We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF or read online on Scribd
You are on page 1/ 34
Page 3
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No. 51,2203
18.2400
PROVINCIAL ELECTRICITY AUTHORITY November 26, 1997
2.0 CHECKLIST FOR EQUIPMENT DOCUMENTS
Cheektlist for 115kV GIS
3 Phase or 1 phase bus
Bus ground switches
Ground switches around BKR disconnects
Incoming ground switch +
BKR removal space
Expansion at one end possible
Fic in the building space
Roof clearance OK
Crane access OK
Line & Transformer PT's
Bus PT's
Where are ground switches in relation to breakers
Air -SF6 bushings
Oil-SF6 bushings
Legend on one line
115 kV cable access , TRF access
Getting equipment in & out of the building
Provide holes in the floor for future HV & LV cables so we don’t have
to cut later
Eacthing bus continuous
Bonding of enclosures and treatment of enclosure currents
Pressure relief device for each compartment
Bypass function operate in local mode only?
File number correct (letter)
Co-ordination with civil drawing
Co-ordination with cable tray layout drawing
Does equipment agree with what was quoted in the contract: Page 4
=
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No. 51.2204
18.2400
PROVINCIAL ELECTRICITY AUTHORITY | November 26, 1997
2.2 Checklist for Disconnect and Grounding Switches
WON ANEUNS
10.
is
13,
4
15,
16.
7.
18.
19
20,
24.
2
24
25,
26.
27
28.
23.
29.
Voltage correct
Continuous current correct
Momentary current
Phase spacing correct
Height correct
Mechanism handle correct height
Motor operator / manual interlock
Ground platforms a
Insulator rating, cantilever & colour
Mechanism correct size
Ground blade no interference of clearance problem
Auxiliary switches correct
‘Anti condensation heater for mechanism & aux. sw.
Ground braids on pipes
Mechanism control voltage right
Stop push button
Local remote switch
Ground switch mechanical interlock
Ground switch electrical interlock
Galvanized parts
Mechanism enclosure paint,
Padlock provisions
Quantities correct
Conduit entrances indicated
Mechanism ground connector
Operations counter
Fuses & knife switches in motor operator
Does equipment agree with what was quoted in the contract
File number correct (leite:
foe
Aes
G8 2 dite
shes
eePage 5 :
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No. 51.2207
18.2400
PROVINCIAL ELECTRICITY AUTHORITY Noveinber 26, 1997
2.3 Check fist tor CVT
1. Quantities right 7
2.500 kV BIL
3. Capacitance (6000 Pf) 4
4. VA of winding, combination cs
3. LV MCB with alarm
6. Ground pad
7. Top pad, mech. loading
8. Porcelain Colour brown .
9. Rated voltage factor IEC (1.5 UN 305) :
| 10. IEC accuracy classes ate
| Ul, 30 Hz 4
12. Voltage rations *
13. Max, voltage 123/1.732 e
14, Drawings right-nameplate-diag-outline
15, Potential ground switch
16. Harmonic suppression filter :
17, Reactor (series) -
18. Protective gap
19. Weight given
20. Conduit interface
21. Does equipment agree with what was quoted in thé contract
22, File number correct (letter)
$8 Ent,
&
nate Fea RE Sater:
PREG |Page 6
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No. 51.2201
18.2400
PROVINCIAL ELECTRICITY AUTHORITY November 26, 1997
Checklist for Insulator
ANSLTR, No. correct (286&202)
Brown porcelain.
Creepage distance 25 XL-L (3050 mm).
Cantilever right.
Bolt circles right.
BIL 530 kV, 95 kV.
Strain insulator M&cE Strength & ANSI class.
How many discs for BIL and Creepage distance.
Strain insulators brown glaze.
Does equipment agree with what was quoted in the contract.
File number correct (letter).
=s
%
ete Le bene Genie aes tee ee ey
wed +
Bor
Dena &
aes Gop:|
Pag 7
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No. 51.20
13.244
PROVINCIAL ELECTRICITY AUTHORITY Novemnber 26, 19h
2.5 Check list for 22 kV Switchgear
u
12
13,
14
6.
16.
7
18.
19.
20.
21.
2.
23.
24.
25
26.
27.
28.
29.
30.
3
32,
33.
34.
35
36
Ratings correct, incoming, tie, outgoing, current, BIL, interrupting,
interrupting ratings of LBS and. tuses
CT ratios and quantities, cores correct, incoming, tie, outgoing, whé
actual taps used
Bus and all compartments isolated by barriers
Equipment agree with one line
Pressure relief device shown & in safe place
Phasing right F-B, L-R, B-T
Is paint correct,
Protection class IP 4X
Expandable both ends
Breaker truck & ES operated without opening door
Copper earthing bus
Steel thicknesses,
Interior light in LV compartment
Height of operating devices , switches etc
Lockabie doors.
