint = 0.083 litres × (RM135.00/5 litre) = RM2.24
5% wastage = RM0.11
Painter = 0.025 hour × (RM40.00/8 hours) = RM0.13
Total = RM6.49
15% profit and overhead = RM0.97
Price/m2 = RM7.46
8. Prepare and apply one coat of “Nippon Vinilex 5100 Sealer” and two finishing coats
of “Nippon” Weatherbond at exposed surfaces of cement board – m2
Prepare surface, stirring paint
Materials, say = RM0.50
Ladders, brushes, etc, say = RM0.10
Subtotal RM0.60
5% wastage = RM0.03
Painter = 0.03 hour x (RM40.00/8 hours) = RM0.15
Sealer coat
Paint = 0.057 litres x (RM75.00/5 litres) = RM0.86
5% wastage = RM0.04
Painter = 0.025 hour × (RM40.00/8 hours) = RM0.13
First coat
Paint = 0.063 litres × (RM145.00/5 litre) = RM1.83
5% wastage = RM0.09
Painter = 0.025 hour × (RM40.00/8 hours) = RM0.13
Second coat
Paint = 0.083 litres × (RM145.00/5 litre) = RM2.41
5% wastage = RM0.12
Painter = 0.025 hour × (RM40.00/8 hours) = RM0.13
Total = RM6.52
15% profit and overhead = RM0.98
Price/m2 = RM7.50
Material cost
Copings= 10 No x RM0.27 = RM2.70
Mortar = 0.025m3 x RM186.20 = RM4.66
Brick reinforcement = 3.60m x RM0.60 = RM2.16
Subtotal = RM9.52
Labour cost
Coping layer = 1.00 hour × (RM60.00/8 hours) = RM7.50
General worker = 0.35 hour × (RM40.00/8 hours) = RM1.75
Subtotal = RM9.25
Total cost = RM18.77
15% profit and overhead = RM2.81
Price/m = RM21.59
Material cost
Copings= 16 No x RM0.27 = RM4.32
Mortar = 0.025m3 x RM186.20 = RM4.66
Brick reinforcement = 3.60m x RM0.60 = RM2.16
Subtotal = RM11.14
Labour cost
Coping layer = 1.00 hour × (RM60.00/8 hours) = RM7.50
General worker = 0.35 hour × (RM40.00/8 hours) = RM1.75
Subtotal = RM9.25
Total cost = RM20.39
15% profit and overhead = RM3.06
Price/m = RM23.45
Material cost
Copings= 47 No x RM0.27 = RM12.69
Mortar = 0.025m3 x RM186.20 = RM4.66
Brick reinforcement = 3.60m x RM0.60 = RM2.16
Subtotal = RM19.51
Labour cost
Coping layer = 1.00 hour × (RM60.00/8 hours) = RM7.50
General worker = 0.35 hour × (RM40.00/8 hours) = RM1.75
Subtotal = RM9.25
Total cost = RM28.76
15% profit and overhead = RM4.31
Price/m = RM33.07
Material cost
Copings= 10 No x RM0.27 = RM2.70
Mortar = 0.025m3 x RM186.20 = RM4.66
Brick reinforcement = 3.60m x RM0.60 = RM2.16
Subtotal = RM9.52
Labour cost
Coping layer = 1.00 hour × (RM60.00/8 hours) = RM7.50
General worker = 0.35 hour × (RM40.00/8 hours) = RM1.75
Subtotal = RM9.25
Total cost = RM18.77
15% profit and overhead = RM2.81
Price/m = RM21.59
14. 150mm x 100 mm thick protrude of cement sand brick copings-m
Number of copings of wall = (150mm x 100mm)/1000 = 15 No
5% wastage = 0.75 No.
Total = 16 No.
