Nabard SBD
Nabard SBD
GOVERNMENT OF HARYANA
PW (B&R) DEPARTMENT
Name of work:
TABLE OF CONTENTS
e-Tender Notice
PRESS NOTICE
__________________________
______________Department
______________ Circle
Phone No.______________
Email_________________
4
The [Governor of Haryana] invites the bids from the contractors who have created
login ID on the portal http://works.haryana.gov.in through online bids on the
website: Error! Hyperlink reference not valid. for the work detailed in the table
below.
i. “Single tender shall normally not be considered unless there are special
circumstances to do so. In such eventuality, decision to accept the single
tender shall be as prescribed in the rules. If special circumstances are
not present, tenders shall be re-called. If re-tendering again results in a
single
Tender, its acceptance may be considered with proper justification and
reasons”. Where on first call of tender, number of bidders participate in
the tender but on Technical evaluation only one participating bidder
qualifies, the tender shall be re-invited treating it as single tender.
ii. Those bidders shall not be required to pay tender document fees, who
choose to submit bids again on tender being re-called on account of
single tender being received or single bidder qualifies on first call.
6. Bidders shall have to pay the e-Service Fees of Rs. 1180/- in favour of ‘Society
for IT initiative fund for e-Governance through Debit Cards & Internet Banking
Accounts are required to be paid online directly through Internet Baking
Accounts.
10. The bid for the work shall remain open for acceptance during the bid validity
period to be reckoned from the last date of ‘Submission of Online Bids. Bids as
submitted online shall be valid for 120 days from the date of bid closing i.e. from
last date of submission of online bids. In case the last day to accept the tender
happens to be holiday, validity to accept tender will be the next working day.
11. Bidders may bid for any one or more of the works mentioned in the Table above.
12. To qualify for a package of contracts made up of this and other contracts for
which bids are invited in the same NIT, the bidder must demonstrate having
experience and resources sufficient to meet the aggregate of the qualifying
criteria for the individual contracts.
13. Other details can be seen in the bidding documents. The Employer shall not be
held liable for any delays due to system failure beyond its control. Even though
the system will attempt to notify the bidders of any bid updates, the Employer
shall not be liable for any information not received by the bidder. It is the
bidders’ responsibility to verify the website for the latest information related to
the tender.
6
14. Conditional tenders will not be entertained and are liable to be rejected.
15. In case the day of opening of tenders happens to be holiday, the tenders will be
opened on the next working day. The time, mode and place of receipt of tenders
and other conditions will remain unchanged.
16. The invitation of this tender can be cancelled without assigning any reason.
17. The societies shall produce an attested copy of the resolution of the Co-operative
department for the issuance of tenders.
18. The tender without Earnest money Earnest money Declaration form and tender
document fee will not be opened.
20. The tender of the bidder who does not satisfy the qualification criteria in the bid
documents are liable to be rejected and financial bids will not be opened.
21. The Pre-bid meeting will be held as per the details in Appendix to ITB.
22. The bidders may note that the works are to be carried out strictly as per the
applicable laws, permits, rules and regulations. Any damages / penalties
imposed by any statutory authority, like NGT etc, on account of noncompliance
of any applicable laws, permits, rules and regulations shall have to be borne by
the contractor.
23. The undersigned reserves the right to reject any or all of the bids without
assigning any reason.
24. Maintenance Period is five years from the completion date. The bidder is not required to
quote his rate for routine maintenance. The rates to be paid for routine maintenance are
indicated in the bid document. Further, the payment for routine maintenance to the
contactor shall be regulated based on his performance of maintenance activities
______________Department______ Circle
Phone No.______________
Email_________________
7
KEY DATES
A. General
1. Scope of Bid
1.2 The successful Bidder will be expected to complete the Works by the
Intended Completion Date specified in the Contract data and do the routine
maintenance of roads for five years from the date of completion.
1.3 Throughout these documents, the terms “bid” and “tender” and their
derivatives (bidder/tenderer, bid/tender, bidding/tendering etc.) are
synonymous.
2. Source of Funds
2.1 The expenditure on this project will be met from the budget provided by the
Govt. of Haryana.
2.2 The Government of the State has decided to provide funds for the routine maintenance
of the roads.
3. Eligible Bidders
3.1 The Invitation for Bids is open to all registered bidders on the portal
http://works.haryana.gov.in and eligible bidders meeting the eligibility
criteria as defined in ITB.
3.2 The bidders in Joint Ventures are allowed as per the Appendix to ITB.
3.3 Bidders shall not be under a declaration of ineligibility for corrupt and
fraudulent practices by the Central Government, the State Government or
any public undertaking, autonomous body, authority by whatever name
called under the Central or the State Government.
A) For works put to tender upto Rs. 25.00 Lacs, a valid Registration/
contractor’s id on Haryana Engineering Works Portal.(No technical
evaluation shall be carried out for this category). The intending bidders
who are not registered are required to submit the following documents in
place of Registration:
10
Interested bidders who are not registered should upload the following
documents at the time of bidding:
a. Mandatory Documents
i. Proof of Constitution - Partnership deed (in case of the partnership firm
registration); or Certificate of Incorporation (in case of Private limited
company, public limited company, Public sector undertaking, Limited
Liability Partnership, registration); or Any proof substantiating constitution
(in the case of society, trust, AOP, Government department, local authority,
statutory body registration.)
ii. PAN Card
iii. GST Certificate
iv. Undertaking of Non-Blacklisting – (Certificate that contractor has not been
blacklisted previously)
v. Proof of immovable properties/self-certification that doesn't have any
property
vi. Cancelled Cheque / Proof of bank account
vii. Proof of Address
viii. Similar works experience for the category of registration
ix. The applicant himself or his employee (at least one) should be a Diploma
Holder Engineer (Civil/Electrical/Agri./Hort.) as applicable. Accordingly,
self-declaration certificate of applicant and his employee along with copy of
Diploma certificate is to be submitted.
x. In case of registration for electrical works the applicant or the employee of
the applicant should submit valid Wireman License from Chief Electrical
Inspector, Haryana
b. Optional Documents
i. TAN Number Document
ii. MSME Registration Certificate (If Applicable)
iii. Form 26AS for last three years (Provided by Income Tax Department)
iv. LLCs (Limited Liability Company) to upload last audited balance sheet
v. Change of constitution of agency
vi. Litigation History (If any)
vii. List of Abandoned works (if any)
viii. Any Other relevant documents
In case during examination it is found that any bidder for this
category of works has not submitted above mandatory documents or
has submitted false documents his bid shall be rejected.
B) For works put to tender from Rs. 25.01 Lacs to Rs. 64.00 Lacs, a valid
registration and contractor’s id on Haryana Engineering Works Portal
with proof of ownership/ lease of specified machinery/ manpower as
listed in Clause 39 of this document.
(Technical Evaluation shall be carried out as per the requirement
specified in Clause 39 of this document and financial bid of only
responsive qualifying bidders shall be opened)
11
C) For works put to tender from Rs. 64.01 Lacs onwards, following
qualification criteria is required to be fulfilled:-
4.2 All bidders participating in tenders costing more than Rs. 25.00 lacs
shall include the following information and documents with their
bids in Section 2, Qualification Information unless otherwise stated
in the Appendix to ITB:
(d) The undertakings as per the format and language given in Section 7 of
the document. The undertakings should be of a date after the
invitation of this tender. The bids accompanying with the language
deviated from the language of the draft provided in Section 2 shall be
treated as non – responsive.
4.3 All care should be taken by the bidder to submit correct information and
documents in first place. No cognizance of the documents submitted
subsequently by the bidder on his own regarding his technical bid shall be
taken. However, clarification can be sought upto the extent of clearing any
doubt on the documents already submitted online.
4.4 Joint Ventures are permitted to bid for the work as defined in the
Appendix to ITB. Bids submitted by a Joint Venture (JV) shall comply with
the following requirements:
a. There shall be a Joint Venture Agreement (as per the format given in
Section-7) specific for these contract packages between the constituent
firms, indicating clearly, amongst other things, the proposed distribution
of responsibilities both financial as well as technical for execution of the
work amongst them. For the purpose of this clause, the most experienced
lead partner will be the one defined. A copy of the Joint Venture
agreement shall be submitted before any award of work could be finalized.
12
b. The bid, and in the case of the successful bidder, the Form of Agreement,
etc., shall be signed and / or executed in such a manner as may be
required for making it legally binding on all partners (including operative
parts of the ensuing Contract in respect of Agreement of Arbitration, etc.).
On award of work, the Form of Agreement and Contract Documents shall
be signed by all partners of the Joint Venture to conclude Contract
Agreement.
c. Lead partner shall be nominated as being partner-in-charge; and this
authorization shall be evidenced by submitting a power of attorney signed
by the legally authorized signatories of all the partners.
e. All partners of the Joint Venture shall be liable jointly and severally for the
execution of the Contract in accordance with the Contract terms, and a
relevant statement to this effect shall be included in the authorization
mentioned under sub clause I above as well as in the Form of Tender and
the Form of Agreement (in case of a successful bidder).
f. In the event of default by any partner, in the execution of his part of
Contract, the Employer shall be so notified within 30 days by the partner-
in-charge, or in the case of the partner-in-charge being the defaulter, by
the partner nominated as partner-in-charge of the remaining Joint
Venture. The partner-in-charge shall, within 60 days of the said notice,
assign the work of the defaulting partner to any other equally competent
party acceptable to the Employer to ensure the execution of that part of
the Contract, as envisaged at the time of bid. Failure to comply with the
above provisions will make the Contractor liable for action by the
Employer under the Conditions of Contract. If the Most Experienced i.e.
Lead Partner defined as such in the Communication approving the
qualification defaults, it shall be construed as default of the Contractor
and Employer will take action under the Conditions of Contract.
h. The bid submitted shall include all the relevant information as required
under the provisions of Sub-Clause 4.5 D of ITB and furnished separately
for each partner.
13
4.5A To qualify for award of the contract, each bidder in its name should have :-
i) Minimum average annual financial turnover (as certified by the
Chartered Accountant) during the last three years, ending 31 st March of
the previous financial year, should not be less than 30% of the value of
work. The turn over shall be updated to price level of the last financial
year at the rate of 8% per year compounded yearly.
(a) Three similar works each costing not less than 40% of the value of
work.
Or
(b) Two similar works each costing not less than 50% of the value of work.
Or
(c) One similar work costing not less than 80% of the value of work.
The amount of works shall be updated to price level of the last financial
year at the rate of 8% per year compounded yearly.
Note 1:- The works may have been executed by the applicant as Prime contractor or
as a member of Joint Venture or sub-contractor. As sub-contractor, he
should have acquired the experience of execution of all major items of
works under the proposed contract. In case a project has been executed by
a Joint Venture, the turnover or experience shall be evaluated in proportion
to their participation of the Joint Venture. In case of experience as a sub-
contractor, the certificate from the Principal Employer shall have to be
furnished.
Note 2:-Substantially completed works means those works which are at least 95%
completed as on the date of submission (i.e. gross value of work done upto
the last date of submission is 95% or more of the original contract price or
enhanced contract price as the case may be) and continuing satisfactorily.
Note 3:-Similar works means road work for road tender, building work for building
tender, bridge work for bridge tender and so on.
For these, a certificate from the employer shall be submitted along with
qualification information clearly mentioning the name of work, Contract Value,
billing amount. Date of commencement of works, satisfactory performance of the
Contractor and any other relevant information.
The amount put to bid above would not include maintenance cost for 5 years
and the turnover will be indexed at the rate of 8% per year.
4.5 B Each bidder must produce:
(i) An affidavit in the prescribed format given in this document in
Section 7. The affidavit should be of a date later then the date of calling
of tender; and
14
4.5 C To qualify for a package of contracts made up of this and other contracts
for which bids are invited in the Notice Inviting Tender, the bidder must
demonstrate having experience and resources sufficient to meet the
aggregate of the qualifying criteria for the individual contracts.
i. The lead partner shall meet not less than 50% of qualification criteria
given in sub-clause 4.5 A (i) & (ii) of ITB above.
ii. Each of the remaining partners shall meet not less than 25% of all the
criteria given in sub-clause 4.5 A (i) & (ii) of ITB above.
iii. The Joint Venture must also collectively satisfy the subject of the criteria
of Clause 4.5 B and 4.5 C of ITB for this purpose the relevant figures for
each of the partners shall be added together to arrive at the Joint
Venture total capacity which shall be 100% or more.
iv. In the event that the Employer has caused to disqualify under Clause
4.7 of ITB below all of the Joint Venture partners will be disqualified.
4.6 Bidders who meet the minimum qualification criteria will be qualified only if
their available bid capacity for construction work is equal to or more than the
total bid value excluding maintenance. The available bid capacity will be
calculated as under:
N = Number of years prescribed for completion of the works for which bids
are invited (period up to 6 months to be taken as ½ and more than 6
months as 1 in a year).
B = Value, at the current price level (compounded yearly @8% per year), of
existing commitments and on-going works to be completed during the
period of completion of the works for which bids are invited.
4.7 Even though the bidders meet the above qualifying criteria, they are
subject to be disqualified if they have:
made misleading or false representations in the forms, statements,
affidavits and attachments submitted in proof of the qualification
requirements; and/or
record of poor performance such as abandoning the works, not
properly completing the contract, inordinate delays in completion,
litigation history, or financial failures etc: and/or.
participated in the previous bidding for the same work and had quoted
unreasonably high bid prices and could not furnish rational
justification to the employer.
7.1 The Bidder, at the Bidder’s own responsibility and risk is encouraged to visit
and examine the Site of Works and its surroundings and obtain all
information that may be necessary for preparing the Bid and entering into a
contract for construction of the Works. The costs of visiting the Site shall be
at the Bidder’s own expense. The Bidder acknowledges that prior to the
submission of the bid, the Bidder/Contractor has, after a complete and
careful examination, made an independent evaluation of the Scope of the
Project, Specifications and Standards of design, construction and
maintenance, Site, local conditions, physical qualities of ground, subsoil and
geology, suitability and availability of access routes to the Site and all
information provided by the Employer or obtained, procured or gathered
otherwise, and has determined to its satisfaction the accuracy or otherwise
thereof and the nature and extent of difficulties, risks and hazards as are
likely to arise or may be faced by it in the course of performance of its
obligations hereunder. The Employer makes no representation whatsoever,
express, implicit or otherwise, regarding the accuracy, adequacy, correctness,
reliability and/or completeness of any assessment assumptions, statement or
information provided by it and the Bidder confirms that it shall have no claim
whatsoever against the Employer in this regard.
16
BIDDING DOCUMENTS
8. Content of Bidding Documents
8.1 The set of bidding documents comprises the documents listed below
and addenda issued in accordance with Clause 10 of ITB.
1. Detail Notice Inviting Tender
2. Instructions to Bidders including Appendix to bid
3. Qualification Information and other forms.
4. Conditions of Contract(Part I General Conditions of Contract, and Contract
Data; Part II Special Conditions of Contract)
5. Technical Specifications
6. Drawings
7. Bill of Quantities
8. Form of Acceptance, Form of Agreement, Issue of Notice to Proceed with the
Work,
9. Forms of Securities and Form of Unconditional Bank Guarantee.
10.1 Before the deadline for submission of bids, the Employer may modify the
bidding documents by issuing corrigendum.
11 PREPARATION OF BIDS
Part I Technical bid. This shall be named Technical Qualification Part of Bid and
shall comprise of:
Part II. Financial Bid:-It shall be named Financial Bid and shall comprise of:
The following documents, which are not submitted with the bid, will be deemed
to be part of the bid.
Section Particulars
1 Detail Notice Inviting Tender
2 Instructions to Bidders
3. Conditions of Contract
4. Contract Data
5. Technical Specifications
6. Drawings
13.1 The Contract shall be for the whole Works, as described in Clause 1.1 of ITB,
based on the priced Bill of Quantities submitted by the Bidder.
13.2 For item rate tenders, the bidder shall fill in item rate at its appropriate place
in figures. Items for which no rate or price is entered by the bidder will not be
paid for by the employer. Such item, where the bidder does not quote the price
or leaves it blank, will be treated as item to be executed free of cost item from
the contractor.
13.3 For percentage rate tender, the bidder shall make its due diligence and quote
a single percentage above or below HSR items including any premium if
applicable and individual rate for NS items which are in the BOQ but not in
HSR. NS Items in the BOQ, for which no rate or price is entered by the bidder
will not be paid for by the Employer and considered as nil rate items.
13.4 All duties, taxes (excluding GST), royalties, compensation, cost and other
levies payable by the Contractor under the Contract or to execute item(s) of
work or for any other cause, shall be included in the rates, prices, and total
Bid price submitted by the Bidder online. The GST amount shall be
reimbursed on production of proof of deposit of GST with Govt. for the
previous payment.
13.5 The rates and prices quoted by the bidder are subject to adjustment during
the performance of the Contract in accordance with the provision of Clause 42
A of the Conditions of Contract.
13.6 The Bidder is not required to quote his rate for Routine Maintenance. The rates to be
paid for routine maintenance by the Employer are indicated in the Bill of Quantities.
14. Currencies of Bid
14.1 The unit rates and the prices shall be quoted by the bidder entirely in Indian
Rupees.
15. Bid Validity
15.1 Online Bids shall remain valid for a period of not less than 120 days after the
deadline date for bid submission specified in ITB. A bid valid for a shorter
period shall be rejected by the Employer as non-responsive.
19
15.2 In exceptional circumstances, prior to expiry of the original time limit, the
Employer may request the bidders to extend the period of validity for a
specified additional period. The request to the bidders’ shall be made in
writing or by email. A bidder may refuse the request without forfeiting his
Earnest money. A bidder agreeing to the request will not be required or
permitted to modify his bid, but will be required to extend the validity of his
Earnest money for a period of the extension, and in compliance with Clause
16 of ITB in all respects.
16.1. The Bidder who does not have contractor id on HEWP cannot participate in
tendering process. Bidders who have contractor ID but have not registered on
HEWP can participate in tendering process by paying the earnest money
through online payment on the portal. Bidders who have contractor Id and are
registered on HEWP and also have deposited one time deposit are eligible for
participation in the tender by annexing bid specific Earnest Money
Declaration Form generated from HEWP.
a) Deleted
b) Deleted.
c) Deleted.
d) Deleted.
e) Deleted.
16.2 Deleted.
16.3 Deleted.
16.4. The bidder who is registered as contractor with Haryana Government and is
availing the exemption available for earnest money, shall upload bid specific
Earnest Money Declaration form duly downloaded from HEWP.
16.5 Any bid from the registered bidders not accompanied by an acceptable
Earnest Money Declaration form (in case exemption is availed) as above or not
secured as indicated in Sub-Clauses 16.1 above shall be rejected by the
Employer as non-responsive.
16.6. The successful bidder shall be de-registered with forfeiture of his/its one time
deposit of EMD exemption amount on HEWP and further barred from
participation in future bidding for a period of 2 years, in case of failure to
submit the Performance Bank Guarantee as per Clause 34 of this document.
17.1 Bidders shall submit offers that comply with the requirements of the bidding
documents, including the Bill of Quantities and the basic technical design as
indicated in the drawings and specifications. Conditional offer or alternative
proposals will be rejected as non-responsive.