Window viewing
Shutters and shutter interlocks,
‘Anti condensation heaters
Plug in for auxiliary connections
Track/Rack position indicator
Type of breaker , SF6 , vacuum
Mechanism type ~
Operating sequence 0-3s-CO-3 min-CO or 0-3s-CO-15s-CO
Interrupting time
125 VDC supply
Manual spring charging mechanism
Spare auxiliary switches
Fault making earthing switches,
Bus insulation , bus material
Cable sealing ends provided
Cast resin inst. TRFS ratings
AIL CT. ratings , accuracy classes correct , measuring & protection
Recording instruments chart type with cassettes and RS 232 interface
WhM class 2 switchboard type
Floor seailing after cables pulled
Are detection system in all compartments or bus only
cer) 4
a0 =a
UE Rites
ey
ors
by psten.i
Pag 8
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No. 51.201
13.20 |
PROVINCIAL ELECTRICITY AUTHORITY Noveinber 26, 197
37.
38
39.
40.
4.
42.
43.
44.
45,
46.
47.
48.
49.
50.
Sl
Check list for 22 kV Switchgear (Con't)
All breaker accessories provided on, off PB's , OP. counter
Earth switch mechanically interlocked
Detail of cable sealing ends given
Power cable support bracke's
Cable size right , incoming 2 x 500 sq.mm. CU, feeders Ix 240
sq.mm. or 1x 400 sq.mm.
BiL-ground 125 kV , across isolating gap 145 kV
Fuse sizes for station service TRF (FLC = I.131 A) & VT
Mimic diagram
Does LBS open when one fuse blows
Close & latch capability of LBS
Bus voltmeters provided
Is the phasing of the entrance & exits clear (ABC L-R)
Interface switches with Remote control desk and CSCS
File number correct (letter)
Does equipment agree with what was quoted in the contract.
ees
eee stele neem ye
Fenwee «
5 Raniegate tak
deePage 9
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No. 51.2213
182400
PROVINCIAL ELECTRICITY AUTHORITY
November 26, 1997
Checklist for 22 kVCapacitor Bank
Stages right-three ?
Rating of stages
Number of series groups
Parallel units /group
Wye-Wye ungrounded
Cap cating correct
Switch rating correct
CT for unbalance, rating correct, 1A or SA
Unbalance relays provide, rating current input from CT correct
VAR& stage controller
Dimensions right -space
Floor loading OK
Series reactor correct
Openings for cables
Cap fused , discharge
Capacitor unit over voltage capability
Enclosure grounding terminal
Indication which stage is on
Selector switch 2
Schematics for controi é& protection
Disconnect switch for visible break
File number correct (letter)
Clearance between reactor and capacitor bank casing is sufficient.
Co-ordination with C/B equipment layout
125 VDC or 48 VDC voltage supply
Does equipment agree with what was quoted in the contract
Any signal provide for CSCS
a at 4
ee Pea ei
ee re ees
es
++Page 10
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No. 51.2209
18.2400
PROVINCIAL ELECTRICITY AUTHORITY November 26, 1997
2.7 Checklist for 115 kV Surge Arrester
\. Duty cycle (voltage rating ) 96 kV
2. Corresponding MCOV is 76 kV
3. 10 kA voltage level spec. =374 kV typical (ABB)
4. Metal oxide
5. Station class
6. 50 Hz
7. 65 kA discharge current
8. {EC class,3 or A discharge rating
9. Venting duct
10. Dimensions (HT. 1500mm)
IL Surge counter -ground wire size
12. Insulating base
13. Brown porcelain
14, Terminal connector
15. Power losses given
16, Test requirement met
17. Quantities right
18. Pressure relief class A
19. Compare all data to design/daya values in spec/executed contract
20. Creepage
21. Energy value ki/kV
2, Filé number correct (letter)
3. Does equipment agree with what was quoted in the contract
oe be
Fn ee ERS eg
ok ae
$esePage U1
| CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No. 51.2209
18.2400,
| PROVINCIAL ELECTRICITY AUTHORITY November 26, 1997
|
|
2.8 Checklist for 22 kV Surge Arrester
Max rated voltage 20-21 kV
MCOV > 17kV
10 kA voltage level (8/20 1S current wave) spec = 76 , typical (Joslyn)
30.5
Metal oxide
Heavy duty distribution class
50 Hz
65 kA ? Discharge current (pressure reliet)
Nominal discharge current (IEC) 10 kA
Line discharge class (IEC) 3 (or 2)
Venting duct
Polymer -?- brown,
Terminal connector
Pressure relief class
Compate all data to design / data values in spec/ exeeuted contract
Creepage spec = 600 Josiy:. ZSP = 823
Energy value ( Joslyn = 6.1 KJ/KV min)
File number correct (letter).