Mortar Cost
Material Cost
1m3 cement = 28 bags x RM15.45 = RM432.60
3m3 sand = 3 x RM32.00 = RM96.00
Subtotal = RM528.60
1/3 for shrinkage and wastage = RM176.20
Cost for 4 m3 = RM704.80
Cost/m3 = RM176.20
Labour cost
To mix
General worker = 2 hours x (RM40.00/8 hours) = Rm10.00
Cost/m3 mortar = RM186.20
Material cost
Copings= 16 No x RM0.27 = RM4.32
Mortar = 0.025m3 x RM186.20 = RM4.66
Brick reinforcement = 3.60m x RM0.60 = RM2.16
Subtotal = RM11.14
Labour cost
Coping layer = 1.00 hour × (RM60.00/8 hours) = RM7.50
General worker = 0.35 hour × (RM40.00/8 hours) = RM1.75
Subtotal = RM9.25
Total cost = RM20.39
15% profit and overhead = RM3.06
Price/m = RM23.45
Mortar Cost
Material Cost
1m3 cement = 28 bags x RM15.45 = RM432.60
1m3 sand = RM32.00 x 1m3 = RM32.00
2m3 aggregate = RM41.00 x 2m3 = RM82.00
Subtotal = RM546.60
1/3 for shrinkage and wastage = RM182.00
Cost for 4 m3 = RM728.60
Cost/m3 = RM182.15
Labour cost
To mix
General worker = 2 hours x (RM40.00/8 hours) = Rm10.00
Cost/m3 mortar = RM186.20
Material cost
Copings= 10 No x RM0.27 = RM2.70
Mortar = 0.025m3 x RM182.15 = RM4.55
Brick reinforcement = 3.60m x RM0.60 = RM2.16
Subtotal = RM9.41
Labour cost
Coping layer = 1.00 hour × (RM60.00/8 hours) = RM7.50
General worker = 0.35 hour × (RM40.00/8 hours) = RM1.75
Subtotal = RM9.25
Total cost = RM18.66
15% profit and overhead = RM2.80
Price/m = RM21.46
Labour cost
To mix
General worker = 2 hours x (RM40.00/8 hours) = Rm10.00
Cost/m3 mortar = RM186.20
Material cost
Bricks = 45 No x RM0.27 = RM12.15
Mortar = 0.025m3 x RM186.20 = RM4.66
Brick reinforcement = 3.60m x RM0.60 = RM2.16
Subtotal = RM18.97
Labour cost
Bricklayer = 1.00 hour × (RM60.00/8 hours) = RM7.50
General worker = 0.35 hour × (RM40.00/8 hours) = RM1.75
Subtotal = RM9.25
Total cost = RM28.22
15% profit and overhead = RM4.23
Price/m2 = RM32.45
2. Cement and sand brick in cement mortar(1:3) of half bricks walls (75mm thick);
reinforced with and course reinforcement as described at every fourth course, well
lapped. – m2
Assumption:
Width of brick = 210mm
Wastage 5 %
Cost for cement = RM15.45/bag (50kg)
Cost for sand = RM32/m3
Cost for cement and sand brick = RM0.27/no
Material cost
Bricks = 68 No x RM0.27 = RM18.36
Mortar = 0.025m3 x RM186.20 = RM4.66
Brick reinforcement = 3.60m x RM0.60 = RM2.16
Subtotal = RM25.18
Labour cost
Bricklayer = 1.00 hour × (RM60.00/8 hours) = RM7.50
General worker = 0.35 hour × (RM40.00/8 hours) = RM1.75
Subtotal = RM9.25
Total cost = RM34.43
15% profit and overhead = RM5.16
Price/m2 = RM39.59
Material cost
Price of wall panel = RM42.00
Nails = 0.35 x RM4.50 = RM1.58
Wastage of 5% = RM2.18
Subtotal = RM45.76
Labour cost
Layer of skilled worker = 2 hours x (RM60.00/8 hours) = RM15.00
2 general worker = 2 hours x (RM40.00/8 hours) x 2 = RM20.00
Total = RM80.76
15% profit and overhead = RM12.11
Price/m2 = RM92.87
Material cost
Price of wall panel = RM60.00
Nails = 0.35 x RM4.50 = RM1.58
Wastage of 5% = RM3.08
Subtotal = RM64.66
Labour cost
Layer of skilled worker = 2 hours x (RM60.00/8 hours) = RM15.00
2 general worker = 2 hours x (RM40.00/8 hours) x 2 = RM20.00
Total = RM99.66
15% profit and overhead = RM14.95
Price/m2 = RM114.61
Material cost
Price of cement board = RM40.00
Nail = 0.35 x RM4.50 = RM1.58
Wastage of 6%= RM2.49
Subtotal = RM44.07
Labour cost
1 skilled worker = 1.5 x (RM60.00/8 hours) = 11.25
2 general worker = 2 hours x (RM40.00/8 hours) x 2 = RM20
Total = RM75.32
15% profit and overhead = RM11.30
Price/m2 = RM86.62
6. 19mm thick plaster of cement and sand (1:3) finished with a steel trowel to walls,
beams and columns-m2
Cost for cement = RM15.45/50kg
Cost for sand = RM32/m3
Cement= 1m3 (1442kg)
Output of labour = 2.10 m2/hour
Material cost
Cement = 1442kg/50kg x RM15.45 = RM445.58
Sand= 3m3 x RM32.00 = RM96.00
