SWMS Power Float
SWMS Power Float
Where an exclusion zone is required, the SWMS must clearly state the detail of the required exclusion zone,
including the person responsible for implementation and supervision.
Work Location (Attach Site Plan): Refer Attachments Duration: From 30/6/2017 (Date) to 30/12/2017 (Date)
Remarks:
- Nil
2 Yes No
3 Yes No
4 Yes No
5 Yes No
6 Yes No
7 Yes No
8 Yes No
10
Designation: Safety and Health Officer Date: …30……. /……6…. /……17…. Designation: Project Manager Date: …30……. /……6…. /……17….
Applicable Environment, Safety & Health (ES&H)
Risk Assessment Team Approved Code of Practice (COP) and/or CSR
Legislation
Name Designation Signature
A HIGH risk requires immediate action to control the hazard as detailed in the
HIGH RISK
15- 25 hierarchy of control. Actions taken must be documented on the risk assessment form
(H)
including date for completion.
A MEDIUM risk requires a planned approach to controlling the hazard and applies
MEDIUM RISK
5 – 12 temporary measure if required. Actions taken must be documented on the risk
(M)
assessment form including date for completion.
A risk identified as LOW may be considered as acceptable and further reduction may
LOW RISK
1–4 not be necessary. However, if the risk can be resolved quickly and efficiently, control
(L)
measures should be implemented and recorded.
The result of the hazard identification and risk assessment exercise shall be documented.
Table 2:
Severity (S)
Negligible Minor Serious Fatal Catastrophic
(1) (2) (3) (4) (5)
Probability (P)
Risk Assessment can be calculated Most likely using the following formula:
5 10 15 20 25
(5)
P x S = Relative Risk; Where P is Possible Probability and S is Severity
4 8 12 16 20
(4)
Conceivable
3 6 9 12 15
(3)
Remote
2 4 6 8 10
(2)
Inconceivable
1 2 3 4 5
(1)
NO Job Steps Hazard Risk Risk Control / Control Measures L I Risk Accountable Person
Rating
1 Delivery of Material and Equipment to Site Contact between Severe injury to - PPE must be worn at all time.
personnel and personnel due to - Safety Toolbox Briefing must be conducted beforehand.
moving vehicles impact from moving - Signal man/ Traffic man must be presented at the entrance to 1 4 4
vehicle guide the transportation flow (when transporter moving in/out). Supervisor/ Traffic Man
- Traffic must be controlled by experienced signal man/traffic
man.
Contact between Damage to property of - Entrance pathway to site must not be obstructed.
moving vehicle and relevant party - Proper Signage must be installed at the visible area.
permanent - Safety Toolbox Briefing must be brief to signal man/traffic man
structure/ portable beforehand.
equipment - Signal man/ Traffic man must be presented at the entrance to 1 3 3 Supervisor/ Traffic Man
guide the transportation flow (When transporter moving in/out).
- Traffic must be controlled by experienced signal man/traffic
man.
2 Unloading of materials / Shifting of Falling object on Moderate to severe - Avoid overhead lifting.
materials site personnel injury to personnel due - Constant communication between signal man and crane
to impact from heavy operator.
object/ load - Lifting object/ load shall be guided via double tag lines.
- Lifting operation area shall be barricaded from unauthorized
personnel.
- Lifting operation shall be carried out with competent lifting team
members only. 2 3 6 Lifting Supervisor
- Lifting operation shall be under supervision from lifting
supervisor at all time.
- PPE must be worn at all time.
- Safety Toolbox briefing must be conducted beforehand.
- Safety pre-check on lifting equipment prior lifting operation.
- Unloading/ Loading platform shall be maintained in good shape,
rigid and stable.
Tripping of Damage to property of - Avoid overload lifting. 2 3 6 Lifting Supervisor/ Crane
Machinery/ Crane relevant party - Constant communication between signal man and crane Operator
operator.