Does equipment agree with what was quoted in the contract
to
ce ees
oH oe ete
Fete
eg
=
haPage 12
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No. 51.2211
18.2400
PROVINCIAL ELECTRICITY AUTHORITY Noversser 26, 1997
Checklist for Conduit & Duct
Is cable trench drained ?
Roads crossings correct
Control house entrance details shown - sealing of entrance
Width of cable trenches correct per contract , and sufficient
Future breakers and TRES - knockouts in handholes or trencles for
future conduits
No RGS conduit below grade
Conduit to all necessary equipment - transformer control , lights etc
Depth of conduits below grade
Handhole elevations show
Seal conduits after circuits are pulled
Sufficient manholes or handhole for pulling
Conduit to all necessary equipment
Conduit to transformers for control circuits
File number correct (letter)
8
Prey
é
i
4
i
!
i
pate:
ear
tie i3
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No. 51
18.400
PROVINCIAL ELECTRICITY AUTHORITY November 26, 1997
2.10 Checklist for Control Cable es
4
|. Twisted shielded pairs ?
7 Solid & stranded conductor ¥
3. Colour code :
4, Insulation - PVC or XLPE
5. Jacket -PVC
6. Shielded or not
7. Voltage level
8. 2.5,4, and 6 sq.mm
9. File number correct (letter)
10. Does equipment agree with what was quoted in the contract
s
4
”
2
®
:
x
4
4
i
+
dieeiePage 14
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No. 51.1601
18.2400
PROVINCIAL-ELECTRICITY AUTHORITY November26, 1997
2.1 Checklist for AC Station Service
1. Sizeof SS TRF , 50 kVA?
2. Throw over manual , interlock.
3. Loss of AC alarm.
4. INT. capacity of BKRS.
5. All loads indicated A
6. Spring charging load?
a
8.
9.
“af
Bottom entrance to DC panel , cable sealing.
Cable sizes.
Bolt on breakers.
10. Instrumentation -AMM ,VM , kWh.
LL, Test sws or facilities for kWh.
12, Phasing L-R , RYB.
13, Station service diagram required.
14, Co-ordination main feeder breakers :
15. Feeder cable sizes indicated & BKR sizing right for protection. *
16, Nameplates right.
17, Colour code right RYB & N
18. Panel paint right RAL 7036?
19. Wire sizes correct & correct in accordance with breaker frame.
20. CT and PT ratios right for kWh meter.
21. Watch out at stations with 100 kVA SSTR.
22, Scales of maters.
23. Does VM select switch the correct phases.
24. Does ammeter selecter switch the right phases and does it never permit
open CT secondary circuits.
5. File number correct (letter)
6. Does equipment agree with what was quoted in the contract
&
&
%
%
x
8
aCHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No.
Page 15
31.2209
18.2400
PROVINCIAL ELECTRICITY AUTHORITY
| November 26,- 1997
Checklist for DC Station Service
DC BKR interrupting rating
Loss of DC alarm
All loads indicated
Spring charging load?
Bottom entrance
Cables sizes right
Bolt on breakers
Instrumentation AM, VM
9. +, = Left to right or what
10, DC diagram required
UL, Feeder cable sizes indicated & BKR sizing right for jrotection
12. Co-ordination main feeder breakers
13, Nameplates right
14, Colour code right for +, -
15, Panel paint right RAL 7036
16. What is output ripple of battery charger . With battery connected or not
17. Noise level of charger
18. DC system ungrounded
19. Charger cabinet size & Floor glan, ventilated
20. File number correct (letter)
2L. Does equipment agree with what was quoted in the contract,
IMDS GR CERN ORES EE ROBIN Cee RETR tn So
TARE A okPage 16
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No. 51.1201
18.2400
PROVINCIAL ELECTRICITY AUTHOR:TY November 26, 1997
2.13 Checklist for Relay & Control Panels & B/M's
Line up agree with contracts & convention.
Construction quantities on panels correct.
Equipment quantities on panels correct.
panels for fully equipped spares included.
Can syne panel be viewed from all breaker positions.
Heights of operating switches OK.
All electrically operated devices provided with switches.
Lite iniicators/semaphores for all position.
Mimic bus
All metering included & shown.
Annunciators correct.
Relays correct.
Equipment agree with one line.
All test switches there.
Incoming/Outgoing lines correct.
Who supplies LTC panel.
Is the form (A, C etc.) of the panels OK ?
Are all the panels there ?
Will panels fit inch. ,
Anaunciator window layout & engraving.
In arrangement clear, e.g.R + C panels + 22 kV SWGR, or R panels
+ 115 kV Mimic (remote control) board + 22 kV SWGR. Annunciators
in the right place. CSCS ?