Deleted
20
These conditions will over-rule the conditions stated in the tender documents,
wherever relevant and applicable.
All the bidders intending to participate in the tenders processed online are
required to get registered on the centralized e – Procurement Portal
i.e.https://etenders.hry.nic.in. Please visit the website for more details.
19. 2.1 The Bids submitted online should be encrypted and signed electronically
with a Digital Certificate to establish the identity of the bidder bidding
online. These Digital Certificates are issued by an Approved Certifying
Authority, by the Controller of Certifying Authorities, Government of India.
19.2.3 The bidders may obtain Class-II or III digital signature certificate from any
Certifying Authority or Sub-certifying Authority authorized by the
Controller of Certifying Authorities or may obtain information and
application format and documents required for the issue of digital
certificate from the authority.
19.2.4 The bidder must ensure that he/she comply by the online available
important guidelines at the portal https://etenders.hry.nic.in for Digital
Signature Certificate (DSC) including the e-Token carrying DSCs.
19.2.5 Bid for a particular tender must be submitted online using the digital
certificate (Encryption & Signing), which is used to encrypt and sign the
data during the stage of bid preparation. In case, during the process of a
particular tender, the user loses his digital certificate (due to virus attack,
hardware problem, operating system or any other problem) he will not be
able to submit the bid online.
Hence, the users are advised to keep a backup of the certificate and also
keep the copies at safe place under proper security (for its use in case of
emergencies).
21
19.2.6 In case of online tendering, if the digital certificate issued to the authorized
user of a firm is used for signing and submitting a bid, it will be considered
equivalent to a no-objection certificate/power of attorney /lawful
authorization to that User. The firm has to authorize a specific individual
through an authorization certificate signed by all partners to use the
digital certificate as per Indian Information Technology Act 2000. Unless
the certificates are revoked, it will be assumed to represent adequate
authority of the user to bid on behalf of the firm in the department tenders
as per Information Technology Act 2000. The digital signature of this
authorized user will be binding on the firm.
19.2.7 In case of any change in the authorization, it shall be the responsibility of
management / partners of the firm to inform the certifying authority about
the change and to obtain the digital signatures of the new person / user
on behalf of the firm / company. The procedure for application of a digital
certificate however will remain the same for the new user.
19.2.8 The same procedure holds true for the authorized users in a private/Public
limited company. In this case, the authorization certificate will have to be
signed by the directors of the company.
The bidders can view the detailed N.I.T and the time schedule (Key Dates) for
all the tenders floated through the single portal e-Tender system on the Home
Page at http://etenders.hry.nic.in
The tender documents can be downloaded free of cost from the e-Tender
portal http://etenders.hry.nic.in
The bidders are strictly advised to follow dates and times as indicated in the
online Notice Inviting Tenders. The date and time shall be binding on all
bidders. All online activities are time tracked and the system enforces time
locks that ensure that no activity or transaction can take place outside the
start and end dates and the time of the stage as defined in the online Notice
Inviting Tenders.
22
19.7 Online Payment of eService fee & Bid Preparation & Submission (PQQ/
Technical & Commercial/Price Bid):
Online Payment e-Service fee:
The online payment for eService fee can be done using the secure electronic
payment gateway by bidders/ Vendors online directly through Debit Cards
& Internet Banking Accounts. The secure electronic payments gateway is an
online interface between contractors and Debit card / online payment
authorization networks.
Important Note:-
(a) Any intending bidder can contact the helpdesk on or before prior to 4 hours
of the scheduled closing date &time of respective e-Auction/Tender event.
(b) For queries pertaining to e-Payment, please contact the help desk atleast 2
business days prior to the closing date & time of e-Auction/Tender event.
Help-desk support will remain closed during lunch break i.e. from 1:30
Pmupto2:15 PM on each working day.
23
Haryana e-Tender Help Desk Office will remain closed on Saturday, Sunday
and National Holidays.
NOTE: Bidders participating in online tenders shall check the validity of his/her
Digital Signature Certificate before participating in the online Tenders at the
portal http://etenders.hry.nic.in.
For help manual please refer to the ‘Home Page’ of the e-Tender website at
https://etenders.hry.nic.in and click on the available link ‘How to ...? to
download the file.
20.1 Complete Bids in two parts as per clause 19 above must be submitted by the
Bidder online not later than the date and time indicated in the Appendix to
ITB.
20.2 The Employer may extend the deadline for submission of bids by issuing an
amendment in accordance with Clause 10.3 of ITB. In such case all rights and
obligations of the Employer and the bidders previously subject to the original
deadline will then be subject to the new deadline.
21.1 Any Bid received by the Employer after the deadline prescribed in Clause 20
will be returned unopened to the bidder.
21.2. Deleted.
Bid Opening
23.1 The Employer inviting the bids or its authorized representative will open the
bids online in the presence of the bidders or their representatives who choose
to attend at time, date and the place specified in Appendix to ITB.
23.2 In the event of the specified date for the Opening of bids being declared a
holiday for the Employer, the Bids will be opened at the appointed time and
location on the next working day.
23.3 The file containing the Part-I of the bid will be opened first.
23.4 The amount, form and validity of the cost of bidding document and earnest
money furnished with each bid will be announced. If the cost of bidding
document and earnest money furnished does not conform to the amount and
validity period as specified in the Invitation for Bid, and has not been
furnished in the form specified in Clause 16, the remaining technical bid will
not be opened and will be disqualified for opening of financial bid. Similarly for
registered bidders, bid not accompanied by the Earnest Money declaration
form, shall be rejected and technical bid not be opened.
23.5 The Employer will also prepare minutes of the Bid opening, including the
information disclosed in accordance with Clause 23.4 of ITB.
23.6
(i) Subject to confirmation of the earnest money, the bids accompanied with valid
earnest money/earnest money declaration form will be taken up for evaluation
with respect to the Qualification Information and other information furnished in
Part I of the bid pursuant to Clause 12.1.
(ii) The technical bid will be evaluated on the basis of the documents submitted
online by the bidder and no modification of his technical bid will be sought
from the bidder. No cognizance of the documents submitted subsequently by
the bidder on his own regarding his technical bid shall be taken. However,
clarification can be sought upto the extent of clearing any doubt the documents
already submitted online.
(iii) The bidders will respond in not more than 7 days of issue of the clarification
letter, which will also indicate the date, time and venue of opening of the
Financial Bid.
23.7 The Employer shall hoist the result of technical evaluation of bids alongwith
the reasons for rejection of Part-I of the bid (Technical bid) on the website.
Thereafter, the employer shall wait for 7 days before opening the financial bid
of the qualified bidders so as to give the disqualified bidders and opportunity
to avail, if they so desire, any remedy available under the Law.
25
23.8 Part II (Financial Bid) of bids of only those bidders will be opened online, who
have qualified in Part I of the bid. The bidders’ names, the Bid prices, the total
amount of each bid, and such other details as the Employer may consider
appropriate will be notified by the Employer at the time of bid opening.
23.9 The Employer shall prepare the minutes of the online opening of Part-II of the
Bids.
24 Process to be Confidential
Information relating to the examination, clarification, evaluation, and
comparison of bids and recommendations for the award of a contract shall not
be disclosed to bidders or any other persons not officially concerned with such
process until the award to the successful Bidder has been announced. Any
attempt by a Bidder to influence the Employer’s processing of bids or award
decisions may result in the rejection of his Bid.
25.1 No Bidder shall contact the Employer on any matter relating to its bid from
the time of the bid opening to the time the contract is awarded except as
specified in clause 25.3 here under. If the bidder wishes to bring additional
information to the notice of the Employer, it should do so in writing.
25.2 Any attempt by the bidder to influence the Employer’s bid evaluation, bid
comparison or contract award decision may result in the rejection of his bid.
25.3 To assist in the examination, evaluation, and comparison of Bids, the
Employer may, at his discretion, ask any Bidder for clarification of his Bid,
including breakdowns of unit rates. The request for clarification and the
response shall be in writing or by email, but no change in the price or
substance of the Bid shall be sought, offered, or permitted.
26. Examination of Bids and Determination of Responsiveness
26.1 During the detailed evaluation of “Part-I of Bids”, the Employer will determine
whether each Bid
(a) meets the eligibility criteria defined in Clauses 3 and 4;
(b) has been properly signed;
(c) is accompanied by the required securities; and
(d)is substantially responsive to the requirements of the bidding documents.
During the detailed evaluation of the “Part-II of Bids”, the responsiveness of
the bids will be further determined with respect to the remaining bid conditions, i.e.,
priced bill of quantities.
26.2 A substantially responsive “Financial Bid” is one which conforms to all the
terms, conditions, and specifications of the bidding documents, without
material deviation or reservation. A material deviation or reservation is one
(a) which affects in any substantial way the scope, quality, or performance of
the Works;
(b) which limits in any substantial way, inconsistent with the bidding
documents, the Employer’s rights or the Bidder’s obligations under the
Contract;
or
whose rectification would affect unfairly the competitive position of other
bidders presenting substantially responsive bids.
26
26.3 If a Bid is not substantially responsive, it will be rejected by the Employer, and
may not subsequently be made responsive by correction or withdrawal of the
non-conforming deviation or reservation.
27. Correction of Errors.
27.1. “Financial Bids” determined to be substantially responsive will be checked by
the ‘Employer’ for any errors. Errors will be corrected by the Employer as
follows:
Where there is a discrepancy between the unit of any item mentioned in
BOQ, from that in HSR, the unit mentioned in HSR shall prevail and
the total resulting from multiplying the quoted rate by the quantity,
shall be taken in to account.
27.2. The amount stated in the “Financial Bid” will be corrected by the Employer in
accordance with the above procedure and the bid amount adjusted in the
following manner.
(a) If the Bid price increases as a result of these corrections, the amount as
stated in the bid will be the ‘bid price’ and the increase will be treated
as rebate;
(b) If the bid price decreases as a result of the corrections, the decreased
amount will be treated as the ‘bid price’.
28. Adjusted in bid price pursuant to clause 27 above, shall be considered as
binding upon the Bidder. If the Bidder does not accept the corrected amount
the Bid will be rejected, and action as per provisions of Earnest Money
Declaration Form shall be initiated or Earnest Money shall be forfeited as
applicable.
29. Evaluation and Comparison of Bids
29.1 The Employer will evaluate and compare only the bids determined to be
substantially responsive in accordance with Clause 26 of ITB.
29.2 In evaluating the Bids, the Employer will determine for each Bid the evaluated
Bid Price by adjusting the Bid Price as follows:
29.3 If the Bid of the successful Bidder is seriously unbalanced in relation to the
Engineer’s estimate of the cost of work to be performed under the contract,
the Employer may require the Bidder to produce detailed price analysis for
any or all items of the Bill of Quantities, to demonstrate the internal
consistency of those prices. After evaluation of the price analysis, the
Employer may require that the amount of the Performance Security set forth
in Clause 34 of ITB be increased at the expense of the successful Bidder to a
level sufficient to protect the Employer against financial loss in the event of
default of the successful Bidder under the Contract. The amount of the
increased Performance Security shall be decided at the sole discretion of the
Employer, which shall be final, binding and conclusive on the bidder. The
amount of additional performance security shall be equal to an amount
arrived at as below: -
27
(i) If the Bid price offered by the contractor is negatively unbalanced upto the
10% of the estimated project cost (as per analytical rates / N.S. rates).
In such cases no additional performance security shall be taken from the
successful bidder;
(ii) If the bid price offered by the contractor is negatively unbalanced below
10% and upto 20% of the estimated project cost (as per analytical rates /
N.S. Rates): -
(iii) If the bid price offered by the contractor is further negatively unbalanced
below 20% of the estimated project cost (as per analytical rates / N.S.
Rates): -
(iv) 20% of the total unbalanced amount of all the seriously unbalanced items
(i.e. unbalanced by more than 40% of the estimated amount of that
particular item/items).
Out of (i), (ii), (iii) and (iv) above Whichever is higher is to be deposited by the
successful bidder.
29.4 Validity of above Additional performance Security shall be valid until a date 28
days from the date of issue of the certificate of completion.
29.5 The Employer reserves the right to accept or reject any variation or deviation.
Variations and deviations and other factors, which are in excess of the
requirements of the Bidding documents or otherwise result in unsolicited
benefits for the Employer, shall not be taken into account in Bid evaluation.
29.6 The estimated effect of the price adjustment conditions under Clause 47 of the
Conditions of Contract, during the period of implementation of the Contract,
will not be taken into account in Bid evaluation.
30. The agency/Bidder to whom the work is allotted shall be paid lowest of the
following in the running/final bills.
F. AWARD OF CONTRACT
31. Award Criteria
31.1 Subject to Clause 32 of ITB, the Employer will award the Contract to the
Bidder whose Bid has been determined:
(i) To be substantially responsive to the bidding documents and who has offered
the lowest evaluated Bid price and
(ii) To be within the available bid capacity adjusted to account for his bid price
which is evaluated the lowest in any of the packages opened earlier than the
one under consideration. In no case, the contract shall be awarded to any
bidder whose available bid capacity is less than the evaluated bid.
32. Employer’s Right to Accept any Bid and to Reject any or all Bids
32.1 Notwithstanding Clause 31 above, the Employer reserves the right to accept or
reject any Bid, and to cancel the bidding process and reject all bids, at any
time prior to the award of Contract, without thereby incurring any liability to
the affected Bidder or bidders or any obligation to inform the affected Bidder
or bidders of the grounds for the Employer’s action.
33. Notification of Award and Signing of Agreement
33.1 The bidder whose Bid has been accepted will be notified of the award by the
Employer prior to expiration of the Bid validity period by email confirmed by
registered letter. This letter (hereinafter and in the Part I General Conditions of
Contract called the “Letter of Acceptance”) will state the sum that the
Employer will pay to the Contractor in consideration of the execution,
completion and maintenance of the works, by the Contractor during defect
liability period as prescribed by the Contract (hereinafter and in the Contract
called the “Contract Price”).
33.2 The notification of award will constitute the formation of the Contract, subject
only to the furnishing of a Performance Security in accordance with the
provisions of Clause 34.
33.3 The Agreement will incorporate all agreements between the Employer and the
successful Bidder. It will be signed by the Employer and the successful Bidder
after the Performance Bank Security is furnished.
33.4 Upon the furnishing by the successful Bidder of the Performance Security, the
Employer will promptly notify the other Bidders that their Bids have been
unsuccessful.
33.5 Upon the furnishing by the successful Bidder of the Performance Security, the
Employer shall issue the letter to proceed with the work.
33.6 If the lowest tenderer (L-1) backs out, his earnest money shall be forfeited or
action as per conditions of Bid Security Declaration Form shall be initiated.
The agency will be de-barred for giving tenders for two year and the second
lowest tenderer (L-2), third lowest tenderer (L-3) in order of sequence, may be
called upon to bring his offer to the same level as the originally first lowest
tenderer. In the event of their refusal to do so, tenders shall be recalled. In
case of great urgency, authority competent to accept the tender may authorize
call of limited or short notice tenders.
29
34.2 If the performance security is provided by the successful Bidder in the form of
a Bank Guarantee/FDR, it shall be issued either (a) at the Bidder’s option, by
a Nationalized/Scheduled Indian Bank or (b) by a foreign bank located in
India and acceptable to the Employer.
34.3 Failure of the successful Bidder to comply with the requirements of Sub-
Clause 34 shall constitute sufficient grounds for cancellation of the award and
forfeiture of the Earnest money/action due as per Earnest Money declaration.
The bidder shall also be debarred for period of 2 year from participation in
tenders in any of the Departments/Boards/Corporations etc. of Haryana
Government. If the work of is an urgent nature and cannot brook delay
involved in re-tendering, the remaining tenderers shall be offered the lowest
approved rates. If more than one tenderer turns up, then preferences shall be
given to the tenderer graded according to the rates quoted in the first
instance.
Illustration:
Original Amount Enhancement Amount after Additional Performance
of agreement enhancement
Rs 1,00,000.00 Rs 10,000.00 1,10,000.00 Nil
Rs 1,00,000.00 Rs 15,000.00 1,15,000.00 5% of Rs 15,000.00
30
35. Advances
36.1 The ‘Employer’ will reject a proposal for award if it determines that the Bidder
recommended for award has engaged in corrupt or fraudulent practices in
competing for the contract in question and will declare the firm ineligible,
either indefinitely or for a stated period of time; to be awarded a contract by
Haryana Government in any of Departments/Boards/Corporations etc.
36.2 The successful bidder shall be required to sign an Integrity Pact as provided
in Section 7.
36.3 The Employer requires the Bidders/Contractors to strictly observe the laws
against fraud and corruption in force in India, namely, Prevention of
Corruption Act, 1988.
37. Debarring
If a registered but unverified bidder submits Financial Bid online but he/it
fails to submit the Earnest Money instruments in physical form by 5:00 pm
with the Executive Engineer on the last date of submission of this tender, he /
it shall be blacklisted for participation in the bidding in all future tenders
floated by any of Department/Boards/Corporations etc. of Government of
Haryana, for a period of 2 years.
38. Completion of work
The agency to whom the work is allotted shall complete the entire work as per
drawings irrespective of quantities in the DNIT. The agency is bound to
consult the drawings before tendering and tender the work accordingly.
However, Clause 37 of GCC shall be applicable on the varied quantities.
Note:- After Clause 38 of ITB, any of the tendering Departments may include
one or more clauses in the ITB as per specific requirement of the
department/work.
31
(i) (For works of any value involving bituminous work of DBM and /or
BC irrespective of amount of work)
In case the agency does not possess the Batch Type Hot Mix Plant
within a radial distance of 50 kms then the agency shall furnish
unconditional Bank Guarantee of Rs. 1.00 Cr. which shall be released
after the installation of Batch Type Hot Mix Plant within a radial
distance of 50 kms.
In case the bidder does not install Batch Type Hot Mix Plant within a
radial distance of 50 kms, when the plant is required for execution of
work, the Bank Guarantee shall be forfeited.
In case the agency does not possess the Drum Type / Batch Type Hot
Mix Plant within a radial distance of 50 kms, then the agency shall
furnish unconditional Bank Guarantee of Rs. 25.00 Lacs which shall be
released after the installation of Drum Type / Batch Type Hot Mix Plant
within a radial distance of 50 kms as stated above.
In case the bidder does not install Drum Type / Batch Type Hot Mix
Plant within a radial distance of 50 kms, when the plant is required for
execution of work, the Bank Guarantee shall be forfeited.
The Drum Type / Batch Type Hot Mix Plant should have suitable
arrangements for mixing RAP.
32
Appendix to ITB
Instructions to Bidder Clause Reference
___________________,
__________Department.
__________Circle
34
Section-2
Qualification Information
Notes on Form of Qualification Information
The information to be filled in by bidders in the following pages will be used for
purposes of post-qualification as provided for in Clause 4 of the Instructions to Bidders.
This information will not be incorporated in the Contract. Attach additional pages as
necessary.
1. Individual Bidders
1.3.1 Work performed as prime Contractor (in the same name and style) on
construction works of a similar nature and volume over the last Five years. Attach
certificate from the Engineer-in-charge.
1.3.2 Work performed as Sub-Contractor (in the same name and style) on
construction works of a similar nature and volume over the last Seven years. Attach
certificate from Principal Employer (Main Client). Attach legal document of
agreement / subcontract, Form 26 AS of the sub-contractor.
