Assignment 2 2023
Assignment 2 2023
2. Design the formwork for a concrete slab 6 in. thick. Sheathing will be 1-in. (nominal thickness) lumber, with
0.75” effective thickness and the following allowable stresses: Fb = 1075 psi; Fv = 174 psi; and E =
1,360,000. Joists are 2 x 8 in. and Stringers are 4 x 8 in. lumber. Assume that all members are continuous
over three or more spans. Commercial 4000-lb shores will be used. The weight of the formwork is 5 lb/sqft
and live load is 50 lb/sqft. Allowable stresses for the joists and stringers are: Fb = 1250 psi; Fv = 180 psi;
Fc⊥ = 405 psi; FcII = 850 psi; and E = 1,400,000. If joists are spaced at 2 feet, stringers at 8 feet span, and
shores at 5 feet spacing, check the safety of this design and suggest any changes. Also, check the bearing
of the joist on the stringer. Deflection must not exceed l/360.
3. The brickwork on the front face and one side of a house has the dimensions illustrated in the following
drawing. Perform quantity take off and duration estimation using three types of bricks: Standard, King, and
Jumbo. The bricklaying crew would be four brick masons and two laborers. The average production rates
and the brick quantities per square foot of wall surface area (includes factor for waste) are shown the
following table. Ignore the openings in the walls.
LENGTH = 59’
B SS = 2 D G
(4) (5) (2)
A J L
(2) (7) (2)
C E H
(3) (4) (4)
F FS = 3 K
(8) (4)
5. The cross section of a highway under construction is shown below. You are involved with the earth-
moving subcontractor engaged in the following activities:
1.8 m 12 m 0.9 m 1.5 m
Subbase
Base=
a) Investigate and list possible methods to do the common-earth Excavation using the optional wheel-
mounted front-end loader capacities in the attached RS Means tables. What choice would you make?
b) Determine the crew type, duration, and cost of the activities above (each highway section is 300m).
6. You are to develop a plan for building your own dream bungalow home of one floor and a finished basement, using
the activities shown in the figure below:
a. Check several web resources on house construction, including the video on Learn;
b. Divide the activities into two categories: substructure; and superstructure. List important construction
precautions that should be followed to ensure quality in each category (10 each). Provide references;
c. Create a table with a list of the activities involved in each category. Identify the relationships among the
activities and draw an AON for the construction plan.
Ref: RS Means Square Foot Costs
7.
a. Why is a WBS needed?
A To suit our CPM needs. e. This relationship means:
B To facilitate work packaging and estimating.
C To perform forward pass calculations.
D To draw the Bar Chart.
A The start of B is after the start of A by 3 days.
B B is a successor to A.
b. What do the categories in the MasterFormat represent? C Lag time of B is 3 days.
A 16 categories of possible building tasks. D All of the above.
B All WBS tasks of a project linked to the OBS.
C 4 categories: FS, SS, SF, and FF
f. Select the TRUE statements:
c. Critical activity is one that: A Delaying a non-critical activity decreases its total float
A Lies on the longest path in the network B CPM takes into account project deadline
B Has negative total float C Slow construction methods are less costly than fast ones
C Has positive total float
Duration
k. An activity has an (ES) of 4, a (LF) of 19, and duration of
10 days. The activity: o. Select the TRUE statements:
A Is on the critical path A Parametric estimating is suitable for the design stage
B Is progressing well B Elemental estimating offers highest accuracy
C Can be delayed 5 days without affecting project duration C Detailed estimates are not needed for the bidding stage
D Has a total float of 10 days