Panel colour RAL 7032 gray ?
Mimic - 115 kV orange, 22 kV blue.
File number correct (letter;
Do we have up to date schematics
Does equipment agree with what was quoted in the contract
rege ke
be ang
Siena
a
aah
degeuxes oe bayPage 17
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No, 31.1409
18,2400
PROVINCIAL ELECTRICITY AUTHORITY November 26, 1997
2.14 Check list for CCTV System
Equipment per contract manufacturer
Equipment per contract quantities
Camera quantities right
Weatherproof outdoor cameras
Camera locations per contract
Better location per the later contracts
Cabling right, power and coaxial cables
AC&DC supplies shown
Conduit to all equipment OK
Drawings checked and signed
Does layout drawings agree with the C/S dwg’s -entrances -control room
layout, etc.
File number correct (letter)
Does equipment agree with what was quoted in the contract. Page 18
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No. 51.1200
18.1400
PROVINCIAL ELECTRICITY AUTHORITY November 26, 1997]
3.0 CHECKLIST FOR ELECTRICAL DESIGN RRAWINGS
3.1 Checkiist for Single Line
SKY Single Line Di
1 Agree with contract one lines as amended 4
2. LIS KV lines correct position
3. 115 kV transformers correct position
4. Breaker & Switches correct position, numbered correct,
5. Ground switches on lines
6. Breakers and switches correct ratings
7.
8
9.
~*
; CCVT (one phase) on lines correct phase, correct rating
i CVT's on bus (3 phases) correct rating
. Surge arresters on bus, correct rating
10. Buses labelled correctly
U1, CT's correct, correct ratios, accuracy
12. One line agree with layout
13. future equipment and connections shown correctly
14. Are incoming and outgoing lines shown correctly
18, Legend to indicate ratings and manufacturers
16. Quantities of 115 kV breakers “correct, future breakers indicated
|
1
1. Correct ratings
2, LTCshown
3. Surge arresters correct.
4
5
6.
PERIL Ot eae we ah
22 KV cable rating correct
Phasors correct (vector group correct)
Supplier of transformer indicated correctly (PEA or contractor)
22.4Y Single Line Diagram
1. Agree with contract one lines as amend
2. 22kV circuits correct position and labelled correctly
3. SSTR & PT’s correct position labelled correctly, correct ratings
4. Breakers & switches correct positions & nutnber correctly
5. Ground switches on circuits and SSTR
6. Breakers & fuses correct ratings
7. — Outgoing cables cating correct
8, Surge arresters shown on circuits, correct rating
hbk bee hice ewe we pensePage 19
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No. 31.1200
18.1400,
PROVINCIAL ELECTRICITY AUTHORITY November 26, 1997
3.1 Checklist for Single Line Diagrams (Con't)
9.
10.
ul
12,
13
Buses labelled correctly
AIL CT's correct ratios and accuracy
One line agree with switchgear layout
Future equipment and connections shown correctly
Switchgear drawout points shown correctly, breakers, uses
General ‘
itle block correct drawing no., revision
All signatures on
Legends complete
Equipment list complete
CAD system indicated
Reference drawing complete
Does drawing physically agree with layout
File number correct (letter)
oe et Ga
«
FN ae
feb wakeante a,
nie
a merPage.20
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No. 51.2200
|
|
|
|
PROVINCIAL ELECTRICITY AUTHORITY
November 26, 1997
Checklist for General Plan
Latest general plan
Check PEA -any change to site location , position of substation, land
boundaries, one line (line positions)
22 kV duct correct , quant"ies & position of 22 kV poles
Are 22 kV circuits numbers identified
Operator house in right position , future house . See plumbing & paving
layout
ILS kV pole numbers (Std Nos) right
Any communication towers on any sites, Position on plan
Manhole types correct, can cable pulling radii be met
Control building shown right size
Power & control ducts into building , entrances correct
All dimensions correct
Duct & trench road crossings right
Drain pipes under road
Guuers right , periodic drainage
Main road & entrance road in right position
Legend complete & correct
North arrow shown :
Check PEA for position of 22 kV poles add 115 kV poles
Property lines correct
Fence correct
Dimensions correct
Trenches correct position., widths, & vehicle Passovers correct
Duct to 22 kV all correct
22 kY pole positions given , circuit numbers correct per PEA
115 kV bays shown correctly
115 kV Pole references to standard drawings correct
PVC drainage pipes (PVC) correct
Roadways shown correct .
Has there been any change to general plan since original contract let
File number correct (letter)
SO Same tes
A alee es
Re
oo
"
4
: bh agsPage 21
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No. 51,2200
P 18.1400
PROVINCIAL ELECTRICITY AUTHORITY November 26, 1997
33
Checklist for Bus Structure Plan & Sections
23
24
25
26.