Project Name of Description Value of Contract Date Stipulated Actual Date Remarks
Name Employer of work contract No. of date of of explaining
Issue completion Completion reasons
of for delay,
Work if any
Order
35
1.3.3 Information on Bid Capacity (works for which bids have been
submitted and works which are ongoing and yet to be completed) as on the
date of this bid.
Note:- Here, any of the departments may specify the quantities of the
work executed by the bidder.
36
Section 3
Conditions of Contract
Table of Contents
Section 3
Part I General Conditions of Contract
A. General
1. Definitions
Terms which are defined in the Contract Data are not also defined in the Conditions
of Contract but keep their defined meanings. Capital initials are used to identify
defined terms.
Bill of Quantities means the priced and completed Bill of Quantities forming part of
the Bid.
The Completion Date is the date of completion of the Works as certified by the
Engineer, in accordance with Clause 48.1.
The Contract is the Contract between the Employer and the Contractor to execute,
complete, and maintain the Works. It consists of the documents listed in Clause 2.3.
The Contract Data defines the documents and other information which comprise
the Contract.
The Contractor is a person or corporate body whose Bid to carry out the Works,
including routine maintenance, has been accepted by the Employer.
The Contract Price is the price stated in the Letter of Acceptance and thereafter as
adjusted in accordance with the provisions of the Contract.
A Defect is any part of the Works not completed in accordance with the Contract or
distressed development in the work irrespective of any causes.
The Maintenance means the activities required to be carried out for routine
maintenance of road relating to works covered in scope of work as per the agreement
or enhanced agreement.
The Employer is the party as defined in the Contract Data, who employs the
Contractor to carry out the Works, including routine maintenance. The Employer
may delegate any or all functions to a person or body nominated by him for specified
functions.
The Engineer is the person named in the Contract Data (or any other competent
person appointed by the Employer and notified to the Contractor, to act in
replacement of the Engineer) who is responsible for supervising the execution of the
Works and administering the Contract.
The Initial Contract Price is the Contract Price listed in the Employer’s Letter of
Acceptance.
The Revised Contract Price is the Contract Price agreed after signing of a
supplementary agreement with the Employer.
The Intended Completion Date is the date on which it is intended that the
Contractor shall complete the Works. The Intended Completion Date is specified in
the Contract Data. The Intended Completion Date may be revised only by the
Engineer by issuing an extension of time.
Materials are all supplies, including consumables, used by the Contractor for
incorporation in the Works.
Plant is any integral part of the Works that shall have a mechanical, electrical,
electronic, chemical, or biological function.
Site Investigation Reports are those that were included in the bidding documents
and are reports about the surface and subsurface conditions at the Site.
Specification means the Specification of the Work included in the Contract and any
modification or addition made or approved by the Engineer. Specifications for Road
and Bridge Works (Latest Edition as on date of Tender) published by Ministry of Road
Transport & Highways shall be applicable or any or all other specifications/IS Codes
applicable to a work.
The Start Date is given in the Contract Data. It is date when the Contractor shall
commence execution of the works. It does not necessarily coincide with any of
the Site Possession Dates.
39
Temporary Works are works designed, constructed, installed, and removed by the
Contractor that are needed for construction or installation of the Works.
The Works as defined in the Contract Data, are what the Contract requires the
Contractor to construct, install, maintain, and hand over to the Employer. Routine
maintenance is defined separately. Routine Maintenance is the maintenance of roads for five
years as specified in the Contract Data.
Substantial completion means those works which are at least 95% completed as on
the date of submission (i.e. gross value of work done upto the last date of submission
is 95% or more of the original contract price) and continuing satisfactorily.
2. Interpretation
2.1 In interpreting these Conditions of Contract, singular also means plural, male
also means female or neuter, and the other way around. Headings have no
significance. Words have their normal meaning under the language of the
Contract unless specifically defined. The Engineer will provide instructions
clarifying queries about these Conditions of Contract.
2.3 The documents forming the Contract are to be taken as mutually explanatory,
and unless otherwise expressly provided elsewhere in the Contract, the
priority of the documents, in the event of any ambiguity between them, shall
be interpreted in the following order of priority:
3.1 The language of the Contract shall be English. The law governing the Contract
are the Acts/Rules/Guidelines etc. notified by Government of India and
Government of Haryana.
3.2 The works are to be carried out strictly as per the applicable laws, permits,
rules and regulations. Any damages / penalties imposed by any statutory
authority, like NGT etc, on account of noncompliance of any applicable laws,
permits, rules and regulations shall have to be borne by the contractor.
4. Engineer’s Decisions
4.1 Except where otherwise specifically stated, the Engineer will decide
contractual matters between the Employer and the Contractor in the role
representing the Employer. However, if the Engineer is required under the
rules and regulations and orders of the Employer to obtain approval of some
other authorities for specific actions, he will so obtain the approval.
4.2 Except as expressly stated in the Contract, the Engineer shall not have any
authority to relieve the Contractor of any of his obligations under the Contract.
5. Delegation
5.1 The Engineer, with the approval of the Employer, may delegate any of his
duties and responsibilities to other person, after notifying the Contractor, and
may cancel any delegation after notifying the Contractor.
6. Communications
7. Subcontracting
7.1(a) The Contractor may subcontract part of the work with the approval of
the Employer in writing, up to percent defined in contract data of the
contract price, also part or full routine maintenance work after completion of
construction work but will not assign the Contract. It is expressly agreed that
the Contractor shall, at all times, be responsible and liable for all his
obligations under this Agreement notwithstanding anything contained in the
agreements with his Sub-contractors or any other agreement that may be
entered into by the Contractor and no default under any such agreement shall
exempt the Contractor from his obligations or liability hereunder.
41
7.1 (b) However, any specialized work can be Sublet to a Sub Contractor possessing
required valid Experience and certificate required if any after approval from
the Employer.
7.2 The Contractor shall not be required to obtain any consent from the Employer
for:
(a) the sub-contracting of any part of the Works for which the Sub-
Contractor is named in the Contract;
(b) the provision for labour, or labour component.
(c) the purchase of Materials which are in accordance with the standards
specified in the Contract.
7.3. The Engineer should satisfy himself before recommending to the Employer
whether the Sub-Contractor so proposed for the Works possesses the
experience, qualifications and equipment necessary for the job proposed to be
entrusted to him in proportion to the quantum of Works to be sub-contracted.
7.4 While sub-contracting part of construction work or full routine maintenance for
five years as per provisions of Clause 7.1 and7.3 above, the Contractor shall
enter into formal sub-contract with sub-contractor making provisions for such
requirements as may be specified by the Engineer including a condition that
to the extent of inconsistency, provision of the Contract shall prevail over the
provisions of the sub-contract. A copy of document of formal sub-contract
shall be furnished to the Employer within a period of 30 days from the date of
such sub-contract. In all such cases, on completion of the Contract, the
Engineer, unless for reasons recorded in writing decides otherwise shall issue
a Certificate of Experience to the contractor and in such certificate, the
experience of the sub-contractors shall also be mentioned. The Copy of such
certificate would also be endorsed to the sub-contractor.
8. Other Contractors
8.1 The Contractor shall cooperate and share the Site with Other Contractors,
public authorities, utilities, and the Employer between the dates given in the
Schedule of Other Contractors, as referred to in the Contract Data. The
Contractor shall also provide facilities and services for them as described in
the Schedule. The Employer may modify the Schedule of Other Contractors,
and shall notify the Contractor of any such modification.
8.2 The Contractor should take up the works in convenient reaches as decided by
the Engineer to ensure there is least hindrance to the smooth flow of traffic
including movement of vehicles and equipment of Other Contractors till the
completion of the Works.
9. Personnel
9.1 The Contractor shall ensure that the personnel engaged by it in the
performance of its obligations under this Contract are at all times
appropriately qualified, skilled and experienced in their respective functions.
42
9.2 The Contractor shall employ for the construction work routine maintenance and
operation of lab, the technical personnel named in the Contract Data or other
technical persons approved by the Engineer. Before signing the agreement the
contractor will submit the bio data of the technical personnel, as given in
contract data, he proposes to employ on this work to the Engineer and will get
the bio data approved from the Engineer. The Engineer will approve any
proposed replacement of technical personnel only if their relevant
qualifications and abilities are substantially equal to or better than those of
the personnel stated in the Contract Data.
9.3 If the Engineer asks the Contractor to remove a person who is a member of the
Contractor’s staff or work force, stating the reasons, the Contractor shall
ensure that the person leaves the Site within seven days and has no further
connection with the Works in the Contract. The Contractor shall then appoint
(or cause to be appointed) a replacement.
9.4 The Contractor shall not employ any retired Gazetted officer who has worked
in the Engineering Department of the State Government and has either not
completed two years after the date of retirement or has not obtained State
Government’s permission for employment with the Contractor.
9.5 The Engineer may require the Contractor to remove (or cause to be removed)
any person employed on the Site or Works, including the Contractor’s
Representative, who in the opinion of the Engineer:
10.1 The Employer carries the risks which this Contract states are Employer’s
risks, and the Contractor carries the risks which this Contract states are
Contractor’s risks.
11.1 The Employer is responsible for the excepted risks which are (a) in so far as
they directly affect the execution of the Works in the Employer’s country, the
risks of war, invasion, act of foreign enemies, rebellion, revolution,
insurrection or military or usurped power, civil war, riot commotion or
disorder (unless restricted to the Contractor’s employees) and contamination
from any nuclear fuel or nuclear waste or radioactive toxic explosive.
13. Insurance
13.1 The Contractor at his cost shall provide, in the joint names of the Employer and
the Contractor, insurance cover from the Start Date to the date of completion,
in the amounts and deductibles stated in the Contract Data for the following
events which are due to the Contractor’s risks:
(a) loss of or damage to the Works and material, plant and machinery to be
incorporated in the work.
(b) Personal injury or death.
(c) Loss of damage to property of third party other than the Contractor and
the Employer (except works, plant, material and equipments) in
connection with the Contract.
13.2 Insurance policies and certificates for insurance shall be delivered by the
Contractor to the Engineer for the Engineer’s approval before the Start
Date. All such insurance shall provide for compensation to be payable in
Indian Rupees to rectify the loss or damage incurred.
13.3 (a) The Contractor at his cost shall also provide, in the joint names of the
Employer and the Contractor, insurance cover from the date of completion
to the end of Defect Liability-cum-Maintenance Period, in the amounts
and deductibles stated in the Contract Data for personal injury or death
which are due to the Contractor’s risks:
13.3 (b) Insurance policies and certificates for insurance shall be delivered by the
Contractor to the Engineer for approval before the completion date/start
date. All such insurance shall provide for compensation to be payable in
Indian Rupees.
13.4 Alterations to the terms of insurance shall not be made without the
approval of the Employer.
13.5 Both parties shall comply with any conditions of the insurance policies.
14.1 The Contractor, in preparing the Bid, may, at his own risk, rely on any
Site Investigation Reports if referred to in the Contract Data,
supplemented by any other information available to him, before
submitting the bid.
16.1 The Contractor shall construct, and install and maintain the Works and do the
work of routine maintenance in accordance with the Specifications and Drawings.
17.1 The Contractor may commence execution of the Works on the Start Date and
shall carry out the Works in accordance with the Programme submitted by the
Contractor, as updated with the approval of the Engineer, and complete them
by the Intended Completion Date.
18.1 The Contractor shall submit Specifications and Drawings showing the
proposed Temporary Works to the Engineer, who is to approve them.
18.2 The Contractor shall be responsible for design and safety of Temporary Works.
18.3 The Engineer’s approval shall not alter the Contractor’s responsibility for
design and safety of the Temporary Works.
18.4 The Contractor shall obtain approval of third parties to the design and safety
of the Temporary Works, where required.
18.5 All Drawings prepared by the Contractor for the execution of the temporary or
permanent Works, are subject to prior approval by the Engineer before their
use.
19. Safety
19.1 The Contractor shall be responsible for the safety of all activities on the Site.
19.2 The Contractor shall be responsible for safety of all persons, employed by him
on Works, directly or through petty contractors or Sub-Contractors, and shall
report accidents to any of them, however, and wherever occurring on Works, to
the Engineer or the Engineer’s Representative and shall make every
arrangement to render all possible assistance and to provide prompt and
proper medical attention. The compensation for affected Workers or their
relatives shall be paid by the Contractor in such cases expeditiously in
accordance with the Workmen’s Compensation Act and other labour Laws and
regulations.
20. Discoveries
22.1 The Contractor shall allow access to the Site and to any place where work in
connection with the Contract is being carried out, or is intended to be carried
out to the Engineer and any person/persons/agency authorized by:
Except where otherwise stated, the contractor shall pay all tonnage and other
royalties, rent and other payments of compensation, if any, for getting stone,
sand, gravel, clay or other materials required for the works or excavation of
earth on the site of work.
The contractor has to give proof for making payment of royalty to any state
Government for procuring stone soling, stone metal, bajri and earth etc. If
these are arranged from quarries situated in Haryana but not auctioned by
Industries Department, Government of Haryana, the Engineer shall be at
liberty to make recovery of royalties after due notice to the contractor. The
decision of Employer in this regard shall be final.
23. Instructions
23.1 The Contractor shall carry out all instructions of the Engineer, which comply
with the applicable laws where the Site is located.
24.2 Either of the parties is barred from making reference to the competent
authority after 120 days from completion of work i.e. the claims will be time
barred if the reference to the competent authority is not made within 120
days from the completion of work.
24.3 Either Party will have the right to apply for arbitration as provided here in
after if he/it is not satisfied with decision of the competent authority.
25. Arbitration
(a) Where any of the party is not satisfied with the order passed by the
competent authority can apply for appointment of Arbitrator. In case the
party invoking arbitrator is contractor he shall deposit a sum as security
deposit, proportionate to the claim amount, determined as per the values
given in ‘Contract Data’ with ‘Engineer’. On termination of the arbitration
proceedings, this fee shall be adjusted against the cost, if any, awarded by
the arbitrator against the claimant party and the balance remaining after
such adjustment, and in the absence of such cost being awarded, the whole
of the sum bill will be refunded within one month of the date of award.
(b) For agreement amounts upto Rs. 10.00 Crore (after adjusting the contract
price any increase/decrease due to variations etc.) the matter will be
referred to a single Arbitrator to be appointed by the Engineer-in-Chief from
the panel of arbitrators approved by the Government.
(c) For agreement amounts more than Rs. 10.00 Crore (after adjusting the
contract price any increase/decrease due to variations etc.) the matter will
be referred to an Arbitral Tribunal consisting of 3 arbitrators, one each to be
appointed by the Employer after taking approval from Engineer-in-Chief
and the contractor and the third arbitrator to be chosen by the two
arbitrators so appointed by both the parties to act as Presiding Arbitrator.
In case of failure of the two arbitrators appointed by the parties to reach
upon a consensus within a period of 30 days from the appointment of the
arbitrator appointed subsequently, the Presiding Arbitrator shall be
appointed by the Administrative Secretary, of the department to which the
work belongs (Principal Secretary/ Additional Chief Secretary) as the case
may.
(d) If one of the parties fails to appoint its arbitrator in pursuance of sub-clause
(c) above within 30 days after receipt of the notice of the appointment of its
arbitrator by the other party, then the Administrative Secretary, of the
department to which the work belongs shall appoint the arbitrator. A
certified copy of the order of the Administrative Secretary, of the department
to which the work belongs, making such an appointment shall be furnished
to each of the parties.
47
(e) The decision of the majority of arbitrators shall prevail both parties.
(f) Arbitration proceedings shall be held in India, and the language of the
arbitration proceedings and that of all documents and communications
between the parties shall be English.
(g) The cost and expenses of Arbitration proceedings will be paid as provided
hereinafter. However, the expenses incurred by each party in connection
with the preparation, presentation, etc. of its proceedings as also the fees
and expenses paid to the arbitrator appointed by such party or on its behalf
shall be borne by each party itself. The fee and expenses of presiding
Arbitrator shall be borne by both the parties equally.
(h) Performance under the contract shall continue during the arbitration
proceedings and payments due to the contractor by the employer shall not
be withheld, unless they are the subject matter of the arbitration
proceedings.
(i) The fee and other charges payable to an arbitrator shall be as per of “THE
ARBITRATION AND CONCILIATION (AMENDMENT) ACT., 2016.
48
B. Time Control
26. Programme
26.1 Within the time stated in the Contract Data, the Contractor shall submit to
the Engineer for approval a Programme showing the general methods,
arrangements, order, and timing for all the activities in the Works, for the
construction of works.
26.2 The Contractor shall submit the list of equipment and machinery being
brought to site, the list of key personnel being deployed, the list of
machinery/ equipment being placed in field laboratory and the location of
field laboratory along with the Programme. The Engineer shall cause these
details to be verified at each appropriate stage of the programme.
26.4 The Contractor shall submit to the Engineer for approval an updated
Programme at intervals no longer than the period stated in the Contract
Data. If the Contractor does not submit an updated Programme within this
period, the Engineer may withhold the amount stated in the Contract Data
from the next payment certificate and continue to withhold this amount until
the next payment after the date on which the overdue Programme has been
submitted.
26.5 The Engineer’s approval of the Programme shall not alter the Contractor’s
obligations. The Contractor may revise the Programme and submit it to the
Engineer again at any time. A revised Programme shall show the effect of
Variations and Compensation Events.
27.1 The Engineer shall extend the Intend Completion Date, with approval from
authority competent to grant time extension as mentioned in clause 16.16.6
of PWD code through Employer, if a Compensation Event occurs or a
Variation is issued which makes it impossible for Completion to be achieved
by the Intended Completion Date without the Contractor taking steps to
accelerate the remaining work and which would cause the Contractor to
incur additional cost.
27.2 The Engineer with the approval of the authority competent to grant time
extension as per PWD Code Clause 16.16.6 through employer shall decide
whether and by how much to extend the Intended Completion date within 56
days of the Contractor asking the Engineer for a decision upon the effect of a
compensation event or variation and submitting full supporting information.
If the Contractor has failed to give early warning to delay or has failed to
cooperate in dealing with a delay, the delay by the failure shall not be
considered in accessing the new Intended Completion Date.
27.3 The Engineer shall within 14 days of receiving full justification from the
contractor for extension of Intended Completion Date refer to the employer.
The employer shall refer the case to the authority competent to grant time
extension as per Clause 16.16.6 of PWD Code within further 14 days for his
decision. It the authority competent to grant time extension fails to give his
acceptance within next 28 days, the engineer shall not grant the time
extension and the Contractor may refer the matter to the Dispute Redressal
System under clause 24.1. In case the employer happens to be the authority
competent to grant time extension, he would convey his decision to the
Engineer within 42 days.
28.1 The Engineer may instruct the Contractor to delay the start or progress of any
activity within the Works. Delay/delays totaling more than 30 days will
require prior written approval of the Employer.
29.1 The Engineer may require the Contractor to attend a management meeting.
The business of a management meeting shall be to review the plans for the
Works.
29.2 The Engineer shall record the business of management meetings and provide
copies of the record to those attending the meeting. The responsibility of the
parties for actions to be taken shall be decided by the Engineer either at the
management meeting or after the management meeting and stated in writing
to all those who attended the meeting.