Subtotal = RM541.58
33.33% shrinkage = RM180.51
Cost for 4 m3 = RM722.09
Cost for 1m3 = RM772.09/4m3 = RM193.02
10% wastage = RM19.30
Total = RM212.32
Cost of 19mm thick plastering for 1m2 = RM212.32 x 0.019m = RM4.03
Labour cost
Plasterers = 2 × (RM64.00/8 hours) = RM16.00
1 general worker = RM40.00/8 hours = RM5.00
Subtotal = RM21.00
Output of labour/hour = 2.10 m2
Labour cost for 1 m2/hour = 0.476 hour × RM21.00 = RM10.00
Erect and dismantle scaffold = 0.5 hour × (RM40.00/8 hours) = RM2.50
Total cost of plastering = RM16.53
15% profit and overhead = RM2.48
Price/m2 = RM19.01
7. 5mm thick plaster of cement and sand (1:3) finished with a steel trowel to wall
panels-m2
Cost for cement = RM15.45/50kg
Cost for sand = RM32/m3
Cement= 1m3 (1442kg)
Output of labour = 2.10 m2/hour
Material cost
Cement = 1442kg/50kg x RM15.45 = RM445.58
Sand= 3m3 x RM32.00 = RM96.00
Subtotal = RM541.58
33.33% shrinkage = RM180.51
Cost for 4 m3 = RM722.09
Cost for 1m3 = RM772.09/4m3 = RM193.02
10% wastage = RM19.30
Total = RM212.32
Cost of 5mm thick plastering for 1m2 = RM212.32 x 0.005m = RM1.06
Labour cost
Plasterers = 2 × (RM64.00/8 hours) = RM16.00
1 general worker = RM40.00/8 hours = RM5.00
Subtotal = RM21.00
Output of labour/hour = 2.10 m2
Labour cost for 1 m2/hour = 0.476 hour × RM21.00 = RM10.00
Erect and dismantle scaffold = 0.5 hour × (RM40.00/8 hours) = RM2.50
Total cost of plastering = RM13.56
15% profit and overhead = RM2.03
Price/m2 = RM15.59
8. 5mm thick plaster of cement and sand (1:3) finished with a steel trowel to cement
boards-m2
Cost for cement = RM15.45/50kg
Cost for sand = RM32/m3
Cement= 1m3 (1442kg)
Output of labour = 2.10 m2/hour
Material cost
Cement = 1442kg/50kg x RM15.45 = RM445.58
Sand= 3m3 x RM32.00 = RM96.00
Subtotal = RM541.58
33.33% shrinkage = RM180.51
Cost for 4 m3 = RM722.09
Cost for 1m3 = RM772.09/4m3 = RM193.02
10% wastage = RM19.30
Total = RM212.32
Cost of 5mm thick plastering for 1m2 = RM212.32 x 0.005m = RM1.06
Labour cost
Plasterers = 2 × (RM64.00/8 hours) = RM16.00
1 general worker = RM40.00/8 hours = RM5.00
Subtotal = RM21.00
Output of labour/hour = 2.10 m2
Material cost
Tiles = 6 No./m2 x RM5.00 = RM30.00
Unloading, say 3% = RM0.90
5% wastage = RM1.50
Subtotal = RM32.40
Mortar = 0.012 x RM186.20 = RM2.23
Cost of material for 1 m2 = RM34.63
Labour cost
2 tilers = 2 × (RM64.00/8 hours) = RM16.00
1 general worker = RM40.00/8 hours = RM5.00
Subtotal = RM21.00
Output of labour/hour = 1.6 m2
Cost of laying and pointing for 1 m2/hour = 0.625 hour × RM21.00 = RM13.13
Total = RM47.76
15% profit and overhead = RM7.16
Price/m2 = RM54.92
Material cost
Tiles = 11 No./m2 x RM5.00 = RM55.00
Unloading, say 3% = RM1.65
5% wastage = RM2.75
Subtotal = RM59.40
Mortar = 0.012 x RM186.20 = RM2.23
Cost of material for 1 m2 = RM61.63
Labour cost
2 tilers = 2 × (RM64.00/8 hours) = RM16.00
Material cost
Tiles = 11 No./m2 x RM5.00 = RM55.00
Unloading, say 3% = RM1.65
5% wastage = RM2.75
Subtotal = RM59.40
Mortar = 0.012 x RM186.20 = RM2.23
Cost of material for 1 m2 = RM61.63
Labour cost
2 tilers = 2 × (RM64.00/8 hours) = RM16.00
1 general worker = RM40.00/8 hours = RM5.00
Subtotal = RM21.00
Output of labour/hour = 1.6 m2
Cost of laying and pointing for 1 m2/hour = 0.625 hour × RM21.00 = RM13.13
Total = RM74.76
15% profit and overhead = RM11.21
Price/m2 = RM85.97
12. Prepare and apply one coat of “Nippon Vinilex 5100 Sealer” and two finishing coats
of “Nippon Matex Pro” at plastered walls, beams and columns – m2
Prepare surface, stirring paint
Materials, say = RM0.50
Ladders, brushes, etc, say = RM0.10
Subtotal RM0.60
5% wastage = RM0.03
Painter = 0.03 hour x (RM40.00/8 hours) = RM0.15
Sealer coat
Paint = 0.057 litres x (RM75.00/5 litres) = RM0.86
5% wastage = RM0.04
Painter = 0.025 hour × (RM40.00/8 hours) = RM0.13
First coat