27.
28.
29.
30.
31
32
33,
34
Agree with contract one lines as amended
Phasing correct in agreement through out
Transformer access roadway
Agree with lay-out on general plan
Dimensions correct
Centrelines of transformers and structure correct
Structures identified correctly
Lightning shielding is station shielded
Access for removal of equipment
Switch blade openings correct clearances
Pull off angles & spans for structure loading
North arrow indicated
Space for future equipment shown correctly
Reference drawings indicated and correct
Clearances to fence sufficient
Baselines indicated
Check all clearances and bus spacings
Co-ordination with T/C lay-out drawings
Co-ordination with Trench/Conduit drawings
Co-ordination with Foundation plan
Co-ordination with Ground plan
Operators for breakers and switches agree with conduit & grounding
plan
Switch operating platforms correct ?
Equipinent numbers correct and agree with one line diagrams
Bus supported adequately
Bus calculation
Taps flexible enough for -xpansion & contraction
Future equipment ( TRES ) are fittings installed for future connections
Side break switches clearance OK
SAG charts required
Turnbuckle adjustment for long spans
Elevations of roads , finished site building floors etc. flood levels
Does equipment agree with what was quoted in the contract
File number correct (letter)
0 Ran ld fade
a it ha eee
y
Pee eePage 22
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No.” 51.1200
18.1400
PROVINCIAL ELECTRICITY AUTHORITY November 26, 1997
34
Checklist for R&M One Line Diagrams
Agree with single lines
CT cores correct number & correct ratings -all
EGAT interface cores correct
Bus differential per contract one or two zones
Bus differential supervision relay
Over/under voltage relays per contract
Recorders included per contract
22 kV incoming , tie , & outgoing cores correct,
AC station service diagram per contract, two panels or one
Bus PT's per contract , relay&meter potemtials shown correctly
Line & Transformer PT's correct
Line reclosers shown 115 kV & 22 kV
Line distance relays
If 22 kV from EGAT are CT cores on incoming correct
115 kV to EGAT backup directional over current relays
BF relays shown
Arc detector current monitors shown
22 kV incoming PT's shown
Legend of all devices given
SYNC relays 115 kV shown, ‘manual syne. switch facilities shown
TRF relays complete : 87,50/51 H ,50/SIGH, 50/51L,51G on neutral
CT 51G on LV conns , rest EF on LV
File number correct (letter)
Do we have up to date schematics
Does equipment agree with what was quoted in the contract
;
i
i
dees «Page 23
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No. 51.1201
18.1400,
PROVINCIAL ELECTRICITY AUTHORITY November 26, 1997
Checklist for AC Schemes
Phasing right
Phases labelled
‘TRE Phasors right & DYN ? agrée with spec
CT ratios right , cores labelled
CT burden capability right
CT connections for zones right way ground
CVT on right phase
CVT fatios right
Bus protection I or 2 zones
Bus main & check in series
Test switches in current circuits bridge devices
Current test switches right for differential relays
Relay application right , particularly for transformers
Fast fuse protection for 115 KV lines
Transducers there for SCADA and CSCS
Selogic equations and setiings given for Schweitzer relays
Unused CT 's shorted and grounded
Main connections shown right with all equipment , particularly
switchgear interface p
Do we have catalog cuts for all devices
Shunt resistors for metrosils for MFAC 34 relays
Manual syne facilities provided and correct
Is phasing correct per the physical drawings particularly transformers
TRF differential'delta wye CT 's OK
All reference drawings there
CT secondaries grounded one place -at panel
Relay legend given , complete and correct
Drawing list given
Ace all drawings there - main bus CVT 's , synchronizing , Reclosing
AC connections BT CBF
Cross check versus panel arrangements and B/M 's
File number correct (letter)
Does equipment agree with what was quoted in the contract
eb cz
ide
Lab de
RCH ited tr0.4Page 24
|
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No. 51.1201
PROVINCIAL ELECTRICITY AUTHORITY
18.1400
November 26, 1997
3.6
Checklist for DC Schemes
10,
2
3.
4
15
16,
ie
18.
19
20.
2
22.
23
24.
25
26
27.
28
29.
30.
3
32.
33.
34
35
36.
Switch developments shown.
Syne modes - HL/ DB, DB/ HL SYNC
BF trip bus relay.
BF selection on DB SB schemes.
GIS ground switch interlocks.
Loss of DC alarms.
Annunciator loss of DC to another annunciator
Test ahd disconnect switches correct .
Bus CT shorting
BF and bus trip & lockout.
All loss of DC alarm relays in .
Alarm contact on CT shorting, Power Supply to shorting relays.
All annunciator points.
All SCADA points , CSCS points.
For SEL relays with multiple inputs & outputs - need relay word & logic
equations.