50
C. Quality Control
30. Identifying Defects
30.1 The Engineer shall check the Contractor’s work and notify the Contractor of
any Defects that are found. Such checking shall not affect the Contractor’s
responsibilities. The Engineer may instruct the Contractor to search for a
Defect and to uncover and test any work that the Engineer considers may
have a Defect.
31. Tests
31.1 For carrying out mandatory tests as prescribed in the specifications, the
Contractor shall establish field laboratory at the location decided by Engineer
with in the time period defined in Contract Data. The field laboratory will have
minimum equipments as specified in the Contract Data. The Contractor shall
be solely responsible for :
32.1 The Engineer shall give notice to the Contractor of any Defects before the end
of the Defect Liability-cum-Maintenance Period, which begins from the
Completion Date and ends after five years. The Defect Liability-cum-Maintenance
Period shall be extended for as long as the Defects remain to be corrected.
32.2 Every time notice of Defect/Defects is given, the Contractor shall correct the
notified Defect/Defects within the duration of time specified by the Engineer’s
notice.
32.3 To fulfill the objectives laid down above, the Contractor shall undertake
detailed inspection of the roads at least once in a month. The Engineer can
increase this frequency in case of emergency. The Contractor shall forward to
the Engineer, the record of inspection and rectification each month. The
Contractor shall pay particular attention on those road sections which are
likely to be damaged or inundated during rainy season.
32.4 The Engineer may issue notice to the Contractor to carry out maintenance of
defects or deficiencies in maintenance, if any, noticed in his inspection, or
brought to his notice. The Contractor shall remove the defects within the
period specified in the notice and submit to the Engineer a compliance report.
51
32.6 Incompliance to Programme of Routine maintenance work (as per clause 26.1)
submitted by the contractor, he shall carry out monthly inspection of roads
under maintenance, based on which, he shall submit monthly bills, as detailed
in subsequent clauses.
(vi) Any other maintenance operation required to keep the road traffic
worthy at all times during the maintenance period.
(viii) The maintenance activity includes clearing of tree branches to keep the
sight distance visible all the time
32.7 The maintenance shall be carried out as mentioned in contract data and as
per direction of Engineer
33 Uncorrected Defects
33.1. If the Contractor has not corrected a Defect within the time specified in the
‘Engineer’s notice, the ‘Engineer’ will assess the cost of having the Defect
corrected, and the Contractor will pay double of this amount.
33.2If the contractor fails to pay the amount as intimated by the ‘Engineer’ to the
contractor as per clause 36.1 the same shall be recovered from the running
bill or the security amount and it if is more than the security amount then
the same shall be recovered from the performance security.
52
D. Cost Control
34.1 The Bill of Quantities shall contain items for the construction, installation,
testing, and commissioning works maintaining works, and lump sum amount per
km for yearly routine maintenance for each of the five years separately to be done by
the Contractor.
35 The Bill of Quantities is used to calculate the Contract Price. The Contractor is
paid for the quantity of the work done at the rates in the Bill of Quantities for
each item for the construction of roads. The payment for routine maintenance of roads
to the Contractor is performance based.
36. Variations
36.1 The Engineer shall, having regard to the scope of the Works and the sanctioned
estimated cost, have power to order, in writing, Variations within the scope of
the Works, he considers necessary during the progress of the Works. Such
Variations shall form part of the Contract and the Contractor shall carry them
out and include them in updated Programmes produced by the Contractor.
Oral orders of the Engineer for Variations, unless followed by written
confirmation, shall not be taken into account.
37.2. If requested by the ‘Engineer’ / Employer, the Contractor shall provide the
‘Engineer’ / Employer with a detailed cost breakdown of any rate in the Bill of
Quantities.
38.1 When the Programme is updated, the Contractor shall provide the Engineer
with an updated cash flow forecast.
53
39.1. The Contractor shall submit to the ‘Engineer’ monthly statements of the
estimated value of the work completed less the cumulative amount certified
previously by 1st week of the month. In case contractor does not submit his
bill by 1st week of the month, ‘Engineer’ shall get the monthly statement of the
estimated value of work completed less cumulative amount prepared by the
end of third week of the month. This procedure will be followed even if no work
is carried out at the site of work.
39.2. The ‘Engineer’ shall check the Contractor’s monthly statement within 21 days
of the date of submission and certify the amount as per agreement to be paid
to the Contractor. The amount so checked and certified by the ‘Engineer’ shall
be paid to the contractor within 30 days from such certification failing which
an interest @10% per annum for the period of delay shall be paid. In case the
payment is made earlier than 51 days then deduction of interest @ 10% per
annum for the number of days of early payment shall be deducted from the
next bill.
39.3. After submission of e-MB, a period of 21 (twenty one) days is given to the Junior
Engineer, Sub Divisional Engineer & Executive Engineer for passing of the bill. A
period of 04 (four) days is given to EE to send the bill submitted by the
contractor to the concerned SDE and JE. Further, for checking and verification of
bill, a period of 06 (six) days is given to the JE, 05 (five) days are given to SDE
and 06 (six) days are given to the EE. In case of delay on the part of any of
officer, the concerned shall be liable for the delay in payment.
39.5 The payment to the Contractor will be as follows for routine maintenance:
c. If any two segments get less than 80 marks or any particular segment
continuously gets less than 80 marks, the payment for whole road shall be
denied. Details are as below.
ROUTINE INSPECTIONS
1. Every road must be inspected for Routine Inspection (RI) at least once in
two months. (Bi-monthly frequency)
2. Routine inspection can be carried out by any of the PIU officers including Sub
Engineer/JE/AE/DE/AEE/EEor equivalent.
3. For the purpose of RI, each road shall be divided into segments of one
kilometer or part thereof. Complete road length shall be compulsorily
inspected during a routine inspection.
PERFORMANCE EVALUATION
1. Every road must be evaluated at least once in two months.(Bi-monthly
frequency)
2. PE can be carried out by any of the PIU officers including Sub Engineer/
JE/AE/DE/AEE or equivalent.
3. For the purpose of PE, each road shall be divided into segments of one
kilometer or part thereof. Based on the grading of RI and photographs
uploaded during RI, every segment is given marks out of 100 on the
parameters fixed for PE. The weighted average marks are then evaluated for the
entire road.
PE, PIU-in-charge may change the marks given to the road by the inspecting
officer, along with mentioning the reasons for the change made.
5. Criteria for Payment based on the marks obtained in PE is as follows:
a) If the weighted average marks for the entire road is 100 then full payment will
be done.
b) If the weighted average marks for the entire road is between 80 and 100, then
proportion at e payment will be done. For e.gif the marks obtained is 88 out of
100 then 88% of the amount of bill raised will be paid.
c) If the weighted average marks for the entire road is less than 80 then no
payment will be done for the entire road.
d) If any two segments of a road get less than 80 marks in the same PE, then no
payment will be done for the entire road.
e) If any particular segment of a road gets less than 80 marks in two consecutive
PE, then no payment will be done for the entire road.
f) The Contractor shall submit to the Engineer a bill every month for the
routine maintenance of the roads from the date the maintenance period
starts i.e. from completion date as defined in Clause 1.1, it will be
supported with a copy of the record of the Contractor’s monthly inspection
and other instructions received from the Engineer.
g) The payment will be made Six monthly for the monthly bills received and
as certified by the Engineer based on performance by the Contractor.
h) The contractor shall submit monthly bills by the 10th day of the next
month and If the bill for a month is not received from the Contractor, he
forfeits his right for the payment and no payment shall be due to the
contractor.
56
40. Payments
40.1 Payments shall be adjusted for deductions for advance payments, security
deposit/retention, other recoveries in terms of the contract and taxes at
source, as applicable under the law.
40.2 Payment for the routine maintenance of the roads will be made Six Monthly for
the satisfactory maintenance of the Works and based on the monthly bills
submitted by the Contractor as per Clause 39.5 above and certified by the
engineer, within 15 days of the date of each certificate.
41. The Employer may appoint another authority, as specified in the Contract
Data (or any other competent person appointed by the Employer and notified
to the Contractor) to make payment certified by the Engineer.
42. Items of the Works for which no rate or price has been entered in the Bill of
Quantities, will not be paid for by the Employer and shall be deemed covered
by other rates and prices in the Contract.
43. The agency / bidder to whom the work is allotted shall be paid lowest of the
following in the running / final bills:-
1. Amount calculated with the accepted rates of lowest agency.
2. Amount worked out with the accepted percentage above /below
HSR+CP/analytical rates/NS item rates, worked out in financial
statement. Financial statement will be made a part of agreement.
44.1 The following are Compensation Events unless they are caused by the
Contractor:
a. The Employer does not give access to 80% of the area of project Site by
the Site Possession Date stated in the Contract Data.
b. The Employer modifies the schedule of other contractors in a way which
affects the work of the contractor under the contract.
c. The Engineer orders a delay or does not issue drawings, specifications
or instructions required for execution of works on time.
57
44.3 If a Compensation Event would prevent the Works being completed before
the Intended Completion Date, the Intended Completion Date shall be
extended. The Engineer shall recommend to the Employer whether and by
how much the Intended Completion Date shall be extended. Final approval
shall rest with the Employer.
45. Tax
The Price Bid by the Contractor shall include all custom duties, import duties,
levies, business taxes, income, toll and other taxes, duties, service tax,etc. of
local bodies and authorities as applicable that may be levied in accordance to
the laws and regulations in being as on the closing date for submission of Bid
in the country of Employer on the Contractor’s Equipment, Plant, materials
and supplies (permanent, temporary and consumables) acquired for the
purpose of Contract and on the services performed under the Contract
excluding GST. Nothing in this Contract shall relieve the Contractor from the
responsibility to pay the taxes and duties that may be levied in the Employer’s
country on profits made by him in respect of the Contract. The GST amount
shall be reimbursed on production of proof of deposit of GST with Govt. for the
previous payment.
58
46 Currencies
47.1 Contract price shall be adjusted for increase or decrease in rates with the
principles and procedures and as per formula given in the contact data. The
rate of cement/steel issued under the authority of Engineer-in-Chief
concerned on the date of receipt of tender shall be considered as base rate.
47.2 To the extent that full compensation for any rise or fall in costs to the
contractor is not covered by the provision of this or other clauses in the
contract, the unit rates and prices included in the contract shall be deemed to
include amounts to cover the contingency of such other rise or fall in costs.
47.3 The contractor shall submit original bill/ voucher while claiming the payment
for the work done. The bill/ voucher should pertain to the period of original
contractual time limit and should correspond with the progress of work. No
extra payment due to increase in rate of cement/steel/bitumen will be paid if
the original bill/ vouchers are not submitted by the agency. No increase in
prices of the cement/steel/bitumen shall be reimbursed to the contractor
beyond the original time period allowed for construction as per contract
agreement irrespective of extension of time limit granted to the agency for any
reason, whatsoever.
On completion of the whole of the Works half the total amount retained is
repaid to the Contractor and half when the Defect Liability-cum-Maintenance
Period has passed and the Engineer has certified that all Defects notified by
the Engineer to the Contractor before the end of this period have been
corrected.
On completion of the whole works, the contractor may substitute retention
money with an “on demand” Bank guarantee/FDR.
49.1 In the event of failure on part of the Contractor to achieve timely completion of
the project, including any extension of time granted under Clause 27, he shall,
without prejudice to any other right or remedy available under the law to the
Employer on account of such breach, pay as agreed liquidated damages to the
Employer and not by way of penalty in a sum calculated at the rate per day or
part thereof as stated in the Contract Data. For the period that the Completion
Date is later than the Intended Completion Date, liquidated damages at the
same rate shall be withheld if the Contractors fails to achieve the milestones
prescribed in the Contract Data. However, in case the Contractor achieved the
next milestone, the amount of the liquidated damages already withheld shall
be restored to the Contractor by adjustment in the payment certificate. Both
the Parties expressly agree that the total amount of liquidated damages shall
not exceed 10% (ten percent) of the value of the balance work (amount of
uncompleted work) on the date on which liquidated damages have become
due. The liquidated damages payable by the Contractor are mutually agreed
genuine pre-estimated loss and without any proof of actual damage likely to be
suffered and incurred by the Employer; and the Employer is entitled to receive
the same and are not by way of penalty.
The Employer may, without pre-judice to any other method of recovery, deduct
the amount of such damages from any sum due, or to become due to the
Contractor or from Performance Security including Additional Performance
Security or any other dues from Government or semi-Government bodies
within the state.
The payment or deduction of such damages shall not relieve the Contractor
from his obligations to complete the Works, or from any other of his duties,
obligations or responsibilities under the Contract.
The Contractor shall use and continue to use his best endeavor to avoid or
reduce further delay to the Works, or any relevant Stages.
49.2 The Employer, with the approval of the competent authority, based on the
justified reasons, can extend the intended completion date. The liquidated
damages can be deferred/reduced/waived (whole or part) by the SE
concerned for contract(s) upto Rs.1.00 cr., CE from Rs.1.00 cr. to Rs.10.0.
cr. and E-In-C for contract(s) above Rs.10.00 cr. This will be done on
the written request of the contractor and written recommendations of
EE/SE as the case may be. If the Intended Completion Date is extended
after liquidated damages have been paid, the Engineer shall correct any such
payment of liquidated damages by the Contractor by adjusting the next
payment certificate.
60
49.3 It is agreed by the Contractor that the decision of the Employer as to the
liquidated damages payable by the Contractor under this Clause shall be final
and binding.
50.1. The Employer shall make advance payment to the Contractor of the amounts
stated in the Contract Data by the date stated in the Contract Data, against
provision by the Contractor of an Unconditional Bank Guarantee in a form as
per Section-7 and by a bank acceptable to the Employer in amounts and
currencies equal to the advance payment. The guarantee shall remain effective
until the advance payment has been repaid, but the amount of the guarantee
shall be progressively reduced by the amounts repaid by the Contractor.
Interest will be charged on the advance payment as specified in the contract
data.
50.2. The Contractor is to use the advance payment only to pay for Equipment,
Plant and Mobilization expenses required specifically for execution of the
Works. The Contractor shall demonstrate that advance payment has been
used in this way by supplying copies of invoices or other documents to the
‘Engineer’.
51 Securities
51.1 The Performance Security equal to 5% (five percent) and additional security for
unbalanced bids shall be provided to the Employer no later than the date
specified in the Letter of Acceptance and shall be issued in an amount and
form by a bank or surety acceptable to the Employer, and denominated in
Indian Rupees. The Performance Security shall be valid until a date 45days
from the date of expiry of Defect Liability-cum-Maintenance Period and the
additional security for unbalanced bids shall be valid until a date 28 days from
the date of issue of the certificate of completion.
Illustration:
Original Amount Enhancement Amount after Additional Performance
of agreement enhancement
Rs 1,00,000.00 Rs 10,000.00 1,10,000.00 Nil
Rs 1,00,000.00 Rs 15,000.00 1,15,000.00 5% of Rs 15,000.00
53.1 The Contractor shall request the Engineer to issue a Certificate of Completion
of the works and the Engineer will do so upon deciding that the Work is
completed, within 21 days of the receipt of request or within a reasonable
period as per nature of the work.
53.2 The Contractor shall request the Engineer to issue the certificate of completion
of the Routine Maintenance and the Engineer will do so upon deciding that
the work of Routine Maintenance is completed
54.1 The Employer shall take over the Works within seven days of the Engineer’s
issuing a certificate of Completion of Works. The Contractor shall continue to
remain responsible for its Defect Liability-cum-Maintenance period during
the Defect Liability-cum-Maintenance Period.
54.2 The Employer shall take over the maintained work within seven days of the
Engineer issuing a certificate of clearance of Defect Liability-cum-
Maintenance Period.
57.1. The Contractor shall supply to the ‘Engineer’ a detailed account of the total
amount that the Contractor considers payable under the Contract before the
end of the Defects Liability Period. The ‘Engineer’ shall issue a Defect Liability
Certificate and certify any final payment that is due to the Contractor within
56 days of receiving the Contractor’s account if it is correct and complete. If it
is not, ‘Engineer’ shall issue within 56 days a schedule that states the scope of
the corrections or additions that are necessary. If the Final Account is still
unsatisfactory after it has been resubmitted, the Engineer shall decide on the
amount payable to the Contractor and issue a payment certificate, within 56
days of receiving the Contractor’s revised account.
63
57.2 The contractor will submit the final bill of construction within 21 days of issue
of Completion Certificate. The Engineer will process and pass the final bill
within 21 days of the submission of final bill by the contractor.
57.3 The Contractor shall submit to the Engineer a detailed account of the total amount that the
Contractor considers payable for maintenance of works under the contract 21 days before the
end of the Routine Maintenance Period. The Engineer shall issue a Routine Maintenance
Completion Certificate and certify any final payment that is due to the Contractor within 21
days of receiving the Contractor's account if it is correct and complete. If it is not, the Engineer
shall issue within 21 days a schedule that states the scope of the corrections or additions that
are necessary. If the revised account is still unsatisfactory after it has been resubmitted by the
Contractor, the Engineer shall decide on the amount payable to the Contractor and issue a
payment certificate within 28 days of receiving the Contractor’s revised account. The payment
of final bill for routine maintenance will be made within 14 days thereafter.
57.4 In case the account for routine maintenance is not received within 21 days of issue of
Certificate of Completion as provided in clause 57.3 above, the Engineer shall proceed to
finalize the account and issue a payment certificate within 28 days. The payment of final bill
for routine maintenance will be made within 14 days thereafter.
58.1 The Contractor shall submit “as built” drawings for the work by the dates
given in the contract data. If “as built” Drawings and/or operating and
maintenance manuals are required, the Contractor shall supply them by the
dates stated in the Contract Data.
58.2 If the Contractor does not supply the Drawings and/or manuals by the dates
stated in the Contract Data, or they do not receive the Engineer’s approval, the
Engineer shall withhold the amount stated in the Contract Data from
payments due to the Contractor.
59. Termination
59.1 The Employer or the Contractor may terminate the Contract if the other party
causes a fundamental breach of the Contract.
59.2 Fundamental breaches of the Contract shall include, but shall not be limited
to, the following:
(a) the Contractor stops work for 28 days when no stoppage of work is shown on
the current Programme and the stoppage has not been authorized by the
Engineer;
(b) the ‘Engineer’ instructs the Contractor to delay the progress of the Works and
the instruction is not withdrawn within 56 days the Contractor is declared as
bankrupt or goes into liquidation other than for approved reconstruction or
amalgamation;
64
(c) the Engineer gives Notice that failure to correct a particular Defect whether
pertaining to construction work or pertaining to Defect Liability-cum-
Maintenance Period is a fundamental breach of the Contract and the
Contractor fails to correct it within a reasonable period of time determined by
the Engineer;
(g) if the Contractor, in the judgment of the Employer, has engaged in the
corrupt, fraudulent or coercive practice in competing for or in executing the
Contract. For the purpose of this clause, “corrupt practice” means the offering,
giving, receiving, or soliciting of anything of value to influence the action of a
public official in the procurement process or in Contract execution.