Paint = 0.063 litres × (RM90.00/5 litre) = RM1.13
5% wastage = RM0.06
Painter = 0.025 hour × (RM40.00/8 hours) = RM0.13
Second coat
Paint = 0.083 litres × (RM90.00/5 litre) = RM1.49
5% wastage = RM0.07
Painter = 0.025 hour × (RM40.00/8 hours) = RM0.13
Total = RM4.82
15% profit and overhead = RM0.72
Price/m2 = RM5.54
Material cost
Tiles = 14 No./m2 x RM5.00 = RM70.00
Unloading, say 3% = RM2.10
5% wastage = RM3.50
Subtotal = RM75.60
Mortar = 0.012 x RM186.20 = RM2.23
Cost of material for 1 m2 = RM77.89
Labour cost
2 tilers = 2 × (RM64.00/8 hours) = RM16.00
1 general worker = RM40.00/8 hours = RM5.00
Subtotal = RM21.00
Output of labour/hour = 1.6 m2
Cost of laying and pointing for 1 m2/hour = 0.625 hour × RM21.00 = RM13.13
Total = RM90.96
15% profit and overhead = RM13.64
Price/m2 = RM104.60
2. 600mm x 600mm x 25mm acotiles wall tiles with 75mm high drop – m
Assumptions:
Wall tiles = 12 No.tiles/m2
Cost of tiles = RM5.00/pc
Mortal for 1 m2 = 0.012m3
Cost of mortar= RM186.20/m3
Material cost
Tiles = 12 No./m2 x RM5.00 = RM60.00
Unloading, say 3% = RM1.80
5% wastage = RM3.00
Subtotal = RM64.80
Material cost
Tiles = 13 No./m2 x RM5.00 = RM65.00
Unloading, say 3% = RM1.95
5% wastage = RM3.25
Subtotal = RM70.20
Mortar = 0.012 x RM186.20 = RM2.23
Cost of material for 1 m2 = RM72.43
Cost of material for 1 m = RM72.43 x (50/1000) = RM3.62
Labour cost
2 tilers = 2 × (RM64.00/8 hours) = RM16.00
1 general worker = RM40.00/8 hours = RM5.00
Subtotal = RM21.00
Output of labour/hour = 1.6 m
Cost of laying and pointing for 1 m/hour = 0.625 hour × RM21.00 = RM13.13
Total = RM16.75
15% profit and overhead = RM2.51
Price/m = RM19.26
4. 400mm x 400mm x 25mm thick acotiles wall tiles to floors in all bedroom - m2
Assumptions:
Wall tiles = 24 No.tiles/m2
Cost of tiles = RM5.00/pc
Mortal for 1 m2 = 0.012m3
Cost of mortar= RM186.20/m3
Material cost
Tiles = 24 No./m2 x RM5.00 = RM120.00
Unloading, say 3% = RM3.60
5% wastage = RM6.00
Subtotal = RM129.60
Mortar = 0.012 x RM186.20 = RM2.23
Cost of material for 1 m2 = RM131.83
Labour cost
2 tilers = 2 × (RM64.00/8 hours) = RM16.00
1 general worker = RM40.00/8 hours = RM5.00
Subtotal = RM21.00
Output of labour/hour = 1.6 m2
Cost of laying and pointing for 1 m2/hour = 0.625 hour × RM21.00 = RM13.13
Total = RM144.96
15% profit and overhead = RM21.74
Price/m2 = RM166.70
5. 400mm x 400mm x 25mm thick acotiles wall tiles to floors in all bedroom with
75mm high drops - m
Assumptions:
Wall tiles = 24 No.tiles/m2
Cost of tiles = RM5.00/pc
Mortal for 1 m2 = 0.012m3
Cost of mortar= RM186.20/m3
Material cost
Tiles = 24 No./m2 x RM5.00 = RM120.00
Unloading, say 3% = RM3.60
5% wastage = RM6.00
Subtotal = RM129.60
Mortar = 0.012 x RM186.20 = RM2.23
Cost of material for 1 m2 = RM131.83
Cost of material for 1 m = RM131.83 x (75/1000) = RM9.89
Labour cost
2 tilers = 2 × (RM64.00/8 hours) = RM16.00
1 general worker = RM40.00/8 hours = RM5.00
Subtotal = RM21.00
Output of labour/hour = 1.6 m2
Cost of laying and pointing for 1 m2/hour = 0.625 hour × RM21.00 = RM13.13
Total = RM23.02
15% profit and overhead = RM3.45
Price/m = RM26.47
6. 400mm x 400mm x 25mm thick acotiles wall tiles to floors in all bedroom with
50mm high drops - m
Assumptions:
Wall tiles = 24 No.tiles/m2
Cost of tiles = RM5.00/pc
Mortal for 1 m2 = 0.012m3
Cost of mortar= RM186.20/m3
Material cost
Labour cost
2 tilers = 2 × (RM64.00/8 hours) = RM16.00
1 general worker = RM40.00/8 hours = RM5.00
Subtotal = RM21.00
Output of labour/hour = 1.6 m2
Cost of laying and pointing for 1 m2/hour = 0.625 hour × RM21.00 = RM13.13
Total = RM19.72
15% profit and overhead = RM2.96
Price/m = RM22.68
7. 400mm x 400mm x 25mm thick acotiles wall tiles to floors in kitchens - m2
Assumptions:
Wall tiles = 24 No.tiles/m2
Cost of tiles = RM5.00/pc
Mortal for 1 m2 = 0.012m3
