Civil - Drawing - Bridge - 301
Civil - Drawing - Bridge - 301
CH:844.40
OF PRO. BRIDGE NO. 301 AT m CAUTION SBC END MYS END
AS SIZE OF1 x 1.8X2M (Clear ht. 2.0)
m RCCBOX EXG. RL. :756.319 INDICATOR SPEED INDICATOR TERMINATION
INDICATION
KM:0.847
KM:0.841
PRO. RAIL LEVEL : 755.856
(SHUNTING NECK) AT Km.2.047 AT Km. 0.877
670
EXG. FL :755.649 AT Km. 0.126
20
762
T
PRO. FORMATION LEVEL : 755.094 OF EXG.TRACK SHUNTING LINE
5.320m
30 m 715 m
HAS END MYS END
8000
1200 m
OF EXG.TRACK DN MAIN LINE
7.270m
C/L OF PIT LINE -2
C/L OF OVER RUN LINE OF EXG. TRACK (UP MAIN LINE)
9.480m
C/L OF SHUNTING NECK
715 m 1200 m
30 m OF EXG.TRACK HAS LINE
6479
11.530m
20
T
EARTH CUSHION 7484 C/L TRACK CONNECTING PRO. PIT LINE 2
4.470m
9734
9941 TERMINATION SPEED INDICATOR CAUTION
9179 1116 INDICATION AT Km. 0.811 INDICATOR C/L PRO. OVER RUN LINE
7150
5.460m
AT Km. 1.559
24.641m
8000
AT Km.0.0
C/L PRO. SHUNTING TRACK
150
900
600
BERM
DIRECTION
600
350
OF FLOW
1800 1166 1600 500 TEMPORARY ENGINEERING INDICATORS NOTES:
U/S
5066 (NOT TO SCALE) BORE HOLE
STEPS 5366 1. PROPOSALS ARE SHOWNRED SITE PLAN
2000 2. TRACK IS STRAIGHT ON BRIDGE LOCATION. (NOT TO SCALE)
2350
2000
HFL : 746.915 EXG. HFL 746.915 1800
2700
350 NOTES :
SAFETY NOTES
1000
1000
BED LEVEL : 745.915 EXG. BL: 745.915 1. ADEQUATESAFETY MEASURESFOR RUNNING TRAINS SHALL BE ADOPTED WHILE DOING 1.
ALL DIMENSIONS ARE IN mm OTHERWISE STATED.
150
300
900 600
PREPARATORY WORKS. 2.
PROPOSALS ARE SHOWN IN RED, DISMANTLING WORKS ARE SHOWN IN YELLOW.
600 2. DURINGCONSTRUCTION OF BOX,THEEXISTINGTRACKSHALLBE PROTECTED SUITABLYBY IMPOSING 3.
DO NOT SCALE THE DRAWING. FOLLOW WRITTEN DIMENSIONS ONLY.
NECESSARY SPEED RESTRICTIONS BY PROVIDING TEMPORARY ENGINEERING INDICATORS. 4.
BEFORE EXECUTION OF THE WORK, THE FIELD ENGINEER SHOULD VERIFY VARIOUS LEVELS INCLUDING RAIL LEVEL,
150
3000 3. THE GRADUAL RELEASE OF SPEED RESTRICTIONS SHALL BE AS PER PARA 637(1)(F) OF IRPWM.
4. NECESSARYSHORINGARRANGEMENTS TO BE MADETO PROTECTEXISTINGBRIDGESTRUCTURE FORMATION LEVEL, HFL, MAXIMUM OBSERVED SCOUR LEVEL ON UPSTREAM, FOUNDATION LEVEL, BORE LOG DATA,
90R RAIL OR ABOVE WHEREVER NECESSARY. TYPE OF SOIL, BEARING CAPACITY ETC.,
AT 700 INTERVALS 5. ALL THE DEVIATIONS MADE FROM THIS DRAWING AS PER SITE REQUIREMENTS & AS PER DIRECTIONS OF
5. JOINT PROCEDURE ORDER FROM SAFETY RELATED ISSUES PERTAINING TO WORK SITE IN
150
CONSTRUCTION PROJECT (Lt No. W.339/SAFETY PRECAUTIONS Dt:18.02.2011) ENGINEER-IN-CHARGE DURING EXECUTION OF THE WORK, SHOULD BE INCORPORATED IN THE COMPLETION
CTE Lt.WIDE
No.