“Fraudulent Practice” means a willful misrepresentation or omission of facts or
submission of fake/forged documents in order to induce public official to act
in reliance thereof, with the purpose of obtaining unjust advantage by or
causing damage to justified interest of others and/or to influence the
procurement process to the detriment of the Government interests. And, this
includes collusive practice among Bidders (prior to or after bid submission)
designed to establish bid process at artificial non-competitive levels and to
deprive the Employer of the benefits of free and open competition. “Coercive
practice” means the act of obtaining something, compelling an action or
influencing a decision through intimidation, threat or the use of force directly
or indirectly, where potential or actual injury may befall upon a person, his/
her reputation or property to influence their participation in the tendering
process.
(h) if the Contractor, in the judgment of the Employer, has engaged in the
corrupt, fraudulent practice to extract undue payments from the department
while executing the Contract. For the purpose of this clause, “corrupt practice”
means the offering, giving, receiving, or soliciting of anything of value to
influence the action of a public official in the procurement process or in
Contract execution. “Fraudulent Practice” means a willful misrepresentation
or omission of facts or submission of fake/forged documents / claims / bills
in order to induce public official to act in reliance thereof, with the purpose of
obtaining unjust advantage detriment of the Government interests.
59.3 When either party to the Contract gives notice of a breach of contract to the
‘Engineer’ for a cause other than those listed under Sub Clause 59.2 above,
the ‘Engineer’ shall decide whether the breach is fundamental or not.
59.4 Notwithstanding the above, the Employer may terminate the Contract for
convenience.
65
59.5 If the Contract is terminated, the Contractor shall stop work immediately,
make the Site safe and secure, and leave the Site as soon as reasonably
possible.
61. Property
61.1 All materials on the Site, Plant, Equipment, Temporary Works and Works are
deemed to be the property of the Employer, if the Contract is terminated
because of a Contractor’s default to make recoveries.
66
62.1 If the Contract is frustrated by the outbreak of war or by any other event
entirely outside the control of the Employer or the Contractor, the Engineer
shall certify that the Contract has been frustrated. The Contractor shall
make the Site safe and stop work as quickly as possible after receiving this
certificate and shall be paid for all work carried out before receiving it and for
any work carried out afterwards to which a commitment was made.
Further, the first running bill of the contractor shall be cleared only after the
receipt of registration certificate under the Building & Other Construction
Workers Welfare (RE&CS) Act, 1996 and registration of all the eligible
construction workers as a beneficiary of the Haryana Building & Other
Construction Worker Welfare Board.
1.2 The Contractor shall, unless otherwise provided in the Contract, make his own
arrangements for the engagement of all staff and labour, local or other, and for
their payment, housing, feeding and transport.
1.3 The Contractor shall, if required by the ‘Engineer’s, deliver to the ‘Engineer’ a
return in detail, in such form and at such intervals as the ‘Engineer’ may
prescribe, showing the staff and the numbers of the several classes of labour
from time to time employed by the Contractor on the Site and such other
information as the ‘Engineer’ may require.
(ii) In relation to any other establishment to which this Act may be applicable at
any time after such commencement, within a period of 60 days from the date
on which this Act becomes applicable to such establishment, make an
application to the registering officer for the registration of establishment.
c) Employee P.F. and Miscellaneous Provision Act 1952:- The Act Provides for
monthly contributions by the employer plus workers @10% each. The
benefits payable under the Act are:
d) Maternity Benefit Act 1951:- The Act provides for leave and some other
benefits to women employees in case of confinement or miscarriage etc.
e. Contract Labour (Regulation & Abolition) Act 1970:- The Act provides for
certain welfare measures to be provided by the Contractor to contract
labour and in case the Contractor fails to provide, the same are required to
be provided by the Principal Employer by Law. The Principal Employer is
required to take Certificate of Registration and the Contractor is required
to take licence from the designated Officer. The Act is applicable to the
establishments or Contractor of Principal Employer, if they employ 20 or
more contract labour.
70
f. Minimum Wages Act 1948:- The Employer is supposed to pay not less
than the Minimum Wages fixed by appropriate Government as per
provisions of the Act, if the employment is a scheduled employment.
Construction of Buildings, Roads, Runways are scheduled employments.
(g) Payment of Wages Act 1936:_ It lays down as to by what date the wages are
to be paid, when it will be paid and what deductions can be made from the
wages of the workers.
(h) Equal Remuneration Act 1979:- The Act provides for payment of equal
wages for work of equal nature to Male and Female workers and for not
making discrimination against Female employees in the matters of
transfers, training and promotions etc.
(i) Deleted
(j) Industrial Disputes Act 1947:- The Act lays down the machinery and
procedure for resolution of Industrial disputes, in what situations a strike
or lock-out becomes illegal and what are the requirements for laying off or
retrenching the employees or closing down the establishment.
(l) Trade Unions Act 1926:- The Act lays down the procedure for registration
of trade unions of workmen and employers. The Trade Unions registered
under the Act have been given certain immunities from civil and criminal
liabilities.
(m) Child Labour (Prohibition & Regulation) Act 1986:- The Act prohibits
employment of children below 14 years of age in certain occupations and
processes and provides for regulation of employment of children in all other
occupations and processes. Employment of Child Labour is prohibited in
Building and Construction Industry.
(a) The Contractor shall pay not less than the fair wage to labourers
engaged by him on the work.
EXPLANATION:-Fair Wage’ means wage whether for time of piece
work notified from time to time for the area and where such wages
have not been so notified the wages specified by the Public Works
(B&R) Deptt. Haryana for the district in which the work is done.
(b) The Contractor shall not withstanding the provisions of any agreement
to the contrary, caused to be paid fair wages to labour, indirectly
engaged on the work including any labour engaged by his sub-
contractors in connection with the said work, as if the labourers had
been directly employed by him.
(c) In respect of labour directly or indirectly employed on the works for the
performances of the contractor’s part on this agreement the contractor
shall comply with or cause to be complied with the Haryana PWD
Contractor’s Labour’s Regulations made by the Government from time
to time in regard to payment of wages wage period deductions from
wages recovery of wages not paid and deductions unauthorized made
maintenance of wage register wage book, wage slip, publication of
wages and other terms of employment inspection and submission of
periodical returns and all other matters of a lime nature.
72
(f) The regulations shall be deemed to be a part of this contract and any
branch there shall be deemed to be branch of this contract.
2.4.1 Rules for the Protection of Health and Sanitary Arrangements for
Workers Employed by the Haryana Public Works Department or its
Contractors
The Contractor shall at his own expense provide or arrange for the provision of
foot wear for any labour doing cement mixing work (the Contractor has
undertaken to execute under this contract) to the satisfaction of the Engineer
– in – charge and on his failure to do so Government shall be entitled to
provide the same and recover the cost thereof from Contractor.
The Contractor shall submit by the 4th and 19th of every month to the
Executive Engineer a true statement showing in respect of the second half of
the proceeding month and the first half of the current month respectively (i)
the number of labourers employed by him on the work (ii) their working hours
(iii) the wages paid to them (iv) the accident that occurred during the said
forthright showing the circumstances under which they happened and the
extent of damage and injury caused by them and (v) the number of female
workers who have been allowed Maternity benefit according to clause 19-F and
the amount paid to them failing which the Contractor shall be liable to pay to
Government a sum not exceeding Rs. 50/- for each default or materially
incorrect statement. The decision of the Executive Engineer shall be final in
deducting from any bill due to the contractor the amount levied as fine.
Maternity benefit for female workers employed by the Contractor, leave and
pay during leave shall be regulated as follow: -
2. PAY (i) In case of delivery, leave pay during maternity leave will be at the
rate of the woman’s average daily earning calculated on the total wages
earned on the day when full time work was done during a period of 3
months immediately preceding the date of which she gives notice that she
excepts to be confined or at the rate of Rs. 12/- per day which ever is
greater.
4. Conditions for the grant of Maternity leave:- No Maternity leave benefit shall
be admissible to a woman unless she produces a certificate of confinement
and excepted delivery within 4 weeks proceeding the date on she proceeds
on leave.
(a) At every work place, there shall be maintained in readily accessible place
first aid appliances including an adequate supply of sterilized dressing and
cotton wools. The appliances shall be kept in good order and in large
workplaces it shall be placed under the charge of a responsible person
who shall be readily available during the working hours.
(b) All large work places where hospital facilities are not available within easy
distance of the work, first aid post shall be established and be run by a
trained compo under.
(c) Where large work places are remote from regular hospital an indoor ward
shall be provided with one bed for every 250 employees.
(d) Where large work places are situated in cities, towns in their suburbs and
no beds are considered necessary owing to the proximity of city or town
hospitals a suitable transport shall be provided to facilitate removal of
urgent cases to these hospitals.
(e) At other work place, the conveyance facilities such as car shall be kept
readily available to take injured or persons suddenly taken seriously ill, to
the nearest hospital.
74
These shall be provided within the precinct of every work places, Latrines and
Urinals in an accessible place and the accommodation separately for each of them
shall not be less than the following scales : -
No. of Sheds
In particulars cases the Executive Engineer shall have the powers to very the scale
where necessary.
If women are employed, separate latrines and urinals screamed from these for
men and marked in vernacular in conspicuous letters ‘FOR WOMEN ONLY’
shall be provided on the scale laid in rules, Similarly those for men shall be
marked ‘FOR MEN ONLY’ A poster showing the figures of a man and women
shall also be exhibited at the entrance of latrine for each sex. There shall be
adequate supply of water close to latrines.
Except in work places provided with flush latrines concerned with a water
borne sewerages systems all latrines shall be provided with receptacies order
earth system which shall be in working order and kept in strictly sanitary
conditions. The receptacles shall be tarried inside and outside at least once a
year.
2.4.6 CRECHE:
At every work place these shall be provided free of cost two suitable sheds one
main and the other for the use of labour. The height of the shelter shall not be
less than eleven feet from the floor level to the lowest part of the roof.
The huts shall be provided with suitable and sufficient opening for light and
ventilations. There shall be adequate provision of sweepers to keep the place
clean. There shall be two day attendant. Sanitary, utensils shall be provided to
the satisfaction of Health Office of the area concerned. The use of the hut shall
be restricted to children, their attendant and mothers of the children.
2.4.8 CANTEEN:
A cooked food canteens on a moderate scale shall be provided for the benefit of
workers where over it is considered expedient.
(i) Suitable scaffolds shall be provided for all workmen for all works that
cannot be safely done from a ladder or by other means.
1. be of sound material.
2. be of adequate strength having regard to the load and strains to
which they will be subjected and
3. be maintained in proper condition.
4. scaffolds shall not be overloaded and so far as practicable, the load
shall be evenly distributed.
76
(1) All necessary personal safety equipment shall be kept and available for
use of the persons employed on the site be maintained in condition
suitable for immediate use.
77
(2) The worker shall be required to use the equipment thus provided and the
employed shall take adequate steps to ensure proper use of the equipment
by these concerned.
(3) Adequate provision shall be made for prompt first aid treatment of all
injuries likely to be sustained during the course of the work.
3.0 Environment
a) The contractor shall take all reasonable steps to protect the environment
at and off the Site and to avoid damage or nuisance to persons or to
property of the public or others resulting from pollution, noise or other
causes arising as a consequence of his methods of operation.
b) During continuance of the contract, the contractor and his sub-
contractors shall abide at all times by all existing enactments on
environmental protection and rules made there under, regulations,
notifications and by laws of the State or Central Government or local
authorities and any other law, bye law, regulations that may be passed
for notification that may be issued in this respect in future by the State
or Central Government or the local authority.
3.1 Salient features of some of the major laws that are applicable are given below:
(i) The water (Prevention and Control of Pollution) Act 1974: This provides for
the prevention and control of water pollution and the maintaining and
restoring of wholesomeness of water. ‘Pollution’ means such
contamination of water or such alternation of physical, chemical or
biological properties of water or such discharge of any sewage or trade
effluent or of any other liquid, gaseous or solid substance into water
(whether directly or indirectly) as may, or is likely to, create a nuisance or
render such water harmful or injurious to public health or safety, or to
domestic, commercial, industrial, agricultural or other legitimate uses, or
to the life and health of animals or plants or of aquatic organisms.
(ii) The Air (Prevention and Control of Pollution) Act 1981: This provides for
prevention, control and abatement of air pollution. ‘Air Pollution’ means
the presence in the atmosphere of any ‘air pollutant’, which means any
solid, liquid, or gaseous substance (including noise) present in the
atmosphere in such concentration as may be or tend to be injurious to
human beings or other living creatures or plants or property or
environment.
iii) The Environment (Protection) Act 1986: This provides for the protection
and improvement of environment and for matters connected therewith,
and the prevention of hazards to human beings, other living creatures,
plants and property. ‘Environment’ includes water, air and land and the
interrelationship which exists among and between water, air and land,
and human beings, other living creatures, plants, micro-organism and
property.
78
iv) The Public Liability Insurance Act 1991: This provides for public liability
insurance for the purpose of providing immediate relief to the persons
affected by accident occurring while handling hazardous substances and
for matters connected herewith or incidental thereto. Hazardous
substance means any substance or preparation which is defined as
hazardous substance under the Environment (Protection) Act 1986, and
exceeding such quantity as may be specified by notification by the Central
Government.
4.1 The Contractor shall duly comply with the provisions of the Apprentices Act,
1961 (III of 1961), the rules made there under and the orders that may be
issued from time to time under the said Act and the said Rules and on his
failure or neglect to do so, he shall be subject to all liabilities and penalties
provided by the said Act and said Rules.
5.0 Amendment
The Haryana Government may, from time to time and to amend any of the
Labour or Pollution or other regulations, all amendments in any or all Acts
shall also be followed.
6.2 The Contractor shall not disclose details of Drawings furnished to him and
works on which he is engaged without the prior approval of the Employer in
writing. No photograph of the works or any part thereof or plant employed
thereon, except those permitted under clause 58.1, shall be taken or permitted
by the Contractor to be taken by any of his employees or any employees of his
sub-Contractors without the prior approval of the Employer in writing. No
photographs/ Video photography shall be published or otherwise circulated
without the approval of the Employer in writing.
6.3 The various works shall be done in line to line level and grade. The periodical
checking of these by the Engineer or Engineer’s representative shall not
absolve the Contractor of his responsibility regarding their accuracy. In case
of any deviation or discrepancy in line, level or grade at the meeting faces, the
Contractor shall make good the discrepancy at his own cost and without any
compensation for the additional work, if any involved. The Engineer shall
further have right, if need be, to rectify the discrepancies and recover the cost
from the Contractor.
6.4 All materials, before being incorporated in the work, shall be inspected by the
Engineer or his representative and, if necessary, tested before use. Any work,
on which such materials are used without approval and written permission of
the Engineer, is liable to be considered as defective and not acceptable.
79
6.5 The day to day and periodical tests, to be carried out on materials, mixes and
placed concrete, etc., shall be specified by the Engineer from time to time and
the Contractor shall allow all the facilities and cooperation towards collections
of samples etc. All labour for collecting samples for tests will be supplied by
the Contractor free of cost to the Engineer. Where testing facility is not
available in the field lab, the Engineer-in-Charge will get the test conducted
from some approved laboratory and testing and transportation charges shall
be borne by the Contractor in all such cases.
6.6 An authorized representative of the Contractor shall remain present at the
time when the samples are taken and shall authenticate the facts, if so
required. If the Contractor’s representative fails to be present as aforesaid, the
samples or cores, etc. as are taken by the Engineer or his representatives shall
be considered to be authentic. The Contractor will however be informed of the
details of such samples having been taken.
6.7 The materials, mixes and the cores shall be tested day to day and periodically
at the laboratory and the results given thereby shall be considered correct and
authentic by the Contractor. The Contractor shall be given access to all
operations and tests that may be carried out as aforesaid so that he may
satisfy himself regarding the procedure and method adopted. It shall then be
the Contractor’s responsibility to produce the works, materials and finished
item to the standards based on the laboratory design and tests.
7.0 The methods of sampling, testing, procedures and standards shall be laid
down by the Engineer from time to time.
8.0 The quality and quantity of material shall be the responsibility of the
Contractor, irrespective of the test results being good.
9. Arrangement of water and electric power, etc. required by the Contractor for
the work shall be made by him at his own cost. Engineer will, however,
recommend to the concerned State Electricity Utilities for providing the
connection and power to the Contractor, however, the Engineer will bear no
responsibility in this respect.
9.1 Contractor shall not be allowed to start the work till Engineer is satisfied with
the proper arrangement of good quality water for execution of work including
curing for 28 days. For this, the Contractor shall have to construct water
storage tanks of sufficient capacity. No extra payment shall be made on this
account. Any delay in execution of work due to non-availability of sufficient
water will be responsibility of the Contractor. In case water is used from
Government source, the contractor has to pay 0.5% of the cost of the part of
such work for which the water is used.
9.2 The Contractor shall not set fire to any standing jungle, trees, ‘bush’ wood or
grass without a written permission from the Engineer.
9.3 When such permission is given and also in all cases when destroying of dug
trees, bush wood, grass, etc. by fire the Contractor shall take necessary
measures to prevent such fire spreading to or otherwise damaging
surrounding property.
80
9.4 Any damage caused by the spreading of such fire, whether in or beyond limits
of the Engineer’s property shall be made good by the Contractor within a
period specified by the Engineer or in default the amount of the damage shall
be recovered by the Engineer from the Contractor’s bill as damages or
deducted by any other duly authorized officer from any sums that may be due
or become due from the Employer to the Contractor under the Contract or
otherwise.
9.5 The Contractor shall bear the expenses of defending any action of law
proceedings that may be brought by any person by injury sustained owing to
neglect of precautions to prevent the spread of fire and shall pay any damage,
and cost that may be awarded in consequence.
10. The Engineer may order the Contractor to suspend any work that may be
subject to damage by climatic conditions and no claim of the Contractor will
be entertained by the Engineer on this account.
11. A site order book shall be kept on the site of the work. As far as possible, all
orders, regarding the work are to be entered in this Book. All entries therein
shall be signed by the Engineer or his authorized representative and the
Contractor or his authorized representative. In important cases, the Engineer
will countersign the entries which have been made. The site order book shall
not be removed from the work site except with the written permission of the
Engineer and the Contractor or his representative shall be bound to take note
of all instructions and directions meant for the Contractor as entered in the
site order book without having to be called on separately to note them. The
authorized representative of the Engineer shall submit periodically copies of
the remarks in the site order book to the Engineer for record and to the
Contractor for submitting compliance report.
12. The Contractor shall confirm to the regulations, safety precautions,bye-laws or
any other statutory rules made by any local authority or by the Government
and shall protect and indemnify the Engineer against any claims or liability
arising from or based on the violations of any such laws, ordinance,
regulations, orders and decrees, etc.
13. The Contractor shall make his own arrangement for supply of all materials
including cement and steel. The Contractor shall be responsible for all
transportation and storage of the materials at site and shall bear all the
related costs. The Engineer shall be entitled, at any time, to inspect or
examine all such materials. The Contractor shall provide reasonable
assistance for inspection or examination as may be required.
14. The Contractor shall keep an accurate record for use of materials like cement
and steel used in the works in a manner prescribed by the Engineer.