Cost of mortar= RM186.20/m3
Material cost
Tiles = 24 No./m2 x RM5.00 = RM120.00
Unloading, say 3% = RM3.60
5% wastage = RM6.00
Subtotal = RM129.60
Mortar = 0.012 x RM186.20 = RM2.23
Cost of material for 1 m2 = RM131.83
Labour cost
2 tilers = 2 × (RM64.00/8 hours) = RM16.00
1 general worker = RM40.00/8 hours = RM5.00
Subtotal = RM21.00
Output of labour/hour = 1.6 m2
Cost of laying and pointing for 1 m2/hour = 0.625 hour × RM21.00 = RM13.13
Total = RM144.96
15% profit and overhead = RM21.74
Price/m2 = RM166.70
8. 400mm x 400mm x 25mm thick acotiles wall tiles to floors with 150mm high drops -
m
Assumptions:
Wall tiles = 24 No.tiles/m2
Cost of tiles = RM5.00/pc
Mortal for 1 m2 = 0.012m3
Cost of mortar= RM186.20/m3
Material cost
Tiles = 24 No./m2 x RM5.00 = RM120.00
Unloading, say 3% = RM3.60
5% wastage = RM6.00
Subtotal = RM129.60
Mortar = 0.012 x RM186.20 = RM2.23
Cost of material for 1 m2 = RM131.83
Cost of material for 1 m = RM131.83 x (150/1000) = RM19.77
Labour cost
2 tilers = 2 × (RM64.00/8 hours) = RM16.00
1 general worker = RM40.00/8 hours = RM5.00
Subtotal = RM21.00
Output of labour/hour = 1.6 m2
Cost of laying and pointing for 1 m2/hour = 0.625 hour × RM21.00 = RM13.13
Total = RM32.90
15% profit and overhead = RM4.94
Price/m = RM37.84
Material cost
Tiles = 11 No./m2 x RM5.00 = RM55.00
Unloading, say 3% = RM1.65
5% wastage = RM2.75
Subtotal = RM59.40
Mortar = 0.012 x RM186.20 = RM2.23
Cost of material for 1 m2 = RM61.63
Labour cost
2 tilers = 2 × (RM64.00/8 hours) = RM16.00
1 general worker = RM40.00/8 hours = RM5.00
Subtotal = RM21.00
Output of labour/hour = 1.6 m2
Cost of laying and pointing for 1 m2/hour = 0.625 hour × RM21.00 = RM13.13
Total = RM74.76
15% profit and overhead = RM11.21
Price/m2 = RM85.97
10. 300mm x 300mm x 25mm acotiles wall tiles with 25mm high drops – m
Assumptions:
Wall tiles = 11 No.tiles/m2
Cost of tiles = RM5.00/pc
Mortal for 1 m2 = 0.012m3
Cost of mortar= RM186.20/m3
Material cost
Tiles = 11 No./m2 x RM5.00 = RM55.00
Unloading, say 3% = RM1.65
5% wastage = RM2.75
Subtotal = RM59.40
Mortar = 0.012 x RM186.20 = RM2.23
Cost of material for 1 m2 = RM61.63
Cost of material for 1 m = RM61.63 x (25/1000) = RM1.54
Labour cost
2 tilers = 2 × (RM64.00/8 hours) = RM16.00
1 general worker = RM40.00/8 hours = RM5.00
Subtotal = RM21.00
Output of labour/hour = 1.6 m2
Cost of laying and pointing for 1 m2/hour = 0.625 hour × RM21.00 = RM13.13
Total = RM14.67
15% profit and overhead = RM2.20
Price/m = RM16.87
Material cost
Tiles = 11 No./m2 x RM5.00 = RM55.00
Unloading, say 3% = RM1.65
5% wastage = RM2.75
Subtotal = RM59.40
Mortar = 0.012 x RM186.20 = RM2.23
Cost of material for 1 m2 = RM61.63
Labour cost
2 tilers = 2 × (RM64.00/8 hours) = RM16.00
1 general worker = RM40.00/8 hours = RM5.00
Subtotal = RM21.00
Output of labour/hour = 1.6 m2
Cost of laying and pointing for 1 m2/hour = 0.625 hour × RM21.00 = RM13.13
Total = RM74.76
15% profit and overhead = RM11.21
Price/m2 = RM85.97
12. 300mm x 300mm x 25mm acotiles wall tiles with 25mm high drops – m
Assumptions:
Wall tiles = 11 No.tiles/m2
Cost of tiles = RM5.00/pc
Mortal for 1 m2 = 0.012m3
Cost of mortar= RM186.20/m3
Material cost
Tiles = 11 No./m2 x RM5.00 = RM55.00
Unloading, say 3% = RM1.65
5% wastage = RM2.75
Subtotal = RM59.40
Mortar = 0.012 x RM186.20 = RM2.23
Cost of material for 1 m2 = RM61.63
Cost of material for 1 m = RM61.63 x (25/1000) = RM1.54
Labour cost
2 tilers = 2 × (RM64.00/8 hours) = RM16.00
1 general worker = RM40.00/8 hours = RM5.00
Subtotal = RM21.00
Output of labour/hour = 1.6 m2
Cost of laying and pointing for 1 m2/hour = 0.625 hour × RM21.00 = RM13.13
Total = RM14.67
15% profit and overhead = RM2.20
Price/m = RM16.87
13. Prepare and clean surface two coats of “SikaTop Seal 107” at concrete surfaces of
floor slabs – m2