Separate primary, BU, & BFI relays.
All BFI’s in circuit.
Put BKR “a” switches in BFI circuit.
SEL 321 - Real or Recluse out of service, Reset Z extension .
SEL 321 used for trip coil monitoring
MYAX 31 used for trip coil monitoring
Alll outputs given for SEL 321.
SEL 321 relay fail contact for alarm.
SEL 279 master timer initiated.
SEL 279 DTL initiated correctly.
SEL 279 alarm for relay failure.
BKRS - SCADA trip & ¢lose correct.
SCADA close thru syne check:
For DB SB schemes , bus selector switch interlocks to trip if both
switches closed.
Can breaker be closed if line switches is open
For GIS are ground switch interlock in.
BER internal details shown , wo trip coils.
Reclosing in/out latching relay provided.
How is breaker/switch open & close indication given.
Discrepancy switched correct for DB SB schemes
‘Alarm on discrepancy positionPage 25
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No. 51.2203
18.2400
PROVINCIAL ELECTRICITY AUTHORITY November 36, 1997
3.6 Checklist for DC Schemes (Con't)
37.
38.
39.
40.
4
42
43.
4
45
46.
47.
48.
49,
50.
TT
52
33
54
55.
56.
37
58
59.
60.
6
62
63
64
65,
66.
67.
68.
69.
Recluse in progress and shutdown lamps.
Annunciator horn , lamp test potential indication , external contacts for
SCADA. window layout key , annunciator
For special circuits ( eg. EGAT ) does the relay scheme interface
correctly.
SEL 587- high side & low side O/C's used , VE sequence used.
TRE -high side ground relay ? 7
Interface with low side right .
Internal TRF projections shown.
Separate trip/lock out relays for separate relay systems.
Differential cut-off switch lamp & alarm
MCB alarm contacts for AC system also.
All targets given ( or through annunciator ).
DC supply circuits redundancy.
Cross tripping of both trip coils.
Local & remote selector switch application.
Manual synchronizing facilities.
AIL SCADA interfaces shown.
All drawing references clear.
Are all alarm points accounted for annunciator schematic,
High speed fuse failure relay (for VT fuses ) eg GEC PVFS provided
application correct.
Put FF relay at the end of VT leads ( supervises leads also )
Trip circuit supesvision relay provided & correct?
Operation of discrepancy switches & lamps , horn , lamp test.
Annunciator layout logical & per spec.
Do we have target lamps on all relays reset facilities and cut off
switches
Masier local / remote switch for CSCS system.
Two breaker trip coils .
DC + & - labelled
Are all schemes there MOAB control scheines interlock schemes with
latching relays , communication schemes
How does Reclosing work -HS then timed
How does auto sync work SCADA & CSCS close supervised by syne:
Relay legend given , complete and correct.
Drawing list given.
All indicating lites accounted for - RS shutdown etc.
Ah bie
wPage 26
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING
File No.
51,2201
18.1400,
PROVINCIAL ELECTRICITY AUTHORITY,
November 26; 1997
3.6 Checklist for DC Schemes (Con't)
70. Cross check versus panel arrangements and B/M's.
71. File number correct (letter).
72. Redundant DC supplies to breaker - Ist & 2nd trip coil, and spring
motor.
73. Do we have up to date schematics
74, Does equipment agree with was quoted in the contract.
4Page 27
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | FileNo, 51.2212
18.1400,
PROVINCIAL ELECTRICITY AUTHORITY November 26, 1997
3.7 Checklist for Control House and Outdoor Lighting,
Receptacles Etc.
wna
10.
ul
2
3.
14
15
16,
17.
18,
19
20.
2.
AC panel BKR AT/AF OK. for load & cable
| phase , 3 phases Breaker right
Main feeder sufficient ( 35 sq.mm.)
INT. Capability of BKRS OK. (25 kA)or (10 kA)
380/220 V, 50 Hz
Catalog cuts of panels
AC & DC SSTR. Diagram
Enough lighting ? ~ 2 watts/sq.ft in control room and 1/2 watt/sq.mm in
basement
Enough 3 way switches
Emergency Lite packs in GIS buildings
Concealed conduit in concrol room
RGS conduit outside building
IMC conduit exposed in the building . EMT for lites
Enough receptacles and no circuit overloaded
Timer switch for battery room exhaust fan
‘Three phase power receptacle in switchgear and GIS roorn ? anywhere
else? ,
Lighting in outdoor areas per PEA practice . Transformer area?
Lighting panels shown in logical place?