15. Large stock of cement shall not be kept at the work site but only sufficient
quantities shall be kept to ensure continuity of the work. The Contractor shall
provide and maintain efficient water proof storage sheds for cement on the site
of work. It shall be stacked on the platform 30 cm above the floor level and
shall be covered with tarpaulin or any other impervious covering material in
81
order to protect the cement bags from moisture. The cement shall be neatly
stacked in an orderly manner so as to allow an easy access and count. The
arrangement of storage and utilization shall be such as to ensure the
utilization of cement in order of its arrival at the stores and the Contractor
shall maintain satisfactory records which would at any time show the date of
receipt and proposed utilization of cement lying in the stores at site.
16. The Contractor shall also construct and equip at his cost a working office with
electricity and water arrangement for his site Engineer.
17. The contractor shall also provide instruments for setting up field laboratory at
his own cost to site Engineer. No separate payment shall be made for this.
18. The Engineer shall have the right to deduct from the money due to Contractor
any sum required or estimated to be required for making good the loss
suffered by a worker or workers by reason of non-fulfillment of the condition of
Contract for the benefit of the workers vis-à-vis the Haryana Government, the
Contractor shall be primarily liable for all payments to be made under and
for the observance of the rules, regulations and labour law without prejudice
to his right to claim indemnity from his sub-Contractor.
19. Third Party Inspection –The Engineer-in-Charge may opt for 3rd party
inspection other than department in addition to inspection by department
staff, the 3rd party would inspect to ensure execution of work as per
specification/ agreement and also quality control i.e. draw of samples, testing
and other items etc. The report of the same would be submitted to Engineer-
in-Charge by the 3rd party. The agency/ contractor shall be bound by the
report of 3rd party inspection and shall take remedial measures for execution
of work as per specifications in agreement at their own cost. The cost of 3 rd
party inspection will be borne by the employer.
20. The Contractor shall confirm to the regulations, safety precautions,bye-laws or
any other statutory rules made by any local authority or by the Government
and shall protect and indemnify the Engineer against any claims or liability
arising from or based on the violations of any such laws, ordinance,
regulations, orders and decrees, etc.
21. The Contractor shall make his own arrangement for supply of all materials
including cement and steel. The Contractor shall be responsible for all
transportation and storage of the materials at site and shall bear all the
related costs. The Engineer shall be entitled, at any time, to inspect or
examine all such materials. The Contractor shall provide reasonable
assistance for inspection or examination as may be required.
22. The Contractor shall keep an accurate record for use of materials like cement
and steel used in the works in a manner prescribed by the Engineer.
23. Large stock of cement shall not be kept at the work site but only sufficient
quantities shall be kept to ensure continuity of the work. The Contractor shall
provide and maintain efficient water proof storage sheds for cement on the site
of work. It shall be stacked on the platform 30 cm above the floor level and
shall be covered with tarpaulin or any other impervious covering material in
82
order to protect the cement bags from moisture. The cement shall be neatly
stacked in an orderly manner so as to allow an easy access and count. The
arrangement of storage and utilization shall be such as to ensure the
utilization of cement in order of its arrival at the stores and the Contractor
shall maintain satisfactory records which would at any time show the date of
receipt and proposed utilization of cement lying in the stores at site.
24. The Engineer may order the Contractor to suspend any work that may be
subject to damage by climatic conditions and no claim of the Contractor will
be entertained by the Engineer on this account.
25. Cement contents–Actual cement required for the aggregates in concrete to be
used shall be determined by laboratory test while designing the concrete
mixes. If the cement contents of the design mix of that grade come less than
the provision of cement contents provided in the Haryana Scheduled of Rates,
(with latest amendments) due to durability conditions, the cement contents as
provided in the Haryana Schedule of Rates shall be used and no extra
payment on this account shall be made to the contractor. No extra amount
over and above the minimum cement content as provided in the Haryana
Schedule of Rates shall be paid.
Note: - Each department may specify any other special conditions of contract
as per requirement of the work
83
vi) The periodicity of routine maintenance activities shall be as follows, this is for
guidance only, however, road is to be maintained in service able condition all the
time and payment is performance based, as per performance evaluation and marks
obtained.
84
Name of Frequency PI
Sr. Item/ Activities of
operation Plain & Hilly
No.
in a year Rolling Terrain
Terrain
1. Maintenance of As and
Bituminous surface road when
and/ or gravel road required
and/or WBM road
including filling potholes
and patch repairs etc. As 50 40
per clause 1904, 1906 of
the MoRD Specifications (
As per Annexure- 14.10
of Operation manual)
2. Restoration o rain cuts Once
and dressing of side generally
slopes/berms as per after rains
clause 1902 of the (In case of
Specification (As per areas having 10 5
Annexure- 14.10 of rainfall
Operation manual) more than
1500 mm
per year, as
and when
required).
3. Making up of As and
berms/shoulders as when 20 20
per clause1903 o the ( required
As per Annexure-
14.10 of Operation
manual)
4. Maintenance of drains Twice (In
as per clause 1907 of case of hill
the Specifications. (As roads as
per Annexure-14.10 of and when 3 8
Operation manual) required
6. Maintenance of Maintenance e as
guard rails and and when 1 1
parapet rails as per required.
clause 1911 of the
MoRD Repairing once in
Specifications ( As a year
per Annexure-
14.10of
Operation manual)
7. Maintenance of road Maintenance as
signs, speed and when 2 4
breakers, standing required.
trees adjacent to
Repairing once in
road wherever
required as per every two years
clause 1910 of the
MoRD
Specifications (As
per Annexure-
14.10 of
Operation manual).
8. Maintenance of Maintenance as
200 m and kilo and when 2 2
meter stones as per required.
clause 1912 of the Repairing once in
MoRD a year
Specifications (As
per Annexure-
14.10 of Operation
manual).
9. Cutting of Once generally
branches of trees, after rains (In 3 5
shrubs and case of areas
trimming of having rainfall
grass and weeds more than 1500
etc. as per clause mm per year,
1914 of the MoRD as and when
Specifications (As required.
per Annexure-14.10
of Operation
manual).
10. White washing Once in a year 2 3
parapet of Works
including CD (As per
Annexure-14.10
of Operation manual)
11. Painting of Twice in a year 2 1
guard stones
88
(i) Appendix 11.3, ibid, covers the special problems of Road Maintenance in
Heavy Rainfall
/ Snow fall areas.
(ii) Appendix 11.4, ibid, explains the nature of duties in maintenance of shoulders,
drainage structures and cause ways.
8. The following documents also form part of the Undertakings of the [Cl.2.3
Contract : bidder if any (11,12)]
14. a. The period for submission of the programme for approval of [Cl.26.1]
Engineer shall be 15 days from the issue of Letter of Acceptance
Price adjustment for increase or decrease in the cost of bitumen shall be paid
as follows:
That the rate of bitumen/ emulsion at the refinery on the date of close for
financial bidding shall be considered as base rate if during execution of the works,
the rate of bitumen/ emulsion increase or decrease at refinery, the difference in cost
shall be paid/ recouped from the contractor in the bill, subject to the following
conditions:-
(A) The contractor shall submit original bill/ voucher of the refinery while claiming
the payment for the work done. The bill/ voucher should pertain to the period
of original contractual time limit and should correspond with the progress of
work. No extra payment due to increase in rate of bitumen / emulsion will be
paid if the original bill/ voucher are not submitted by the agency.
(C) After approval of tender, the contractor shall submit the work programme for
execution of work and get it approved from the Engineer-in-Charge in the time
limit prescribed in the tender document. The increase in rates of bitumen,
emulsion shall only be paid if the bitumen work is carried out within the
prescribed period as per approved work programme.
(D) Only actual difference of rates of Bitumen will be payable / deductable to the
contractor. No overhead charges and contractor profit etc. are to be added /
deleted, no tender premium is to be added / deleted.”
(E) The contractor can arrange the bitumen from any of the refinery or import the
same subject to the condition that the quality of bitumen is as per the
requirement of contract and specifications. Regarding payment of price
91
variation of bitumen as per the agreement, that the escalation de-escalation will
be paid on the basis of lesser cost implication to Department / Government on
consideration of the difference in rates as given below subject to financial
regularity and other terms and conditions of agreement :-
(a) Prevailing rates of IOC refineries at Panipat at the time of tender and at the
time of purchase of bitumen.
(b) Prevailing rates at the source from which the bitumen is purchased by the
contractual agency at the time of tender.
(b) When escalation is due to increase in rates of bitumen is due to agency, then
lesser of the difference in rates of IOC Panipat and that of private refinery,
from whom bitumen was purchased, shall be considered.
15 (a) (ii) Adjustment for Grey Cement (OPC/PPC) and, Steel for
reinforcement and structural members (index for MS Long Products) :
(A) If after submission of the, the price of Grey Cement (OPC/PPC)or Steel for
reinforcement and structural members (index for MS Long Products)
incorporated in the works (not being a material supplied form the Engineer-in-
Charge’s Store) increase (s) beyond the price (s) prevailing at the time of the
last stipulated date for financial bid closing of tenders (including extensions, if
any) for the work, then the amount of the contract shall accordingly be varied
and provided further that any such increase shall not be payable if such
increase has become operative after the stipulated date of completion of work
in question.
(B) If after submission of the, the price of Grey Cement (OPC/PPC) / or Steel for
reinforcement and structural members (index for MS Long Products)
incorporated in the works (not being a material supplied form the Engineer-in-
Charge’s Store) is decreased, Govt. shall in respect of these materials
incorporated in the works (not being materials supplied from the Engineer-in-
Stores) be entitled to deduct from the dues of the contractor such amount as
shall be equivalent to the difference between the prices of Grey Cement
(OPC/PPC) as prevailed at the time of last stipulated date for receipt of tenders
including extensions if any for the work and the prices of these materials on
the coming into force of such base price of Grey Cement (OPC/PPC) and
issued under authority of Engineer-in-Chief, Haryana PWD B&R, Chandigarh.
92
(C) It is further clarified that the decrease in the prices of Grey Cement (OPC/PPC)
/ or Steel for reinforcement and structural members (index for MS Long
Products)and shall be deducted from the dues of the contractor if such
decrease has become operative after the stipulated date of completion of work
in question and increase shall not be payable if such increase shall not be
payable if such increase has become operative after the stipulated date of
completion of work in question.
(D) The increase/ decrease in prices shall be determined by the All India
Wholesale Prices Indices for Grey Cement (OPC/PPC) / or Steel for
reinforcement and structural members (index for MS Long Products)as
published by the Economic Advisor to Government of India, Ministry of
Commerce and Industry) and base price for Grey Cement (OPC/PPC) / or
Steel for reinforcement and structural members (index for MS Long
Products)as mentioned in the Bid Document or if not mentioned then asissued
under authority of Engineer-in-Chief, Haryana PWD B&R, Br. Chandigarh as
valid on the last stipulated date of receipt of tender, including extension if any
and for the period under consideration.
Qc= Quantity of Grey Cement (OPC/PPC) used in the works since previous
bill.
CI0= All India wholesale price index for Grey Cement (OPC/PPC) as
published by the Economic Advisor to Government of India, Ministry of
Industry and Commerce as valid on the last stipulated date of receipt of
tenders including extensions if any.
C1= All India wholesale price index for Grey Cement (OPC/PPC) for period
consideration as published by the Economic Advisor to Government of
India, Ministry of Industry and Commerce
93
Vs=Ps x Qs x SI-S1o
S1o
Vs = Variation in cost of Steel (MS Long Products) i.e. increase or decrease in the
amount in rupees in the amount in rupees to be paid or recovered.
Ps = Base price of Steel (MS Long Products), as mentioned in the Bid Document or
if not mentioned then as issued under authority of Engineer-in-Chief, Haryana
PWD B&R Br., Chandigarh at the time of the last stipulated date of receipt of
tender including extensions, if any.
Qs= Quantity of Steel (MS Long Products) paid either by way of secured advance or
used in the works since previous bill (Whichever is earlier).
S1o= All India wholesale Price Index for Steel (MS Long Products) for the period
under consideration as published by Economic Advisor to Government of
India, Ministry of Industry and Commerce as valid on the last stipulated date
of receipt of tenders including extensions, if any.
S1= All India Wholesale Price Index for Steel (MS Long Products) for the period
under consideration as published by Economic Advisor to Government of
India, Ministry of Industry and Commerce.
Base rate of Cement (OPC/PPC) and Steel (MS Long Products)
Grey Cement (OPC/PPC) : Rs. 4940/- per MT excluding taxes..
Steel (MS Long Products): Rs. 50000/- per MT excluding Taxes.
No other increase/decrease in prices is permissible.
15 (a) (iii) Adjustment of POL (fuel and lubricant) component
Price adjustment for increase or decrease in the cost of POL (fuel and
lubricant) shall be paid in accordance with the followings formula:
Vf= 0.85xPf/100xRx(Fl-Fo)/Fo
Vf =increase or decrease in the cost of work during the month under
consideration due to changes in rates for fuel and lubricants.
Fo= The all India wholesale price index for ‘Fuel and Power’ for the calendar
month 28 days preceding the closing date of bids as published by the
Office of Economic Advisor, Government of India, Ministry of Commerce
and Industry, Department of Industrial Policy and Promotion with
website www.eaindustry.nic.in
F1 =The all India average wholesale price index for ‘Fuel and Power’ for the
month under consideration as published by Office of Economic Advisor,
Government of India, Ministry of Commerce and Industry, Department of
Industrial Policy and Promotion with website as www.eaindustry.nic.in
Pf = 5.
R = Value of work executed during the period.
94
16. The proportion of payments retained (Retention Money) shall be 6% from each
bill subject to a maximum of 5% of final contract price.
[CI.48]
17. (a) Milestones to be achieved during the contract period
Milestone dates:
19 The period for setting up a field laboratory with the prescribed [Cl.31.1]
equipment is 28 days from the date of notice to start work
97
20. The Defect Liability-cum-Maintenance Period is five years from [Cl. 56]
the date of completion.
21. The date by which “as-built” drawings (in scale as directed) in 2 sets [Cl.58.2]
are required is within 28 days of issue of certificate of completion of
whole or section of the work, as the case may be.
22. The amount to be withheld for failing to supply “as-built” drawings [Cl.58.2]
by the date required is Rs. 0.5% of agreement amount.
23. The following events shall also be fundamental breach of Contract: [Cl.59.2 (i)]
(i) The Contractor has contravened Clause 7.1 or Clause 9of Part I
General Conditions of Contract
24. The percentage to apply to the value of the work not completed [Cl.60.1(i)]
representing the Employer’s additional cost for completing the
Works shall be 20 (Twenty)percent).
98
Section 4-A
Detailed Scope of Work
Section 4-B
Technical Specifications
A. The work shall be carried out as per MoRT&H and PWD Specifications and
also with latest applicable IRC codes.
The contractor will maintain the existing road from start of contract to the
completion of contract by filling potholes duly covered with bituminous
material to keep the road in traffic worthy condition. This is incidental to main
work and nothing extra shall be payable on this account.
(a) “Bitumen and Bitumen Grade CRMB, wherever to be used in the work,
will be purchased from the refineries only.”
(b) An undertaking should be taken from the agency during the payment of
every bill that:
(c) For controlling the quantity of mixed material the following procedure be
adopted:
(i)The contractor shall provide, install, maintain and operate at his own
cost in good working condition a weigh bridge of suitable capacity at
site of the hot mix plant under the direction of Engineer or his
representative.
(ii) Each truck before loading of the mix shall be weighted on the Weigh
Bridge and its weight shall be recorded in the measurement book
under the signature of authorized representative of the contractor and
of the Engineer.
(iii) The truck shall be again weighed on the weight bridge after loading of
the mix and its weight recorded as per prescribed performa.
The details of mixed material be compiled as per following procedure:-
i) A slip should be issued by JE at the plant site as per Annexure-II.
ii) The slip book should be in three colors i.e. Pink, Yellow and White.
iii) White slip shall be retained at plant site, Yellow & Pink shall be sent to
work site. Yellow slip shall be returned to plant site JE duly signed by
JE & SDE of site in-charge and Pink slip shall be retained by JE work
site.
102
Annexure-I
Annexure-II
SLIP
Signature of Signature of
Signature of
JE at Hot Mix Plant. SDE at site of work. JE
at site of
(d) The agency to whom the work is allotted will have to produce original vouchers
for all quantities in lieu of purchase of bitumen, steel, and cement from the
original manufacturer or other authorized dealers/distributors to the entire
satisfaction of the Engineer for ascertaining the genuineness of material.
Attested copy of voucher will have to be submitted along with bills.
(e) The Job mix formula will be got tested from CRRI New Delhi, NIT Kurukshetra,
PEC, Chd., TTI, Chandigarh, Shriram Institute, Delhi and testing charges will
be borne by the agency. Nothing shall be paid on this account.
(f) When the work under one agreement is being executed, the contractor shall
not undertake any other work from same hot mix plant without written
permission of the Engineer and shall also make separate arrangement of
bitumen for that work.
(g) Before carrying out bituminous work, coating & stripping of bitumen aggregate
mix is to be performed in accordance with IS-6241.If coating and stripping of
bitumen aggregate mix is less than 95%, anti-stripping agent will be used by
103
D. ADDITIONAL CONDITIONS
(i) Before laying any construction layer of GSB, sub grade or base course, earth
work on berms, if it is to be done by the agency against this agreement, should
be completed in all respect simultaneously. Before taking work of any next
layer, earth work on berms should be completed. Payment of any layer will be
released only when earth work on berms are completed.
(ii) No compensation for any damages caused to the earthwork by rains, floods or
any other natural calamities shall be paid to the contractor. The contractor
shall have to make good all such damages at his own cost as per direction of
Engineer.
(iii) The final payment of the tenderer will not be paid until and unless he
furnishes to the satisfaction of the Engineer, proof that the price of earth used
for the work having been fully paid to the owner of the land from which the
earth was removed by the contractor from his (owner) land for the work and to
indemnify against all the losses, damages, cost of land expenses which the
Govt. suffer or incur as a result of such claim.
(iv) In case of embankment with Fly Ash, the contractor shall take special care to
keep the surface wet at all times so that the Fly Ash does not get mixed up
with the atmosphere thus causing poor visibility besides health hazards. If the
contractor does not comply with this provision, the Engineer shall make
necessary arrangement after giving appropriate notice to the contractor, for
keeping the fly ash surface wet and the contractor shall pay the expenses
incurred on demand or otherwise the same shall be recovered by Engineer
from bills due to the contractor.
E. GENERAL CONDITIONS
(i) Correction of defects:- The Engineer shall give notice to the contractor of any
defects before the end of Defect Liability-cum-Maintenance Period which
begins at completion as per definition. The Defect Liability-cum-Maintenance
Period shall be extended as long as defects remain to be corrected. Every time
notice of a defect is given, the contractor shall correct the notice defect within
the length of time specified by the Engineer’s notice. If the contractor has not
corrected a defect within the time specified in Engineer’s notice, the Engineer
will assess the cost of having the defect corrected and the contractor will pay
the amount.
104
(ii) The contractor shall have to provide a fields laboratory fully equipped at work
site and hot mix plant for conducting all the relevant tests mentioned in the
MORT&H specification subject to the approval of the Engineer or his
representative. The record of such tests is to be maintained in proper register
duly singed by the contractor or his representatives, which will become the
property of the department. The contractor will bear all the running expenses
for conducting such tests. All the tests will be carried in the presence of
S.D.E.-in-charge and J.E.-in-charge.
(iii) The quality control test will also be done by the department and the material
for such test will be supplied by the contractor free of cost. In case the
material is not found upto the requirement, the same will be rejected.