Prepare surface, stirring paint
Materials, say = RM0.50
Ladders, brushes, etc, say = RM0.10
Subtotal RM0.60
5% wastage = RM0.03
Painter = 0.03 hour x (RM40.00/8 hours) = RM0.15
First coat
Paint = 0.063 litres × (RM115.00/5 litre) = RM1.45
5% wastage = RM0.07
Painter = 0.025 hour × (RM40.00/8 hours) = RM0.13
Second coat
Paint = 0.083 litres × (RM115.00/5 litre) = RM1.91
5% wastage = RM0.10
Painter = 0.025 hour × (RM40.00/8 hours) = RM0.13
Total = RM4.57
15% profit and overhead = RM0.69
Price/m2 = RM5.26
14. Prepare and apply two finishing coats of “Nippon Matex Pro” on surfaces of ceilings-
m2
Prepare surface, stirring paint
Materials, say = RM0.50
Ladders, brushes, etc, say = RM0.10
Subtotal RM0.60
5% wastage = RM0.03
Painter = 0.03 hour x (RM40.00/8 hours) = RM0.15
First coat
Paint = 0.063 litres × (RM90.00/5 litre) = RM1.13
5% wastage = RM0.06
Painter = 0.025 hour × (RM40.00/8 hours) = RM0.13
Second coat
Paint = 0.083 litres × (RM90.00/5 litre) = RM1.49
5% wastage = RM0.07
Painter = 0.025 hour × (RM40.00/8 hours) = RM0.13
Total = RM3.79
15% profit and overhead = RM0.57
Price/m2 = RM4.36
Conclusion
After the Bill of Quantities (BQ) on this project, we can observe the components
required to carry out this project from the beginning until the end. The assumptions
throughout the project plays an essential role as it determines the outcome of the cost
estimation. Therefore, it is important to adjust the assumptions of the material costs, labour
costs and the cost for the plants, so that the price estimated can acquire greater satisfactions
from the parties.
APPENDIX
References
1. Chong, B. L. 2021, Topic 3: Pricing the works – Unit Rates Build-Up,
lecture notes, UEBQ2153 Estimating, Universiti Tunku Abdul Rahman,
delivered 1 February 2021.
7. White Horse. N.d. Floor Ceramic Tiles [online] Available at: <
http://whitehorse.my/sites/default/files/20210125_Ceramic_Floor_Tiles_4
00x400mm. pdf > [ Accessed 19 April 202]
12.
Q2.
In order to complete a job, there are some costs that exceed the scope of
craftsman and materials needed when build up a new project. As an estimator must be
competent to gather the information on the factors and complete an accurate
estimating. It is important to compile the data because these components will impact
the total cost of the project directly. These factors include the materials, labour,
locations, duration of project, building codes, machinery and also the soil condition at
the site. These factors may not be like important during the project, but it can affect
the duration, cost, and even outcome of a project. For example, customer overestimate
the cost of land acquisition for construction project, or the client might not be aware
the role of weather that play throughout the duration of project. There are the cases of
cost overruns in the construction project when experience severe climates and force
the project delays. The other factors that must be considered include the gas
availability, electricity, water and sewer, and those specific materials that required to
complete the project. For instance, the materials for eco-friendly building are different
with the ordinary project. As not all materials are immediately available and it must
be order in advance to make sure can get the material on time.
2.2 Explain the significant finding you have gained from cost estimating in Question 1
Cost estimate pictures the approximation of the quantity, cost and price of a
project to inform job and budget planning process. A recent study by the Project
Management Institute found that on average, the actual costs were 28% higher than
estimated costs (Sopik , n.d.). However, the accuracy of estimate can be achieved by
having more accurate planning, improved profit margins, improved resource
management and so on.
