0% found this document useful (0 votes)
70 views3 pages

10k Nap-Wir - Frm-001 Rev02

The document is a Work Inspection Request Form requesting inspection of construction works at the 10K Construction Village CV1-2. It provides details of planned inspections for civil, mechanical, and electrical works according to the Inspection and Testing Plan. Upon completion of the inspections, the form will be signed off by the client and project monitors to confirm compliance with specifications.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
70 views3 pages

10k Nap-Wir - Frm-001 Rev02

The document is a Work Inspection Request Form requesting inspection of construction works at the 10K Construction Village CV1-2. It provides details of planned inspections for civil, mechanical, and electrical works according to the Inspection and Testing Plan. Upon completion of the inspections, the form will be signed off by the client and project monitors to confirm compliance with specifications.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Classification | Internal

Work Inspection Request Form (WIR)


10K CONSTRUCTION VILLAGE CV1-2
WIR Ref# 10K-4800000622-NAP-MEC-WIR-000001 Revision # 01

DETAILS OF INSPECTION BY CONSTRUCTION TEAM SECTION A


ALL INSPECTIONS SHOULD BE SUBMITTED TO THE QAQC Min. 24 Hrs AHEAD OF THE PLANNED INSPECTION TIME
Civil EarthWorks
Structural Inspection & Testing Plan Reference ITP:
Civil works (infra) Description Of Works to be Inspected: "Description as stated in ITP"
Roads
Arch & Finishing Works
Test Reports

Mech Fire Fighting


Plumbing Works Location of Inspectio:
HVAC Works
Welding Drawings Nos.:
Coating/Painting (Industrial)
Piping Works (Industrial) Submission Date:
NDT Inspection Date:
Inspection Time:
Elec HCU
LCU Submitted by (Site Engineer):
Instrumentation/BMS
Specify:.
Signature

CONFIRMATION OF NESMA & PARTNERS QA/QC INSPECTION SECTION B


Confirmation of coordination and compliance with specifications, approved drawings & Method Statement

Approved Approved with Comments Rejected Canceled


(Reason)

NOTE: Non Conformity &/or reference to attached Non conformity Report (NCR) NCR#

QA/QC Engr. Name:


Inspection Date: QA/QC Engr. Signatur

Note: All inspection status shall be updated on the system along with the reason of rejection (If any) within 24 hrs of the inspection date.
CLIENT FOR RECORD SECTION C

Reviewed by DBFOM Co. Reviewed by Project Monitor

Name       Date Name       Date

Signature Signature

EPM (Optional) Neom (Optional)

Name       Date Name       Date

Signature Signature

NAP/WIR/FRM/001 Rev02
Classification | Internal

Guidline

Civil EarthWorks All earth works such as( cleaning , surveying ,excavation, backfilling,compaction "FD
Structural All works related to structural and super structures such as ( surveying,formwork,ste
Civil works (infra) Surface preparation of concrete surface, bituminous coating,CMU,Plastering, demo
works....etc.
Roads Sampling and FDT tests of (Subgrade,subbase,base course), - Asphalt works (Prime c
Arch & Finishing Works (Painting, closing ceiling,doors,ceramic tiles, porcelain
Test Report All deliverables that will be submitted in regular basis Weekly/Monthly for record)

Mech
Fire Fighting
Plumbing Works
HVAC Works
Welding
Coating/Painting (Industrial)
Piping Works (Industrial)
NDT

Elec
HCU Grounding, Lighting, power outlet, cable pooling, SMDB, DB, MCC pa
installation, continuity test for cables, insulation resistance test cable

LCU fire Alarm System, Telecom & data, CCTV camera, public address, ac
cables, termination,testing

Instrumentation/BMS instrument cabinet/panel DDC panel, HVAC panel, etc. instrument d


pressure gauge, sensor, etc. installation, continuity test for cables, a

Specify:.

Classification | Internal
Classification | Internal

tion, backfilling,compaction "FDT",soil sampling, box culverts,...etc) expet subbase& base course of Roads.
such as ( surveying,formwork,steel works,concrete pouring,shutter removal, curing, curching,test..etc)
s coating,CMU,Plastering, demolishing, installation of partitions, Gypsum board, C.B.,suspension system of ceiling

course), - Asphalt works (Prime coat MC-1- Asphalt layers - Take coat RC-2, all asphalt tests......etc)

is Weekly/Monthly for record)

ooling, SMDB, DB, MCC panel Switchgear panel,


lation resistance test cables, panel, termination, testing

camera, public address, access control, installation, continuity test for

C panel, etc. instrument devices, like pressure,temperature, level, flow transmitter


ontinuity test for cables, and calibration of the instrument if required.