HALF ELEVATION PRO. BRIDGE HALF SECTION
90R RAIL OR SWR/W.247/SAFETY AT WORK SPOT DT: 20.06.2017 IS TO BE STRICTLY FOLLOWED. DRAWING.
ABOVE AT 6. DURINGEXECUTIONOF WORK,THE MATERIALSUCHAS RELEASEDMATERIALETC., SHOULDNOT
700 6. ENGINEER-IN-CHARGE SHALL GIVE CLEAR DIRECTIONS TO THE FIELD ENGINEER IN CASE THERE IS APPREHENSION OF
INFRINGERUNNINGTRAINS.ALL SAFETYMEASURESTO BE TAKENBY ENGINEER-IN-CHARGE DURING
DAMAGE TO NEARBY STRUCTURES, ETC.,
INTERVALS HEIGHT (H) DEPTH (D=H/3) LAUNCHING. 7. EXECUTIVE DEPARTMENT SHALL CONSULT/ INTIMATE OTHER CONCERNED DEPARTMENTS BEFORE EXECUTION OF THE
(m) (m)
MS PLATE 7. SAFETYPRECAUTIONS MUSTBE ENSUREDAS PER ABOVERELEVANTJPO's ZONALRAILWAYAND
8mm THICK 1 0.333
INSTRUCTIONS OF RAILWAY BOARD. WORK.
2 0.667
8. WORKINGAREASHALLBE BARRICADED TO ENSURESAFETYOF TRACKOPERATIONS 8. SPEED RESTRICTIONS TO BE FOLLOWED BEFORE/ DURING/ AFTER THE EXECUTION. GRADUAL RELEASE OF SPEED
ON RUNNING
H MS PLATE
3 1.000
LINES. RESTRICTION SHALL BE AS PER PARA 637(I)(F) OF INDIAN RAILWAY P.WAY MANUAL.
75R RAILS @ 4 1.333
1000 C/C 8mm THICK 5 1.667
9. ERECTION/LAUNCHING WORKOVERRUNNINGLINESHALLBE CARRIEDOUTUNDERTRAFFICBLOCK,9. THE CRANE CAPACITY OF MIN 250 TONNES IN GOOD WORKING CONDITION TO BE USED. MOREALSO,
CRANE
ONE
6 2.000
UNDER SUPERVISION OF CONCERNED ENGINEER-IN CHARGE. OF SAME CAPACITY IN GOOD WORKING CONDITION SHOULD BE KEPT AS ANDSTANDBY
ENGINEER-IN-CHARGE
7 2.333
10. Ty. GIRDER MUST BE ADEQUATELY SECURED IMMEDIATELY AFTER LAUNCHING. SHOULD ENSURE THE CAPACITY OF CRANE IN ADVANCE.
11. WORK HAS TO BE EXECUTEDUNDER SUPERVISIONOF AN EXPERIENCEDAND COMPETENT 10. DURING THE EXECUTION OF WORK, THE MATERIAL/EQUIPMENTS SUCH AS RELEASED MATERIAL ETC,. SHOULD NOT BE
600
8 2.667
1000 9 3.000 CONTRACTORS/RAILWAY ENGINEER. INFRINGING THE TRAIN TRAFFIC.
GROUND LEVEL 12. ADHERENCE OF PROVISIONSOF SOD TO BE ENSUREDANDVISIBILITYOF SIGNALTO BE CHECKED
0
10 3.333 11. NO CONSTRUCTION JOINTS SHALL BE NORMALLY ALLOWED IN CONCRETE WORKS WITHOUT SPECIAL
0
(SHUNTING LINE)
21. ROUGH STONE FLOORING 300MM THICK GROUTED WITH CM:1:3.
OF EXG. TRACK
22. WEEP HOLES : WEEP HOLES TO BE PROVIDED AS PARA 7.6 OF SUB STRUCTURE CODE & WEEP HOLES SHALL BE OF 75/100
DIA PVC/AC PIPES STAGGERED AT 1000 C/C ABOVE LOW WATER LEVEL IN BOTH WING WALL/RETURN WALL & EARTH
DEPTH SOIL STRATA DESCRIPTION N SBC SPECIFICATIONS: RETAINER OF BOX.
LEGEND 23. INSTRUCTIONS CONVEYED VIDE PCE CIRCULAR No.01/2015 DATED 09.03.2015. TO BE FOLLOWED.