(iv) Various quality control operation will be maintained as per Clause No. 901,
902, 903 of MORT&H (Road Wing) specification (5th revision) of latest edition
and as per instructions issued by MORT&H from time to time upto date.
(v) Contractor shall provide suitable measuring arrangement and leveling
instruments of latest quality as approved by Engineer at the site of work.
(vi) No extra payment on account of quality control measures shall be paid to the
contractor.
(vii) The Engineer at his description can get any type and Nos. of tests carried out
from any other approved laboratory for his satisfaction for which all the
expenses incurred would be borne by the agency. The result so obtained from
the laboratory would be acceptable/binding to the agency.
(viii) The contractor shall be required to provide all such materials/equipment at
site to conduct fields tests and to ensure that the quality of material/item
shall be according to the prescribed specification and no payment of any kind
for such tests shall be made to him. In case the material/item is not found
upto mark, the same will be rejected.
(ix) For cement, bitumen, mild steel and similar other material, the essential tests
are to be carried out at the manufactures plant or at laboratories other than
the site laboratory. The cost of samples, testing and furnishing of test
certificates shall be borne by the contractor. He shall also furnish the test
certificates to the Engineer.
(x) Contractor has to submit the bills (Running as well as final bill) for payment
alongwith quality control test results conducted as per frequency specified in
MORT&H specification. No payment will be made without test results.
(xi) OPC cement duly ISI marked of 43 grade such as JK, Lakshmi, L&T, A.C.C,
Shree and Birla or as approved by Engineer should be arranged by the
contractor.
(xii) TMT Steel Fe-500 duly ISI marked of reputed brand such as of RINL/TISCO
/SAIL/JSW/Jindal Panther/ Electrosteel etc. shall be arranged by the
contractor.
105
(xiii) Before executing the work of drain, proper drawing depicting L-section and X-
section of drain alongwith is proper disposal will be got approved by S.E. in
writing. All culverts and bridges will be constructed as per IRC-SP-13 and also
approved by the SE-in-Charge.
(xiv) Agency will have to submit to the Engineer, the original bills of cement and
steel etc. in token of proof of purchase of material alongwith quality control
test certificate of manufacturer failing which no payment shall be released.
(xv) Agency will get the material tested from any approved laboratory as directed
and whenever required by Engineer and all liability of testing shall be borne by
the agency.
(xvi) The rates are inclusive of cost of traffic management during construction,
Contractor shall provide road signages, boards, gunny bags, sheet etc. for
safety of traffic during construction period which will be incidental to work.
Nothing extra shall be paid on this account.
(xvii) The contractor will supply bills for purchase of RCC Hume Pipes clearly
indicating name of manufacturer, date of manufacturing, Lot no. etc. These
details must painted on the RCC Hume Pipe. The pipe should be ISI marked.
The manufacturer should give proof for validity of ISI license. In case of non
supply of bills, no payment will be released.
(xviii) The contractor himself will arrange all the material such as bitumen, cement,
steel, bricks etc. at his own cost.
(xix) The riding quality of reach after giving treatment of wearing coat will not have
roughness more than 2000mm/km.
(xx) The contractor shall submit the proposal of widening of existing stretch to get
the centerline decided before commencement of work from Engineer.
(xxi) For work of embankment, sub grade & pavement, construction of subsequent
layer of same or other material over the finished layer shall be done after
obtaining written permission from the Engineer. Similar written permission
from the Engineer shall be obtained in respect of all other items of work prior
to proceeding with the next stage of construction.
(xxii) Before start of the work contractor will get his machinery inspected and
approved from the Engineer.
(xxiii) If at any stage, panel of concrete pavement develops cracks/disintegration
during Defect Liability-cum-Maintenance Period, the whole panel will be
changed by contractor at his own cost and nothing extra shall be paid.
(xxiv) 80% material from scarification shall be credited & used at site in items as
mentioned in the BOQ.
(xxv) The pits on account of de-forestation of trees / roots, shall be filled with sand
and compacted to the specification by the agency at his own cost in the entire
length. No payment shall be made and the cost is incidental to work.
G. TECHNICAL CONDITIONS
(a) A register in prescribed form showing day to day receipt, consumption and
balance of cement at site of work will be maintained at the work/test site by
the department, which shall invariably be signed by the contractor or his
authorized representative in token of its correctness.
ii. Record of test for controlling the quality of concrete such as grading,
analysis of Aggregates, silt content of fine aggregates, water content of fine
aggregates, water content of coarse aggregate etc.
iii. Record of test results on samples of mild steel. For steel, high tensile steel.
iv. Record of cement tests for different consignment/batches/sources of
supply.
v. C.P.M/PERT chart, original and as revised/updated.
Technical Specifications
For
Bridge Works
109
1.5 Some stipulations of relevant codes for some of the items are mentioned
in this tender documents. These stipulations are only for guidance. The
work shall be executed as per relevant codes.
2.1. The depth of bored pile shall be as per design and drawing.
2.2. Construction of bored pile foundations shall be strictly in accordance
with the stipulations made in the building digest CBRI India 56 for
bored piles for foundations and IS: 2911/1979 part-I to 4. Wherever
the tilt of the piles exceeds 2% or the piles shifts by more than what is
specified, area will have to be increased and also additional
reinforcement will have to be added and expenditure involved including
cost of cement and steel shall be borne by the contractor.
2.3. The rates quoted by the contractor shall be over all including rate, for
boring through any type of road surface all type of soil whatsoever, use
of special liner casing if required, use of any type of material, machinery
also including all royalties, all taxes (but excluding GST) etc.Nothing
extra will be paid on any account whatsoever.
3.3. It may be necessary to make provision for holes/ grooves in the form
work to house the various services, for which neither any extra payment
shall be made to the contractor/s for making these provisions nor any
deduction shall be made on a/c of any saving in RCC/PSC work due to
these provision.
3.4. Wherever chamfer or rounded corners are mentioned in the drawing
formwork should be such that no chiseling/cutting is required.
3.5. The surface of formwork shall be clear, smooth and free of cement
mortar etc.
3.6. The Contractor shall give the Engineer In-charge due notice before
placing any concrete in the forms to permit him to inspect and accept
the form work and forms as to their strength, alignment and general
fitness but such inspection shall not relieve the contractor of his
responsibility for safety of works, men, machinery, materials and for
result obtained.
4.2 While fixing the time for removal of form work, due consideration shall
be given to the local conditions, character of the structure, the weather
and the other conditions that influence the setting of concrete and of
the material used in the mix.
4.3 The period shall be suitably increased in case of temperature lower than
25 degree Celsius and for any other conditions tending to delay the
setting of concrete.
4.4 These field operation are controlled by strength tests of concrete, the
removal of the load supporting arrangements of soffit may commence
when concrete has attained strength equal to twice the stress to which
the concrete will be subjected to, at the time of striking props including
the effect of any further additions of loads. When field operations are
not controlled by strength test of the concrete the vertical forms of
beams columns & walls may be removed as per orders of the Engineer
In-charge.
112
4.5 All formwork shall be removed without causing any damage to the
concrete. Centering shall be gradually and uniformly lowered in such a
manner as to avoid any shock or vibrations. Supports shall be removed
in such a manner as to permit concrete to take stress due to its own
weight uniformly and gradually. Where internal metal ties are
permitted, their removable parts shall be extracted without causing any
damage to the concrete and the remaining holes filled with mortar. No
permanently embedded metal parts shall have less than 40mm cover to
the finished concrete surfaces, where it is intended to re-use released
form work, it shall be cleaned and make good to the satisfaction of
Engineer-in-charge.
5. REINFORCEMENT:
5.1 Reinforcement may be TMT (Fe500) as per the drawings and confirming
to the latest ISI/IRC codes. Steel will be procured from TISCO/Rastriya
Ispat Nigam Limited/SAIL/Jindal Steel and Power Ltd. (Jindal Panther),
JSW Steel ltd, Electro Steel Steels Ltd(V-XEGA) and M/s Super Shakti.
5.2 Before use, contractor’s will be required to obtain test certificate for the
quality of reinforcement used, at his/their own cost form the
laboratory/institute, approved by the Engineer-in charge.
5.3 Contractor will ensure that before fixing reinforcement, bars are cleaned
with dry gunny bags to remove the light rust or other impurities, if any.
5.6 Nothing extra will be paid for overlaps and wastage of steel.
5.8 Payment for the steel reinforcement shall be made on the basis of
standard unit weights as per approved drawings and nothing extra will
be paid for overlaps and wastage of steel involved in cutting the bars to
their required sizes. Nothing extra will be paid for over weight steel and
no deduction will be made for under weight steel within the limit of
tolerances permitted as per IS 1786-1985.
5.9 Steel having unit weights per meter not falling within the tolerances
specified in above IS code shall not be accepted.
6. CEMENT:
6.3 Quality test certificate for cement as per IS-4031 Code shall be furnished
by the contractor before use of cement supplied.
6.4 Cement for use in works, shall be procured by the contractor from the
main producers or their authorised dealers only.
6.5 Cement older than 3 months from the date of manufacture as marked
on the bags shall not be accepted. Cement bags preferably in paper bag
packing should bear the following marking:-
7.0 Engineer in Charge may also take samples during the course of
execution of works and get the cement tested to ascertain its conformity
to the relevant IS specifications at contractor/s cost before a particular
lot is put to use. Frequency of testing shall be as prescribed by the
relevant IS code. Following test interalia shall be carried out.
i) Fineness
ii) Compressive strength
iii) Initial and final setting time
iv) Consistency
v) Soundness.
7.1 In case samples tested do not pass quality tests conducted, the entire
batch of cement supplied shall be rejected and returned to the
contractor/s. No payment for such cement shall be made to the
contractor.
7.2 For storage of cement, the contractor shall have to construct a
temporary Godown of adequate capacity at his own cost. The contractor
shall bring the cement to the site of work only on written instructions
from representative of Engineer. It will be obligatory on the part of the
contractor to get every consignment/truck of cement weighed in the
presence of Engineer or his representative and supply the original copy
of weight slip alongwith consignment. The representative of Engineer
will verify the weight of cement brought to the site of work and return
one verified weigh slip to the contractor after the same is stacked inside
the cement Godown under his supervision.
7.3 The record of cement brought to the site of work, daily consumption,
daily opening balance and closing balance shall be maintained at the
site jointly by the representative of Engineer of work and contractor/s
or his/ their authorized representative. For this purpose, 2 sets of
registers duly reconciled and signed by the contractor/s and the
representative of Engineer of work certifying the opening balance,
consumption, closing balance should be maintained. One register each
shall be kept in the custody of representative of Engineer of work and
contractor or his authorized representative.
115
7.4 The contractor shall be the custodian of cement Godown and shall keep
the Godown under his lock and key to ensure safe custody of cement.
The contractor shall ensure that the cement once brought to the site
and accounted shall be used at the site only and shall not be taken
away from site for any other purpose.
7.5 The contractor shall make the cement Godown available for inspection
alongwith connected record to the site Engineer or his representative as
and when required.
7.6 The contractor shall ensure that after completion of the work and or
termination of the contract for any reason whatsoever, the temporary
cement Godown shall be dismantled and all dismantled material
/debris shall be removed and the clear site shall be handed over back to
Department. All the released material shall be the property of the
contractor/s and no payment shall be made by the Department for
dismantling etc.
7.7 Tolerance requirements for the mass of cement
(i) Cement supplied one time will be taken as forming one batch.
The number of bags taken for sample from each batch shall be
as under:-
Sr. No. Batch Size Sample Size
1. 100 to 150 20
2. 151 to 280 32
3. 281 to 500 50
4. 501 to 1200 80
5. 1201 to 3200 125
6. 3201 and above 200
(iii) The number of bags in sample showing a minus error greater than 2
percent of the specified net mass (50 kg) shall be not more than 5
percent of bags in the sample. Also the minus error in none of such
bags in the sample shall exceed 4 percent of the specified net mass of
cement in the bags. In case, the minus error exceeds the percentages
herein specified, the entire batch of cement samples shall be rejected.
7.9 Cement shall be stored in such a manner as to permit easy access for
proper inspection. Cement should be stacked not more than ten layers
high to prevent bursting of bags in the bottom layers and formation of
clods. The stacks of cement bags shall be covered with tarpaulin during
monsoons so as to obviate the possibility of deterioration of cement by
moisture in the atmosphere. Cement that is set or partially set is not to
be used.
9. WATER:
9.0 The contractor shall be responsible for the arrangements to get the
supply of water necessary for the works at his own cost and rates
quoted shall also include the cost of water or any other arrangements
required to be made for procuring water and leading/ transporting and
carrying water to the site of the work irrespective of the distance from
the source of water. The water shall, however, conform to I.S-456 If
water as per prescription of IS-456 is not available then contractor will
have to install RO Plant free of cost to obtain the water as per
specification. No extra payment for the same admissible at any point of
time during the execution or defect liability period later on.
10. CONCRETING: -
10.1 The design mix concrete of strength as indicated as per approved
drawings shall be used for foundation, sub-structure and super-
structure of the bridge. The contractor will submit design mix along
with the calculations to the Engineer-in-Charge. The design mix will
have to be got approved from the Engineer In-Charge before use in the
construction.
10.2 The concrete shall be mixed properly in mechanical mixer and shall be
of proper consistency. The proper consistency shall be determined by
Engineer-In charge through tests that shall be carried out by the
contractor/s. The Concreting shall be commenced only after the
Engineer-in charge has inspected the shuttering, the placement of
reinforcement and passed the same. Cost of concrete moulds and other
test shall be borne by the contractor/s.
10.3 The concrete shall be compacted immediately after placing by means of
mechanical vibrator of approved quality.
10.4 The mixing time of concrete in mixer will be decided by the Engineer,
depending upon the type of work and strength of concrete.
10.5 The contractor shall make adequate arrangements for casting of
necessary numbers of cubes and cure and finish them as per direction
of Engineer.
10.6 The contractor shall establish laboratory in field and provide the
necessary equipments to carryout all preliminary test and working out
the grading and proportioning of aggregate, assessing the moisture
content, casting and testing of cubes etc., in order to obtain and
maintain uniform quality of work confirming to codal practices.
118
10.7 The exposed surface of plain, R.C.C/P.S.C. work shall be rubbed with
Carborandum stone and rendered smooth if necessary with cement to
leave surface smooth and even. Nothing extra will paid on this account.
Cement for the same will be arranged by the contractor/s at his own
cost and no payment shall be made.
10.8 The controlled concrete ingredients should be weigh batched in
approved type weigh- batcher.
10.9 The slump of the approved trial mix shall be measured and this slump
shall not be exceeded through out all the batches of concrete made from
the same materials mixed in the same proportion as the trial mixes and
used in those parts of the work as instructed.
10.10 Concreting in hot weather: Hot weather is defined as any combination
of high air temperature, low relative humidity, and wind velocity tending
to impair the quality and properties of fresh or hardened concrete. In
hot weather, the contractor shall ensure that the temperature of the
concrete at the time of placing does not exceed 30 degree C and that the
maximum internal temperature attained during setting does not exceed
75 degree C.
The contractor shall provide the effective measures suggested by the
Engineer Incharge to protect the concrete from the effects of high
temperatures. No concreting in hot weather shall be put in hand until
the proposed measures have been approved by the Engineer.
10.11 Concreting in cold weather: Cold weather is defined as the situation
existing at the work where either or both of the following conditions
exist:
i) The air temperature at the time considered is below 5 degree C.
ii) The mean daily air temperature over three or more successive
days has dropped below 5 degree C.
On no account may concrete be placed in contact with frozen ground or
for work in contact with ice, snow or frost on the ground or on form
work of reinforced concrete shall not be made with frozen materials,
Concreting may proceed in cold weather provided special precautions
are taken to ensure that the surface temperature of the concrete at the
time of placing is not less than 5 degree C.
The contractor shall provide the effective measures suggested by the
Engineer to take to protect the concrete from the effects of low
temperatures and with details of the methods he proposes to use to
assess the correct timing at which such protection may be removed. No
concreting in cold weather shall be put in hand until the proposed
measures have been approved by the Engineer.
119
10.13 MEASUREMENTS:
10.13.1 All work will be paid for at the tendered rates on the basis of actual
measurements taken at site. No cognizance will be taken for heights
and thickness of structural members over those shown in the plan.
10.14 FOUNDATIONS:
10.14.1 The bed of open foundations should be made horizontal and sides
neatly dressed and in all cases got approved by the Engineer before
concrete is laid. If foundations are laid in sandy or clay soil, the
variation in levels should not be more than 15mm but in case it is
laid on soft rock/boulder studded soil larger variation may be
120
10.14.2 It is expected that design of open foundation will suit in all the
bridges. Payment for excavation of foundation of all the structures
including foundation of pucca side and catch water drains (embedded
concrete and masonry portion) and floor of bridges will be made as
per relevant item. It will be applicable to all types of soil including all
lead and lift, including excavation water requiring pumping and
bailing out of water including back filling in 15cm layers with proper
watering & ramming. The payment for excavation of foundation will
be as per MORT&H/PWD Standard Specification for material and
works irrespective of the fact that excavation has been done in slopes
and there have been slips etc. or any shoring or shuttering has been
done. The surplus earthwork from foundation (quantity of excavation
minus quantity of refilling of earth in foundation limited to vertical
dimension) should compulsorily be lead to the adjoining filling
without any extra payment for loading, unloading, crossing of
nallaha/streams, rehandling, dressing the filling irrespective of facts
whether surplus earthwork from foundations has been utilized or not.
No cognizance for any boulder more than 15 kg and 15 cm in
dimension will be taken for purpose of any claim and contractor is
free to take away such boulders free of cost after paying due royalty
etc. to State Govt. if any.
The space between the side of the foundation trenches and the
masonry/concrete is to be filled with the excavated material well
rammed in layers not exceeding 15 cm each layer being watered,
rammed and consolidated before the succeeding one is laid. Earth
shall be rammed with iron rammers where feasible and with the butt
ends of crow bars where rammers cannot be used. Earth used for
filling shall be free from salts organic or other foreign matter. All
clods of earth shall be broken or removed.
The foundation of the bridge shall be of well/pile foundations as per
drawing supplied by the Department.
121
The contractor shall give notice to the Engineer when and as soon as
the excavation of any portion of the site for obtaining foundations or
bottom whether above or below water has reached the depth and
width shown on the drawings. The contractor shall also give further
notice to the Engineer whenever any foundation or bottom is ready
for inspection and whenever it is necessary to cover up any work in
respect of which previous inspection is desired by the Engineer so
that the Engineer may inspect the same before it is covered up. No
foundations or bottom, of work shall be covered up or filled or built
upon without the previous consent of the Engineer. In default of
such notice and consent aforesaid the foundation or bottom of work
shall on the order of the Engineer be uncovered and any filling put in
or work built thereon be removed or pulled down by the contractor at
his own cost.
12.0 FINISHING
12.1 No plastering shall be done over the exposed surface of RCC/PSC
work, special care should be taken in centering and shuttering and
casting to ensure good finish, wherever necessary rendering in 1:3 (1
cement: 3 coarse sand) shall be done to the satisfaction of Engineer-
In-Charge. Nozzle and form vibrators are to be used for RCC/PSC
work.
