Unit Commitment R
Unit Commitment R
JlMin and JlMax are the duals associated with the constraints on lower and
upper reactive generation limit respectively while MCq is the marginal cost
of reactive power delivery at a bus [33, 26]. It is to be noted that the above
formulation for real and reactive power prices can be extended to include the
duals of other operating constraints as well.
~ Fuel Cost: There have been two different approaches to represent fuel
costs in UC models. The first and the most common approach has been
to use a cost characteristic derived from the heat-rate characteristics and
represented by a polynomial function, which is usually quadratic, and
can be written as follows,
(20)
(21)
a is a fixed cost associated with the unit start-up, ~ is the cost involved
in a cold start-up,ro FF
is the time for which the unit has been off and 't
is a time-constant representing the cooling speed of the unit.
Another approach has been to use a constant cost representation,
which is included in the objective function when the unit is on start-up.
UST, USD and Ware integer decision variables denoting the status of the
unit at hour k. W denotes the unit status (I = running, 0 = oft); UST denotes
= =
the unit start-up state (I start-up, 0 no start-up) and USD denotes the unit
= =
shut down state (I shut down, 0 no shut down).
NG
IPi,k ·Wi,k +(Ik -Ek)~POk +RESVk (23)
i=1
The term RESV denotes the spinning reserve in the system, which is a
reserve available to the operator from among its spinning units, i.e. from the
generators already running. Therefore, this reserve is available almost
instantaneously to the operator in case of need. The operator has the very
important responsibility of maintaining adequate spinning reserves in the
system, not only on a total-MW basis, but he also needs to take care of the
location aspect of this reserve, taking into account transmission capacities
available in the system.
The operator generally uses his experience or certain rules for
determining this reserve to be maintained in his system. As mentioned in
[35], the RESV component could typically comprise a base component, a
fraction of the load requirement and a fraction of the high operating limit of
the largest on-line unit.
MUT
L USD1h,k-n+l ~ I; V k~MUT
n=1
(24)
MDT
L UST1h,k_m+1 ~ I; V k~MDT
m=1
MUT is the minimum time in hours the unit should be running before
shut down; MDT is the minimum time in hours the unit should remain shut
down before start-up,
pMin < p. .
i - I.k
w.I,k -< pMax
i (25)
V ieMR (26)
4.2.1 Multi-Area UC
RUP and RON are the ramp-up and ramp-down constants of a unit. This
constraint links the generation variable of the previous hour to that of the
52 Chapter 2
2 Non-utility generation or NUG was the term used to classify co-generating units and all such
units, which satisfied the PURPA minimum efficiency and fuel use criteria. Such units
were called qualifying facilities. However, NUG could also include large independent
power producers. which provided capacity sales to utilities [50).