T/Sqm
3425
3425
(m) VALUES ALL WORKS ARE TO BE CARRIED OUT AS PER THE FOLLOWING (LATEST REVISIONS TO BE REFERRED) 24. ALL THE PRECAUTIONARY MEASURES TO BE TAKEN BEFORE EXECUTING THE WORK.
1. INDIAN RAILWAY UNIFIED STANDARD SPECIFICATIONS FOR WORKS AND MATERIALS 2021. 25. LAY THE BACK FILL MATERIAL BEHIND RCC BOX AS PER PARA 7.5 OF IRS BRIDGE STRUCTURE & FOUNDATION CODE FOR
2. IRS CONCRETE BRIDGE CODE 2004 EARTH RETAINING STRUCTURE.
3. IRS BRIDGE SUB-STRUCTURE & FOUNDATION CODE.
4. IRS BRIDGE RULES. 26. DURING EXECUTION OF WORK , MEASURES ADVISED BY CCRS/LUCKNOW VIDE LETTER NO.
OF EXG. TRACK 5. IR BRIDGE MANUAL M.15013/01/2017-18-T.N. DATED 27.042018 & COMMUNICATED BY CRS/SBC VIDE LETTER NO.
0.5 6. IS 456-2000, IS 1786-2008 & RELEVANT IS SPECIFICATIONS. Q.2201/1/2013-14 SWR, DATED 09.05.2018 SHALL BE ADOPTED.
(SHUNTING LINE) 27. IN ADDITION TO STEEL SHEET STRIPS (AS GIVEN IN CCRS LETTER ) CONCRETE CANVAS OF 500mm WIDE & 5mm/8mm
REFERENCE : THICK TO BE PROVIDED.
FILLED UP SOIL
1. RCC BOX AS PER RDSO/B-10155 28. THE RCC BOXES SHALL BE PLACED OVER PRE-CAST BASE SLABS IN SUCH A MANNER THAT THE BOX SEGMENTS ARE
1.0 2. RETURN WALL DRG NO. SWR/CN/BNC/ST/217-07 (Sheet 02 of 02). STAGGERED WITH THE JOINT OF SLABS. GAP BETWEEN THE BOX SEGMENTS ARE TO BE SEALED BY PRESSURIZED CEMENT
3. WEEP HOLES AS PER PARA 7.6 OF SUB-STRUCTURE CODE. GROUTING FOLLOW BY EPOXY POINTING.
5320
13 15 6. BACKFILL MATERIAL BEHIND RCC BOX TO PROVIDE AS PER PARA 7.5 OF IRS BRIDGE SUBSTRUCTURE & INSTRUCTIONS CONVEYED VIDE PCE CIRCULAR NO: 01 / 2015 DT:09-03-15, REGARDING 'WORK DISCIPLINE AT SITE'
30. THE
1.5 FOUNDATION CODE. AND AS PER PCE CIRCULAR NO 01/2021 DATED: 22.06.2021 REGARDING 'ENSURING QUALITY OF WORK AND
MODUS OPERANDI : MAINTAINING SITE RECORDS IN WORKS CONTRACTS TO BE STRICTLY FOLLOWED.
FDN LEVEL : GRADE OF CONCRETE
745.265 PRELIMINARY
2.0 1. INSTALL THE TEMPORARY ENGINEERING INDICATORS AT THE APPROACHES OF BRIDGE AND IMPOSE NON No. GRADE
DESCRIPTION OF COMPONENTS SIZE OF AGG.
BROWNISH SILTY SAND WITH PRESENCE OF STOP SPEED RESTRICTION OF 20 KMPH.