Gaie lighting and buzzer for GIS substations
File number correct (letter)
Does equipment agree with what was quoted in the contract
Provide any facilities for warning light for communication tower.
i
2
7
z
iPage 28
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No. 51.2212
18.1400
PROVINCIAL ELECTRICITY AUTHORITY November 26, 1997
i
|
| 3.8 Checklist for Building Lighting, Receptacle, Air Condition,
Grounding
1. Load center location
2. Conductor right , coordination, protection of cables
3. Interrupting capacity
4. Copper cables
5. EMT, IMC conduits
6. Station service AC diagram
7. Lighting levels, calculations
8. Receptacle types & locations
9. Outside lighting
10. Exhaust fan in battery room at least 2
UL. Orientation of building right, north arrow
12. Cooling units for relay room “100,000 bru/hr
13, Voltages , frequency right .
14. DC station service details
15, Who supplies service entrance load center etc.
16. File number correct (letter)
17, Does equipment with what was quoted in the contractI
"CHECKLIST FOR ELECTRICAL DRAWING REVIEWING
Page 29
| File No. 51.0401
18.1400
PROVINCIAL ELECTRICITY AUTHORITY
| November 26, 1997
3.9 Checklist for Control Building Lay Out
Switchgear line up agree with mfrs layout
Access to rear of switchgear
Arc panel shown
Relay & control panels 115 kV shown correctly , labels correct
Control desks shown correct
LTC control panels correct
Is the orientation and the sequencing of the panels correct
SCADA, RTU shown
Substation CSCS shown
UL. Furniture , radio etc. shown .
Ss
I
2
3
4
5}
6. AC & DC panels, load center, chargers, batteries correct
7
8
9.
12. Is the orientation of the building (north arrow ) correct
13. _ Is there room for future panels and switchgear sections
14. Cable trench entrances shown correct
15. File number correct (letter)
16. Capacitor banks shown correct
17. Cable tray shown correct
18, Co-ordination with civil drawings
19. Floor block-out for all equipment correct
welt te te gars casPage 30
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING
File No. 51.0401
18.1400
PROVINCIAL ELECTRICITY AUTHORITY
November 26, 1997
3.10 Checklist for Control Building Cable Tray
1, Separate power & control trays
with the contractors conduit plan
3. Control to communication towers
2. Are Power & control entrances to CB correct per general plan & agree
4. Do 22 KV UG circuit routes agree with the PEA 22 kV pole layout &
circuit
No tray overloading with circuits
All tray details given
Tray going up to capacitor banks
HV& LV connections to SSTR OK
Are tray crossings logical in,
Power cable sweep radii’OK for bending radius
File number correct (letter)
waornan
pes
Does equipment agree with what was quoted in the contract
ebeieee soe onei, Page 31
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | FileNo. 51.2211
18.1400,
PROVINCIAL ELECTRICITY AUTHORITY November 26, 1997
3.11 Checklist for Manhole & Cable Riser 22 kV Cable Layout
1. Dimension
2. Entrance dimensions
3. Wall thickness
4. Rebar details
5. Pulling irons
6. Sump & slope to sump
7. — Ground rods & grounding details
8. Cover above minimums
9. Cable racks shown right
10. Hooks and pulling irons for cable pulling tackle
11. Compaction under manhole
12. Interface PEA - CONTRACTOR correct on riser pole
13. Clamps , mountings etc. provided by who at interface point
14. Pole heights correct
15. Is cable installed in conduit to sufficient height for safety
16. Grounding for cable screen shown correctly and ground cable in conduit
17, Do we have details of all equipment
18. Fuse disconnect
19. Surge arrestor
20. Is depth of pole setting shown”
21. SW & GUYS shown (usually no sw.)
22, Is hardware bonded to ground
23. Sump/water space in MH
24, Ladder in MH =
25. Ducts shown correctly
26. 22 kV circuit numbers right
27. Ground wires over cable trench
28. Are cable sizes right
29. Will duct go in MH (3 x 4 )(W x H)
30. Is duct entering & exiting MH logical avoid cable crossings in MH
31. Sections of duct to show which circuits go where
32. At pole is riser conduit protected
33, Is MH sump located under MH entrance
34. MH cable racks bonded to ground .
35. File number correct (letter)
bea.Page 32
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | FileNo. 51.2210
18.1400
PROVINCIAL ELECTRICITY AUTHORITY November 26, 1997
3.12 Checklist for Grounding System
13.
ry
15.
16.
7
18,
19.
20.
2
22.
23.
24.
25.
26.
27
28.
29.
Ground wires over 22 kV cables to riser poles
Shield wire grounding on insulators
Grounding cables provides
Enough ground rods
Two risers to all equipment and structures
Two connections ,separate ,to TR. neutrals and surge arresters
95 sq.m conductor outdoor
Depth of burial
Ring in the building , with ground rods
Ring in the building to provide two current paths
All cable trays multiple bonded to ground conductor
Grounds to all equipment and metal in the building -AVAC motors,
ailings, AC/DC panels, etc., building structural steel!