In the BQ, we are using precast concrete slab with fibre mesh as fibre mesh
can
increase its flexural strength and tensile strength. The major advantages
of adding such fibre in concrete is it can increase the ductility of concrete. Then, we can
notice that the cost of rebar is expensive, which cost RM2,850.00/tonne. This is because raw
material for steel bars has been increased significantly. Global Times (2021) states that in
2020, China produced 1.325 billion tons of steel products, recording a year-on-year increase
of 7.7 percent. China as a major buyer of bulk raw materials, and because of its post-
pandemic economic recovery has been more prominent than in other countries, hence leading
to the return of foreign trade orders to China and thus rising steel demand. Construction
industry in our country had trade with China for their scrap metal in order to produce rebar
however the cost of the scrap metal is also being increased significantly in order to boost
country’s economy. Therefore, the price of the rebar appear to be high. Besides that,
“Acotec” fire-rated precast panel is added for fire resistance purpose. The fire rating of
Acotec panel 100mm is 2 hours.
The information in the preliminary estimate includes the date of the estimate and
date of assumed tender, the brief detail of specification and drawings, the expected
differences from estimate to actual cost of project, the cost for different categories like
sanitation, electricity, water supply and others and also the details of person that
prepare the estimate. The more details provided, the small variation will be form.
By prepare the preliminary estimate, clients and contractors both have the benefits
to each other. It will help clients to find the most suitable contractor based on their
preliminary estimates. Each party will aware to the probable costs and gain early
financial commitment. Both parties can prepare the budget management costs. They
can advise to architect and engineers of the project cost and duty that required.
Most of the preliminary estimate are based on the information from previous
project. It can be based on the factors like project type, geographical region and
construction method. A good preliminary estimate can avoid the strain on relationship
of the construction and clients.
2.4 Elucidate the construction cost estimating analyses for a project based on the
knowledge and experience that you have now.
A good cost estimation is very important in order to keep a project under
budget. An estimating plan has to include the scope definition of the project, defining
the boundaries and time plan. We are clear that every estimate is associated with
uncertainty, which also associated with the probability of underrunning or
overrunning the predicted cost. To achieve the accuracy that we expect our estimate to
have, we can decide to use the estimating technique that best fit the situation. There
are some important estimate methodologies, which are factor estimating, parametric
estimating and detailed estimating.
Firstly, factor estimating. This is also known as top-down estimating, generally is
used in the identification phase. We can use this when the project is not well defined yet,
which means the scope is incomplete and there are a number of alternatives that need to be
worked out more detail. Next, parametric estimating. Parametric estimating is used in earlier
phases (identification and definition) of a project where there is not much specific
information but there is historical data from previous similar projects. A company might have
a collection of previous quotes, contract values and prices hence, we can put this to use by
developing parametric estimation techniques. For example, we might be able to find the cost
estimate relationships (CERs) by studying how the size and material type of pumps relate to
cost (Cost Engineering Consultancy, 2021).
Then, detailed estimating. This is also known as bottom-up estimating,
generally is used when the maturity level of project definition is high (execution and
operational phase). This approach is both time-consuming and costly, it also results in
the most accurate estimates. In short, parametric and detailed estimating are usually
the techniques that can provide most accurate cost projections.
On the other hand, there are many factors that are uncertain to be faced during cost
estimating. This causes challenges to cost estimation. As an example, experience won’t help
in guiding if the project is not like prior ones and also, if the planning horizon is further out, it
faces a greater uncertainty (Westland, 2019). One of the challenges is the quality of available
data. Limited time affect the quality and quantity of data that estimators can obtain. If the
time given is insufficient, estimators may use secondary data sources that lack of thorough
documentation instead of original source. Besides that, large number of organizations
involved is also one of the challenges might be faced during cost estimating. Estimators must
be aware when collecting data which involves many different data sources and organizations.
Estimators have to communicate and coordinate with all these sources to make sure the
information are true and accessible.
Moreover, there are some trends that impact cost estimating today including: Building
Information Modelling (BIM), Sustainability and LEED certification and Lean Construction
and Cost Control. A building information model is a digital model of a structure with all its
characteristics and dimensions. As such, there is an increasing demand for cost estimating to
become an aspect of BIM. Next, LEED Certification is a point system for rating buildings
according to their environmental performance. Estimator is responsible to obtain LEED
certification which involved both calculating the cost of scoring LEED points and
communicating these to clients. Then, for lean construction and cost control, this is a fairly
new approach which is the systematic effort to reduce waste without affecting productivity.
Ramos (2017) states that studies indicate that by applying lean principles in construction
projects helps in saving cost. As such, good understanding of lean principles is a good asset
for cost engineers who apply principles of value engineering to construction projects.
A good construction cost estimating wins jobs. In general, customers usually select
the lowest bid that meet the standards and specifications which set by them. Hence, the time
and effort an estimator spend in preparing the estimate are a cost of doing business and also
an investment in winning the job.
In conclusion, a good cost estimate prevents the builder from losing money
and also helps the customer in preventing them from overpaying.
3 Roles of The Estimator In The Estimating Team
3.1 General
Building construction estimating is that the determination of probable
construction prices of any given project (Frank, n.d.). Several items influence and
contribute to the cost of a project; each item must be analysed, quantified, and priced.