122
14.1 The contractor shall set up a field laboratory his own at work site
which should be open for use and inspection by the PWD B&R
Department at any time. The laboratory shall be equipped with
necessary equipments to carry out the various tests such as sieve
analysis, compression tests on cubes, slump tests, workability test
etc. on aggregate, cement, water and concrete required for acquiring
the required quality and standard conforming to codal provisions and
Special specifications.
14.2 All the pressures gauges, machines, equipments and other measuring
and testing equipments of the laboratory shall be got
checked/calibrated regularly as directed by the Engineer and the
necessary certificates produced to the Engineer.
14.3 The Contractor shall render all reasonable assistance and help in
making the checks and tests. All the equipments, machinery etc.
shall be kept in good working conditions.
14.4 Cost of setting up the laboratory, equipping the same, maintaining,
conducting all tests on materials and cubes shall be borne by the
contractor and nothing extra shall be paid on this account.
15.0 CURING:
15.1 All concrete work in cement mortar, plaster, pointing etc., shall be
continuously cured for the prescribed period as per direction of the
Engineer, Curing shall be done by covering the newly laid concrete
with gunny bags and keeping them wet constantly. If it is found that
the contractor is not observing properly these instructions, the
123
Engineer may get the curing done through another agency, labour
without any notice to the contractor at the cost of the contractor. The
cost incurred along with incidental charges of 2% and along with
supervision charges 12 ½ % of the cost will be debited to the
contractor.
17.5 Engineer-in-charge, if required may get the soil samples tested from
another outside agency as deemed suitable and the cost for the same if
any shall be borne by the contractor.
17.6 Before the earthwork is started by the contractor the ground between
the line where filling/excavation is to be done for embankments,
cuttings and training works shall be cleared of all trees along with the
roots, shrubs heavy grass, and under growth of every kind. None of the
items of work mentioned in this para will entitle the contractor/s to any
extra payment.
17.7 The contractor should commence work systematically at one or more
points in consultation with the Engineer and should maintain
continuous and steady progress to complete the work in continuous
length including leveling and dressing.
17.8 Any extra earth deposited on the top and slopes of the formation shall
be removed within 48 hours after a written notice. If not complied, the
same shall be removed by other means at contractor/s cost. Cost of
which shall be recovered from contractor/s bill. The payment shall be
made as per designed cross section only.
17.9 It must be clearly understood that the rates are intended to cover the
full cost of the finished works . The banks and cuttings are to be
correctly dressed to profile with such slopes as specified in each case by
the Engineer. The rates for earth work shall also include the following:-
i) Site clearance as per specifications including cutting of trees.
ii) Benching in side long ground and existing bank.
17.10 The rates also include maintenance of the banks and cutting to correct
profile including repairs of all rain cuts, making good earth work due to
base settlement, natural or otherwise due to rains etc. In case of filling
embankments and removal of silts and slips that may be accumulated
in cutting during rains etc.
17.11 Until the final measurements have been recorded and banks/cutting
taken over by the Department, the item rate of BOQ and quantities will
cover the full cost of finished work of cutting and embankments.
17.12 The following category of soil shall not be permitted.
(a) Organic clays, organic silts, peat, chalks and dispersive soils as detailed
below:-
(i) Poorly graded gravels sands with Cu less than 2.
(ii) Clays and silts of high compressibility i.e. MH, CH
20. BEARINGS.
POT PTFE bearing shall be provided for the girders. The bearings shall be in
accordance with the IRC-83 (Pt.III) 2002. (Latest Edition)
These bearings shall be correctly manufactured according to the approved
drawings subject to the permissible tolerances. The bearing shall be got
approved from Engineer In-charge prior to placement under the girder. For
example (Bearing of METCO, Sanfield, Mageba), M/S Steel Auto Industries
and any other brand/make with the approval of department.
22. Material steel nosing: The steel nosing shall be of angle section ISA 100x100
conforming to weldable structural steel as per IS:2062. The thickness of legs
shall not be less than 12mm. The top face of the angle shall be provided with
Bleeder holes of 12mm diameter spaced at maximum 100mm centers so as to
ensure that there are no voids in the concrete beneath the angle.
23. Anchorage: The anchorage steel shall conform to IS: 2062 or equivalent. The
steel nosing shall be anchored to the deck by reinforcing bars, headed studs
or bolts or anchor plates cast in concrete or a combination of anchor plate and
reinforcing bars, headed studs or bolts. Anchor bars, studs or bolts shall
engage the main structural reinforcement of the deck and in case of anchor
plates or anchor loops, this shall be achieved by passing transverse bars
through the loops or plates.
The minimum thickness of anchor plate shall be 12mm. Total cross sectional
area of bars, studs or bolts on each side of the joint shall not be less than
1600 mm sq. per meter length of the joint and the center to center spacing
shall not exceed 250mm. The ultimate resistance of anchorage shall not be
less than 500 KN/m in any direction.
Corrosion protection: All steel section shall be protected against corrosion by
hot dip galvanizing or any other approved anticorrosive coating with a
minimum thickness of 100 micron.
127
Lubricant cum adhesive: The type and application of material used in bonding the
preformed joint seal to the steel nosing and concrete shall be as recommended by the
manufacturer/supplier of the seal system.
Handling and storage:
a) The expansion joint material shall be handled with care and stored
under cover.
128
b) All joint material and assemblies shall be protected from damage and
assemblies shall be supplied to maintain true shape and alignment
during transportation and storage.
INSTALLATION:
The expansion joint shall be installed by the manufacturer/supplier or their
authorized representative, who will ensure compliance of installation
procedure and instructions.
The dimension of the joint recess and the width of the gap shall conform to the
approved drawing.
Anchoring steel shall be welded to the main reinforcement in the deck
maintaining the level and alignment of the joint.
Concreting of pocket/recess shall be done with great care using proper mix
conforming to same grade as that of the deck concrete but not less than M35
grade in any case. The water-cement ratio shall not be more than 0.40. If
needed suitable admixtures may be used to achieve the workability. The
width of pocket shall not be less than 300mm on either side of the joint. Care
shall also be taken to ensure efficient bonding between already cast existing
deck concrete and the concrete in the joint recess.
At the time of installation, joint shall be clean and dry and free from spoils
and irregularities, which might impair a proper joint seal.
Concrete or metal surfaces shall be clean, free of rust, laitance, oils, dirt, dust
or other deleterious materials.
The lubricant cum adhesive shall be applied to both faces of the joint and joint
seal prior to installation in accordance with the manufacturer’s instructions.
The joint seal shall be compressed to the specified thickness for joint opening
and ambient temperature at the time of installation which shall be between
+ 5 to + 35 degree C.
The joint seal shall be installed without damage to the seal. Loose fitting or
open joints shall not be permitted.
Steel nosing system shall be installed in correct camber and alignment of the
joint in the recess provided with adequate support bars and loops which shall
be welded with the sinusoidal bars of the anchorage system and the exposed
reinforcement of the deck slab/PSC girder.
That recess portion shall be concreted with cement concrete (CC) in
accordance with M.O.S.T. specification.
The top of expansion joint cc block and top of wearing coat shall be in the
same level.
The EVAZOTE – 380 ESP shall be installed between the angle nosing
subsequent to sand blasting and applying BONDER no.1 on vertical faces of
nosing angle on curing of concrete. The width of seal is 25% more than the
expansion gap so the seal is installed in compressed, state.
129
29. Coordination with Railway for end span (regarding issues of bridges the
coordination with Railway considered to be deleted) only for ROB & RUB.
The contractor has to made coordination with the Railway Authorities, during
the execution of work. The end span of approaches shall be laid only after
consultation with Railway. Nothing extra shall be paid on account of delay of
railway portion. However suitable time extension on this account, if any, will
be granted by the department.
130
Section 5
Drawings
List of Drawings:-
131
132
Section 6
Bill of Quantities
Preamble
10) The work will be carried out strictly in accordance with the PWD book
of specification 1990 edition, CPWD Specifications and MoRT&H
Specifications as applicable and that will form part and parcel of this
contract agreement.
11) The ‘Engineer’ shall be entitled to order work against any item or work
shown in this contract schedule of rates hereinafter called the
“Schedule” to any extent and without any limitation whatsoever as may
be required in his opinion for the purpose of work irrespective of the
fact the quantities are omitted altogether in the “Schedule” or shown
more or less than the work ordered to be carried out.
12) In this contract schedule of rates only essential portion of items has
been written, but it will deem to cover the entire items as fully
described in Haryana PWD schedule rates 2021 till the date of opening
of tender and will be applicable on this contract schedule of rates.
13) All the items in this contract schedule of rates 2021 subject to the foot
notes given in the Haryana PWD schedule of rates 2021 till the date of
opening of tender and will be applicable on this contract schedule of
rates.
14) Quantities given in the BOQ may vary at the time of execution of works
done at site by the contractor.
15) Unless otherwise specified all material, machinery and labour input are
to be arrange by the contractor.
134
16) All amendments issued to the Haryana PWD schedule of rates will be
applicable on the contract schedule of rates.
17) As and when contractor gives condition that arrangement of water shall
be made by the department, it shall be deemed that all the charges
incurred thereon shall be borne by the department and recovery on the
total work done shall be made from him.
18) No claim will be entertained from the contractor in case of any mistake
in description, rate or unit occurred on account of typing or comparison
or over sight. If there is any mistake, the same shall be rectifiable by
the ‘Engineer’ at any stage as per Haryana PWD schedule of rates 2021
and all the amendments received from time to time.
19) The premium should be quoted above or below for HSR items and
individual rates for NS Items. No conditional offer should be made. In
case any conditions is tendered, this will be considered as null and void
and only the premium or discount quoted by the tenderer small be
accepted. In case any tendered refused to accept the above afterwards,
his earnest money will be forfeited or the action as per conditions of Bid
Security Declaration Form shall be taken.
21) Rate quoted by the contractor for each N.S. item shall be for complete
job including all taxes(but excluding GST), carriage etc. Nothing extra
on any account shall be paid.
22) The payment will be made according to the actual work done by the
contractor.
135
BILL OF QUANTITIES
NAME OF WORK:-________________________________________________.
Signature__________
Notes:-
1. The item for which no rate or price has been entered in will not be paid
for by the Employer when executed and shall be deemed to be covered
by the other rates and prices in the Bill of Quantities (Refer: ITB Clause
13.2).
2. Unit rates and prices shall be quoted by the bidder in Indian rupees
exclusive of GST. [ITB Clause 14.1].
136
Section 7
Standard Forms
Letter of Acceptance
and
Other Forms
137
Standard Forms
(A) Letter of Acceptance
LETTER OF ACCEPTANCE
(Letterhead paper of the Employer)
No.________ Dated___________________
To
Dear Sir,
Authorized Signature
Name and title of Signatory
Name of Employer
for and on behalf of Governor of Haryana
138
To
——————————————
Dear Sirs:
Yours faithfully,
1. In this Agreement, words and expressions shall have the same meanings
as are respectively assigned to them in the Conditions of Contract
hereinafter referred to, and they shall be deemed to form and be read and
construed as part of this Agreement.
140
i) Letter of Acceptance;
ii) Notice to Proceed with the works;
iii) Contractor’s Bid;
iv) Contract Data;
v) Special Conditions of Contract and General Conditions of Contract;
vi) Specifications;
vii) Drawings;
viii) Bill of Quantities; and
ix) Any other document listed in the Contract Data as forming part of
the Contract.
________________________________________________________________________
Guarantee
SEALED with the common seal of the said Bank this ___________ day of
____________, 20
(1) If after Bid opening the Bidder withdraws his bid during the period of
Bid validity specified in the from of tender.
OR
(2) If the Bidder having been notified to the acceptance of his bid by the
Employer during the period of Bid validity:
hereby waived. Any demand in respect of this guarantee should reach the
Bank not later than the above date.
* The Bidder should insert the amount of the guarantee in words and
figures denominated in Indian Rupees. This figure should be the same as
shown in Clause 16.1 of the Instructions to Bidders.
** 45 days after the end of the validity period of the Bid. Date should be
inserted by the employer before the Bidding documents are issued.
143
2. I, on behalf of the bidder, (Name of Bidder), also accept the fact that in
case the bid is withdrawn or modified during the period of its validity or
if we fail to sign the contract in case the work is awarded to us or we fail
to submit a performance security before the deadline defined in clause
34.1 of the tender document, then (Name of Bidder) will be debarred for
participation in the tendering process in any of the Department/
Boards/ Corporations etc. of the Government of Haryana for a period of
Two year from the bid due date of this work.
To
____________________________ [name of Employer]
____________________________ [address of Employer]
____________________________
Contractor shall in any way release us from any liability under this guarantee,
and we hereby waive notice of any such change, addition or modification.
This guarantee shall be valid until 28 days from the expiry of the
Defect Liability-cum-Maintenance Period.
Signature and Seal of the guarantor_____________
Name of Bank_________________________
Address _____________________________
Date________________________________
______________________________________________________________________
______________________________________________________
______________________________________________________________
6. DELIVERY: Lessee shall not be responsible for all expenses and costs i)
at the beginning of the Lease Term, of transporting the equipment/
machinery Lessee’s premises and ii) at the end of the Lease Term, of
transporting the equipment/ machinery back to Lessor’s premises.
Either party may change such address from time to time by providing
notice as set for the above.
LESSOR
______________________
__________________
LESSEE
___________________________
____________________________
149
WHEREAS all the parties are desirous of recording the terms and
conditions of this Joint Venture to avoid future disputes.
1. That in and under this Joint Venture agreement the work will be
done jointly by the First Party and Second Party in the name and style
of M/s _______________ ________________M/s
_____________________________ and
M/s._________________________________).
2. This all the parties shall be legally liable, severally and or jointly
responsible for the satisfactory/successful execution/completion of the
work in all respects and in accordance with terms and conditions of the
contract.
5. That all the parties of this Joint Venture shall depute their
experienced staff as committed commensuration with their role and
responsibility and as required for the successful completion of the
works in close consultation with each other.
6. That the investment required for the works under this Joint
Venture shall be brought in by the parties as agreed to between them
from time to time.
NOW THE PARTIES HAVE JOINED HANDS TO FORM THIS JOINT VENTURE ON
THIS ______________ DAY OF _______________ TWO THOUSAND WITH REFERENCE
TO AND IN CONFIRMATION OF THEIR DISCUSSIONS AND UNDERSTANDING
BROUGHT ON RECORD ON _____________.
IN WITNESS THEREOF ALL/BOTH THE ABOVE NAMED PARTIES HAVE SET THEIR
RESPECTIVE HANDS ON THIS JOINT VENTURE AGREEMENT ON THE DAY,
MONTH AND YEAR FIRST ABOVE MENTIONED IN THE PRESENCE OF THE
FOLLOWING WITNESS;
WITNESSES:
1. FIRST PARTY
2. SECOND PARTY
151
This guarantee shall remain valid and in full effect from the date of the
advance payment under the Contract until _______________________________
[name of Employer] receives full repayment of the same amount from the
Contractor.
Yours truly,
AND WHEREAS the contractor has applied to the Employer that he may
be allowed advanced on the security of materials absolutely belonging to him
and brought by him to the site of the works the subject of the said agreement
for use in the constructions of such of the works as he has undertaken to
executive at rates fixed for the finished work (inclusive of the cost of materials
and labour and other charges).
(2) That the materials details in the said Account of Secured Advances
which have been offered to an accepted by the Employer as security
153
(3) That the materials detailed in the said account of Secured Advances
and all other materials on the security of which any further advance
or advances may hereafter be made as aforesaid (hereafter called the
said materials) shall be used by the Contractor solely in the
execution of the said works in accordance with the directions of the
‘Engineer’.
(4) That the Contractor shall make at his own cost all necessary and
adequate arrangements for the proper watch, safe custody and
protection against all risks of the said materials and that until used
in construction as aforesaid the said materials shall remain at the
site of the said works in the Contractor’s custody and on his own
responsibility and shall at all times be open to inspection by the
‘Engineer’ or any officer authorized by him. In the event of the said
materials or any part thereof being stolen, destroyed or damaged or
becoming deteriorated in a greater degree than is due to reasonable
use and wear thereof the Contractor will forthwith replace the same
with other materials of like quality or repair and make good the same
required by the ‘Engineer’.
(5) That the said materials shall not be any account be removed from
the site of the said works except with the written permission of the
‘Engineer’ or an officer authorized by him on that behalf.
(6) That the advances shall be repayable in full when or before the
Contractor receives payment from the Employer of the price payable
to him for the said works under the terms and provisions of the said
agreement. Provided that if any intermediate payments are made to
the Contractor on account of work done than on the occasion of each
such payment the Employer will be at liberty to make a recovery
from the Contractor’s bill for such payment by deducting there from
the value of the said materials than actually used in the
construction and in respect of which recovery has not been made
previously, the value for this purpose being determined in respect of
each description of materials at the rates at which the amounts of
the advances made under these presents were calculated.
(7) That if the Contractor shall at any time make any default in the
performance or observance in any respect of any of the terms and
provisions of the said agreement or of these presents the total
amount of the advance or advances that may still be owing of the
Employer shall immediately on the happening of such default be re-
154
BETWEEN
AND
Preamble
Whereas, the Employer has floated the Tender (NIT No.......... dtd
.......................} (hereinafter referred ’to as “Tender/Bid”) and intends
to award, under laid down organizational procedure, contract/s for
{Name of the work}(hereinafter referred to as the “Contract”).
And Whereas the Employer values full compliance with all relevant
laws of the land,
rules of land, regulations, economic use of resources and of fairness/
transparency in its relations with its Bidder(s) and/ or
Contractor(s)/Concessionaire (s)/Consultant(s).
And whereas to meet the purpose aforesaid, both the parties have
agreed to enter into this Integrity Pact (hereafter referred to as
“Integrity Pact” or “Pact”) the terms and conditions of which shall
156
(For & On behalf of the Employer) (For & On behalf of the Bidder/
Contractor Concessionaire (s)/Consultant(s)/)
(Office Seal)
Place Date
Witness I : (Name & Address):
Witness 2 : (Name & Address):
163
(J) Undertaking
UNDERTAKING
To :
Address :
1. With full understanding that Part II of our bid (Financial bid) will be
opened only if I/We qualify on the basis of evaluation in Part I of the
Bid (Technical bid), I/We offer to execute the Works described above
and remedy any defects therein in conformity with the conditions of
Contract, specifications, drawings, Bill of Quantities and Addenda for
an amount quoted in the Financial Bid.
2. I/We agree to abide by this Bid for the period of 120 days from the date
fixed for receiving the same, and it shall remain binding upon us and
may be accepted at any time before the expiration of that period.
3. Unless and until a formal Agreement is prepared and executed this Bid,
together with your written acceptance thereof, shall constitute a binding
contract between us.
4. I/We undertake, if our Bid is accepted, to commence the Works as soon
as is reasonably possible after the receipt of the Engineer’s notice to
commence, and to complete the whole of the Works comprised in the
Contract within the time stated in the document.
5. I/We understand that you are not bound to accept the lowest or any
tender you may receive.
(H) AFFIDAVIT
Deponent
Signed by an
Authorized
Officer of the firm
(Deponent)
Place: ……………..
Date: ………………
* not applicable if the bidder is an individual and is signing the bid on his own
behalf.