Lightning shielding for building separate
50 sq.mm is permitted in building separate
Capacitor bank and switchgear grounding especial attention
Disconnect points for test
Does geometry of outdoor grid look right .
Fence & gate perimeter ground
Ground platforms at switches nd ground switches
Switch handle & ground platform especial attention
Ground conductor in 22 kV power cable trench.
Ground shield wire over control cable trench
Ground jumpers around splices in cable tray
Ground under communication room for equipment therein
Are there enough entrances ,in pipe .into the building 1
Gradient control steel! rods(or cu?) in concrete floors & slabs
Molds (thermoweld) right size for 95 sq.mih conductor
Heavy duty molds or not
File number correct (letter)
Does equipment agree with what was quoted in the contract
| idanPage 33
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No. 51.2001
{8.1400
[Provincia ELECTRICITY AUTHORITY Noveinber 26, 1997
|
313 Checklist for 22 kV Switchgear Control
| Interfaces right with (15 kV side
CT rations right .taps right
Logic of tripping right
Relays logically located 115 kV and 22 kV
Logic of UV relay tripping correct
Logic of UV relay «ripping and selection correct.
Annunciator equipment shown
Mimic diagrams correct
Relay/control legend furnished
Breaker mechanism control correct. anti pump drawout
Spring charge alarms
125 VDC
CT's grounded one place
Phasing right F-B,L-R,B-T
Trip supervision relays logic correct
Remote control switch (discrepancy switch)
Supervisory control agree with points list status also
Interlocks with 115 kV breaker correct
Are detection trips ,logic correct
Drawing lists given a
Cable entrances shown and correct
Cable sizes & types correct
Meters at a readable height
CS at an operable height
Bill of material given
Test switches ,current and potential given
DC indication light there
All zones protected and backed up
Breaker (&other) CS developments shown
Local /remote control correct
Reclosing correct
Phasing L-R of meters and relays correct
All annunciator points shown
Lamp test indicated
File number correct (letter)
UF. & UV connected to PT's bus
Does equipment agree with what was quoted in the contract
Future equipment shown on one line & accounted for in lineup
| einsbaes ~Ba>Page 34
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING | File No, 51.2003
18.1400,
PROVINCIAL ELECTRICITY AUTHORITY November 26, 1997
3.14 Checklist for Circuit List, Connection Diagram
Colour or wire codes shown-agree with PEA standard.
Circuits to all equipment CB's, DS, CT's, PT's, mimic board, relay
panels, CSCS, Transformer RCC, cap banks, CCTV, fire protection,
22 kV switchgear, interface with EGAT.
CT, PT neutrals grounded only in one place-inside building,
Solid link (shorting) TB’s on CT's.
Reference drawings indicated
Do TB layout physically 2g:2e with manufacturers TB layouts
CT & PT's connected on the right ratios
Are conduit fills OK. Segregation of circuits.
Some spare conductors included.
Separation of neutrals in CT's and PT's
Bus differential CT's combined in the switchyard not at relay panel
External connections to the correct side of terminal blocks.
Mechanism anti condensation heaters connected.
Primary and backup trips etc. in separate cables.
What procedure did the contractor use to check the cable list and
connection diagrams versus the schematics.
Do we have up to date schematics
File number correct (letter) ”
ee
Bre:a Page 35
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING File No. SL.L40L
18.2400
PROViNCIAL ELECTRICITY AUTHORITY November 26, 1997
3.15 Checklist for Building, Paving, Drainage Layout
wor auesencn
u
12
13
14
15
16
17
18.
19.
20.
22.
2.
Are property lines right
Substation position on the property
Operator houses position , future operator houses
Gutter inside property , interceptors
Slopes right
Where does water drain to
Water meters
Water tank
Water pressure in CB
Duct entrances to CB right
North arrow
Substation bays correct, future bay
Control building size right
Fence right , gates right
Road paving right , expansion joints
Sign board right position
Crushed rock No. 2, 0.101i thick
Water valves complete & correct
Pipe material & valves correct
Barb wire fence at perimeter
Will the drawing coordinate with the cut & fill drawing , if applicable
File number correct /letter)
sti ht
cd Saab dees 6 =e ne ee is
arse r
Be SC RR Bald 3 ons eet 252: A Page 37
CHECKLIST FOR ELECTRICAL DRAWING REVIEWING File No. 84.1000
PROVINCIAL ELECTRICITY AUTHORITY c November 26, 1997
4.0 Checklist for Payment Requests
Local material (A series), transportation (B series) or installation (C series).
Prices agree with contract prices.
Payment method agree with contract method.
Is all arithmetic correct.
Recorded in tracking system.
File number correct.
Is letter definitive.
Has spreadsheet been updated with costs.
File number correct (letter).
wer aueuve