Because the estimate is ready before the particular construction, abundant study and
thought must be place into the construction documents. The estimator who can
visualize the project and accurately confirm its cost will become one of the most
important persons in any construction company.
For projects constructed with the design-bid-build (DBB) delivery system, it is
necessary for contractors to submit a competitive cost estimate for the project (Frank,
n.d.). The competition in construction bidding is intense, with multiple companies
vying for a single project. To remain in business, a contractor must be the lowest-
qualified bidder on a precise number of projects, while maintaining an acceptable
profit margin. This profit margin must offer the general contractor an acceptable rate
of return and compensation for the risk associated with the project. Because the
estimate is ready from the working drawings and the project manual for a building,
the ability of the estimator to visualize all the different phases of the construction
project becomes a prime ingredient in successful bidding.
The working drawings typically contain info relative to the design, location,
dimensions, and construction of the project, whereas the project manual may well be a
written supplement to the drawings and includes info concerning to materials and
workmanship, further as info regarding the bidding process. The working drawings
and also the project manual represent most of the contract documents, define the
scope of work, and must be thought of along once preparing an estimate. The two
complement each other, and they typically overlap within the information they
convey. The bid submitted must be based on the scope work provided by the owner or
the architect (Frank, n.d.). The estimator is responsible for including everything
contained within the drawings and also the project manual within the submitted bid.
Because of the complexness of the drawings and also the project manual, coupled
with the potential cost of an error, the estimator must read everything thoroughly and
recheck all items. Initially, the plans and also the project manual must be checked to
confirm that they are complete. Then the estimator can begin the process of
quantifying all the materials conferred. Every item included within the estimate must
contain as much information as possible. The quantities determined for the estimate
can ultimately be used to order and purchase the required materials. The estimated
quantities and their associated projected costs will become the premise of project
controls within the field (Frank, n.d.).
Estimating the ultimate cost of a project needs the combination of many
variables. These variables fall under either direct field costs or indirect field costs.
The indirect field costs also are stated as general conditions or project overhead costs
in building construction. The direct field costs are the material, labour, equipment, or
subcontracted items that are permanently and physically integrated into the building
(Frank, n.d.). As an example, the labour and materials for the foundation of the
building would be a direct field cost. The indirect field costs are the cost for the items
that are needed to support the sector construction efforts. As an example, the project
site workplace would be a general conditions cost. Additionally, factors like weather,
transportation, soil conditions, labour strikes, material availability, and subcontractor
availability need to be integrated into the estimate. Despite the variables concerned,
the estimator must strive to prepare as accurate an estimate as possible. Since
subcontractors or specialty contractors might perform abundant of the work in the
sector, the estimator must be able to articulate the scope of work for these
corporations to furnish a price quote (Frank, n.d.). The complexness of an estimate
requires organization, estimator’s best judgment, complete specialty contractors’
(subcontractors’) bids, accurate quantity take-offs, and accurate records of completed
projects.
2. Gerardi, J., 2021., Why is Construction Estimating Important? [online] Available at:
<https://proest.com/construction/estimating/why-is-estimating-important/> [Accessed
30 March 2021]
3. Global Times., 2021. Rising Steel Demand in China Helps Elevate Global Market:
CISA, [online] Available at: https://www.globaltimes.cn/page/202101/1214105.shtml
[Accessed on 31 March 2021]
4. IFMA Knowledge Library, n.d., Preliminary Cost Estimate. [online] Available at:
<https://www.pearsonhighered.com/assets/samplechapter/0/1/3/4/013470116X.pdf >
[Accessed 1 April 2021]
5. Kiper, D., 2020., The Purpose of the Estimate. [online] Available at:
<https://www.ecmweb.com/construction/estimating/article/21119807/the-purpose-of-
the-estimate> [Accessed 30 March 2021]
10. Ramos, D., 2017. Construction Cost Estimating: The Basics and Beyond. New
Aspects of Construction Cost Estimating, [online] Available at:
https://www.smartsheet.com/construction-cost estimating#:~:text=Construction
%20cost%20estimating%20is%20the,of%20building%20a%20physical
%20structure.&text=It's%20a%20core%20component%20of,total%20time%20and
%20cost%20estimate. [Accessed on 2 April 2021]
11. Sopik, P., n.d. WorkflowMax. What is a cost estimate? The importance of accurate
estimating for your service business, [online] Available at:
https://www.workflowmax.com/blog/what-is-cost-estimate [Accessed on 30 March
2021]
12. Technomics., 2018. Top 5 Challenges to Cost Estimating, [online] Available at:
https://www.technomics.net/blog/top-5-challenges-to-cost-estimating [Accessed on 2
April 2021]
14. Westland, J., 2019. Project Manager. Cost Estimation for Projects: How to Estimate
Accurately, [online] Available at: https://www.projectmanager.com/blog/cost-
estimation-for-projects [Accessed on 2 April 2021]