Moderate to severe - Crane operate platform shall be properly formed, ensure its
injury to personnel due rigid, and firm.
to impact from - Lifting crane shall be operated by experienced operator.
collapsing machinery - Lifting operation shall be barricaded from unauthorized
3 Floor Hardener Application Orally entering Stomach poisoning - PPE must be worn at all time.
body due to orally entering - Safety Toolbox briefing must be conducted beforehand.
body - Working area shall be barricaded from unauthorized site
Direct contact with personnel.
skin and eyes Skin disease due to - Extra PPE such as face mask
contact with anti - Floor hardener must only be handled by appointed worker 1 3 3 Supervisor / Supplier
termite - Avoid applying under strong wind
- Floor hardener must kept out of any un authorised reach
Major injury to eyes if - Floor hardener spills must be treated as schedule waste
contact with anti
termite
4 Power Floating Electrical shock Minor / Major injury - PPE must be worn at all time.
due to electric shock - Safety Toolbox briefing must be conducted beforehand.
Trip and fall - Working area shall be barricaded from unauthorized site
Trip and fall due to personnel.
Equipment long cable - PPE must be worn at all time
vibration - Trowel must only be handled by appointed worker 1 3 3 Supervisor
Hand numbness due - Check equipment and cable for worn and tear before use
to vibration - Use only industrial cable and plug for supply
- Keep cable organized at all time during usage
- Avoid working long hours / Worker needs to take rest every ½
hour when using trowel
- Delivery of Material and Equipment to Site - Designated traffic man shall be aware upon arrival of transporter.
- Upon arrival of transporter, the traffic man shall control the traffic flow, to ensure the
vehicle movement can be diverted or controlled. Visible orange vest,
- Traffic man shall equipped with proper PPE which include the following:- Traffic
Whistle, Red/ Green
Controller
A visible vest Flag
A whistle
A pair of red/ green flag – indicator to stop/ move the vehicle flow
- Unloading of materials / Shifting of materials - Heavy load/ object shall have PE endorsed on the particular lifting points/ design.
- Lifting load/ object shall be guided and directed by double tag lines system.
- Lifting load/ object shall be lift and hooked at designed lifting points only.
- Lifting operation shall be under supervision of experienced lifting supervisor only.
- Lifting supervisor and riggers shall pre-check the lifting equipment, to ensure the lifting
equipment are in good condition, free from defects.
- Overhead lifting is strictly prohibited.
Lifting
- Prior unloading/ loading, the crane operator shall pre-inspect the working platform of the Lifting
Supervisor
designated area, to ensure the area is safe, firm and rigid to perform the lifting
operation.
- Signal man shall constantly communicate with crane operator, to guide, to lead the
movement of lifting object/ load.
- The lifting team shall ensure the working area is barricaded and prevent from
unauthorized personnel.
- The unloading/ loading platform shall be in good shape, barricaded, and rigid to use.
- Floor Hardener Application (60%) - The concrete shall be ready for floor hardener application when the foot imprint on the
concrete surface doesn’t exceed 5mm depth
- The floor hardener that will be used is SIKAFLOOR – 3 QUARTZTOP
Face mask, long Supervisor /
- The floor hardener shall come in packets that can be carried around by man power
sleeves clothing Supplier
- The first 60% of the floor hardener shall be applied equally around the floor using scoop
to scope it out from the bags and spread around manually
- The floor hardener is of powder form
Enter SWMS No and Version here Page 8 of 10
- Power Floating - Next power floating activity shall be conducted
- One worker shall compact the surface using a trowel until the surface is fully compacted
linearly Supervisor
- Floor Hardener Application (remaining 40%) - The concrete surface then shall be applied with floor hardener powder again
- The floor hardener that will be used is SIKAFLOOR – 3 QUARTZTOP
Face mask, long Supervisor /
- The floor hardener shall come in packets that can be carried around by man power
sleeves clothing Supplier
- The floor hardener shall be applied equally around the floor using scoop to scope it out
from the bags and spread around manually
- Power Floating - Next power floating activity shall be conducted again
- One worker shall compact the surface using a trowel until the surface is fully compacted Supervisor
linearly
- Curing - After the floor surface is fully power floated, it shall be protected with a layer of curing
Face mask, long
compound Supervisor
sleeves clothing
- Curing compound shall be applied with brush to all over the floor area equally
Section 3: Verification
I have provided, accurate and sufficient information and instructions pertaining to this Safe Work Method Statement - the aspects / hazards associated with each work process and activity, the type of potential impact,
incident or accident, and the risk controls / practicable measures to be taken in the course of work and during an emergency - to ensure its / their safe undertaking.
Instructed by (print name): …………………………………………………………………….. Signed: ………………………………………….. Date: …..../…...../……… Time: .............. am / pm