Module 8 (Lecture 23)
Module 8 (Lecture 23)
Chemical Transformation
FUNCTIONAL ELEMENTS OF MSWM
Primary collection
Secondary
collection
Lecture 23
Waste-to-Energy (WtE) plants (Case studies)
Pyrolysis and Gasification
WHY INDIA’S FIRST WASTE INCINERATION PLANT FAILED ???
In 1987, the Ministry of Non-Conventional Energy Sources (MNES) commissioned the TIMARPUR REFUSE
INCINERATION-CUM POWER GENERATION STATION at a capital cost of Rs. 20 crores which was
imported from Volund Miljotecknik Ltd. of Denmark.
The plant was designed to incinerate 300 tons of municipal solid waste (MSW) per day to generate 3.75 MW of
electricity.
The plant was shut down after 21 days trial operation due to the poor quality of incoming waste.
The calorific value of the supplied waste was in the range of 600-700 kcal/kg while it required waste with net
calorific value of 1462.5 kcal/kg.
The Ministry incurred an expenditure of Rs 1.25 crore on maintenance and insurance of the plant.
Spread over 100 acres of land, the Rs. 458 crore has
been developed on PPP model by Ramky Group, a
Hyderabad-based waste management company, in
collaboration with the North Corporation.
Total unsegregated waste handling at Okhla was increased to 2000 TPD against approved 1200-1525 TPD.
Single boiler of 750 MT/day was comissioned but three boilers were installed (1500 MT/day)
MSW was handled at only one location instead of two (other one in Timarpur) which resulted in larger
collection/transportation/segregation of MSW than that was permitted. So, higher RDF was processed with
higher emissions.
Where waste with a calorific value of at least 1600 kcal/kg is required for efficient burning, the Okhla plant
had been burning wet waste along with other unsegregated waste (Wet waste has a lower calorific value of
about 1300 kcal/kg).
Above all, the Okhla plant operated in the middle of a densely populated area.
The Union Ministry of Environment and Forest (MoEF) has allowed the
Okhla WtE plant to increase its power from 16 MW to 23 MW by
amending the environmental clearance the plant had received in the year
2007, without increasing the MSW intake and without installing any
additional equipment.
i. Counter-current
ii. Co-current
Cylinder shaped reactors mounted vertically and waste is fed from top of
the reactor and the solid outputs collected from the bottom.
The gasification agent is supplied from the bottom and the off-gases are
collected at the top, the gases thereby flowing in an updraft manner.
The gasification agent and the waste flow co-currently towards the
bottom of the gasifier.
Advantages
Disadvantage
Advantages
Disadvantage
Less need for flue gas cleaning: smaller volumes of flue gas with a better quality.
Gasification units operating with a low fuel load, potentially facilitating small plants producing less than 1 MW.
PROCESS PARAMETERS
A long range of parameters may influence the pyrolysis and gasification processes-
Reactor design
Waste composition
Waste pretreatment
Process temperatures
Heating
Residence times
Pressure
TECHNOLOGY
Long range of pyrolysis and gasification technologies exists.
From a waste point of view two main aspects differentiate the technologies:
Energy recovery: focus on generating a syngas suitable for utilization in a gas motor, gas turbine to produce
electricity or combustion in a boiler to generate heat.
Material recovery: focus on producing a stable solid residue for use in construction works or using the
syngas as chemical feedstock.
The pyrolysis processes typically take place in the first reactor while the gasification processes occur in the
second reactor after introduction of a gasification agent.
The pyrolysis/gasification process may also be combined with combustion, either in a separate combustion
chamber or integrated in the last part of a second stage.
CHALLENGES OF UTILIZING PYROLYSIS AND GASIFICATION IN THE INDIAN CONTEXT
Requires specific feedstock quality, which has a direct impact on the efficiency
and commercial viability of the product.
Specific size and consistency of solid waste should be achieved before MSW can
be used as feed.
Ganganagar, Rajasthan, India- A case study of WtE plant (Gasification)
Kalpataru Power Transmission Ltd (KPTL) set up a Biomass plant at Padampur in the Ganganagar
district of Rajasthan in the year 2003.
This plant uses agricultural waste and crop residues (biomass) as inputs and generates 7.8 MW of
power.
Gold Standard is the only premium quality standard for carbon emission reduction projects with added
sustainable development benefits and guaranteed environmental integrity.
The Gold Standard label distinguishes projects and emissions under the Clean Development Mechanism,
joint implementation, and voluntary offset markets.
Source: https://kalpatarupower.com/biomass-plants/
Pune, India- A case study of WtE plant (Gasification)
Pune Municipal Corporation (PMC) takes care of 50% of the city’s waste in alliance with Concord Blue
Technology Private Ltd.
The tipping fee for the tech solution providers = Rs. 300 per tonne.
The cost of the plant was 14-15 crore/ MW with the generated cost of electricity coming to Rs. 13/ kWh.
This is offset by actual price paid by the electricity board, the tipping fee involved and other incentives.
Generates energy through gas / power, and fertilizer ensuring waste is utilized thoroughly.
Economical implementation.
Financially viable.
Thank you