OF EXG. TRACK GRAVELS STAGE I : BETWEEN TRAIN TIMINGS i. RCC BOX M30 20MM
1. IMPOSE SPEED RESTRICTION IF NECESSARY BEFORE THE EXCAVATION WORK.
(DOWN MAIN LINE) 2. DIVERT OR RESTRICT THE WATER FLOW BY PROVIDING BUND ON UPSTREAM SIDE OF THE BRIDGE. ii. WEARING COURSE M25 20MM
2.5
3. EXCAVATE THE EARTH TO BE DONE FOR PROPOSED BARREL LENGTH. iii. LEVELLING COURSE M20
2.7 >50 4. DISMANTLE THE ABUTMENTS, RETURNS IF IT IS REQUIRED WITH THE HELP OF BREAKERS. 20MM
WHITE GREY COMPLETELY WEATHERED ROCK 5. EXCAVATE THE REMAINING EARTH TO REQUIRED DEPTH FOR BOX PORTION. iv. EARTH RETAINER/RETURN
2.9 M25 20MM
6. LEVEL THE GROUND SURFACE, AND CONSTRUCT RCC BOX AS PER GAD, DULY PROVIDING
CLEAN JOINT BETWEEN EXISTING AND PROPOSED BRIDGE. v. CURTAIN WALL M20 20MM
BORE LOG DETAILS 7. DULY PROVIDING DOWEL BARS AT CLEAN JOINT BETWEEN THE PROPOSED AND EXISTING BOX
PORTION AND FILL WITH CONCRETE OF REQUIRE GRADE.
12. FILL THE EARTH AND MAKE THE FORMATION GOOD AS REQUIRED DULY COMPACTING THE SOIL. CERTIFIEDTHATTHE PRORCCBOXBRIDGEAS PER RDSO/B-10155 TO BE CONSTRUCTED
IS OF SUCH
10. COMPLETE THE WORK IN ALL RESPECT SUCH AS CONSTRUCTION OF WING, RETURN, PARAPET DESIGN,DIMENSIONS AND CONSTRUCTIONS AS WILL ENABLEIT TO CARRYTHE DEAD LOAD OF THE
7270
7270
2000
PRO.BRIDGE:25T-AXLE LOAD 2008 STANDARD
500
1650
PRO.DEPTH OF CONSTRUCTION
FOR 1 x 1.22 x 1.35 m RCC BOX
C/S OF CURTAIN WALL
9480
9480
RAIL 60 kg : 172 mm
TRACK DETAILS (PRO.BRIDGE)
GR PAD : 10 mm
LOADING : 25 T-AXLE LOAD :
PSC SLEEPER 230 mm
OF EXG. TRACK
(HAS LINE)
2008-STD
SECTION ON - AA
ALIGNMENT : STRAIGHT BALLAST CUSHION : 350 mm
GRADE : R 1 IN 100 : 6479 mm
EARTH CUSHION
RAIL LEVEL : 755.856m
BOX THICKNESS : 350 mm
FORMATION LEVEL: 755.094 m
BOX CLEAR HEIGHT : 2350 mm
OF EXG. TRACK BOX CLEAR HEIGHT : 9941 mm
(HAS LINE)
EXG.DEPTH OF CONSTRUCTION
FOR 1 x 1.2m PIPE
600
TRACK DETAILS (EXG.BRIDGE)
RAIL TO FORMATION : 670 mm
LOADING : BGML-1926
ALIGNMENT : STRAIGHT EARTH CUSHION : 7484 mm
OF PRO. TRACK ( CONNECTING
PRO. PIT LINE 2)
11530
1800
4470
24641
(SHUNTING LINE)
OF PRO. TRACK
2350
5460
5460
350
350
150
150
150
B RAMASUBBAIAH DIGITALLY SIGNED BY B RAMASUBBAIAH
DYCPM-ENGG-GSU-MYS
DATE:2023.02.11 13:45:48 -08'00'
STATION: MYSURU PROJECT ID: 14.03.16.18.1.55.001
500
500
1600
500
CPM-GSU-MYS
VISHNU BHUSHAN DATE:2023.04.04 10:37:45 -07'00' PROJECT NAME
2000
STATION AND TERMINAL AT NAGANAHALLI
450
1650 5066
5366
450 716
1166
DEN-W-MYS
600
STEPS 762
PRO. FORMATION LEVEL : 755.094
8000
SrDEN/Co-ord/MYS
GENERAL ARRANGEMENT DRAWING
1800
1800
DRM/MYS
8900
900
NAME OF WORK: BR. No. 301 @ KM. 0/8-9 OF EXG. SPAN
DIRECTION OF
150
AXEN/BRIDGE/HQ
RCC BOX
U/S
HALF PLAN AT TOP HALF SECTION AT BOTTOM SCALE - 1:100 DRG.NO: GSU/MYS/BR/2023/GAD/Extn. of Br. No. 301
DYCE/BRIDGE/HQ
Signature Not
Verified
Digitally signed by B
RAMASUBBAIAH
Date: 2023.04.17
16:21:45 IST
Reason: IREPS-CRIS
Location: New Delhi